NOTE 4 — UNCONSOLIDATED INVESTMENTS


Unconsolidated investments, mainly in power plants, consist of the following:


   

March 31,

2014

   

December 31,

2013

 
   

(Dollars in thousands)

 

Sarulla

  $ 7,510     $ 7,076  

The Sarulla Project


The Company (through a subsidiary) is a 12.75% equity stake member of a consortium (the “Sarulla” Consortium”) which is in the process of developing the Sarulla geothermal power project in Indonesia with expected generating capacity of approximately 330 megawatts (“MW”). The Sarulla project is located in Tapanuli Utara, North Sumatra, Indonesia and will be owned and operated by the consortium members under the framework of a Joint Operating Contract (“JOC”) and Energy Sales Contract (“ESC”) that were signed on April 4, 2013. Under the JOC, PT Pertamina Geothermal Energy, the concession holder for the project, has provided the consortium with the right to use the geothermal field, and under the ESC, PT PLN, the state electric utility, will be the off-taker at Sarulla for a period of 30 years. In addition to its equity holdings in the consortium, the Company designed the Sarulla plant and is expected to supply its Ormat Energy Converters (“OECs”) to the power plant. The supply contract was signed on October 2013. 


The consortium has started preliminary testing and development activities at the site and signed an engineering procurement and construction agreement (“EPC”) with an unrelated third party. The project will be constructed in three phases of 110 MW each, utilizing both steam and brine extracted from the geothermal field to increase the power plant’s efficiency.


On March 28, 2014, the consortium signed financing agreements in an aggregate amount of $1.17 billion to finance the development of the Sarulla project with a consortium of lenders comprised of Japan Bank for International Cooperation (“JBIC”), the Asian Development Bank and six commercial banks to obtain construction and term loan under limited-recourse financing package backed by political risk guarantee from JBIC.


Upon financing closing, the consortium is expected to begin full scope of construction with the first phase of operations expected to commence in 2016. The remaining two phases of operations are scheduled to commence within 18 months thereafter. The Company will supply its Ormat Energy Converters to the power plant and will add the $254.0 million supply contract to its product segment backlog once the Notice to Proceed is issued, upon closing of the financing. According to the current project plan we expect to recognize revenue from the project over the course of the next three to four years starting in the third quarter of 2014.  


During the first quarter of 2014, the Company made additional investment contributions of $0.6 million to the Sarulla project, consistent with its pro rata share in the consortium.


The Company’s share in the results of operations of the Sarulla project was not significant for each of the periods presented in these condensed consolidated financial statements.