RANDGOLD POSTS NEW PRODUCTION RECORD, SPEEDS UP EXPLORATION DRIVE

 

London, 5 November 2015 Randgold Resources boosted production to a new record level in the third quarter of the year on the back of a steady all-round operational performance while stepping up exploration programmes designed to find its next world-class discovery as well as to expand its existing reserves.

 

Gold production for the quarter was 305 288 ounces, up more than 5 000 ounces on Q2, with Kibali and Morila doing exceptionally well. Heavy rains in Mali resulted in a pump system failure at Loulo, which temporarily cut off access to the high grade ore sections underground at Yalea. This resulted in lower than forecast grades and production, impacting on total cash cost per ounce, which rose to $699/oz (Q2: $684/oz). A further drop in the gold price also depressed profits, which were $48.8 million against the previous quarter’s $59.2 million.

 

Chief executive Mark Bristow said considering that the gold price had declined by 6% over this period to its lowest point since the first quarter of 2010, Randgold’s profit performance continued to be creditable. He noted that the company remained debt-free, with net cash increasing significantly from $109 million to $168 million, further strengthening its balance sheet.

 

During the quarter, Tongon paid back the last of its shareholders’ loans of $448 million, and can now start paying dividends, Kibali repaid another tranche of its shareholders’ loans and Gounkoto declared a dividend of $11 million, bringing its total for the year to date to $51.7 million. Kibali remains on track to exceed its full-year production guidance of 600 000 ounces and the group as a whole is expected to be within its guidance range.

 

Bristow said the group’s intensified exploration drive was producing positive results across the board, and in the new field season its generative team would be chasing opportunities to expand its footprint in its West and Central African target areas.

 

“Key developments to date have been the good results from Sofia in Senegal, which have significantly enhanced the prospects of our Massawa project, the ongoing brownfields drilling at Gara and Yalea, the extension of resources and reserves around the Gounkoto and Tongon orebodies, and our improved understanding of the controls and styles of mineralisation across the Kibali permit, which I believe will deliver substantial additional resources,” he said.

 

“In the fourth quarter we’ll be putting a big effort into our highly prospective holdings in Côte d’Ivoire, with a VTEM survey scheduled across the Boundiali and Makono permits in the north of the country. We’ll also be progressing the due diligence study on our Obuasi opportunity.”

 

Bristow said despite the state of the gold market Randgold continued to invest in its structured sustainability programmes, designed in line with its philosophy that mining companies had a moral obligation to put part of the value of the orebodies they exploit back into the creation of sustainable economic activities for the local communities.

 

These initiatives included the development of an agribusiness training centre between Loulo and Gounkoto, officially inaugurated last week, the establishment of microfinance businesses at all Randgold’s operations, completed feasibility studies on an agribusiness at Morila and a large-scale palm oil business at Kibali, and an entrepreneur training programme, also at Kibali.

 

“The gold mining industry is severely stressed and Randgold is certainly not immune to the pressure. Relative to our peers, however, we are still doing well. We have a proven strategy against which we constantly test our businesses, and we are relentless in our drive to deliver on our plans,” he said.

 

RANDGOLD ENQUIRIES:

Chief Executive

Mark Bristow

+44 788 071 1386

+44 779 775 2288

Financial Director

Graham Shuttleworth

+44 1534 735 333

+44 779 771 1338

Investor & Media Relations

Kathy du Plessis

+44 20 7557 7738

Email: randgold@dpapr.com

 

Website: www.randgoldresources.com

 

 

 

 

 

REPORT FOR THE THIRD QUARTER ENDED 30 SEPTEMBER 2015

Randgold Resources Limited (‘Randgold’) had 93.2 million shares in issue as at 30 September 2015.

 

Key Performance Indicators

§Another record gold production quarter
§Cash cost per ounce up slightly quarter on quarter, in line with corresponding quarter of prior year
§Profit down due to lower average grade and gold price received
§Increase in cash from operations strengthens balance sheet
§Good performance by Loulo-Gounkoto despite operational challenges
§Kibali on track to beat 600 000oz full year guidance
§Morila continues to deliver on plan and advances Domba project
§Tongon improves all-round operational performance and repays shareholder loans
§Exploration team plans regional VTEM survey in Côte d’Ivoire and gears up for new field season
§Positive drill results from Sofia point to additional potential at Massawa

 

SUMMARISED FINANCIAL INFORMATION

$000 

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Average gold price received ($/oz)   1 122    1 189    1 277    1 174    1 288 
Gold sales1   340 723    354 776    376 796    1 040 131    1 094 933 
Total cash costs1   212 300    204 012    204 140    617 087    589 163 
Profit from mining activity1   128 423    150 764    172 656    423 044    505 770 
Exploration and corporate expenditure   9 791    12 992    8 897    31 460    33 284 
Profit for the period   48 761    59 173    66 032    159 248    216 781 
Profit attributable to equity shareholders   42 345    53 601    58 008    144 149    185 351 
Net cash generated from operations   109 678    71 446    125 149    282 844    248 289 
Cash and cash equivalents2   168 434    109 249    63 424    168 434    63 424 
Gold on hand at period end3   12 812    11 688    11 993    12 812    11 993 
Group production (oz)   305 288    300 039    299 320    884 858    860 366  
Group sales1 (oz)   303 718    298 421    295 018    885 763    850 410 
Group total cash cost per ounce1 ($)   699    684    692    697    693 
Group cash operating cost per ounce1 ($)   643    627    632    642    630 
Basic earnings per share ($)   0.45    0.58    0.63    1.55    2.00 
1Refer to explanation of non-GAAP measures provided. Randgold consolidates 100% of Loulo, Gounkoto and Tongon, 40% of Morila and 45% of Kibali in the consolidated non-GAAP measures.
2Cash and cash equivalents excludes $8.3 million of cash at 30 September 2015 (an overdraft of $0.2 million at 30 September 2014 and $16.7 million of cash at 30 June 2015) that relates to the group’s attributable cash held in Morila, Kibali and the group’s asset leasing companies which are equity accounted.
3Gold on hand represents gold in doré at the mines (attributable share) multiplied by the prevailing spot gold price at the end of the period.

