LIQUIDITY
12 Months Ended
Dec. 31, 2017
LIQUIDITY.  
LIQUIDITY

NOTE 2 — LIQUIDITY

 

The cash needs for the development of the Mt. Hope Project are significant and require that we and/or the LLC arrange for financing to be combined with funds anticipated to be received from POS-Minerals in order to retain its 20% membership interest.  If we are unsuccessful in obtaining financing, we will not be able to proceed with the development of the Mt. Hope Project.

 

Although hampered by the slowly recovering low molybdenum prices, the Company continues its efforts to obtain full financing of the Mt. Hope Project.  As evidenced with the Tranche 2 close under the amended AMER Investment Agreement, AMER continues its support and agreement to work with the Company to procure a Bank Loan of approximately $700 million from a major Chinese bank or banks for the development of the Mt. Hope Project, and to provide a guarantee for the Bank Loan.  As discussed in Note 1, on November 30, 2015, the Company announced the receipt of funds to successfully close the first tranche of the amended Investment Agreement, resulting in a $4 million cash inflow to the Company. 

 

Additionally, as discussed in Note 1 above, on October 16, 2017, the Company and AMER announced the closure of the second tranche of the parties’ three-tranche financing agreement, resulting in a $6.0 million cash inflow to the Company.  The equity sale proceeds of $5.5 million are available for general corporate purposes, while $0.5 million will be held in the loan procurement account to cover costs related to the Mt. Hope Project financing and other jointly sourced business development opportunities. Based on our current operating forecast, and the combination of the liquidity provided by the closure of Tranche 2 under the AMER Investment Agreement and our current cash on hand, the Company expects to be able to fund its operations and meet its financial obligations into the second quarter of 2019.  However, there can be no assurance that the Company will be successful in achieving its forecast.

 

There is no assurance that the Company will be successful in obtaining the financing required to complete the Mt. Hope Project, or in raising additional financing in the future on terms acceptable to the Company, or at all. 

 

We continue to work with our long-lead vendors to manage the timing of contractual payments for milling equipment.  The following table sets forth the LLC’s remaining cash commitments under these equipment contracts (collectively, “Purchase Contracts”) at December 31, 2017 (in millions):

 

 

 

 

 

 

 

    

As of

 

 

 

December 31,

 

Year

 

2017 *

 

2018

 

$

 

2019

 

 

1.4

 

2020

 

 

0.4

 

Total

 

$

1.8

 


* All amounts are commitments of the LLC, and as a result of the agreement between Nevada Moly and POS-Minerals are to be funded by the reserve account, now $9.9 million as discussed above in Note 1, until such time that the Company obtains financing for its portion of construction costs at the Mt. Hope Project or until the reserve account balance is exhausted, and thereafter are to be funded 80% by Nevada Moly and 20% by POS-Minerals. POS-Minerals remains obligated to make capital contributions for its 20% portion of equipment payments required by approved budgets of the LLC, and such amounts contributed by the reserve account on behalf of POS-Minerals will reduce, dollar for dollar, the amount of capital contributions that the LLC is required to return to POS-Minerals, as described under Note 1 above.

 

If the LLC does not make the payments contractually required under these purchase contracts, it could be subject to claims for breach of contract or to cancellation of the respective purchase contract.  In addition, the LLC may proceed to selectively suspend, cancel or attempt to renegotiate additional purchase contracts if necessary to further conserve cash.  If the LLC cancels or breaches any contracts, the LLC will take all appropriate action to minimize any losses, but could be subject to liability under the contracts or applicable law.  The cancellation of certain key contracts could cause a delay in the commencement of operations, and could add to the cost to develop the Company’s interest in the Mt. Hope Project.

 

Through December 31, 2017, the LLC has made deposits and/or final payments of $87.9 million on equipment orders.  Of these deposits, $70.4 million relate to fully fabricated items, primarily milling equipment, for which the LLC has additional contractual commitments of $1.8 million noted in the table above.  The remaining $17.5 million reflects both partially fabricated milling equipment, and non-refundable deposits on mining equipment.  As discussed in Note 12, the mining equipment agreements remain cancellable with no further liability to the LLC. The underlying value and recoverability of these deposits and our mining properties in our consolidated balance sheets are dependent on the LLC’s ability to fund development activities that would lead to profitable production and positive cash flow from operations, or proceeds from the sale of these assets. There can be no assurance that the LLC will be successful in generating future profitable operations, selling these assets or that the Company will secure additional funding in the future on terms acceptable to us or at all.  Our consolidated financial statements do not include any adjustments relating to recoverability and classification of recorded assets or liabilities.

 

With our cash conservation plan, our Corporate and Liberty related cash requirements are estimated to decline to approximately $1.3 million per quarter in 2018, while all Mt. Hope Project related funding is payable out of the $36.0 million reserve account, the balance of which was $9.9 million and $13.0 million at December 31, 2017 and 2016, respectively.  Accordingly, based on our current cash on hand and our ongoing cash conservation plan, the Company expects it will have adequate liquidity in order to fund our working capital needs into the second quarter of 2019.  Additional potential funding sources include public or private equity offerings, including closing or a negotiated acceleration of tranche 3 with respect to the remaining $10.0 million investment from AMER described in Note 1, or sale of other assets owned by the Company.  There is no assurance that the Company will be successful in securing additional funding.  This could result in further cost reductions, contract cancellations, and potential delays which ultimately may jeopardize the development of the Mt. Hope Project.