NOTE 12 — COMMITMENTS AND CONTINGENCIES

 

Mt. Hope Project

 

The Mt. Hope Project is owned/leased and will be operated by the LLC under the LLC Agreement.  The LLC currently has a lease (“Mt. Hope Lease”) with Mount Hope Mines, Inc. (“MHMI”) for a period of 30 years from October 19, 2005 and for so long thereafter as operations are being conducted on the property.  The lease may be terminated earlier at the election of the LLC, or upon a material breach of the agreement and failure to cure such breach.  If the LLC terminates the lease, termination is effective 30 days after receipt by MHMI of written notice to terminate the Mt. Hope Lease and no further payments would be due to MHMI.  If MHMI terminates the lease, termination is effective upon receipt of a notice of termination due to a material breach, representation, warranty, covenant or term contained in the Mt. Hope Lease and followed by failure to cure such breach within 90 days of receipt of a notice of default.  MHMI may also elect to terminate the Mt. Hope Lease if the LLC has not cured the non-payment of obligations under the lease within 10 days of receipt of a notice of default.  In order to maintain the Lease Agreement, the LLC must pay certain minimum advance royalties as discussed below.

 

The Mt. Hope Lease requires a royalty advance (“Construction Royalty Advance”) of 3% of certain construction capital costs, as defined in the Mt. Hope Lease.  The LLC is obligated to pay a portion of the Construction Royalty Advance each time capital is raised for the Mt. Hope Project based on 3% of the expected capital to be used for those certain construction capital costs defined in the Mt. Hope Lease.  Through March 31, 2017, we have paid $24.6 million of the total royalty advance.  Based on our Mt. Hope Project capital budget we estimate that a final reconciliation payment on the Capital Construction Cost Estimate (the “Estimate”) will be due following the commencement of commercial production, after as-built costs are definitively determined.  The Company estimates, based on the revised capital estimate discussed above and the current timeline for the commencement of commercial production, that an additional $4.2 million will be due approximately 20 — 24 months after the commencement of construction.  This amount was accrued as of March 31, 2017.  The capital estimates may be subject to escalation in the event the Company experiences continued delays in achieving full financing for the Mt. Hope Project.

 

The LLC is also obligated to make a minimum annual advance royalty payment (“Annual Advance Royalty”) of $0.5 million each October 19 for any year wherein commercial production has not been achieved or the MHMI Production Royalty (as hereinafter defined) is less than $0.5 million.  As commercial production is not anticipated to commence before late-2019, the Company has accrued $1.5 million in Annual Advance Royalty payments which will be due in three $0.5 million installments in October 2017, 2018, and 2019, respectively.  The Estimate and the Annual Advance Royalty are collectively referred to as the “Advance Royalties.”  All Advance Royalties are credited against the MHMI Production Royalties once the mine has achieved commercial production.  After the mine begins production, the LLC estimates that the MHMI Production Royalties will be in excess of the Annual Advance Royalties for the life of the Mt. Hope Project.  Until the advance royalties are fully credited, the LLC will pay one half of the calculated Production Royalty annually.  Assuming a $12 molybdenum price, the Annual Advance Royalties will be consumed within the first five years of commercial production.

 

Deposits on project property, plant and equipment

 

As discussed in Note 2, the LLC has active orders with varying stages of fabrication on milling process equipment comprised of two 230kV primary transformers and substation, a primary crusher, a semi-autogenous mill, two ball mills, and various motors for the mills with remaining cash commitments of $2.2 million due on these orders. 

 

Equipment and Supply Procurement

 

Through March 31, 2017, the LLC has made deposits and/or final payments of $87.4 million on equipment orders and has spent approximately $199.0 million for the development of the Mt. Hope Project, for a total Mt. Hope Project inception-to-date spend of $286.4 million.

 

In 2012, the LLC issued a firm purchase order for eighteen haul trucks.  The order provides for delivery of those haul trucks required to perform initial mine development, which will begin several months prior to commercial production.  Non-refundable down-payments of $1.2 million were made in 2012, with pricing subject to escalation as the trucks were not delivered prior to December 31, 2013.  Since that time, the LLC has renegotiated the timelines for truck delivery and delayed deliveries into December 2017.  The contract is cancellable with no further liability to the LLC.

