Operating Leases

The Company leases manufacturing and office space and equipment under various lease agreements which expire at various dates through March 2020. Rental expenses were $1,404, $1,350, and $1,200, for the years ended June 30, 2014, 2013, and 2012, respectively.

Future minimum lease payments under the agreements as of June 30, 2014 are as follows (in thousands):
 
2015
$
1,141

2016
760

2017
467

2018
460

2019
460

Thereafter
345

 
$
3,633



Amounts payable under the Company’s Texas production facility lease are included in the amounts above. A portion of those rent payments may reduce the deferred grant incentive liability rather than being recorded as expense. See Note 12 for additional information.





Construction of New Headquarters

On June 11, 2014, the Company entered into a Redevelopment Agreement, a Design-Build Contract, and a Development Services Agreement (as defined below) as well as various ancillary agreements related to the acquisition of real property located in New Brighton, Minnesota and the development of such property into the Company’s new corporate headquarters.
Pursuant to that certain Contract for Private Redevelopment by and among the City of New Brighton (the “City”), Ryan Companies US, Inc. (“Ryan”), and the Company, dated June 11, 2014 (the “Redevelopment Agreement”), the Company purchased approximately ten acres of real property from the City for a purchase price of $500. The City also granted the Company the option to purchase an additional 3.6 acres prior to May 31, 2021 pursuant to certain terms set forth in the Redevelopment Agreement.

Pursuant to that certain Design-Build Cost Plus Construction Contract by and between Ryan and the Company, dated June 11, 2014, the Company has contracted with Ryan to furnish all services, labor, materials, equipment, procurement services, project management and other duties and services necessary for construction of the Company’s new headquarters on the land purchased from the City. The Company and Ryan expect to have construction substantially completed by March 1, 2015, and, pursuant to the Redevelopment Agreement discussed above, Ryan and the Company have agreed to complete construction by December 31, 2015. The Company will pay Ryan a fee of 3.85% of the cost of the work.

The Company also entered into a Development Services Agreement with Ryan, dated June 11, 2014, pursuant to which Ryan will perform certain development services to facilitate development of the project, including coordination with the City and overall coordinate of development strategy. The Company will pay Ryan a fee for the development services, which includes a sum equal to 3.25% of the adjusted total project costs, payable at certain points in the construction process and a sum equal to 5% of the adjusted total project costs, payable upon substantial completion of the project, as well as reimbursement of certain expenses incurred by Ryan.

In connection with the agreements above, the Company was required to hold approximately $9,128 in an escrow account which will be used to fund the final construction payments. The escrow is classified as construction in progress in property and equipment, net, on the consolidated balance sheet.