Note 3 - Cost and Estimated Earnings on Uncompleted Contracts
12 Months Ended
Dec. 31, 2014
Contractors [Abstract]  
Long-term Contracts or Programs Disclosure [Text Block]

NOTE 3 — COST AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS


Cost and estimated earnings on uncompleted contracts consist of the following:


   

December 31,

 
   

2014

   

2013

 
   

(Dollars in thousands)

 

Costs and estimated earnings incurred on uncompleted contracts

  $ 127,959     $ 51,550  

Less billings to date

    (124,890 )     (38,236 )

Total

  $ 3,069     $ 13,314  

These amounts are included in the consolidated balance sheets under the following captions:


   

December 31,

 
   

2014

   

2013

 
   

(Dollars in thousands)

 

Costs and estimated earnings in excess of billings on uncompleted contracts

  $ 27,793     $ 21,217  

Billings in excess of costs and estimated earnings on uncompleted contracts

    (24,724 )     (7,903 )

Total

  $ 3,069     $ 13,314  

The completion costs of the Company’s construction contracts are subject to estimation. Due to uncertainties inherent in the estimation process, it is reasonably possible that estimated contract earnings will be further revised in the near term.