 

Also in 2012, the LLC issued a firm purchase order for four mine production drills with a non-refundable down-payment of $0.4 million, and pricing was subject to escalation if the drills were not delivered by the end of 2013.  Since that time, the LLC accepted a change order which delayed delivery into December 2017.  The contract remains cancellable with no further liability to the LLC.

 

On June 30, 2012, the LLC’s contract to purchase two electric shovels expired.  On July 11, 2012, we signed a letter of intent with the same vendor providing for the opportunity to purchase the electric shovels at prices consistent with the expired contract, less a special discount in the amount of $3.4 million to provide credit to the LLC for amounts paid as deposits under the expired contract.  The letter of intent provides that equipment pricing will remain subject to inflation indexes and guarantees production slots to ensure that the equipment is available when required by the LLC.  Since that time, the parties agreed to extend the letter of intent through December 31, 2018.

 

Obligations under capital and operating leases

 

We have contractual operating leases that will require a total of $62,000 in payments over the next three years.  Operating leases consist primarily of rents on office facilities and office equipment.  Our expected payments are $62,000, nil, and nil for the years ended December 31, 2017, 2018, and 2019, respectively.

 

Creation of Agricultural Sustainability Trust

 

On August 19, 2010, the LLC entered into an agreement with the Eureka Producers’ Cooperative (“EPC”) whereby the LLC will fund a $4.0 million Sustainability Trust (“Trust”) in exchange for the cooperation of the EPC with respect to the LLC’s water rights and permitting of the Mt. Hope Project.  The Trust will be tasked with developing and implementing programs that will serve to enhance the sustainability and well-being of the agricultural economy in the Diamond Valley Hydrographic Basin through reduced water consumption.

 

The Trust may be funded by the LLC over several years based on the achievement of certain milestones, which are considered probable, and as such $4.0 million has been accrued in the Company’s financial statements and is included in mining properties, land, and water rights.

 

Permitting Considerations

 

In the ordinary course of business, mining companies are required to seek governmental permits for expansion of existing operations or for the commencement of new operations. The LLC was required to obtain approval, in the form of a Record of Decision (“ROD”), from the BLM to implement the Mt. Hope Project Plan of Operations (“PoO”).  The LLC was also required to obtain various state and federal permits including, but not limited to, water protection, air quality, water rights and reclamation permits.  In addition to requiring permits for the development of the Mt. Hope Project, we will need to obtain and modify various mining and environmental permits during the life of the Mt. Hope Project.  Maintaining, modifying, and renewing the necessary governmental permits is a complex and time-consuming process involving numerous jurisdictions and often involving public hearings and substantial expenditures.  The duration and success of the LLC’s efforts to obtain, modify or renew permits will be contingent upon many variables, some of which are not within the LLC’s control.  Increased costs or delays could occur, depending on the nature of the activity to be permitted and the interpretation of applicable requirements implemented by the permitting authority.  All necessary permits may not be obtained and, if obtained, may not be renewed, or the costs involved in each case may exceed those that we previously estimated.  In addition, it is possible that compliance with such permits may result in additional costs and delays.

 

On November 16, 2012, the BLM issued its ROD authorizing development of the Mt. Hope Project.  On April 23, 2015, the BLM issued a Finding of No Significant Impact (“FONSI”) supporting their Decision to approve an amendment to the PoO.  The ROD and FONSI/Decision approve the PoO and amended PoO, respectively, for construction and operation of the mining and processing facilities and also grant the Right-of-Way, and amended Right-of-Way, respectively, for a 230kV power transmission line, discussed below.  Monitoring and mitigation measures identified in the ROD and FONSI, developed in collaboration with the regulatory agencies involved throughout the permitting process, will avoid, minimize, and mitigate environmental impacts, and reflect the Company’s commitment to be good stewards of the environment.  Ongoing changes to permits and the PoO during the life of mining operations are typical as design evolves and operations are optimized.

