Equipment and Supply Procurement        
Amount committed to be purchased       $ 2.2
Number of primary transformers | instrument       2
Number of ball mills | instrument       2
Eureka Moly LLC | Mt. Hope Project        
Equipment and Supply Procurement        
Aggregate amount of equipment orders       $ 87.4
Development costs       199.0
Total amount spend for Mt. Hope project inception-to-date       $ 286.4
Purchase Commitment | Eureka Moly LLC | Haul trucks        
Equipment and Supply Procurement        
Nonrefundable down payment     $ 1.2  
Number ordered | item     18  
Purchase Commitment | Eureka Moly LLC | Mine production drills        
Equipment and Supply Procurement        
Nonrefundable down payment     $ 0.4  
Number ordered | item     4  
Purchase Commitment | Eureka Moly LLC | Electric shovels        
Equipment and Supply Procurement        
Nonrefundable down payment $ 3.4      
Number ordered | item   2