The results in this report have been neither reviewed nor audited. All financial numbers are in US dollars ($) unless otherwise stated.

 

COMMENTS

Gold sales for the quarter of $340.7 million decreased by 4% compared to the previous quarter, on the back of a 6% drop in the average gold price received of $1 122/oz (Q2 2015: $1 189/oz). This was partially offset by the increased gold production quarter on quarter, following another record quarter of

 

 

 

 

production for the group. The increase in gold production resulted from an increase in ounces sold at the Loulo complex, due to improved recoveries quarter on quarter, as well as at Tongon, driven by increased throughput, grade and recovery.

 

Compared to the corresponding quarter of 2014, gold sales were down 10% as a result of a 12% decrease in the average gold price received (Q3 2014: $1 277/oz), partially offset by the increase in the number of ounces sold.

 

Total cash costs for the quarter of $212.3 million were up 4% compared with the previous quarter, as well as with the corresponding quarter in 2014, in line with the increased throughput. Total cash costs increased at Gounkoto, where additional stripping was undertaken during the rainy season, and at Tongon and Kibali as a result of additional throughput. Total cash cost per ounce was slightly up from the previous quarter, mainly due to lower grades and production at Kibali and Morila, and in line with the corresponding quarter of 2014.

 

Profit from mining was down 15% quarter on quarter and by 26% from the corresponding quarter of 2014, due to the drop in gold prices received as well as increased cash costs, as described above.

 

Exploration and corporate expenditure of $9.8 million for the current quarter decreased by 25% from the previous quarter due to decreased exploration fieldwork and drilling activity, in line with plan for the rainy season in West Africa. Expenditure increased by 10% compared to the corresponding quarter in 2014, in line with a relative increase in exploration activity.

 

Depreciation and amortisation of $39.4 million decreased by 8% against the previous quarter and was in line with the corresponding quarter in 2014, reflecting revisions made to estimates associated with the unit of production calculations.

 

Other income of $6.7 million increased by 76% from the previous quarter’s $3.8 million and by 429% from the corresponding quarter in 2014 of $1.3 million. Other income includes management fees from Morila and Kibali. Other income also includes operational exchange gains. These arise from the settlement of invoices in currencies other than the US dollar, as well as the translation of balances denominated in currencies such as South African rand, Canadian dollar and the euro to the US dollar rate and reflect movements in these currencies during the quarter.

 

Share of profits from equity joint ventures decreased by $20.2 million from the previous quarter and by $4.4 million from the corresponding quarter in 2014, to $13.4 million. The decrease quarter on quarter is the result of reduced production and profits at Kibali during the quarter, as a result of a planned drop in grade and recovery. In addition, profits from Morila decreased quarter on quarter in line with production at the mine.

 

Income tax expenses of $8.6 million decreased by 33% quarter on quarter and by 37% from the corresponding quarter in 2014. The decrease from the prior quarter is in line with lower profitability at the Loulo complex.

 

Basic earnings per share dropped 22% to $0.45 (Q2 2015: $0.58) quarter on quarter, and by 29% from the corresponding quarter in 2014, following the movements in profit mentioned above.

 

OPERATIONS

 

LOULO-GOUNKOTO COMPLEX

The combined quarterly gold production for the Loulo-Gounkoto complex was 162 246oz (Loulo 93 202oz and Gounkoto 69 044oz), an increase of 4% compared to the previous quarter (Q2 2015: 155 989oz). Tonnes processed during the quarter decreased slightly by 1% to 1 140kt (Q2 2015: 1 148kt), while the head grade milled was in line at 4.8g/t. Recoveries improved significantly by 3% to 91.4%, resulting in a decrease in total cash cost per ounce to $683/oz (Q2 2015: $686/oz) following the increase in ounces produced.

 

The significant increase in plant recovery resulted from additional interventions by management, including the implementation of improved blending based on advanced bottle roll recovery prediction, similar to advanced grade control. Laboratory test work was conducted on each individual ore source to predict recoveries ahead of mining. A recovery committee consisting of geologists, metallurgists and miners is

 

 

 

 

actively working to build a geo-metallurgical database to improve our understanding of the orebodies. Yalea orebodies previously defined in two areas (inside and outside the Purple Patch) were revisited and requalified into five distinct domains based on copper and arsenic threshold. Composites were collected to conduct offsite test work to better understand the metallurgical response. Two technical audits were also conducted during the quarter, on the gravity circuit and to identify gaps to enhance plant performance.

 

LOULO-GOUNKOTO COMPLEX RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   8 208    7 779    7 301    22 912    20 101 
Ore tonnes mined (000)   1 019    1 203    1 018    3 410    3 454 
Milling                         
Tonnes processed (000)   1 140    1 148    1 091    3 358    3 321 
Head grade milled (g/t)   4.8    4.8    5.1    4.6    5.2 
Recovery (%)   91.4    88.8    90.4    89.5    90.4 
Ounces produced   162 246    155 989    160 285    447 468    503 090 
Ounces sold   160 156    154 737    158 047    449 314    498 238 
Average price received ($/oz)   1 121    1 187    1 278    1 172    1 287 
Cash operating costs1 ($/oz)   615    615    599    641    570 
Total cash costs1 ($/oz)   683    686    675    712    647 
Gold on hand at period end2 ($000)   6 987    4 897    5 901    6 987    5 901 
Profit from mining activity1 ($000)   70 201    77 600    95 263    206 882    318 930 
Gold sales1 ($000)   179 520    183 709    201 994    526 574    641 094 
1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

LOULO

One LTI was recorded during the quarter with an LTIFR of 0.69 per million hours worked versus 1.42 recorded in the previous quarter. No major environmental incident or social grievance occurred this quarter. A legal environmental audit showed that the mine is compliant with national legal requirements. The other requirements, which the mine has subscribed to, will be audited in Q4. A microfinance business was opened during the quarter in order to reinforce local economic development.