 

 

On February 15, 2013, Great Basin Resource Watch and the Western Shoshone Defense Project (“Plaintiffs”) filed a Complaint against the U.S. Department of the Interior and the BLM (“Defendants”) in the U.S. District Court, District of Nevada, seeking relief under the National Environmental Policy Act (“NEPA”) and other federal laws challenging the BLM’s issuance of the ROD for the Mt. Hope Project, and on February 20, 2013 filed a Motion for Preliminary Injunction.  The District Court allowed the LLC to intervene in the matter.

 

On August 22, 2013, the District Court denied, without prejudice, Plaintiffs’ Motion for Preliminary Injunction based on a Joint Stipulation to Continue Preliminary Injunction Oral Argument, which advised the District Court that as a result of economic conditions, including the Company’s ongoing financing efforts, all major ground disturbing activities had ceased at the Mt. Hope Project.

 

On July 23, 2014, the District Court denied Plaintiffs’ motion for summary judgment in its entirety and on August 1, 2014 the Court entered judgment in favor of the Defendants and the LLC, and against Plaintiffs regarding all claims raised in the Complaint. 

 

Thereafter, on September 22, 2014, the Plaintiffs filed their notice of appeal to the U.S. Court of Appeals for the Ninth Circuit (“Ninth Circuit”) of the U.S. District Court’s dismissal.  Oral argument of the parties before the Ninth Circuit was completed on October 18, 2016.  On December 28, 2016, the Ninth Circuit issued its Opinion rejecting many of the arguments raised by the Plaintiffs challenging the Environmental Impact Statement ("EIS") completed for the Mt. Hope Project, issuing a narrow reversal of the BLM's findings related to air quality analysis. Because of this technical deficiency, the Court vacated the ROD, and the BLM is conducting additional evaluation of air quality impacts and resulting cumulative impact analysis under the National Environmental Policy Act (“NEPA”) through a supplemental EIS to address the concerns noted by the Ninth Circuit.  The Company is confident in the BLM’s process and working closely with the agency to resolve concerns with air quality baseline studies raised by the Ninth Circuit. To resolve the issues identified by the Ninth Circuit, BLM has determined that a Supplemental Environmental Impact Statement (“SEIS”) will be prepared.  The SEIS would disclose additional information to the public related to the selection of appropriate background concentrations to use for dispersion modeling of air pollutants.  Because the SEIS must be prepared in accordance with the NEPA guidelines, the SEIS process will include three publications in the Federal Register, each of which may take several weeks to process.  The first of these publications is the Notice of Intent (“NOI”) which declares the BLM’s intent to prepare the SEIS.  We anticipate that the NOI will be published in the Federal Register in May or June 2017, and look forward to completing the necessary public review to receive a new ROD for the eventual construction and operation of the Mt. Hope Project. 

 

Environmental regulations related to reclamation require that the cost for a third party contractor to perform reclamation activities on the minesite be estimated.  In October 2015, we submitted a request to the BLM to reduce our reclamation liability to current surface disturbance.  Simultaneously, we submitted an application to NDEP-BMRR to modify the Reclamation Permit to reflect this reduced reclamation liability. On October 26, 2015, NDEP-BMRR approved the proposed permit modification, including the reduced reclamation liability amount.   On December 21, 2015, BLM approved the updated reclamation liability estimate, reducing of the reclamation liability to approximately $2.8 million.  We worked with the LLC’s reclamation surety underwriters to satisfy the reduced $2.8 million financial guarantee requirements under the approved amended PoO for the Mt. Hope Project.  As of March 31, 2017, the surety bond program is funded with a cash collateral payment of $0.3 million.

