XML 23 R12.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies
9 Months Ended
Sep. 30, 2017
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies

NOTE 6 – COMMITMENTS AND CONTINGENCIES

 

Commitments

 

On April 17, 2017, the Company received cash in the amount of $524,010, net of legal expenses from the settlement of the Glenny and Maskell litigation. The Company filed the lawsuit on May 25, 2012 at the Ontario Superior Court of Justice, seeking damages consisting of the costs of defense and any damages that may be awarded against the Company, our former CEO John Bordynuik, and former CFO Ron Baldwin in the Class Action and in the SEC Action. The Ontario Superior Court of Justice issued the dismissal order dated May 9, 2017. The case was settled in the U.S. with ACE (Insurance carrier) in or about May 2013, pursuant to what is known as a “Mary Carter” (confidential) settlement.

 

As of September 30, 2017, the Company has committed to purchase certain pieces of key machinery from vendors related to the future expansion of its operations. At December 31, 2016, we recorded impairment loss $1,448,464 on the deposits in accordance to ASC 360-10-50-2 where an impairment loss will be recognized only if the carrying amount of the long-lived assets are not recoverable and exceeds its fair value. The Company will be required to pay approximately $540,000 upon the delivery of these assets which is expected occur with the delivery of processor #4 and processor #5.

 

The Company leased premises in Thorold, Ontario, Canada which was previously used in the operation Plastic2Oil (Canada), Inc. doing business as Regional Recycling of Niagara (“RRON”). During the third quarter of 2013, the Company determined that it would shut down the operations of RRON. The employees of RRON were given notice of the shut down in the first week of September 2013, after which point the Company approached the landlord about terminating the lease; however, there was no formal termination as an agreement to terminate the lease was not reached. During September 2013, the Company was assessing its options with the facility, including potential sublease, but determined that a sublease of the facility was not permitted by the lease and officially decided to cease use of the premises as of September 30, 2013. Accordingly, the Company has applied September 30, 2013 as the cease-use-date in recognizing the liability for the contract termination costs. The property was vacated on November 10, 2015. On January 15, 2016, the Company entered into a Surrender of Lease agreement which terminated its lease, dated December 1, 2010, between Avondale Store Limited Properties and JBI, (Canada) Inc. relating to the Company’s premises located at 1786 Allanport Road, Thorold, Canada. The effective date of the termination was October 31, 2015. The premises was the site of the Company’s Regional Recycling Center, which was part of a business line that was discontinued by the Company in 2013. The Company anticipates the termination will save approximately $1,161,360 in lease payments over the original life of the lease which had a term ending on December 1, 2030. The Company settled all unpaid rent on July 26, 2017, covering the period from May 2016 to October 2016.

 

Contingencies

 

As of September 30, 2017, the Company is involved in litigation and claims which arise from time to time in the normal course of business. In the opinion of management, based upon the information and facts known to them, any liability that may arise from such contingencies would not have a material adverse effect on the unaudited condensed consolidated financial statements of the Company.