XML 56 R43.htm IDEA: XBRL DOCUMENT v3.3.1.900
Property and Equipment (Details)
12 Months Ended
Oct. 31, 2015
USD ($)
bu
Oct. 31, 2014
USD ($)
Oct. 31, 2013
USD ($)
Property, Plant and Equipment [Abstract]      
Property, Plant and Equipment [Table Text Block]
Property and equipment are stated at cost. Depreciation is provided over the following estimated useful lives by use of the straight-line method.
Asset Description
Years
Land improvements
5-20 years
Railroad improvements
5-20 years
Process equipment and tanks
5-15 years
Administration building
10-30 years
Office equipment
5-10 years
Rolling stock
5-15 years
A summary of property and equipment:
 
 
October 31, 2015
 
October 31, 2014
Land and improvements
 
$
13,348,732

 
$
12,307,063

Railroad improvements
 
8,005,523

 
8,005,523

Process equipment and tanks
 
123,405,024

 
113,602,431

Administration building
 
907,652

 
1,015,361

Office equipment
 
569,328

 
265,792

Rolling stock
 
1,777,863

 
1,834,026

Construction in progress
 
2,013,765

 
7,109,796

 
 
150,027,887

 
144,139,992

Less: accumulated depreciation
 
65,723,725

 
56,111,647

Net property and equipment
 
$
84,304,162

 
$
88,028,345

   
Property, Plant and Equipment Disclosure [Text Block]
PROPERTY AND EQUIPMENT

A summary of property and equipment:
 
 
October 31, 2015
 
October 31, 2014
Land and improvements
 
$
13,348,732

 
$
12,307,063

Railroad improvements
 
8,005,523

 
8,005,523

Process equipment and tanks
 
123,405,024

 
113,602,431

Administration building
 
907,652

 
1,015,361

Office equipment
 
569,328

 
265,792

Rolling stock
 
1,777,863

 
1,834,026

Construction in progress
 
2,013,765

 
7,109,796

 
 
150,027,887

 
144,139,992

Less: accumulated depreciation
 
65,723,725

 
56,111,647

Net property and equipment
 
$
84,304,162

 
$
88,028,345



Depreciation expense totaled approximately $9,612,000, $9,209,000, and $5,937,000 for the fiscal years ended October 31, 2015, 2014, and 2013, respectively.

Construction in Progress

On April 8, 2015, GFE executed a construction agreement with an unrelated contractor to construct an additional 750,000 bushel grain storage bin. The grain storage expansion project is expected to cost approximately $2.7 million and is expected to be completed during the first half of our 2016 fiscal year.

On July 31, 2015, HLBE placed a purchase order with an unrelated party for a new regenerative thermal oxidizer and made a down payment of approximately $375,000 to secure the order. The total commitment approximates $1.9 million and is expected to be completed during the latter part of fiscal year 2016.
   
Property, Plant and Equipment [Line Items]      
Depreciation $ 9,612,000 $ 9,209,000 $ 5,937,000
Land and Land Improvements 13,348,732 12,307,063  
Railroad Improvements 8,005,523 8,005,523  
Machinery and Equipment, Gross 123,405,024 113,602,431  
Furniture and Fixtures, Gross 569,328 265,792  
Vehicles 1,777,863 1,834,026  
Administration building 907,652 1,015,361  
Construction in Progress, Gross 2,013,765 7,109,796  
Property, Plant and Equipment, Gross 150,027,887 144,139,992  
Accumulated Depreciation, Depletion and Amortization, Property, Plant, and Equipment 65,723,725 56,111,647  
Property, Plant and Equipment, Net $ 84,304,162 $ 88,028,345  
Grain Storage [Member] | Granite Falls Energy, LLC [Member]      
Property, Plant and Equipment [Line Items]      
Construction in Process, Bushels | bu 750,000    
Construction in Progress, Gross $ 2,700,000    
Regenerative Thermal Oxidizer [Member] | Heron Lake BioEnergy, LLC [Member]      
Property, Plant and Equipment [Line Items]      
Construction in Progress, Gross 1,900,000    
Payments for Construction in Process $ 375,000