0001078782-18-000464.txt : 20180420 0001078782-18-000464.hdr.sgml : 20180420 20180420153347 ACCESSION NUMBER: 0001078782-18-000464 CONFORMED SUBMISSION TYPE: 8-K PUBLIC DOCUMENT COUNT: 2 CONFORMED PERIOD OF REPORT: 20180416 ITEM INFORMATION: Termination of a Material Definitive Agreement ITEM INFORMATION: Regulation FD Disclosure ITEM INFORMATION: Other Events ITEM INFORMATION: Financial Statements and Exhibits FILED AS OF DATE: 20180420 DATE AS OF CHANGE: 20180420 FILER: COMPANY DATA: COMPANY CONFORMED NAME: Mexus Gold US CENTRAL INDEX KEY: 0001355677 STANDARD INDUSTRIAL CLASSIFICATION: GOLD & SILVER ORES [1040] IRS NUMBER: 204092640 STATE OF INCORPORATION: NV FISCAL YEAR END: 0331 FILING VALUES: FORM TYPE: 8-K SEC ACT: 1934 Act SEC FILE NUMBER: 000-52413 FILM NUMBER: 18766548 BUSINESS ADDRESS: STREET 1: 1805 N. CARSON STREET STREET 2: SUITE 150 CITY: CARSON CITY STATE: NV ZIP: 89701 BUSINESS PHONE: (916) 776 1822 MAIL ADDRESS: STREET 1: 1805 N. CARSON STREET, #150 CITY: CARSON CITY STATE: NV ZIP: 89701 FORMER COMPANY: FORMER CONFORMED NAME: Action Fashions, Ltd. DATE OF NAME CHANGE: 20060309 8-K 1 f8k042018_8k.htm FORM 8K CURRENT REPORT Form 8K Current Report

 

SECURITIES AND EXCHANGE COMMISSION

 

Washington, D.C. 20549

 

FORM 8-K

 

CURRENT REPORT

Pursuant to Section 13 OR 15(d) of The Securities Exchange Act of 1934

 

Date of Report (Date of earliest event reported): April 16, 2018

 

MEXUS GOLD US

(Exact name of registrant as specified in its charter)

 

Nevada

 

000-52413

 

20-4092640

(State or other jurisdiction

 

(Commission File Number)

 

(IRS Employer

of Incorporation)

 

 

 

 

Identification Number)

 

 

1805 N. Carson Street, #150

 

 

 

 

Carson City, NV 89701

 

 

 

 

(Address of principal executive offices)

 

 

 

 

 

 

 

 

 

(916) 776-2166

 

 

 

 

(Registrant’s Telephone Number)

 

 

 

N/A

(Former name or former address, if changed since last report)

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

 

[  ] Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

[  ] Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

[  ] Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

 

[  ] Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))


Item 1.02 Termination of a Material Definitive Agreement.

 

On April 16, 2016, Mexus Gold US (“Mexus” or the “Company”) announced that Mexus Gold Mining SA De CVA, a subsidiary of Mexus, terminated its joint venture agreement with MarMar Holdings (the “JV Agreement”). The JV Agreement outlined the contractual obligations of the parties at the Santa Elena project in Caborca, Sonora State, Mexico.

 

The decision to terminate the JV Agreement was made due to MarMar’s failure to provide agreed funding, equipment and general operations for the project, as well as MarMar’s inability to meet environmental standards at the site.

 

The Company does not anticipate any early termination penalties associated with the JV Agreement.

 

Item 7.01 Regulation FD Disclosure

 

On April 16, 2018, Mexus issued a press release which announced that it had terminated its JV Agreement with MarMar Holdings. A copy of the press release issued by Mexus is attached as Exhibit 99.1 and incorporated herein by reference solely for purposes of this Item 7.01 disclosure.

 

Exhibit 99.1 contains forward-looking statements. These forward-looking statements are not guarantees of future performance and involve risks, uncertainties and assumptions that are difficult to predict. Forward-looking statements are based upon assumptions as to future events that may not prove to be accurate. Actual outcomes and results may differ materially from what is expressed in these forward-looking statements.

 

The information set forth under this Item 7.01, including Exhibit 99.1, is being furnished and, as a result, such information shall not be deemed “filed” for purposes of Section 18 of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), or otherwise subject to the liabilities of such Section, nor shall such information be deemed incorporated by reference in any filing under the Securities Act of 1933, as amended, or the Exchange Act, except as expressly set forth by specific reference in such a filing.

 

Item 8.01 Other Events.

 

Mexus intends to move forward with the Santa Elena project with proper equipment and personnel. Due to the lack of funding by MarMar, the Santa Elena site, a disappointing 8.5oz Au was produced in the last 22 months.

 

Mexus President Paul Thompson states that Mexus has contracted with a security firm to provide 24-hour services at the Santa Elena site. Currently, there is equipment on site sufficient to produce an anticipated 500 tons a day and plans are in place to begin hiring staff with production beginning shortly thereafter. In addition, safety fencing will be installed and required site clean-up will occur that will satisfy any environmental concerns at the property. Two separate parties are running tests on the heap leach pad to determine the next steps to allow for recovery of gold and silver within the system.

