XML 129 R41.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Note 8 - Property, Plant and Equipment and Construction-in-process (Tables)
12 Months Ended
Dec. 31, 2019
Notes Tables  
Property, Plant and Equipment [Table Text Block]
   

December 31,

 
   

2019

   

2018

 
   

(Dollars in thousands)

 

Land owned by the Company where the geothermal resource is located

  $ 38,049     $ 38,060  

Leasehold improvements

    7,757       5,718  

Machinery and equipment

    230,465       208,646  

Land, buildings and office equipment

    39,099       35,708  

Vehicles

    8,021       22,074  

Geothermal and recovered energy generation power plants, including geothermal wells and exploration and resource development costs:

               

United States of America, net of cash grants

    2,160,910       2,065,377  

Foreign countries

    721,824       710,775  

Asset retirement cost

    19,824       11,448  
      3,225,949       3,097,806  

Less accumulated depreciation

    (1,254,534

)

    (1,138,228

)

                 

Property, plant and equipment, net

  $ 1,971,415     $ 1,959,578  
Construction In Progress [Table Text Block]
   

December 31,

 
   

2019

   

2018

 
   

(Dollars in thousands)

 

Projects under exploration and development:

               

Up-front bonus costs

  $ 17,018     $ 17,018  

Exploration and development costs

    66,916       53,237  

Interest capitalized

    703       703  
      84,637       70,958  

Projects under construction:

               

Up-front bonus costs

    27,473       27,473  

Drilling and construction costs

    258,484       160,398  

Interest capitalized

    5,961       2,861  
      291,918       190,732  

Total

  $ 376,555     $ 261,690  
Rollforward Of Construction In Process [Table Text Block]
   

Projects under exploration and development

 
   

Up-front Bonus

Costs

   

Exploration and

Development Costs

   

Interest

Capitalized

   

Total

 
   

(Dollars in thousands)

 

Balance at December 31, 2016

  $ 17,385     $ 36,359     $ 703     $ 54,447  

Cost incurred during the year

          11,224             11,224  

Write off of unsuccessful exploration costs

    (367

)

    (1,429

)

          (1,796

)

Balance at December 31, 2017

    17,018       46,154       703       63,875  

Cost incurred during the year

          7,209             7,209  

Write off of unsuccessful exploration costs

          (126

)

          (126

)

Balance at December 31, 2018

    17,018       53,237       703       70,958  

Cost incurred during the year

          17,215             17,215  

Transfer of projects under exploration and development to projects under construction

          (3,536

)

          (3,536

)

Balance at December 31, 2019

  $ 17,018     $ 66,916     $ 703     $ 84,637  
   

Projects under construction

 
   

Up-front Bonus
Costs

   

Drilling and

Construction

Costs

   

Interest

Capitalized

   

Total

 
   

(Dollars in thousands)

 

Balance at December 31, 2016

  $ 37,713     $ 202,211     $ 12,338     $ 252,262  

Cost incurred during the year

          231,926       7,300       239,226  

Transfer of completed projects to property, plant and equipment

    (10,240

)

    (235,194

)

    (16,387

)

    (261,821

)

Balance at December 31, 2017

    27,473       198,943       3,251       229,667  

Cost incurred during the year

          219,610             219,610  

Cost write off

          (1,380

)

          (1,380

)

Fair value of projects under construction acquired in a business combination

          4,668             4,668  

Transfer of completed projects to property, plant and equipment

          (261,443

)

    (390

)

    (261,833

)

Balance at December 31, 2018

    27,473       160,398       2,861       190,732  

Cost incurred during the year

          264,137       3,100       267,237  

Transfer of projects under exploration and development to projects under construction

          3,536             3,536  

Insurance recoveries

          (35,435

)

          (35,435

)

Transfer of completed projects to property, plant and equipment

          (134,152

)

          (134,152

)

Balance at December 31, 2019

  $ 27,473     $ 258,484     $ 5,961     $ 291,918