 

On a standalone basis, Loulo produced 93 202oz of gold (Q2 2015: 97 460oz) at a total cash cost of $750/oz (Q2 2015: $730/oz). The decrease in production was due to a 3% decrease in tonnes processed, a 4% decrease in head grade milled and partially offset by a 2.6% improvement in recoveries, following an increased focus on the ore blend and proactive adjustment of reagents according to the ore feed ratio.

 

Profit from mining of $34.2 million was 22% lower than the previous quarter of $43.9 million, reflecting the lower gold production and gold sales, increased cost of production resulting from the lower head grade milled and lower average gold price received.

 

LOULO STANDALONE RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   630    667    713    1 989    2 141 
Ore tonnes mined (000)   616    642    693    1 930    2 036 
Milling                         
Tonnes processed (000)   680    702    714    1 983    1 948 
Head grade milled (g/t)   4.7    4.9    5.1    4.6    5.1 
Recovery (%)   91.4    88.8    90.4    89.5    90.4 
Ounces produced   93 202    97 460    105 238    261 728    288 299 
Ounces sold   92 379    96 196    103 195    263 952    285 073 
Average price received ($/oz)   1 121    1 187    1 277    1 173    1 287 
Cash operating costs1 ($/oz)   683    659    593    701    606 
Total cash costs1 ($/oz)   750    730    670    771    683 
Gold on hand at period end2 ($000)   3 967    3 206    3 924    3 967    3 924 
Profit from mining activity1 ($000)   34 243    43 939    62 653    105 896    172 026 
Gold sales1 ($000)   103 541    114 192    131 787    309 509    366 760 

 

 

 

 

Randgold owns 80% of Société des Mines de Loulo SA (Loulo) and the State of Mali 20%. Randgold has funded the whole investment in Loulo by way of shareholder loans and therefore controls 100% of the cash flows from Loulo until the shareholder loans are repaid.

Randgold consolidates 100% of Loulo and shows the non-controlling interest separately.

1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

Loulo underground

Loulo underground production for the quarter was slightly lower than the previous quarter, hoisting 330 681 tonnes at Yalea and 285 182 tonnes at Gara. At the same time, development metres decreased at Yalea due to lower plant availability and flooding of the decline after pump failures following a particularly heavy rainy period. This impacted the mine’s ability to deliver the higher grade ore feed that had been planned for the quarter. In Gara the development was 6% ahead of plan in line with the strategy of building flexibility ahead of the transition to owner mining.

 

The transition to owner mining continued according to plan, including the completion of the labour structure and associated recruitment of employees. 22 items of the new Sandvik fleet of equipment have arrived on site; 8 TH663 trucks, 7 LH621 loaders, 3 solos and 4 jumbos, with 3 loaders and 2 trucks already having been introduced in production.

 

A vendor management supply chain has been established in conjunction with Sandvik, and 80% of the spares and consumables are now available on site.

 

UNDERGROUND RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
YALEA                         
Ore tonnes mined   330 681    358 231    414 139    1 073 276    1 212 996 
Development metres   2 043    2 381    2 260    6 708    7 115 
GARA                         
Ore tonnes mined   285 182    284 010    279 051    856 946    554 914 
Development metres   2 356    2 374    1 410    6 740    5 712 

 

GOUNKOTO

No LTI was recorded during the quarter or year to date. No major environmental incident or social grievance was recorded in the reported period.

 

On a standalone basis, Gounkoto produced 69 044oz of gold (Q2 2015: 58 529oz) at a total cash cost per ounce of $590/oz (Q2 2015: $612/oz). The increase in production was due to a 3% increase in tonnes processed, 11% increase in head grade milled as planned and a 2.8% increase in recoveries. The stripping ratio at Gounkoto increased to 17.8, in line with the plan to build flexibility and access to ore during the rainy season, which partially offsets the cost benefits of the increased production.

 

Profit from mining activity for the quarter of $36.0 million was higher than the previous quarter (Q2 2015: $33.7 million), reflecting the higher gold production and gold sold at a lower cash cost of production, partially offset by a lower average gold price received.

 

 

 

 

GOUNKOTO STANDALONE RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   7 578    7 112    6 588    20 922    17 960 
Ore tonnes mined (000)   403    561    325    1 480    1 419 
Milling                         
Tonnes processed (000)   460    447    376    1 375    1 373 
Head grade milled (g/t)   5.1    4.6    5.0    4.7    5.4 
Recovery (%)   91.5    88.7    90.4    89.4    90.3 
Ounces produced   69 044    58 529    55 047    185 741    214 790 
Ounces sold   67 777    58 540    54 852    185 361    213 165 
Average price received ($/oz)   1 121    1 188    1 280    1 171    1 287 
Cash operating costs1 ($/oz)   523    541    609    556    521 
Total cash costs1 ($/oz)   590    612    685    626    598 
Gold on hand at period end2 ($000)   3 020    1 691    1 977    3 020    1 977 
Profit from mining activity1 ($000)   35 958    33 661    32 610    100 986    146 904 
Gold sales1 ($000)   75 979    69 517    70 207    217 065    274 333 

Randgold owns 80% of Société des Mines de Gounkoto SA (Gounkoto) and the State of Mali 20%. Randgold consolidates 100% of Gounkoto and shows the non-controlling interest separately.

