XML 76 R31.htm IDEA: XBRL DOCUMENT v2.4.0.6
COMMITMENTS AND CONTINGENCIES
12 Months Ended
Dec. 31, 2012
COMMITMENTS AND CONTINGENCIES

NOTE 23 — COMMITMENTS AND CONTINGENCIES

Geothermal resources

The Company, through its project subsidiaries in the United States, controls certain rights to geothermal fluids through certain leases with the Bureau of Land Management (“BLM”) or through private leases. Royalties on the utilization of the geothermal resources are computed and paid to the lessors as defined in the respective agreements. Royalty expense under the geothermal resource agreements were $12,048,000, $10,138,000, and $8,690,000 for the years ended December 31, 2012, 2011, and 2010, respectively.

Letters of credit

In the ordinary course of business with customers, vendors, and lenders, the Company is contingently liable for performance under letters of credit totaling $217.8 million at December 31, 2012. Management does not expect any material losses to result from these letters of credit because performance is not expected to be required, and, therefore, is of the opinion that the fair value of these instruments is zero.

Purchase commitments

The Company purchases raw materials for inventories, construction-in-process and services from a variety of vendors. During the normal course of business, in order to manage manufacturing lead times and help assure adequate supply, the Company enters into agreements with contract manufacturers and suppliers that either allow them to procure goods and services based upon specifications defined by the Company, or that establish parameters defining the Company’s requirements.

At December 31, 2012, total obligations related to such supplier agreements were approximately $93.6 million (out of which approximately $42.5 million relate to construction-in-process). All such obligations are payable in 2013.

Grants and royalties

The Company, through Ormat Systems, had historically, through December 31, 2003, requested and received grants for research and development from the Office of the Chief Scientist of the Israeli Government. Ormat Systems is required to pay royalties to the Israeli Government at a rate of 3.5% to 5.0% of the revenues derived from products and services developed using these grants. No royalties were paid for the years ended December 31, 2012, 2011, and 2010. The Company is not liable for royalties if the Company does not sell such products and services. Such royalties are capped at the amount of the grants received plus interest at LIBOR. The cap at December 31, 2012 and 2011, amounted to $1.5 million and $1.4 million, respectively, of which approximately $0.5 million increases based on the LIBOR rate, as defined above.

Contingencies

Securities Class Actions

Following the Company’s public announcement that it would restate certain of its financial results due to a change in the Company’s accounting treatment for certain exploration and development costs, three securities class action lawsuits were filed in the United States District Court for the District of Nevada on March 9, 2010, March 18, 2010 and April 7, 2010. These complaints asserted claims against the Company and certain directors and officers for alleged violations of Sections 10(b) and 20(a) of the Securities Exchange Act of 1934 (the “Exchange Act”). One complaint also asserted claims for alleged violations of Sections 11, 12(a)(2) and 15 of the Securities Act of 1933, as amended (the “Securities Act”). All three complaints alleged claims on behalf of a putative class of purchasers of the Company’s common stock between May 6, 2008 or May 7, 2008 and February 23, 2010 or February 24, 2010. These three lawsuits were consolidated by the Court in an order issued on June 3, 2010, and the Court appointed three of the Company’s stockholders to serve as lead plaintiffs.

Lead plaintiffs filed a consolidated amended class action complaint (“CAC”) on July 9, 2010 that asserted claims under Sections 10(b) and 20(a) of the Exchange Act on behalf of a putative class of purchasers of the Company’s common stock between May 7, 2008 and February 24, 2010. The CAC alleged that certain of the Company’s public statements were false and misleading for failing to account properly for the Company’s exploration and development costs based on the Company’s announcement on February 24, 2010 that it was going to restate certain of its financial results to change its method of accounting for exploration and development costs in certain respects. The CAC also alleged that certain of the Company’s statements concerning the North Brawley project were false and misleading. The CAC sought compensatory damages, expenses, and such further relief as the Court may deem proper.

Defendants filed a motion to dismiss the CAC on August 13, 2010. On March 3, 2011, the Court granted in part and denied in part defendants’ motion to dismiss. The Court dismissed plaintiffs’ allegations that the Company’s statements regarding the North Brawley project were false or misleading, but did not dismiss plaintiffs’ allegations regarding the 2008 restatement. Defendants answered the remaining allegations in the CAC regarding the restatement on April 8, 2011, and the case entered the discovery phase. On July 22, 2011, plaintiffs filed a motion to certify the case as a class action on behalf of a class of purchasers of the Company’s common stock between February 25, 2009 and February 24, 2010, and defendants filed an opposition to the motion for class certification on October 4, 2011.

Subsequently, the parties participated in mediation where they reached an agreement in principle to settle the securities class action lawsuits. The parties thereafter filed a stipulation of settlement with the U.S. District Court for the District of Nevada on March 27, 2012, providing that the claims against the Company and its directors and officers will be dismissed with prejudice and plaintiffs will release the defendants from all claims in exchange for a cash payment of $3.1 million to be funded by the Company’s insurers. The stipulation of settlement received preliminary approval by the Court on March 30, 2012, and final approval on October 16, 2012.

The Company and the individual defendants have steadfastly maintained that the claims raised in the securities class action lawsuits were without merit, and have vigorously contested those claims. As part of the settlement, the Company and the individual defendants continue to deny any liability or wrongdoing under the securities laws or otherwise.

