XML 38 R13.htm IDEA: XBRL DOCUMENT v3.6.0.2
Note 6 - Accumulated Loss of Unconsolidated Company in Excess of Investment
12 Months Ended
Dec. 31, 2016
Notes to Financial Statements  
Equity Method Investments and Joint Ventures Disclosure [Text Block]
NOTE
6
Accumulated loss of unconsolidated company in excess of investment
 
Accumulated loss of unconsolidated company in excess of investment
mainly consist of the following:
 
   
December 31,
 
   
2016
   
2015
 
   
(Dollars in thousands)
 
Sarulla
  $
(11,081
)   $
(8,100
)
 
The Sarulla Project
 
The Company holds a
12.75%
equity interest in a consortium which is in the process of developing the Sarulla geothermal power project in Indonesia with an expected generating capacity of approximately
330
megawatts (“MW”). The Sarulla project is located in Tapanuli Utara, North Sumatra, Indonesia and will be owned and operated by the consortium members under the framework of a Joint Operating Contract (“JOC”) and Energy Sales Contract (“ESC”) that were signed on
April
4,
2013.
Under the JOC, PT Pertamina Geothermal Energy (“PGE”), the concession holder for the project, has provided the consortium with the right to use the geothermal field, and under the ESC, PT PLN, the state electric utility, will be the off-taker at Sarulla for a period of
30
years. In addition to its equity holdings in the consortium, the Company designed the Sarulla plant and will supply its Ormat Energy Converters (“OECs”) to the power plant, as further described below.
 
 
The project is being constructed in
three
phases of a total
321
MW, utilizing both steam and brine extracted from the geothermal field to increase the power plant
’s efficiency. The
first
phase with
110
MW capacity is currently under testing and expected to commence operation in
March
2017.
For the
second
phase power plant, engineering and procurement has been substantially completed, site construction is in progress and all of the major generating units including those to be supplied by Ormat were delivered. For the
third
phase, engineering, procurement and construction work at the site are in progress and manufacturing of equipment to be supplied by Ormat is underway as planned. Drilling for the
second
and
third
phases is still ongoing and the project has achieved to date, based on preliminary estimates, approximately
80%
of the required production capacity and over
85%
of the required injection capacity. The project has missed a few milestones defined under the loan documents, but has received waivers from the lenders and as of now the project is in compliance with lenders requirements. The project is still experiencing delays in the field development and cost overruns resulting from delays and excess drilling costs. Due to the cost overrun in drilling, the lenders have requested from the sponsors to commit for additional equity. The sponsors have agreed and financing documents were revised to reflect this request. With respect to Ormat’s role as a supplier, all contractual milestones under the supply agreement were achieved.
 
On
May
16,
2014,
the consortium closed
$1.17
billion in financing for the development of the Sarulla project with a consortium of lenders comprised of Japan Bank for International Cooperation (“JBIC”), the Asian Development Bank and
six
commercial banks and obtained construction and term loans on a limited recourse basis backed by a political risk guarantee from JBIC. Of the
$1.17
billion,
$0.1
billion (which was drawn down by the Sarulla project company on
May
23,
2014)
bears a fixed interest rate and
$1.07
billion bears interest at a rate linked to LIBOR.
 
The Sarulla consortium entered into interest rate swap agreements with various international banks in order to fix the Libor interest rate on up to
$0.96
billion of the
$1.07
billion credit facility at a rate of
3.4565%.
The interest rate swap became effective as of
June
4,
2014
along with the
second
draw-down by the project company of
$50.0
million.
 
The Sarulla project company accounted for the interest rate swap as a cash flow hedge upon which changes in the fair value of the hedging instrument, relative to the effective portion, will be recorded in other comprehensive income. As such, during the year ended
December
31,
2016
and
2015,
the project recorded a gain of
$9.3
million and $
8.0
million, respectively, net of deferred tax, of which the Company's share was
$1.2
million and
$1.0
million, respectively, which was recorded in other comprehensive income. The related accumulated loss recorded by the Company in other comprehensive income (loss) as of
December
31,
2016
is
$5.9
million.
 
Pursuant to a supply agreement that was signed in
October
2013,
the Company is supplying its OECs to the power plant and has added the
$255.6
million supply contract to its Product Segment backlog. The Company started to recognize revenue from the project during the
third
quarter of
2014
and will continue to recognize revenue over the course
of next year. The Company has eliminated the related intercompany profit of
$12.0
million against equity in loss of investees.
 
During the year ended
December
31,
2016,
the Company made an additional
cash equity investment contribution to the Sarulla project in the amount of
$3.6
million.