1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

Agribusiness project

The development of an agri-training centre at Loulo-Gounkoto continued during the quarter as part of the agribusiness project, with a number of key milestones achieved:

§Construction of the training centre and ancillary buildings completed
§100 students recruited, as well as a coordinator and facilitator
§2 500 chickens received by the poultry section
§Centre inaugurated at the end of October 2015.

 

The project is targeting the following:

§Achieve a 75% conversion rate of motivated and skilled farming entrepreneurs
§Achieve a 25% conversion rate of competent agricultural engineers, managers, and technicians
§Create 50 farms of at least 5 hectares (250 hectares)
§Create at least 12 direct jobs per farm or 600 direct jobs in the local communities
§Create hundreds of seasonal and indirect jobs throughout the value chain
§Contribute towards economic growth and rural development as per SDDR action plans
§Create attractive job opportunities as alternatives to artisanal mining
§Serve as a model for agricultural development for multi-nationals
§Meet community food demand and start exporting by 2019.

 

MORILA

No LTI was recorded during the quarter or year to date. No major environmental incident or social grievance occurred during the quarter. The environmental and social impact assessment of the Domba project indicated dust and noise to be serious issues and the mine’s proposed measures to mitigate these have been approved by the inter-ministerial committee. The feasibility assessment of the agribusiness project was completed during the quarter.

 

The mine’s production was in line with plan, although down on last quarter at 18 735oz, on the back of lower grade ore feed. In line with the drop in grade, the recovery also decreased from 91.1% to 90.3%. However, the plant throughput of 797kt for the quarter increased by 9% on the previous quarter. Total cash costs increased to $861/oz (Q2 2015: $594/oz) on the back of the lower production. Preparation for the Domba project continued during the quarter. The feasibility report for the project has been submitted to the government, and the mine is expecting to obtain authorisation for the immediate start of the project with first delivery of ore to the plant expected in Q4 2015. Mining the Domba pit is expected to add an additional three months of higher grade ore.

 

The TSF de-capping was affected by a temporary shortfall of water from both the river and pit pumping systems, hence the operation was running with a single hydraulic reclamation station. A total of 1 157kt of de-capped material was delivered to the pit at an average grade of 0.21g/t. The high grade slurry pumping installation is underway in preparation of the reprocessing of the TSF material in the plant.

 

 

 

 

During the quarter a World Bank project team delegation and a Rural Development Ministry technical team visited the agribusiness projects and infrastructures along the water pipeline. The draft feasibility report on the agribusiness project has been presented as part of the closure plan.

 

Capital expenditure for the mine for the quarter amounted to $0.4 million (100%).

 

MORILA RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   -    -    4 766    3 425    13 633 
Ore tonnes mined (000)   -    -    463    939    672 
Milling                         
Tonnes processed (000)   797    733    922    2 247    2 370 
Head grade milled (g/t)   0.8    1.7    1.0    1.6    1.1 
Recovery (%)   90.3    91.1    87.4    91.3    89.7 
Ounces produced   18 735    35 341    24 712    104 992    73 899 
Ounces sold   18 735    36 560    24 712    104 992    73 899 
Average price received ($/oz)   1 116    1 157    1 274    1 182    1 288 
Cash operating costs1 ($/oz)   794    565    1 462    587    1 190 
Total cash costs1 ($/oz)   861    594    1 489    610    1 234 
Profit from mining activity1 ($000)   4 772    20 564    (5 321)   60 019    4 012 
Attributable (40%)                         
Gold sales1 ($000)   8 363    16 914    12 594    49 640    38 070 
Ounces produced   7 494    14 136    9 885    41 997    29 560 
Ounces sold   7 494    14 624    9 885    41 997    29 560 
Profit from mining activity1 ($000)   1 909    8 226    (2 128)   24 008    1 605 
Gold on hand at period end2 ($000)   -    -    -    -    - 

Randgold owns 40% of Société des Mines de Morila SA (Morila) with the State of Mali and joint venture partner owning 20% and 40% respectively. The group equity accounts for its 40% joint venture holding in Morila.

1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

TONGON

No LTI was recorded during the quarter compared to two LTIs in the previous quarter. No major environmental incident or social grievance occurred during the quarter. The mine has started the feasibility assessment of its agribusiness project together with the Government.

 

Tongon produced 63 519oz of gold in Q3 2015, 16% higher than the previous quarter, primarily as a result of a 10% increase in tonnes processed. Recovery continues to show an upward trend quarter on quarter with a further 1.8% improvement achieved in Q3 as a result of further stabilisation of the new Rougher Flotation Circuit. Optimising the mass pull and concentrate grade from the Rougher and Scavenger cells and improvement in the Ultra-Fine-Grind (UFG) operation is expected to improve recovery further.

 

Total cash cost per ounce decreased to $850/oz (Q2 2015: $941/oz) on the back of the higher throughput, increased grade and recovery, leading to increased production.

 

Tongon’s power supply continued to be impacted in July by CIE grid power supply reductions and a step up of CIE power outages experienced as a result of the unavailability of sufficient gas and hydro resources to power up the national grid. Supply returned to the targeted 97:3 ratio of grid to generated power by the end of September as increased rainfall restored hydro capacity to the grid. Increased communication between the government, CIE national supply authority and Tongon continued in Q3 to ensure grid utilisation is increased and smooth synchronisation during extended planned power outage periods is achieved.

 

Total mined tonnes increased by 3% compared to Q2, mainly as a result of continued mining in the planned cutbacks in the South Zone pit and ramping up mining of softer, free dig oxides and transitional

 

 

 

 

material in the North Zone pit as per plan. Mining costs were well contained and have decreased further quarter on quarter.

 

The additional 4th Stage Hydrocone Crushing installation, required to produce a finer sized crusher product to achieve design mill throughput, is on track for Phase 1 commissioning in Q4 2015. In conjunction with the crusher supplier, the mine has completed the designs for the crushing circuit at the tail end of the total crushing plant, completed the excavations and earthworks and progressed well with all long lead items procured.

