XML 20 R46.htm IDEA: XBRL DOCUMENT v2.4.0.6
Plant Relocation (Tables)
3 Months Ended
Mar. 31, 2012
Plant Relocation [Abstract]  
Schedule of Plant Relocation Financial Statement Impact
A summary of the financial statement impact associated with the Ticona Kelsterbach plant relocation is as follows:
 
Three Months Ended
 
Total From
Inception Through
 
March 31,
 
 
2012
 
2011
 
March 31, 2012
 
(In $ millions)
Deferred proceeds (1)

 

 
907

Costs expensed

 
13

 
106

Costs capitalized (2)
13

 
49

 
1,105

Lease buyout

 

 
22

Employee termination benefits

 

 
8

_____________________________
(1) 
Included in noncurrent Other liabilities in the unaudited consolidated balance sheets. Amounts reflect the US dollar equivalent at the time of receipt.
(2) 
Includes a decrease in accrued capital expenditures of $8 million and $5 million for the three months ended March 31, 2012 and 2011, respectively.