The following table summarizes environmental remediation activity during the three months ended March 31, 2013 and 2012.
 
2013

 
2012

Beginning balance – January 1

$710

 

$758

Reductions for payments made
(8
)
 
(12
)
Changes in estimates
5

 
12

Ending balance - March 31

$707

 

$758


The liabilities recorded represent our best estimate or the low end of a range of reasonably possible costs expected to be incurred to remediate sites, including operation and maintenance over periods of up to 30 years. It is reasonably possible that we may incur charges that exceed these recorded amounts because of regulatory agency orders and directives, changes in laws and/or regulations, higher than expected costs and/or the discovery of new or additional contamination. As part of our estimating process, we develop a range of reasonably possible alternate scenarios which include the high end of a range of reasonably possible cost estimates for all remediation sites for which we have sufficient information based on our experience and existing laws and regulations. There are some potential remediation obligations where the costs of remediation cannot be reasonably estimated. At March 31, 2013 and December 31, 2012, the high end of the estimated range of reasonably possible remediation costs exceeded our recorded liabilities by $857 and $865.
Product Warranties
The following table summarizes product warranty activity recorded during the three months ended March 31, 2013 and 2012.
 
2013

 
2012

Beginning balance – January 1

$1,572

 

$1,046

Additions for current year deliveries
63

 
109

Reductions for payments made
(129
)
 
(66
)
Changes in estimates
1

 
(6
)
Ending balance - March 31

$1,507

 

$1,083


Commercial Aircraft Commitments
In conjunction with signing definitive agreements for the sale of new aircraft (Sale Aircraft), we have entered into trade-in commitments with certain customers that give them the right to trade in used aircraft at a specified price upon the purchase of Sale Aircraft. The probability that trade-in commitments will be exercised is determined by using both quantitative information from valuation sources and qualitative information from other sources. The probability of exercise is assessed quarterly, or as events trigger a change, and takes into consideration the current economic and airline industry environments. Trade-in commitments, which can be terminated by mutual consent with the customer, may be exercised only during the period specified in the agreement, and require advance notice by the customer.
Trade-in commitment agreements at March 31, 2013 have expiration dates from 2013 through 2023. At March 31, 2013, and December 31, 2012 total contractual trade-in commitments were $1,620 and $1,535. As of March 31, 2013 and December 31, 2012, we estimated that it was probable we would be obligated to perform on certain of these commitments with net amounts payable to customers totaling $173 and $108 and the fair value of the related trade-in aircraft was $173 and $108.
Financing Commitments
Financing commitments related to aircraft on order, including options and those proposed in sales campaigns, totaled $17,714 and $18,083 as of March 31, 2013 and December 31, 2012. The estimated earliest potential funding dates for these commitments as of March 31, 2013 are as follows:
  
Total

April through December 2013

$935

2014
2,841

2015
3,977

2016
3,283

2017
3,064

Thereafter
3,614

 