 

Profit from mining activity increased by 29% to $17.2 million, reflecting the higher sales and lower costs, partially offset by the lower average gold price received.

 

Tongon mine received the President of Côte d’Ivoire Award for the best operating mine for the second year running. In addition, the mine completed repayment of its shareholder loans at the end of Q3.

 

TONGON RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   7 700    7 479    6 431    21 572    19 412 
Ore tonnes mined (000)   896    674    958    2 536    2 629 
Milling                         
Tonnes processed (000)   1 034    941    1 038    2 986    3 042 
Head grade milled (g/t)   2.3    2.2    2.4    2.2    2.3 
Recovery (%)   83.9    82.4    78.8    82.2    77.3 
Ounces produced   63 519    54 685    63 832    175 475    170 740 
Ounces sold   63 254    53 708    63 960    173 033    170 538 
Average price received ($/oz)   1 122    1 189    1 270    1 172    1 286 
Cash operating costs1 ($/oz)   816    905    761    826    854 
Total cash costs1 ($/oz)   850    941    799    861    892 
Gold on hand at period end2 ($000)   2 667    2 554    128    2 667    128 
Profit from mining activity1 ($000)   17 239    13 352    30 159    53 745    67 158 
Gold sales1 ($000)   70 996    63 881    81 241    202 760    219 327 

Randgold owns 89% of Société des Mines de Tongon SA (Tongon) with the State of Côte d’Ivoire and outside shareholders owning 10% and 1% respectively. Randgold has funded the whole investment in Tongon by way of shareholder loans and therefore controls 100% of the cash flows from Tongon until the shareholder loans are repaid. The shareholder loans have been repaid at 30 September 2015. Randgold consolidates 100% of Tongon and shows the non-controlling interest separately.

1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

KIBALI

There were two LTIs recorded at Kibali during the quarter, with a corresponding LTIFR of 0.73 compared with zero LTIs in Q2. The mine passed the Stage 1 ISO 14001 audit and no major environmental incident or social grievance occurred. The mine’s energy efficiency has increased this quarter on the back of the improved hydropower performance. The mine has completed its feasibility study for a large scale palm oil business.

 

Kibali produced 160 065oz in Q3, a decrease of 4% compared to the prior quarter, following the planned 12% drop in head grade milled, partially offset by increased throughput. The increased throughput reflected the continued steady operation of the plant with increases in plant availability. The 1% drop in recoveries reflected the change in ore feed, including additional transitional material from the Mengu Hill pit. Total cash costs for the quarter increased on the back of lower gold production from $553/oz in Q2 to $634/oz in the current quarter.

 

Profit from mining activity decreased to $79.3 million in the current quarter, in line with the lower production, higher costs and lower average gold price received.

 

Kibali started a local economic development programme with its communities during the quarter, with approximately $0.5 million spent on stimulating sustainable business initiatives and entrepreneur training.

 

 

 

 

KIBALI RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Mining                         
Tonnes mined (000)   7 806    7 995    7 930    24 496    20 842 
Ore tonnes mined (000)   1 569    1 635    1 331    4 934    3 849 
Milling                         
Tonnes processed (000)   1 830    1 667    1 485    5 109    3 913 
Head grade milled (g/t)   3.3    3.7    4.0    3.5    3.6 
Recovery (%)   83.0    84.0    77.0    84.2    77.8 
Ounces produced   160 065    167 174    145 152    488 707    348 838 
Ounces sold   161 807    167 450    140 279    492 042    337 944 
Average price received ($/oz)   1 124    1 198    1 283    1 179    1 292 
Cash operating costs1 ($/oz)   586    507    513    553    540 
Total cash costs1 ($/oz)   634    553    557    599    586 
Profit from mining activity1 ($000)   79 271    108 018    101 798    285 649    238 617 
Attributable (45%)                         
Gold sales1 ($000)   81 843    90 273    80 969    261 157    196 430 
Ounces produced   72 029    75 228    65 318    219 918    156 977 
Ounces sold   72 813    75 353    63 126    221 419    152 075 
Gold on hand at period end2 ($000)   3 158    4 237    5 964    3 158    5 964 
Profit from mining activity1 ($000)   35 672    48 608    45 809    128 542    107 378 

Randgold owns 45% of Kibali Goldmines SPRL (Kibali) with the DRC State and joint venture partner owning 10% and 45% respectively. The group equity accounts for its 45% joint venture holding in Kibali.

1Refer to explanation of non-GAAP measures provided.
2Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period.

 

Construction of the metallurgical facility and infrastructure

In order to facilitate the increase in sulphide ore treatment from 2016 onwards, a concentrate de-sliming cyclone circuit providing more capacity at the UFG circuit was commissioned during the quarter. The first phase of the new lined tailings storage facility was also completed during Q3, providing capacity for 2016 CIL tailings deposition. The first phase of Ambarau, the second hydropower station, was completed and commissioning is currently in progress.

 

Declines

Total ore produced from underground operations decreased from Q2 but remains above the plan for the year, with sufficient stopes available to allow for the increased production planned for Q4 2015. Development remains on track with plan. The paste plant is now operating according to plan, with the first two stopes successfully backfilled.

 

KIBALI UNDERGROUND DECLINE RESULTS

  

Quarter

ended

30 Sep

2015

  

Quarter

ended

30 Jun

2015

  

Quarter

ended

30 Sep

2014

  

9 months

ended

30 Sep

2015

  

9 months

ended

30 Sep

2014

 
Ore tonnes mined   169 647    207 490    24 715    515 178    27 558 
Development metres   2 698    2 619    2 066    7 789    5 526 

 

Vertical shaft

Shaft sinking was completed in July 2015 and the remainder of Q3 focused on equipping the shaft, with the programme currently 15 days ahead of schedule. The next milestone for Q4 2015 will be the completion of the equipping from lode level to crusher level and the swinging down of the equipment for the off-shaft development.

