Changes in Estimates
6 Months Ended
Jun. 30, 2016
Changes in Estimates [Abstract]  
Change In Estimate [Text Block]
3.  Changes in Estimates

The Company has a Company-wide quarterly Estimate at Completion (EAC) process in which management assesses the progress and performance of the Company's contracts. This process requires management to review each program’s progress towards completion by evaluating the program schedule, changes to identified risks and opportunities, changes to estimated contract revenues and estimated contract costs over the current contract block and any outstanding contract matters. Risks and opportunities include management's judgment about the cost associated with a program’s ability to achieve the schedule, technical requirements (e.g., a newly-developed product versus a mature product) and any other contract requirements. The majority of the Company's fixed priced contracts are life of aircraft program contracts. Due to the span of years it may take to complete a contract block and the scope and nature of the work required to be performed on those contracts, the estimation of total revenue and costs at completion is complicated and subject to many variables and, accordingly, is subject to change. When adjustments in estimated total contract block revenue or estimated total cost are required, any changes from prior estimates for delivered units are recognized in the current period as a cumulative catch-up adjustment for the inception-to-date effect of such changes. Cumulative catch-up adjustments are driven by several factors including improved production efficiencies, assumed rate of production, the rate of overhead absorption, changes to scope of work and contract modifications. When estimates of total costs to be incurred on a contract block exceed estimates of total revenue to be earned, a provision for the entire loss on the contract block is recorded in the period in which the loss is determined. Changes in estimates are summarized below:
 
 
For the Three Months Ended
 
For the Six Months Ended
Changes in Estimates
 
June 30, 2016
 
July 2, 2015
 
June 30, 2016
 
July 2, 2015
Cumulative Catch-up Adjustment by Segment
 
 
 
 
 
 
 
 
Fuselage
 
$
—

 
$
10.8

 
$
16.2

 
$
10.3

Propulsion
 
(8.8
)
 
6.6

 
(0.7
)
 
14.4

Wing
 
9.8

 
(0.8
)
 
19.1

 
(0.6
)
Total Favorable Cumulative Catch-up Adjustment
 
$
1.0

 
$
16.6

 
$
34.6

 
$
24.1

 
 
 
 
 
 
 
 
 
Changes in Estimates on Loss Programs (Forward Loss)
 
 
 
 
 
 
 
 
Fuselage
 
 
 
 
 
 
 
 
Boeing - All other platforms
 
$
0.9

 
$
3.5

 
$
4.0

 
$
6.4

Airbus A350 XWB
 
(135.7
)
 
—

 
(135.7
)
 
—

Other Platforms
 
0.3

 
—

 
0.3

 
—

Total Fuselage (Forward Loss) Change in Estimate on Loss Programs
 
$
(134.5
)
 
$
3.5

 
$
(131.4
)
 
$
6.4

Propulsion
 
 
 
 
 
 
 
 
Boeing - All other platforms
 
$
(2.4
)
 
$
(1.3
)
 
$
3.1

 
$
(1.3
)
Rolls-Royce BR725
 
—

 
—

 
3.4

 
—

Total Propulsion (Forward Loss) Change in Estimate on Loss Programs
 
$
(2.4
)
 
$
(1.3
)
 
$
6.5

 
$
(1.3
)
Wing
 
 
 
 
 
 
 
 
Boeing - All other platforms
 
$
1.2

 
$
—

 
$
4.2

 
$
—

Total Wing Change in Estimate on Loss Programs
 
$
1.2

 
$
—

 
$
4.2

 
$
—

Total (Forward Loss) Change in Estimate on Loss Programs
 
$
(135.7
)
 
$
2.2

 
$
(120.7
)
 
$
5.1

 
 
 
 
 
 
 
 
 
Total Change in Estimate
 
$
(134.7
)
 
$
18.8

 
$
(86.1
)
 
$
29.2

EPS Impact (diluted per share based upon statutory rates)
 
$
(0.66
)
 
$
0.08

 
$
(0.41
)
 
$
0.13


Airbus A350 XWB

During the second quarter of 2016, Spirit signed a memorandum of agreement with Airbus (the "Airbus 2016 MOA") which, in part, materially reset the pricing for 800 units on the A350 XWB Fuselage and Wing requirements contracts. The Airbus 2016 MOA was negotiated to economically compensate Spirit for significant engineering changes to aircraft design. The new pricing provided the Company with a higher degree of certainty of revenue that will be realized over the 800 unit contracts. Further, the Company analyzed A350 XWB market demand using third party publications as well as Airbus firm orders which indicated that the sustained demand for the A350 XWB program was in excess of 800 units. The Company determined that due to the higher degree of precision of the A350 XWB revenue along with the strong, sustained market demand, it was appropriate to extend the accounting block quantity to 800 units. The contract block quantity change was made in accordance with applicable accounting guidance as well as the Company’s accounting policies and past practices. As a result of the Airbus 2016 MOA, the Company updated its estimated revenues that will be realized over the 800 unit A350 XWB Fuselage and Wing contract accounting blocks.

While the Company continued to make progress on the A350 XWB Fuselage program the Company experienced various disruption and production inefficiencies that exceeded estimates made in previous quarters primarily related to achieving production rate increases. As a result of these disruptions and inefficiencies, cost estimates were updated in the second quarter of 2016 to account for increased labor costs in fabrication and assembly and expedited shipping costs to meet current and future customer production rate increases. The Company also updated its estimates in the second quarter of 2016 due to uncertainty of supply chain cost reductions and achievement of cost affordability projects.

The changes in revenue and cost estimates during the second quarter of 2016 (as described above) resulted in a net forward loss charge of $135.7 and a net $8.2 favorable cumulative catch-up adjustment on the A350 XWB program. The Company could record additional forward loss charges if there are further changes to revenue and cost estimates and/or if risks are not mitigated.