Stockholder Derivative Cases

Four stockholder derivative lawsuits have also been filed in connection with the Company’s public announcement that it would restate certain of its financial results due to a change in the Company’s accounting treatment for certain exploration and development costs. Two cases were filed in the Second Judicial District Court of the State of Nevada in and for the County of Washoe on March 16, 2010 and April 21, 2010, and two cases were filed in the United States District Court for the District of Nevada on March 29, 2010 and June 7, 2010. All four lawsuits assert claims brought derivatively on behalf of the Company against certain of its directors and officers for alleged breach of fiduciary duty and other claims, including waste of corporate assets and unjust enrichment.

The two stockholder derivative cases filed in the Second Judicial District Court of the State of Nevada in and for the County of Washoe were consolidated by the Court in an order dated May 27, 2010, and the plaintiffs filed a consolidated derivative complaint on September 7, 2010. In accordance with a stipulation between the parties, defendants filed a motion to dismiss on November 16, 2010. On April 18, 2011, the Court stayed the state derivative case pending the resolution of the securities class action lawsuits.

The two stockholder derivative cases filed in the United States District Court for the District of Nevada were consolidated by the Court in an order dated August 31, 2010, and plaintiffs filed a consolidated derivative complaint on October 28, 2010. The Company filed a motion to dismiss on December 13, 2010. On March 7, 2011, the Court transferred the federal derivative case to the Court presiding over the securities class action, and on August 29, 2011, the Court stayed the federal derivative case pending the resolution of the securities class action lawsuits.

The parties to all the stockholder derivative cases executed a stipulation of settlement to resolve all cases on September 25, 2012. The stipulation provides that: (i) all claims asserted in the derivative cases will be dismissed with prejudice and that plaintiffs will release the defendants from all claims; (ii) the Company will implement and/or maintain certain corporate governance measures for no less than five years; and (iii) plaintiffs’ counsel will receive attorneys’ fees of $700,000 to be funded by the Company’s insurers. The stipulation of settlement received preliminary approval by the Second Judicial District Court of the State of Nevada in and for the County of Washoe on October 22, 2012 and final approval on December 17, 2012 thereby dismissing the stockholder derivative cases pending in that court. Shortly thereafter on December 27, 2012, the United States District Court for the District of Nevada dismissed the stockholder derivative cases pending before it.

The Company believes the allegations in these purported derivative actions are without merit and, as part of the settlement, continues to deny any liability or wrongdoing.

Other

On December 24, 2012, Laborers’ International Union of North America Local Union No. 783 (“LiUNA”), an organized labor union, filed a petition in Mono County Superior Court, naming Mono County and the Company as defendant and real party in interest, respectively. The petitioners brought this action to challenge the November 13, 2012 decision of the Mono County Board of Supervisors in adopting Resolutions No. 12-78, denying Petitioners’ administrative appeal of the Planning Commission’s approval of Conditional Use Permit (“CUP”), adoption of findings under the California Environmental Quality Act (“CEQA”) and adoption of the final environmental impact report (“EIR”) for the Mammoth Pacific I replacement project. The petition asks the court to set aside the approval of the CUP and adoption of the EIR and cause a new EIR to be prepared and circulated.

The Company believes that the petition is without merit and intends to respond and take necessary legal action to dismiss the proceedings. The Company responded to LiUNA’s petition. Filing of the petition in and of itself does not have any immediate adverse implications for the Mammoth enhancement.

On January 4, 2012, the California Unions for Reliable Energy (“CURE”) filed a petition in Alameda Superior Court, naming the California Energy Commission (“CEC”) and the Company as defendant and real party in interest, respectively. The petition asks the court to order the CEC to vacate its decision which denied, with prejudice, the complaint filed by CURE against the Company with the CEC. The CURE complaint alleged that the Company’s North Brawley Project and East Brawley Project both exceed the CEC’s 50 MW jurisdictional threshold and therefore are subject to the CEC licensing authority rather than Imperial County licensing authority. In addition, the CURE petition asks the court to investigate and halt any ongoing violation of the Warren Alquist Act by the Company, and to award CURE attorney’s fees and costs. As to North Brawley, CURE alleges that the CEC decision violated the Warren Alquist Act because it failed to consider provisions of the County permit for North Brawley, which CURE contends authorizes the Company to build a generating facility with a number of Ormat Energy Converters (“OECs”) capable of generating more than 50 MW. As to East Brawley, CURE alleges that the CEC decision violated the Warren Alquist Act because it failed to consider the conditional use permit application for East Brawley, which CURE contends shows that the Company requested authorization to build a facility with a number of OECs capable of generating more than 50 MW.

The Company believes that the petition is without merit and intends to respond and take necessary legal action to dismiss the proceedings. The parties have filed briefs in the proceeding, and the matter was set for hearing. The court held two hearings and on November 15, 2012 CURE’s petition was denied. Any appeal of the Court’s decision must be filed by Monday, March 4, 2013. The filing of the petition in and of itself does not have any immediate adverse implications for the North Brawley or East Brawley projects and the Company continues to operate the North Brawley project in the ordinary course of business and is proceeding with its development work on the East Brawley project.

From time to time, the Company is named as a party in various other lawsuits, claims and other legal and regulatory proceedings that arise in the ordinary course of its business. These actions typically seek, among other things, compensation for alleged personal injury, breach of contract, property damage, punitive damages, civil penalties or other losses, or injunctive or declaratory relief. With respect to such lawsuits, claims and proceedings, the Company accrues reserves when a loss is probable and the amount of such loss can be reasonably estimated. It is the opinion of the Company’s management that the outcome of these proceedings, individually and collectively, will not be material to the Company’s consolidated financial statements as a whole.