XML 54 R12.htm IDEA: XBRL DOCUMENT v2.4.0.8
Note 4 - Unconsolidated Investments
6 Months Ended
Jun. 30, 2014
Equity Method Investments and Joint Ventures [Abstract]  
Equity Method Investments and Joint Ventures Disclosure [Text Block]

NOTE 4 — UNCONSOLIDATED INVESTMENTS


Unconsolidated investments consist of the following:


   

June 30,

2014

   

December 31,

2013

 
   

(Dollars in thousands)

 
                 

Sarulla

  $ 3,308     $ 7,076  

The Sarulla Project 


The Company (through a subsidiary) is a 12.75% equity stake member of a consortium (the “Sarulla Consortium”) which is in the process of developing the Sarulla geothermal power project in Indonesia with expected generating capacity of approximately 330 megawatts (“MW”). The Sarulla project is located in Tapanuli Utara, North Sumatra, Indonesia and will be owned and operated by the consortium members under the framework of a Joint Operating Contract (“JOC”) and Energy Sales Contract (“ESC”) that were signed on April 4, 2013. Under the JOC, PT Pertamina Geothermal Energy, the concession holder for the project, has provided the consortium with the right to use the geothermal field, and under the ESC, PT PLN, the state electric utility, will be the off-taker at Sarulla for a period of 30 years. In addition to its equity holdings in the consortium, the Company designed the Sarulla plant and is expected to supply its Ormat Energy Converters (“OECs”) to the power plant. The supply contract was signed on October 2013.


The consortium has started preliminary testing and development activities at the site and signed an engineering procurement and construction agreement (“EPC”) with an unrelated third party. The project will be constructed in three phases of 110 MW each, utilizing both steam and brine extracted from the geothermal field to optimize the resource utilization.


On May 16, 2014, the consortium reached financial closing of $1.17 billion financing agreements to finance the development of the Sarulla project with a consortium of lenders comprised of Japan Bank for International Cooperation (“JBIC”), the Asian Development Bank and six commercial banks and obtained construction and term loan under limited recourse financing package backed by political risk guarantee from JBIC.


Of the $1.17 billion, $0.1 billion (which was drawn-down by the Company on May 23, 2014) bears a fixed interest rate and $1.07 billion bears a Libor-based interest rate.


The Sarulla consortium entered into interest rate swap agreements with various international banks in order to fix the Libor interest rate on up to $0.96 billion of the $1.07 billion credit facility at a rate of 3.4565%. The interest rate swap became effective as of June 4, 2014 along with the second draw-down by the Company of $50.0 million.

         The Sarulla project has accounted for the interest rate swap as a cash flow hedge upon which changes in the fair value of the hedging instrument, relative to the effective portion, will be recorded in other comprehensive income. As such, during the period, the project recorded a loss equal to $32.0 million, of which the Company's share was $4.1 million which was recorded in other comprehensive income


The first phase of operations is expected to commence in 2016 and the remaining two phases of operations are scheduled to commence within 18 months thereafter. The Company will supply its Ormat Energy Converters to the power plant and has added the $254.0 million supply contract to its product segment backlog. According to the current project plan, we expect to recognize revenue from the project over the course of the next three to four years starting in the third quarter of 2014.


During the first six months of 2014, the Company made additional investment contributions of $0.6 million to the Sarulla project, consistent with its pro rata share in the consortium.


The Company’s share in the results of operations of the Sarulla project was not significant for each of the periods presented in these condensed consolidated financial statements.