$17,714


As of March 31, 2013, $16,640 of these financing commitments related to customers we believe have less than investment-grade credit. We have concluded that no reserve for future potential losses is required for these financing commitments based upon the terms, such as collateralization and interest rates, under which funding would be provided.
Standby Letters of Credit and Surety Bonds
We have entered into standby letters of credit and surety bonds with financial institutions primarily relating to the guarantee of our future performance on certain contracts. Contingent liabilities on outstanding letters of credit agreements and surety bonds aggregated approximately $4,443 and $4,545 as of March 31, 2013 and December 31, 2012.
Commitments to ULA
We and Lockheed Martin Corporation have each committed to provide ULA with up to $527 of additional capital contributions in the event ULA does not have sufficient funds to make a required payment to us under an inventory supply agreement. See Note 5.
C-17
At March 31, 2013, our backlog included 3 C-17 aircraft under contract with the U.S. Air Force (USAF) and an international order for 9 C-17 aircraft. We are currently producing C-17 aircraft at a rate of 10 per year. Should additional orders not materialize, it is reasonably possible that we will decide in 2013 to end production of the C-17 at a future date. We are still evaluating the full financial impact of a potential production shutdown, including pension curtailment charges, and any recovery that would be available from the U.S. government. Such recovery from the U.S. government would not include the costs incurred by us resulting from our direction to suppliers to begin working on aircraft beyond those currently under contract. At March 31, 2013, we had approximately $410 of inventory expenditures and potential termination liabilities to suppliers associated with 12 aircraft for international customers not currently under contract.
U.S. Government Defense Budget/Sequestration
In August 2011, the Budget Control Act (The Act) reduced the United States defense top line budget by approximately $490 billion through 2021. The Act further reduced the defense top line budget by an additional $500 billion through 2021 if Congress did not enact $1.2 trillion in further budget reductions by January 15, 2012. Should Congress in future years provide funding above the yearly spending limits of The Act, sequestration will automatically take effect and cancel any excess amount above the limits. The annual spending limits of The Act will remain in place until current law is changed.
On March 1, 2013, sequestration was implemented for the U.S. government fiscal year 2013 (FY2013), canceling $42.7 billion of planned U.S. defense budgetary spending. The Office of Management and Budget (OMB) subsequently issued a report to Congress listing illustrative cuts which equal a 7.8% reduction in FY2013 non-exempt defense discretionary funding and a 5.0% reduction in non-exempt nondefense discretionary funding. However, as noted in the OMB report, the effective reduction in funds would be approximately 13% for non-exempt defense programs and 9% for non-exempt nondefense programs if implemented over the seven-month period from March 1, 2013 to September 30, 2013.
While the OMB report and other communications with the United States Department of Defense (U.S. DoD) indicate that there would likely be reductions to our defense business, the U.S. DoD is in the process of identifying specific program and contract reductions required by the FY2013 sequestration order. As such, at this time we cannot determine how sequestration will impact the Company's specific programs and contracts. Any reductions, cancellations or delays impacting existing contracts or programs could have a material effect on our results of operations, financial position and/or cash flows.

BDS Fixed-Price Development Contracts
Fixed-price development work is inherently uncertain and subject to significant variability in estimates of the cost and time required to complete the work. BDS fixed-price contracts with significant development work include Airborne Early Warning and Control, Family of Advanced Beyond Line-of-Sight Terminals, India P-8I, Saudi Arabia F-15, USAF KC-46A Tanker and commercial and military satellites. The operational and technical complexities of these contracts create financial risk, which could trigger termination provisions, order cancellations or other financially significant exposure. Changes to cost and revenue estimates could also result in lower margins or a material charge for reach-forward losses during the next 12 months.
747 and 787 Commercial Airplane Programs
The development and initial production of new commercial airplanes and new commercial airplane derivatives, which include the 747 and 787, entail significant commitments to customers and suppliers as well as substantial investments in working capital, infrastructure and research and development. The 747 and 787 programs have gross margins that are breakeven or near breakeven at March 31, 2013.
Continued weakness in the air cargo market and lower-than-expected demand for large commercial passenger aircraft have resulted in pricing pressures and fewer 747 orders than anticipated. While we received additional orders for aircraft in the first quarter of 2013, we continue to have a number of unsold Freighter and Intercontinental production positions beyond 2013. If we are unable to obtain orders for multiple Freighter aircraft in 2013 consistent with our near-term production plans, we may be required to take actions including further reducing the production rate and/or building airplanes for which we have not received firm orders. If market and production risks cannot be mitigated, the program could face an additional reach-forward loss that may be material.
The cumulative impacts of production challenges, change incorporation, schedule delays and customer and supplier impacts have created significant pressure on 787 program profitability. If risks related to this program, including risks associated with change incorporation, the battery incidents and associated regulatory directives, planned production rate increases, or introducing the 787-9 derivative as scheduled cannot be mitigated, the program could face additional customer claims and/or supplier assertions, as well as a reach-forward loss that may be material.