 

 

 

KIBALI VERTICAL SHAFT RESULTS

  

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Vertical metres   39    6    149    45    479 
Off shaft development   98    298    152    734    282 

 

Capital expenditure

Capital expenditure for the project for the quarter amounted to $55.5 million (at 100%). The Phase 2 capital estimate of the project remains in line with previous guidance.

 

EXPLORATION ACTIVITIES

 

The group has continued with its exploration programme this quarter, notwithstanding the West African wet season which makes access to most exploration projects difficult. Eight drill rigs have been active across the portfolio, testing a range of greenfields and brownfields targets. The Sofia target in Senegal has returned strong intersections as the team progresses the Massawa feasibility study with further modelling and metallurgical sampling of the Central Zone ore. In the Loulo district, ongoing drilling at Gara continues to confirm the potential for the addition of significant resources to replace mining depletion. Meanwhile, exploration on satellite targets around all our mines is being fast tracked to provide the operations with added flexibility in this low gold price environment. A good example of this is the completion of the Domba grade control programme at Morila. We have completed the gradient array IP survey over the Fonondara/Sani corridor in the Boundiali permit in Côte d’Ivoire, greatly assisting further interpretation and paving the way for the large airborne VTEM survey which will be flown over the highly prospective Boundiali belt margin in Q4 2015. At Kibali, an extensive re-logging programme across the KCD deposit is highlighting upside at the margins of the ore lodes and exploration work this quarter has returned positive results from the Tete Bakangwe and Sessenge SW targets.

 

The company continues the drive to advance its understanding of the district scale structures which control the location of world class orebodies and, as part of this project, we have become a major sponsor of Amira’s West African Exploration Initiative programme this quarter in addition to continuing our own in-house research.

 

MALI

Loulo project

Seven exploration holes for 6 353m have been completed in the southern exploration area at Gara. Drill results received to date show the mineralisation has an average true width of 5.86m and a weighted average grade of 5.09g/t, which is in line with the Gara reserve currently being mined. Infill drilling continues on this target with the aim of establishing an inferred resource in 2015. Separately, conversion drilling at depth in the central portion of Gara has concluded with the completion of seven holes for a total of 6 852m. The mineralised system has been confirmed in terms of lithology and alteration, however the tenor and continuity of mineralisation is lower than expected, particularly in the north of the conversion area.

 

The greenfields focus during the quarter has largely shifted to the assessment of additional resource potential across the Loulo permit to provide the mining operation with further flexibility. A number of existing satellites have been reviewed (P125-Loulo 3 Gap, Baboto North and South, Loulo 2 South, Loulo 3, and Loulo 1) and exploration work this quarter has focused on the priority advancement of the Yalea Ridge South and Gara South targets which are not currently in resource. Drilling on these targets is scheduled for Q4 2015.

 

Gounkoto project

Following the conclusion of underground feasibility drilling at MZ1 in Q2, results of exploration and grade control drilling have been used to update the geological model in flitch and section to use as a basis for a revised resource model for Gounkoto MZ1 to MZ4 and P64E. At P64W, re-logging in detail for lithology, alteration and structure continues with the aim to update the geological model on which a revised resource estimate will be based, using results of recent advanced grade control drilling.

 

As with Loulo, the greenfields focus during the quarter has largely shifted to the assessment of additional resource potential across the Gounkoto permit. Drilling was scheduled at Toronto for October to test oxide potential at intersections of the Faraba structure with cross cutting NE chlorite-sericite shears. Trenching at Gounkoto North early in Q3, returned an intercept of 3.7m at 1.44g/t (31.7m), including 1.2m

 

 

 

 

at 3.94g/t (GNWTR02) from a heterolithic breccia with silica-carbonate veinlets, and this programme will resume after the wet season.

 

Mali exploration

Field work on the Mali exploration properties was paused during the wet season. Geological interpretations, prospectivity studies and target generation work were carried out. The work programme at Bakolobi now focuses on the definition of targets along the identified mineralised structures for drill testing as well as eliminating untested targets lying beneath thick transported cover which cannot be transgressed by traditional surface exploration methods such as pitting and trenching. At the Legend JV, on the Souroukoto East target, 8 of the 12 pits excavated late in Q2 2015 at the Souroukoto East target confirmed the continuity over 600m strike length of in-situ gold anomalism within a 30m wide alteration zone with values of 0.16g/t to 11.3g/t in sheared greywackes with silica-carbonate-hematite alteration.

 

Morila

During the quarter the grade control drilling for the Domba deposit at 10 x 15m spacing was completed. The results of the programme are being integrated into an updated model and drill intersections indicate that an increase in grade, compared to the existing model, is possible.

 

SENEGAL

Massawa

At Sofia, five RC holes were completed to eliminate supergene enrichment as a possible cause of high grades seen in the south of the deposit. Three of the five holes returned strong results for the main zone sulphide ore with a weighted average intersection of 31m at 4.7g/t (true width) confirming a hypogene source for the high grade mineralisation. The main ore zone is hosted in a strongly sheared gabbro and felsic intrusive units with silica flooding and carbonate-sericite alteration.

 

The results confirm the extension of the main ore zone over a 650m strike length and up to 100m vertical depth. Potential exists along strike to the north of the area drilled this quarter where the main zone may extend and forms a priority target for further work in Q4 2015.

 

Bottle roll leach test work on 11 Sofia fresh rock ore samples completed during the quarter show gold recoveries between 86% and 95%, with the main ore zone showing recoveries above 90%, confirming that Sofia is a non-refractory ore source on the permit with good potential to increase the grade of the existing inferred resource of 736 000oz at 1.7g/t.

