Property, plant and equipment consisted of the following:
 
   
December 31,
   
December 31,
 
   
2019
   
2018
 
Lab and build-to-suit equipment
  $
7,562,263
    $
7,266,895
 
Office equipment
   
128,669
     
130,460
 
Furniture and fixtures
   
237,951
     
205,051
 
Computer equipment
   
804,046
     
799,515
 
Leasehold improvements
   
11,762,351
     
8,878,361
 
Construction-in-progress
   
91,797
     
155,148
 
Total property, plant and equipment
   
20,587,077
     
17,435,430
 
Accumulated depreciation and amortization
   
(11,333,112
)    
(9,304,722
)
Property, plant and equipment, net
  $
9,253,965
    $
8,130,708
 
 
The Company recorded depreciation and amortization expense of
$2,567,742
and
$1,543,667
for the years ended
December 
31,
 
2019
and
2018,
respectively. Maintenance and repairs are expensed as incurred and were
$220,658
and
$153,278,
respectively, for the years ended
December 
31,
 
2019
and
2018.
 
In
December 
2016,
the Company executed an agreement with a commercial manufacturer to build a PRINT particle fabrication line for the production of
LIQ861.
The ultimate cost was approximately
$1.6
million. The Company financed this transaction with a
third
-party vendor, CSC Leasing Company (“CSC”). CSC made payments to the manufacturer per the payment schedule in the agreement as the asset was fabricated. CSC charged the Company a monthly lease rate on the scheduled payments made to the manufacturer as interim financing costs until the asset was completed and placed in service. Upon completion of fabrication, the lease commenced in
March 
2018
(“CSC Financing”).
 
In accordance with ASC
840,
Leases
, for build-to-suit arrangements where the Company is involved in the fabrication of an asset prior to the commencement of the ultimate financing or takes some level of construction risk, the Company is considered the accounting owner of the assets during the fabrication period. Accordingly, during the fabrication phase, the Company recorded a construction-in-progress asset within Property, Plant and Equipment and a corresponding deferred financing obligation liability for contributions by CSC toward fabrication. Upon completion of the fabrication in
March 2018,
since the Company maintained substantially all of the risk and rewards of ownership of the asset, the Company recorded the transaction as a financing, continuing to record the asset and reclassifying the deferred financing obligation to debt. In accordance with Topic
842,
Leases
, the CSC Financing was recharacterized as a finance lease in the
first
quarter of
2019
and accounted for accordingly (see Note
9
).
 
The following table details the activity of Construction in Progress (“CIP”) in
2019
and
2018
and the associated transfer to Leasehold Improvements and Lab Equipment when the assets were placed in service:
 
   
Leasehold
   
Build-to-suit
   
Lab
   
 
 
 
   
Improvements
   
Equipment
   
Equipment
   
Total
 
Balance as of December 31, 2017
  $
1,208,107
    $
1,583,054
    $
39,246
    $
2,830,407
 
Add: Purchases related to CIP
   
425,438
     
82,687
     
114,102
     
622,227
 
Less: Transfer due to being placed in service
   
(1,570,194
)    
(1,665,741
)    
(61,551
)    
(3,297,486
)
Balance as of December 31, 2018
   
63,351
     
—
     
91,797
     
155,148
 
Add: Purchases related to CIP
   
2,820,640
     
—
     
—
     
2,820,640
 
Less: Transfer due to being placed in service
   
(2,883,991
)    
—
     
—
     
(2,883,991
)
Balance as of December 31, 2019
  $
-
    $
-
    $
91,797
    $
91,797
 
 
The Construction in Progress balance includes
$0
and
$3,925
of capitalized interest costs for the years ended
December 
31,
 
2019
and
2018,