XML 39 R23.htm IDEA: XBRL DOCUMENT v3.3.1.900
Commitments and Contingencies
12 Months Ended
Dec. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
COMMITMENTS AND CONTINGENCIES
OPERATING LEASES
We have operating leases covering office space, equipment, land and vehicles expiring at various dates through 2028. As leases expire, it can be expected that certain leases will be renewed or replaced in the normal course of business.
As of December 31, 2015, the future minimum rental payments required under our operating leases are as follows: 
(Dollars in thousands)
 
2016
$
3,601

2017
3,496

2018
1,464

2019
717

2020
252

2021 and thereafter
88

Total
$
9,618


Operating lease expense was $4.6 million, $4.0 million and $3.6 million for the years ended December 31, 2015, 2014 and 2013, respectively.
LEGAL MATTERS
In January 2007, the Environmental Protection Agency (EPA) notified us that we are a potentially responsible party under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA) and the Clean Water Act for cleanup of a site known as Avery Landing in northern Idaho. We own a portion of the land at the Avery Landing site, which we acquired in 1980 from the Milwaukee Railroad. The land we own at the site and adjacent properties were contaminated with petroleum as a result of the Milwaukee Railroad's operations at the site prior to 1980. On July 5, 2011, the EPA issued an Action Memorandum for the Avery Landing Site selecting contaminant extraction and off-site disposal as the remedial alternative. On May 23, 2012, we signed a consent order with the EPA pursuant to which we agreed to provide $1.75 million in funding for EPA cleanup on a portion of our property (including the adjacent riverbank owned by the Idaho Department of Lands). The EPA cleanup was completed in October 2012. On April 4, 2013, the EPA issued a unilateral administrative order requiring us to remediate the portion of the Avery Landing site that we own. Our remediation was completed in October 2013. On September 25, 2015 the EPA sent us a letter asserting that the EPA and the Department of Transportation (the current owner of a portion of the adjacent property remediated by the EPA) had incurred $9.8 million in unreimbursed response costs associated with the site and that we were liable for such costs. We believe we have meritorious defenses to this claim and we intend to defend ourselves vigorously. We have reserved all of our rights to seek reimbursement for the costs of remediation from all parties potentially responsible. We have executed a tolling agreement with the EPA and DOT suspending the statute of limitations on the claim until June 2016 in order to facilitate negotiations of a final settlement and release. We have not recorded a liability related to this matter and while it is reasonably possible that we may incur some liability in respect of this claim, we are unable to estimate at this time the amount of charges, if any, which may be required for this matter in the future.