 

At Massawa Central Zone (CZ) three test work programmes were initiated during the quarter as part of the ongoing feasibility study and results are expected in Q4. These include multi-element analysis of the ore, a gold deportment study on BLEG residues to help understand the variable leach gold recoveries along the orebody and detailed CIL and gravity test-work of mainly high grade ore samples from the drill orientation area. A new block model for the orientation area was completed during the quarter, further indicated that the CZ will ultimately contain fewer tonnes at a higher grade than the existing Massawa model. The modelling of the remaining CZ ore and lithologies is still in progress.

 

CÔTE D’IVOIRE

At Nielle, the team has spent the quarter re-logging core from the deposit and creating an updated model incorporating recent grade control and exploration drilling results. This has resulted in a larger $1 000/oz pit optimisation and the identification of a number of opportunities on footwall structures which are only widely drilled compared to the main ore zones.

 

The Tongon satellites and the low grade near-mine prospects have been reviewed during the quarter and an infill drilling programme on the two most advanced satellites of Sekala and Seydou South is planned for Q4 2015. This drilling phase aims to confirm whether infill drilling increases the grade and tonnage of the deposits, as we have seen at Tongon. All satellites have a similar anastomosing form to Tongon. Greenfields fieldwork was paused during the wet season.

 

On the Boundiali permit, the encouraging results from the Fonondara drilling reported previously (16.53m at 3.83g/t including 7.40m at 5.88g/t and 8.83m at 28.62g/t including 4.10m at 61.05g/t) have demonstrated the prospectivity of the permit and outlined the controls of the significant surface anomalism along the Boundiali belt margin which hosts a number of existing targets. The subsequent reconnaissance diamond drilling undertaken at the Sani target (9km north of Fonondara) has confirmed a wide and consistent low grade system with best results received from SNDH003: 54.41m at 1.21g/t (from 132.84m) including 9.45m at 3.28g/t within a +200m wide anomalous zone. Mineralisation is linked to

 

 

 

 

coarse grained pyrite and chalcopyrite and initial metallurgical tests conducted on the fresh material returned an average recovery of 87%. Given these positive results and the scale and prospectivity of the Boundiali belt margin, a helicopter VTEM programme is planned in Q4 2015 to cover the full strike of the Boundiali permit and the Mankono permit to the south. An IP survey completed during the wet season over the 20km Fonondara-Sani corridor showed that there is significant potential to change our interpretation of the key structures and identify new targets with additional remote data.

 

The 13km long Fapoha North target and the wide, low grade bulk mining target at Gbongogo on the Mankono permit will be further investigated by trenching once access is possible following the wet season.

 

DEMOCRATIC REPUBLIC OF CONGO

Kibali

Work this quarter focused on advancing brownfields targets along the KZ trend to provide mining flexibility and to contribute to resource addition/replacement while exploration work continued on the Kalimva/Ikamva target.

 

At Tete-Bakangwe, which is an old artisanal pit 4km from the plant, trenching returned significant results including 52m at 1.8g/t (Trench 0006), 43.2 at 1.7g/t (Trench 0011) and 10.8m at 3.3g/t (Trench 0012) highlighting the potential for a near mine satellite which will be further tested in Q4 2015. Initial interpretations are of a large, open, NE plunging fold system with higher grade located in the axial plane and mineralisation hosted by banded iron formation. Preliminary observations indicate two high grade stacked lodes which may be projected down plunge for more than 300m. An estimation based on historical drill holes and new trenches results shows a potential of 40 000oz at 3g/t for 70m of lateral extension.

 

At Bakangwe Aval, a programme of 15 close spaced RC holes was undertaken to confirm the potential of 429 976t at 5.76g/t for 79koz over 260m down plunge length and 90m width. Results from the 15 RC holes failed to return high grade mineralisation as indicated by the historical Barrick drill holes, however the results still enabled the completion of the contiguous Pakaka/Pamao model.

 

At Megi, three holes were cored to evaluate a 100m wide higher grade zone in the 1001 Lode. The holes targeted mineralisation below the base of the conceptual $1 000/oz pit shell and returned 7.75m at 6.5g/t from 112.25m (MIDD0013), 13.53m at 2.65g/t from 131.29m (MIDD0014) and 12.86m at 2.5g/t from 163.98m (MIDD0015) confirming the down plunge extension of the orebody and the potential to host high grade mineralisation.

 

The team completed the rebuilding of lithological, alteration and mineralisation wireframes to enable the evaluation of potential super-pit optimisations at Pakaka, Pamao and Bakangwe Aval for the Pakaka pit, whilst Kombokolo, Sessenge, Gorumbwa and Durba Hill were remodelled and combined for the KCD pit. Optimisations are in progress and results will guide further infill drilling around both pits.

 

The Sessenge SW target to the south of Gorumbwa and KCD was advanced this quarter with programmes of infill trenching, hand auger and a ground magnetic survey. The results from trenching continue to confirm mineralisation beneath the large 100ppb soil anomaly. Auger drill results and ground-mag interpretations are pending and results will be used to optimise the interpretation and develop a drilling strategy going forward.

 

 

 

 

