XML 33 R19.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2017
Commitments and Contingencies.  
Commitments and Contingencies

Note 13—Commitments and Contingencies

 

LeasesWe lease certain property and equipment under non-cancelable operating leases, which expire at various dates through 2024.  The leases require us to pay all taxes, insurance, maintenance, and utilities and are classified as operating leases in accordance with ASC 840 “Leases”.

 

The future minimum lease payments required under non-cancelable operating leases are as follows (in thousands):

 

 

 

 

 

 

 

 

 

 

 

 

    

 

 

    

 

 

    

 

 

 

 

 

 

 

 

 

 

 

 

 

 

For the Years Ending

 

Real

 

 

 

 

Total

 

December 31, 

 

Property

 

Equipment

 

Commitments

 

2018

 

$

5,027

 

$

13,581

 

$

18,608

 

2019

 

 

3,900

 

 

9,314

 

 

13,214

 

2020

 

 

2,464

 

 

5,563

 

 

8,027

 

2021

 

 

1,428

 

 

2,667

 

 

4,095

 

2022

 

 

331

 

 

11

 

 

342

 

Thereafter

 

 

 —

 

 

 —

 

 

 —

 

 

 

$

13,150

 

$

31,136

 

$

44,286

 

 

Total lease expense during the years ended December 31, 2017, 2016 and 2015 was  $25.5 million, $22.5 and $21.8 million, respectively.

 

Withdrawal liability for multiemployer pension plan In November 2011, members of the Pipe Line Contractors Association “PLCA” including ARB, Rockford and Q3C (prior to our acquisition in 2012), withdrew from the Central States Southeast and Southwest Areas Pension Fund multiemployer pension plan (“Plan”).  These withdrawals were made in order to mitigate additional liability in connection with the significantly underfunded Plan.  We recorded a withdrawal liability of $7.5 million, which was increased to $7.6 million after the acquisition of Q3C.  During the first quarter of 2016, we received a final payment schedule.  As a result of payments made and based on this schedule, the liability recorded at December 31, 2017 and 2016 was $4.7 million and $5.7 million, respectively. We expect to pay the remaining liability balance during 2018, and have no plans to withdraw from any other labor agreements.

 

NTTA settlementOn February 7, 2012, we were sued in an action entitled North Texas Tollway Authority (“NTTA”), Plaintiff v. James Construction Group, LLC, and KBR, Inc., Defendants, v. Reinforced Earth Company, Third-Party Defendant (the “Lawsuit”). On February 25, 2015 the Lawsuit was settled, and we recorded a liability for $17.0 million. A second defendant agreed to provide up to $5.4 million to pay for the total expected remediation cost of approximately $22.4 million.  We will use our settlement obligation to pay for a third-party contractor approved by the NTTA.  In the event that the total remediation costs exceed the $22.4 million, the second defendant would pay 20% of the excess amount and we would pay for 80% of the excess amount.  During 2017, we increased our liability by $1.9 million. As of December 31, 2017, we have spent $3.7 million for remediation.  At December 31, 2017, our remaining accrual balance was  $15.2 million.   

 

LitigationWe have been engaged in dispute resolution to collect money we believe we are owed for one construction project completed  in 2014.  Because of uncertainties associated with the project, including uncertainty of the amounts that would be collected, we used a zero profit margin approach to recording revenues during the construction period for the project.  

 

For the project, a cost reimbursable contract, we have recorded a receivable of $32.9 million with a reserve of approximately $17.9 million included in “Billings in excess of costs and estimated earnings.”  At this time, we cannot predict the amount that we will collect nor the timing of any collection. The dispute resolution for the receivable initially required international arbitration; however, in the first half of 2016, the owner sought bankruptcy protection in U.S. bankruptcy court. We have initiated litigation against the sureties who have provided lien and stop payment release bonds for the total amount owed. A trial date has been tentatively set for the second quarter of 2018. 

 

We had been engaged in dispute resolution to collect money we believed was owed to us for another construction project completed  in 2014. During the third quarter 2016, we settled the dispute with an exchange of general releases and receipt of $38.0 million in cash.  We changed our zero estimate of profit and accounted for the settlement as a change in accounting estimate which resulted in recognizing revenues of approximately $27.5 million and gross profit of approximately $26.7 million in the third quarter of 2016.

 

We are subject to other claims and legal proceedings arising out of our business. We provide for costs related to contingencies when a loss from such claims is probable and the amount is reasonably estimable. In determining whether it is possible to provide an estimate of loss, or range of possible loss, we review and evaluate our litigation and regulatory matters on a quarterly basis in light of potentially relevant factual and legal developments. If we determine an unfavorable outcome is not probable or reasonably estimable, we do not accrue for a potential litigation loss.

 

Management is unable to ascertain the ultimate outcome of other claims and legal proceedings; however, after review and consultation with counsel and taking into consideration relevant insurance coverage and related deductibles/self-insurance retention, management believes that it has meritorious defense to the claims and believes that the reasonably possible outcome of such claims will not, individually or in the aggregate, have a materially adverse effect on our consolidated results of operations, financial condition or cash flow.

 

SEC InquiryWe have been cooperating with an inquiry by the staff of the Securities and Exchange Commission which appears to be focused on certain percentage-of-completion contract revenue recognition practices of the Company during the time period 2013 and 2014.  We are continuing to respond to the staff’s inquiries in connection with this matter.  At this stage, we are unable to predict when the staff’s inquiry will conclude or the outcome.

 

BondingAs of December 31, 2017 and 2016, we had bid and completion bonds issued and outstanding totaling approximately $705.7 million and $680.0 million, respectively.