 

Water Rights Considerations

 

In July 2011 and June 2012, respectively, the Nevada State Engineer (“State Engineer”) granted all water permits and approved a Monitoring, Management and Mitigation Plan (“3M Plan”) for the Mt. Hope Project.  Eureka County, Nevada and two other parties comprised of water rights holders in Diamond Valley and Kobeh Valley appealed the State Engineer’s decision granting the water permits to the Nevada State District Court (“District Court”) and then filed a further appeal to the Nevada Supreme Court challenging the District Court’s decision affirming the State Engineer’s decision to grant the water permits.  In June 2013, the appeal was consolidated by the Nevada Supreme Court with an appeal of the State Engineer’s approval of the 3M Plan filed by two water rights holders.  The District Court previously upheld the State Engineer’s approval of the 3M Plan and the two parties subsequently appealed the District Court’s decision to the Nevada Supreme Court.  While the appeals were pending, the 3M Plan had been implemented to collect information on background conditions and aquifer responses to the Mt. Hope Project’s pumping, as well as to address mitigation measures for impacted third-party water rights.

 

On September 18, 2015, the Nevada Supreme Court issued an Order that reversed and remanded the cases to the District Court for further proceedings consistent with the Order.  On October 29, 2015, the Nevada Supreme Court issued the Order as a published Opinion.  The Nevada Supreme Court ruled that the State Engineer did not have sufficient evidence in the record at the time he granted the water permits to demonstrate that successful mitigation may be undertaken so as to dispel the threat to existing water rights holders.

 

On November 23, 2015, the Nevada Supreme Court issued its Remittitur to the District Court for the County of Eureka for further proceedings consistent with its Opinion.  On March 14, 2016, we received the District Court’s Order vacating the 3M Plan, denying the applications and vacating the permits issued by the State Engineer.  The Company filed a Motion to Alter or Amend Judgment with the District Court, requesting the District Court amend its Order and remand the water permits and 3M Plan to the State Engineer to allow further proceedings to address the mitigation issues raised by the Nevada Supreme Court.  The District Court denied the Motion on June 1, 2016.  The State Engineer has filed an appeal to the Nevada Supreme Court concerning the District Court’s interpretation of the Supreme Court’s Opinion and has also argued that the District Court acted in excess of its judicial authority in violation of Nevada’s Constitution and Statutes.  The Company has filed a similar appeal to the Nevada Supreme Court.    The Nevada Supreme Court has ordered Oral Argument to occur on May 1, 2017.

 

Notwithstanding the pendency of the appeal to the Nevada Supreme Court, the Company is working, as expeditiously as possible, to reobtain its water permits with the new change applications that it has filed with the State Engineer, following the Nevada Supreme Court’s September Order.  On August 23, 2016, Eureka County filed a Writ of Prohibition or Mandamus to the Nevada Supreme Court seeking the Supreme Court’s intervention to stop further action by the State Engineer while the appeal discussed above of the District Court Order is pending.  As ordered by the Supreme Court, answers and responses to the Writ were filed by October 21, 2016.  The State Engineer has stopped any action on our applications pending an outcome of the Writ from the Supreme Court.  Along with the State Engineer, we oppose the basis for filing the Writ, and believe the State Engineer can proceed with the review of our applications notwithstanding the appeal to the Supreme Court of the District Court Order.  In the interim, we are continuing to advocate the authority of the State Engineer to act on our applications.  In hearings to be held before the State Engineer, the Company will provide additional evidence of its ability to successfully mitigate any potential impacts to water rights in Kobeh Valley that could result from the Mt. Hope Project’s new change applications for water use.

 

Environmental Considerations

 

Our mineral property holdings in Shoshone County, Idaho include lands contained in mining districts that have been designated as a “Superfund Site” pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act.  This “Superfund Site” was established to investigate and remediate primarily the Bunker Hill properties of Smelterville, Idaho, a small portion of Shoshone County where a large smelter was located.  However, because of the extent of environmental impact caused by the historical mining in the mining district, the Superfund Site covers the majority of Shoshone County including our Chicago-London and Little Pine Creek properties as well as many small towns located in Northern Idaho.  We have conducted a property environmental investigation of these properties, which revealed no evidence of material adverse environmental effects at either property.  We are unaware of any pending action or proceeding relating to any regulatory matters that would affect our financial position due to these inactive mining claims in Shoshone County.