XML 34 R23.htm IDEA: XBRL DOCUMENT v3.20.2
Leases (Tables)
3 Months Ended
Jun. 27, 2020
Leases  
Schedule of components of lease costs

The components of lease costs for the thirteen weeks ended June 27, 2020 and June 29, 2019 were as follows:

Thirteen Weeks Ended

June 27, 2020

June 29, 2019

Operating lease costs

$

22,500

$

22,364

Variable lease costs

 

32

 

472

Total lease costs

$

22,532

$

22,836

Schedule of supplemental cash flow information

Supplemental cash flow information related to our leases for the thirteen weeks ended June 27, 2020 and June 29, 2019 were as follows:

Thirteen Weeks Ended

June 27, 2020

June 29, 2019

Cash paid for amounts included in the measurement of operating lease liabilities

$

11,434

$

22,168

Additions to right-of-use assets

$

28,943

$

15,565

Schedule of weighted average remaining operating lease term and incremental borrowing rate

Weighted average remaining operating lease term and incremental borrowing rate as of June 27, 2020 and June 29, 2019 were as follows:

Thirteen Weeks Ended

June 27, 2020

June 29, 2019

Weighted average remaining lease term (years)

7.1

7.3

Weighted average incremental borrowing rate

14.5

%

8.8

%

Schedule of future minimum lease payments under our operating lease liabilities

    

Operating leases (1)

Within 1 year (remaining)

$

73,320

2 years

 

91,012

3 years

 

77,194

4 years

 

69,586

5 years

 

62,266

Thereafter

 

192,157

Total lease payments

$

565,535

Less amount representing interest

(210,971)

Total lease liability

$

354,564

Less current lease liability

(53,165)

Total noncurrent lease liability

$

301,399