XML 243 R72.htm IDEA: XBRL DOCUMENT v3.25.0.1
Acquisitions and Dispositions of Properties - Dispositions (Details)
$ in Thousands
1 Months Ended 3 Months Ended 12 Months Ended
Nov. 01, 2024
item
MW
Apr. 16, 2024
USD ($)
Mar. 01, 2024
USD ($)
Center
Jan. 11, 2024
USD ($)
Center
MW
Jul. 13, 2023
USD ($)
property
Jan. 31, 2024
USD ($)
Center
Dec. 31, 2024
USD ($)
Sep. 30, 2023
USD ($)
Dec. 31, 2024
USD ($)
property
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Jan. 12, 2024
Schedule of Equity Method Investments [Line Items]                        
Planned campuses to support the construction of data centers | item 10                      
Potential IT load capacity | MW 500                      
Provision for impairment               $ 95,000 $ 191,200      
Number of data centers | Center           2            
Equity in loss of unconsolidated entities                 $ (120,138) $ (29,791) $ (13,497)  
Joint Venture With Mitsubishi Joint Venture                        
Schedule of Equity Method Investments [Line Items]                        
Ownership percentage in joint ventures     35.00%                  
Joint Venture with GI Partners                        
Schedule of Equity Method Investments [Line Items]                        
Ownership percentage in joint ventures   25.00%   20.00%     20.00%   20.00%      
Digital Core REIT (DCRU)                        
Schedule of Equity Method Investments [Line Items]                        
Number of data centers | property                 12      
Hyperscale Data Center Campuses across Frankfurt, Paris and Northern Virginia | Joint Venture with Blackstone Inc                        
Schedule of Equity Method Investments [Line Items]                        
Number of hyperscale data center campuses develop through joint venture | item 4                      
Proceeds from partnership contribution       $ 385,000                
Gain (loss) on disposition             $ 44,500          
Hyperscale Data Center Campuses across Frankfurt, Paris and Northern Virginia | Joint Venture with GI Partners                        
Schedule of Equity Method Investments [Line Items]                        
Number of hyperscale data center campuses develop through joint venture | Center       4                
Planned campuses to support the construction of data centers | Center       10                
Potential IT load capacity | MW       500                
Proceeds from partnership contribution       $ 231,000     385,000          
Gain (loss) on disposition       $ 300     $ 44,500          
Data Center Joint Venture | Brookfield Infrastructure Partners L.P                        
Schedule of Equity Method Investments [Line Items]                        
Equity in loss of unconsolidated entities           $ 8,900            
Hyperscale data center buildings in the Chicago metro area | Joint Venture with GI Partners                        
Schedule of Equity Method Investments [Line Items]                        
Proceeds from partnership contribution   $ 386,000     $ 700,000              
Gain (loss) on disposition   $ 172,000     $ 238,000              
Number of properties sold | property         2              
Percentage of ownership Interest in partnership         65.00%             80.00%
Call option to increase their ownership interest in the joint venture         80.00%              
Percentage of interest in property sold   75.00%                    
Contribution, value   $ 453,000                    
Brookfield Infrastructure Partners L.P | Data Center Joint Venture                        
Schedule of Equity Method Investments [Line Items]                        
Proceeds from partnership contribution           271,000            
Gain (loss) on disposition           $ 191,600            
Number of properties sold | Center           4            
Number of data centers | Center           2            
Gain on sale of investments           $ 200,500            
Brookfield Infrastructure Partners L.P | Data Center Joint Venture | Singapore and Frankfurt                        
Schedule of Equity Method Investments [Line Items]                        
Payments to acquire real estate           $ 57,000            
Brookfield Infrastructure Partners L.P | Data Center Joint Venture | Americas                        
Schedule of Equity Method Investments [Line Items]                        
Number of properties for which lease is amended | Center           3            
Brookfield Infrastructure Partners L.P | Data Center Joint Venture | Digital Core REIT (DCRU)                        
Schedule of Equity Method Investments [Line Items]                        
Number of data centers | Center           2            
Number of leased data centers acquired | Center           3            
Joint Venture With Mitsubishi Joint Venture | Data Centers in Dallas Metro Area                        
Schedule of Equity Method Investments [Line Items]                        
Planned campuses to support the construction of data centers | Center     2                  
Gain (loss) on disposition     $ 7,000                  
Number of data centers | Center     2                  
Percentage of property pre- leased prior to construction     100.00%                  
Purchase Price     $ 261,000                  
Gross Proceeds     $ 153,000                  
Percentage of ownership Interest in partnership     65.00%