 

Using previously developed geological mapping the company plans to mine the Julio quartz vein and the adjacent shear zone via open pit mining. The existing Julio vein, with depths to 30 meters and widths from 1 to 4 meters, has values ranging from 1.5 to 186 grams Au per ton. The adjacent shear zone carries values from .5 to 17 grams Au per ton. Mexus estimates that the shear zone will average 2.5 grams per ton gold equivalent with the Julio vein values being much higher. Additional equipment will be purchased which will enable the company to increase production to 1000 tons a day and beyond. Mexus intends to announce a non-dilutive capital raise plan in the very near future.

 

Lead geologist for Mexus MX, Cesar Lemas, announced that progress at the 8 Brothers project has slowed due to holidays in Mexico and the recent developments at the Santa Elena mine. All the necessary equipment has arrived at the mine site including the large VAT gold recovery tank. It is expected that installation and set-up of all systems will be completed by June 1st, 2018. Mr. Lemas continues to assay material from the mine site showing 3 to 12 grams per ton Au and 30 grams Ag which should equate to excellent returns once the system is operational.

 

Item 9.01 - Financial Statements and Exhibits

 

(d) Exhibits

 

99.1 Press Release


SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, hereunto duly authorized.

 

 

Mexus Gold US

 

/s/

Paul D. Thompson

By:

Paul D. Thompson

Its:

President

 

EX-99.1 2 f8k042018_ex99z1.htm EXHIBIT 99.1 PRESS RELEASE Exhibit 99.1 Press Release

 

Exhibit 99.1

 

Press Release | 04/16/2018

 

Mexus terminates JV agreement with MarMar Holdings; Update on 8 Brothers project

 

CABORCA, Mexico, April 16, 2018 (GLOBE NEWSWIRE) -- Mexus Gold US

 

(OTCQB: MXSG) (“Mexus” or the “Company”) announced today that Mexus Gold Mining SA De CVA, a subsidiary of Mexus Gold US, is terminating its joint venture agreement with MarMar Holdings. The agreement outlined the contractual obligations at the Santa Elena project in Caborca, Sonora State, Mexico. The decision to terminate the agreement was made due to MarMar’s lack of funding for the project, non-compliance with various aspects of the agreement, and their inability to meet environmental standards at the site. Lack of funding by MarMar resulted in a disappointing 8.5oz Au produced in the last 22 months. The agreement stipulated that MarMar was to provide the funding, equipment, and fully operate the mine. Unfortunately, this did not occur.

 

Mexus will move forward with the proper equipment and personnel at the Santa Elena project. Mexus President Paul Thompson states that the company has contracted with a security firm to provide 24-hour services at the mine site. There is equipment on site to produce 500 tons a day and plans are in place to begin hiring staff with production beginning shortly thereafter. In addition, safety fencing will be installed and required site clean-up will occur that will satisfy any environmental concerns at the property. Two separate parties are running tests on the heap leach pad to determine the next steps to allow for recovery of gold and silver within the system.

 

Using previously developed geological mapping the company plans to mine the Julio quartz vein and the adjacent shear zone via open pit mining. The existing Julio vein, with depths to 30 meters and widths from 1 to 4 meters, has values ranging from 1.5 to 186 grams Au per ton. The adjacent shear zone carries values from .5 to 17 grams Au per ton. Mexus estimates that the shear zone will average 2.5 grams per ton gold equivalent with the Julio vein values being much higher. Additional equipment will be purchased which will enable the company to increase production to 1000 tons a day and beyond. The company will announce a non-dilutive capital raise plan in the very near future.

 

Lead geologist for Mexus MX, Cesar Lemas, announced that progress at the 8 Brothers project has slowed due to holidays in Mexico and the recent developments at the Santa Elena mine. All the necessary equipment has arrived at the mine site including the large VAT gold recovery tank. It is expected that installation and set-up of all systems will be completed by June 1st, 2018. Mr. Lemas continues to assay material from the mine site showing 3 to 12 grams per ton Au and 30 grams Ag which should equate to excellent returns once the system is operational.

 

About Mexus Gold US

 

Mexus Gold US is an American based mining company with holdings in Mexico. The fully owned Santa Elena mine is located 54km NW of Caborca, Mexico. Mexus also owns rights to the Ures property located 80km N of Hermosillo, Mexico. This property contains 6900 acres and has both gold and copper on the property. Founded in 2009, Mexus Gold US is committed to protecting the environment, mine safety and employing members of the communities in which it operates.

 

For more information on Mexus Gold US, visit www.mexusgoldus.com.

 

Cautionary Statement

 

Forward looking Statement: Statements in this press release may constitute forward-looking statements and are subject to numerous risks and uncertainties, including the failure to complete successfully the development of new or enhanced products, the Company's future capital needs, the lack of market demand for any new or enhanced products the Company may develop, any actions by the Company's partners that may be adverse to the Company, the success of competitive products, other economic factors affecting the Company and its markets, seasonal changes, and other risks detailed from time to time in the Company's filings with the Securities and Exchange Commission. The actual results may differ materially from those contained in this press release. The Company disclaims any obligation to update any statements in this press release.

 

CONTACT: Inquiries - Paul Dent, 425-478-4908 pdent@mexusgoldus.com