Operating Leases

 

On May 3, 2018, the Company entered into a sublease for 5,104 square feet of space for its corporate offices and laboratory space in Cambridge Massachusetts (the “Cambridge Lease”). The Cambridge Lease commenced on May 3, 2018 and expires October 31, 2023 with no renewal options.  The Cambridge Lease contains rent holiday and rent escalation clauses.

 

In connection with the Cambridge Lease, a standby letter of credit was established for $40 thousand. On November 1, 2018, the standby letter of credit was increased to $60 thousand. Under the Cambridge Lease, the Company will be required to pay its proportionate share of certain operating costs and property taxes applicable to the leased premises in excess of new base year amounts. These costs are considered to be variable lease payments and are not included in the determination of the lease’s right-of-use asset or lease liability.

The Company identified and assessed the following significant assumptions in recognizing its right-of-use assets and corresponding lease liabilities:

·

As the Company’s Cambridge Lease does not provide an implicit rate, the Company estimated the incremental borrowing rate in calculating the present value of the lease payments. The Company has estimated its incremental borrowing rate based on electing the remaining lease term as of the adoption date.

·

Since the Company elected to account for each lease component and its associated non-lease components as a single combined component, all contract consideration was allocated to the combined lease component.

·

The expected lease terms include noncancelable lease periods.

The elements of lease expense are as follows:

 

 

 

 

 

 

 

 

Year Ended December 31, 

 

Lease cost (In thousands)

2020

 

2019

 

Operating lease cost

$

364

 

$

364

 

Short-term lease cost

 

21

 

 

33

 

Variable lease cost

 

139

 

 

63

 

Total lease cost

$

524

 

$

460

 

 

 

 

 

 

 

 

Other information (In thousands)

 

 

 

 

 

 

Cash paid for amounts included in the measurement of lease liabilities:

 

 

 

 

 

 

Operating cash flows from short term leases

$

21

 

$

33

 

Operating cash flows from operating leases

 

375

 

 

243

 

Total cash paid for leases

$

396

 

$

276

 

Weighted-average remaining lease term - operating leases

 

2.83 Years

 

 

3.84 Years

 

Weighted-average discount rate - operating leases

 

7.0%

 

 

7.0%

 

 

Maturities of lease liabilities due under the Company’s Cambridge Lease as of December 31, 2020 is as follows:

 

 

 

 

 

Leases (In thousands)

As of December 31, 2020

    

2021

$

386

 

2022

 

398

 

2023

 

339

 

Total lease payments

 

1,123

 

Less: imputed interest

 

(103)

 

Present value of lease liabilities

$

1,020

 

 

 

 

 

 

 

 

 

 

 

Leases (In thousands)

 

Classification

    

December 31, 2020

 

December 31, 2019

Assets

 

 

 

 

 

 

 

 

Lease asset, net

 

Operating

 

$

928

 

$

1,211

Total lease assets

 

 

 

$

928

 

$

1,211

 

 

 

 

 

 

 

 

 

Liabilities

 

 

 

 

 

 

 

 

Current

 

Operating

 

$

327

 

$

294

Non-current

 

Operating

 

 

693

 

 

1,020

Total lease liabilities

 

 

 

$

1,020

 

$

1,314

 

Clinical Trial Commitments

The Company has engaged and executed contracts with clinical research organizations (“CROs”) to assist with the administration of its ongoing INSPIRE 1.0 and INSPIRE 2.0 clinical trials. As of December 31, 2020, approximately $4.5 million remains to be paid on these contracts. The timelines and related costs necessary to complete these trials may vary depending on a number of factors including the rate of patient enrollment into our INSPIRE 2.0 trial. In the event the Company were to terminate the INSPIRE 2.0 trial, certain financial penalties would become payable to the CROs for costs to wind down the terminated trial.