Commitments and Contingencies Commitments and Contingencies
We lease certain facilities and pipelines under operating leases and finance leases, most of which contain renewal options. These operating leases have various termination dates through 2041. See Note 5 for a schedule of annual minimum undiscounted lease payments under our leases as of December 31, 2022. As of December 31, 2022, we expect to receive aggregate payments totaling $0.8 million over the life of our noncancelable sublease of office space, expiring in 2026.
We also have other long-term contractual obligations consisting of long-term site service agreements with HF Sinclair, expiring in 2058 through 2066, for the provision of certain facility services and utility costs that relate to our assets located at HF Sinclair’s refinery and renewable diesel facilities. We are presenting obligations for the full term of these agreements; however, the agreements can be terminated with 180 day notice if we cease to operate the applicable assets.
In addition, we have long-term contractual obligations associated with rights-of-way agreements, which have various termination dates through 2099. The related payments below include only obligations under the remaining non-cancelable terms of these agreements at December 31, 2022.
At December 31, 2022, these minimum future contractual obligations and other miscellaneous obligations having terms in excess of one year are as follows:
        
Years Ending December 31,(In thousands)
2023$8,856 
20248,803 
20257,030 
20265,944 
20275,943 
Thereafter214,367 
Total$250,943 
We are a party to various legal and regulatory proceedings, none of which we believe will have a material adverse impact on our financial condition, results of operations or cash flows.