XML 18 R9.htm IDEA: XBRL DOCUMENT v3.20.1
ASSET RETIREMENT OBLIGATIONS
3 Months Ended
Mar. 31, 2020
ASSET RETIREMENT OBLIGATIONS  
ASSET RETIREMENT OBLIGATIONS

NOTE 4 — ASSET RETIREMENT OBLIGATIONS

 

Asset retirement obligations (“ARO”) arise from the acquisition, development, construction and normal operation of mining property, plant and equipment due to government controls that protect the environment, and are primarily related to closure and reclamation of mining properties.  The exact nature of environmental issues and costs, if any, which the Company or the LLC may encounter in the future are subject to change, primarily because of the changing character of environmental requirements that may be enacted by governmental authorities.

 

The following table shows asset retirement obligations for future mine closure and reclamation costs in connection with the Mt. Hope Project and within the boundaries of the Plan of Operations (“PoO”):

 

 

 

 

 

 

 

 

(in thousands)

 

At January 1, 2019

 

$

1,633

 

Accretion Expense

 

 

108

 

Adjustments*

 

 

62

 

At December 31, 2019

 

$

1,803

 

Accretion Expense

 

 

27

 

Adjustments*

 

 

 —

 

At March 31, 2020

 

$

1,830

 


*Includes additions, annual changes to the escalation rate, the market-risk premium rate, or reclamation time periods.

 

The estimated future reclamation costs for the Mt. Hope Project have been discounted using a rate of 8%,  which is the rate that existed at the time the liability was originally measured.  The total inflated and undiscounted estimated reclamation costs associated with current disturbance under the PoO at the Mt. Hope Project were $5.8 million at March 31, 2020, inclusive of $2.6 million for mitigation of sage grouse habitat that would be affected by development of the Mt. Hope Project.  Increases in ARO liabilities resulting from the passage of time are recognized as accretion expense.

 

As of March 31, 2020, the LLC had provided the appropriate regulatory authorities with $2.8 million in reclamation financial guarantees through the posting of surety bonds for reclamation of the Mt. Hope Project as approved in the ROD.  As of March 31, 2020, we had $0.3 million in cash deposits associated with these bonds which are specific to the PoO disturbance and recorded in Restricted cash and investments held for reclamation bonds and are unrelated to the inflated and undiscounted liability referenced above.  The LLC posted an additional $0.3 million as a cash bond with the BLM in April 2019 as a result of a required three-year update to the reclamation bond calculation.

 

The LLC has a smaller liability at the Mt. Hope Project for disturbance associated with exploration drilling which occurred outside the PoO boundaries.  The LLC has not discounted this reclamation liability as the total amount is approximately $0.2 million.

 

Total restricted cash for surety bond collateral requirements and other long-term reclamation obligations at the Mt. Hope Project equal $0.6 million.  Another $0.1 million in cash collateral is associated with surety bonds at the Liberty Project.

 

The Company’s Liberty Project is currently in the exploration stage. As the Company is not currently performing any exploration activity at the Liberty Project, the reclamation liability incurred for historical disturbance from previous operations and more recent exploration conducted by the Company of approximately $0.1 million has not been discounted as shown in the table below.

 

 

 

 

 

 

 

 

 

    

Mt. Hope Project

    

 

 

 

 

 

outside PoO

 

 

 

 

 

 

boundary

 

Liberty

 

 

 

(in thousands)

 

At January 1, 2019

 

$

15

 

$

121

 

Adjustments *

 

 

 2

 

 

13

 

At December 31, 2019

 

$

17

 

$

134

 

Adjustments *

 

 

 —

 

 

20

 

At March 31, 2020

 

$

17

 

$

154

 


*Includes reduced / reclaimed disturbance