The Company is subject to environmental laws and regulations worldwide that impose limitations on the discharge of pollutants into the air and water, establish standards for the treatment, storage and disposal of solid and hazardous wastes, and impose record keeping and notification requirements. Failure to timely comply with these laws and regulations may expose the Company to penalties. The Company believes that it is in substantial compliance with all applicable environmental laws and regulations and engages in an ongoing process of updating its controls to mitigate compliance risks. The Company is also subject to retained environmental obligations specified in various contractual agreements arising from the divestiture of certain businesses by the Company or one of its predecessor companies.
The components of environmental remediation reserves are as follows:
 
As of
June 30,
2017
 
As of
December 31,
2016
 
(In $ millions)
Demerger obligations (Note 18)
25

 
18

Divestiture obligations (Note 18)
16

 
16

Active sites
15

 
16

US Superfund sites
11

 
11

Other environmental remediation reserves
2

 
3

Total
69

 
64


Remediation
Due to its industrial history and through retained contractual and legal obligations, the Company has the obligation to remediate specific areas on its own sites as well as on divested, demerger, orphan or US Superfund sites (as defined below). In addition, as part of the demerger agreement between the Company and Hoechst AG ("Hoechst"), a specified portion of the responsibility for environmental liabilities from a number of Hoechst divestitures was transferred to the Company (Note 18). The Company provides for such obligations when the event of loss is probable and reasonably estimable. The Company believes that environmental remediation costs will not have a material adverse effect on the financial position of the Company, but may have a material adverse effect on the results of operations or cash flows in any given period.
US Superfund Sites
In the US, the Company may be subject to substantial claims brought by US federal or state regulatory agencies or private individuals pursuant to statutory authority or common law. In particular, the Company has a potential liability under the US Federal Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended, and related state laws (collectively referred to as "Superfund") for investigation and cleanup costs at certain sites. At most of these sites, numerous companies, including the Company, or one of its predecessor companies, have been notified that the US Environmental Protection Agency ("EPA"), state governing bodies or private individuals consider such companies to be potentially responsible parties ("PRP") under Superfund or related laws. The proceedings relating to these sites are in various stages. The cleanup process has not been completed at most sites, and the status of the insurance coverage for some of these proceedings is uncertain. Consequently, the Company cannot accurately determine its ultimate liability for investigation or cleanup costs at these sites.
As events progress at each site for which it has been named a PRP, the Company accrues, as appropriate, a liability for site cleanup. Such liabilities include all costs that are probable and can be reasonably estimated. In establishing these liabilities, the Company considers the contaminants of concern, the potential impact thereof, the relationship of the contaminants of concern to its current and historic operations, its shipment of waste to a site, its percentage of total waste shipped to the site, the types of wastes involved, the conclusions of any studies, the magnitude of any remedial actions that may be necessary and the number and viability of other PRPs. Often the Company joins with other PRPs to sign joint defense agreements that settle, among PRPs, each party's percentage allocation of costs at the site. Although the ultimate liability may differ from the estimate, the Company routinely reviews the liabilities and revises the estimate, as appropriate, based on the most current information available.
One such site is the Diamond Alkali Superfund Site, which is comprised of a number of sub-sites, including the Lower Passaic River Study Area, which is the lower 17-mile stretch of the Passaic River ("Lower Passaic River Site"), and the Newark Bay Area. The Company and 70 other companies are parties to a May 2007 Administrative Order on Consent with the EPA to perform a Remedial Investigation/Feasibility Study ("RI/FS") at the Lower Passaic River Site in order to identify the levels of contaminants and potential cleanup actions, including the potential migration of contaminants between the Lower Passaic River Site and the Newark Bay Area. Work on the RI/FS is ongoing, with a goal to complete it in 2018.
In March 2016, the EPA issued its final Record of Decision concerning the remediation of the lower 8.3 miles of the Lower Passaic River Site ("Lower 8.3 Miles"). Pursuant to the EPA's Record of Decision, the Lower 8.3 Miles must be dredged bank to bank and an engineered cap must be installed at an EPA estimated cost of approximately $1.4 billion. The Company owned and/or operated facilities in the vicinity of the Lower 8.3 Miles, but has found no evidence that it contributed any of the primary contaminants of concern to the Passaic River. The Company is vigorously defending this matter and currently believes that its ultimate allocable share of the cleanup costs with respect to the Lower Passaic River Site, estimated at less than 1%, will not be material.