XML 81 R12.htm IDEA: XBRL DOCUMENT v2.4.0.8
Contingencies
6 Months Ended
Jun. 30, 2013
Commitments and Contingencies Disclosure [Abstract]  
Contingencies
Contingencies
Litigation
The Company is a plaintiff in a lawsuit against Sonitrol Corporation. The case arose from the December 21, 2002 arson fire at the Denver warehouse in which Sonitrol failed to detect and respond to a four-hour burglary and subsequent arson. In 2010, a jury found in favor of the Company and our insurers. Sonitrol appealed the judgment to the Colorado Appellate Court and on July 19, 2012, the Appellate Court upheld the trial court's ruling on two of the three issues being appealed but set aside the judgment and remanded the case back to the District Court for trial on the sole issue of damages. The Appellate Court's ruling was appealed by Sonitrol to the Colorado Supreme Court on September 21, 2012. On April 29, 2013, the Colorado Supreme Court denied Sonitrol's appeal and the case was returned to the District Court to resolve the sole issue of damages. A trial date has been set for November 4, 2013. We are unable to predict when this litigation will be finally resolved and the ultimate outcome. Any monetary recovery from the lawsuit would be recognized only if and when it is finally paid to the Company.
We are subject to certain legal proceedings, claims, investigations and administrative proceedings in the ordinary course of our business. We make a provision for a liability when it is both probable that the liability has been incurred and the amount of the liability can be reasonably estimated. These provisions, if any, are reviewed at least quarterly and adjusted to reflect the impacts of negotiations, settlements, rulings, advice of legal counsel and other information and events pertaining to a particular case.