Plant Relocation
12 Months Ended
Dec. 31, 2011
Plant Relocation [Abstract]  
Plant Relocation
Plant Relocation
In November 2006, the Company finalized a settlement agreement with the Frankfurt, Germany Airport (“Fraport”) to relocate the Kelsterbach, Germany Ticona operations resolving several years of legal disputes related to the planned Fraport expansion. As a result of the settlement, the Company will transition Ticona’s operations from Kelsterbach to the Frankfurt Hoechst Industrial Park in the Rhine Main area in Germany. Under the original agreement, Fraport agreed to pay the Company a total of €670 million over a five-year period to offset costs associated with the transition of the operations from its current location and the closure of the Kelsterbach plant. The Company subsequently expanded the scope of the new production facilities.
The Company received its final payment from Fraport of €110 million during the three months ended June 30, 2011 and ceased POM operations at the Kelsterbach, Germany Ticona facility prior to July 31, 2011. On September 26, 2011, the Company announced the opening of its new POM production facility in Frankfurt Hoechst Industrial Park, Germany.
A summary of the financial statement impact associated with the Ticona Kelsterbach plant relocation is as follows:
 
Year Ended December 31,
 
Total From
Inception Through
 
2011
 
2010
 
December 31, 2011
 
(In $ millions)
Deferred proceeds (1)
158

 

 
907

Costs expensed
47

 
26

 
106

Costs capitalized (2)
171

 
305

 
1,092

Lease buyout

 
22

 
22

Employee termination benefits
8

 

 
8

___________________________
(1) 
Included in noncurrent other liabilities in the consolidated balance sheets.
(2) 
Includes a decrease in accrued capital expenditures of $33 million and $7 million for the year ended December 31, 2011 and 2010, respectively.