CONSOLIDATED STATEMENT OF COMPREHENSIVE INCOME

   Quarter   Quarter   Quarter   9 months   9 months 
   ended   ended   ended   ended   ended 
   30 Sep   30 Jun   30 Sep   30 Sep   30 Sep 
$000  2015   2015   2014   2015   2014 
REVENUES                         
Gold sales on spot   250 516    247 590    283 234    729 334    860 433 
Total revenues   250 516    247 590    283 234    729 334    860 433 
Share of profits of equity accounted joint ventures   13 385    33 600    17 810    75 380    45 361 
Other income   6 667    3 788     1 260    12 209    6 356 
Total income   270 568    284 978    302 304    816 923    912 150 
COST AND EXPENSES                         
Mine production costs   130 977    127 302    133 100    375 871    395 485 
Movement in production inventory and ore stockpiles   3 928    981    (6 165)   9 606    (14 160)
Depreciation and amortisation   39 356    42 991     38 496    118 422    106 815 
Other mining and processing costs   15 292    15 439    16 340    45 606    48 055 
Mining and processing costs   189 553    186 713     181 771    549 505    536 195 
Royalties   12 878    12 914    14 533    37 611    44 963 
Exploration and corporate expenditure   9 791    12 992    8 897    31 460    33 284 
Other expenses   -    -    16 652    5 725    16 877 
Total costs   212 222    212 619     221 853    624 301    631 319 
Finance income   42    41    -    106    320 
Finance costs   (1 040)   (442)   (818)   (2 444)   (1 408)
Finance costs – net   (998)   (401)   (818)   (2 338)   (1 088)
Profit before income tax   57 348    71 958     79 633    190 284    279 743 
Income tax expense   (8 587)   (12 785)   (13 601)   (31 036)   (62 962)
Profit for the period   48 761    59 173     66 032    159 248    216 781 
Other comprehensive income                         
Gain/(loss) on available-for-sale financial assets   (451)   46    (782)   (530)   4 
Share of equity accounted joint ventures other comprehensive loss   (15)   (10)   (571)   (25)   (20)
Total other comprehensive income / (expense)   (466)   36    (1 353)   (555)   (16)
Total comprehensive income   48 295    59 209     64 679    158 693    216 765 
Profit attributable to:                         
Owners of the parent   42 345    53 601     58 008    144 149    185 351 
Non-controlling interests   6 416    5 572     8 024    15 099    31 430 
    48 761    59 173     66 032    159 248    216 781 
Total comprehensive income attributable to:                         
Owners of the parent   41 879    56 637    56 655    143 594    185 335 
Non-controlling interests   6 416    5 572    8 024    15 099    31 430 
    48 295    59 209    64 679    158 693    216 765 
Basic earnings per share ($)   0.45    0.58    0.63    1.55    2.00 
Diluted earnings per share ($)   0.45    0.57    0.62    1.53    1.98 
Average shares in issue (000)   93 209    93 081    92 663    93 048    92 580 

 

CONSOLIDATED STATEMENT OF FINANCIAL POSITION

   Quarter   Quarter   Quarter 
   ended   ended   ended 
   30 Sep   30 Jun   31 Dec 
$000  2015   2015   2014 
Assets               
Non-current assets               
Property, plant and equipment   1 481 368    1 488 234    1 482 736 
Cost   2 175 106    2 142 616    2 018 105 
Accumulated depreciation and amortisations   (693 738)   (654 382)   (535 369)
Deferred tax   -    398    1 294 
Long term ore stockpiles   173 993    178 381    151 708 
Trade and other receivables   6 629    5 655    10 794 
Investments in equity accounted joint ventures   1 433 868    1 430 594    1 364 579 
Other investments in joint ventures   46 599    46 669    45 469 
Total investments in joint ventures   1 480 467    1 477 263    1 410 048 
Total non-current assets   3 142 457    3 149 931    3 056 580 
Current assets               
Inventories and ore stockpiles   129 478    121 016    154 956 
Trade and other receivables   242 473    248 412    235 208 
Cash and cash equivalents   168 434    109 249    63 424 
Available-for-sale financial assets   937    1 388    1 835 
Total current assets   541 322    480 065    455 423 
Total assets   3 683 779    3 629 996    3 512 003 
Equity attributable to owners of the parent   3 226 862    3 177 794    3 048 250 
Non-controlling interests   211 843    206 839    204 999 
Total equity   3 438 705    3 384 633    3 253 249 
Non-current liabilities               
Loans from minority shareholders   2 765    2 765    2 765 
Deferred tax   33 900    32 650    29 775 
Provision for rehabilitation   55 904    55 904    49 177 
Total non-current liabilities   92 569    91 319    81 717 
Current liabilities               
Trade and other payables   136 640    137 426    139 805 
Current income tax payable   15 865    16 618    37 232 
Total current liabilities   152 505    154 044    177 037 
Total equity and liabilities   3 683 779    3 629 996    3 512 003 

 

 

 

 

These results are presented as the third quarter ended 30 September 2015. They have been prepared in accordance with International Financial Reporting Standards as adopted by the European Union (IFRS) on a basis that is consistent with the accounting policies applied by the group in its audited consolidated financial statements for the year ended 31 December 2014, and which will form the basis of the 2015 annual report. No new or amended accounting standards effective for 2015 have had a significant impact on the group. This announcement has been prepared in compliance with IAS 34 - Interim Financial Reporting. These results do not include all the notes of the type normally included in an annual financial report. Accordingly, this condensed report is to be read in conjunction with the annual report for the year 31 December 2014, and any public announcements made by the group during the reporting period. While the information included in this announcement has been prepared in accordance with the recognition and measurement criteria of IFRS, this announcement does not itself contain sufficient information to comply with IFRS. The auditors’ report for the year ended 31 December 2014 was unqualified and did not include references to any matters which the auditor drew attention to by way of emphasis without qualifying their report.

 

Property, plant and equipment cost increased by $32.5 million for the three months ended 30 September 2015. This is mainly attributed to capital expenditure at the Loulo complex of $31.6 million, including the development of the Yalea and Gara underground mines ($26.0 million).

 

The group’s capital commitments (including its share of equity accounted joint ventures) at 30 September 2015 amounted to $100.2 million with the majority relating to Kibali ($16.9 million) and the Loulo complex ($78.5 million).

 

The long term ore stockpiles balance of $174.0 million relates to the portion of ore stockpiles at Loulo, Gounkoto and Tongon which are expected to be processed after more than one year, in line with the respective mine plans. The 2% decrease from 30 June 2015 relates to decreases in the stockpiles at Loulo and Tongon, in line with mine plans.

 

Investments in equity accounted joint ventures reflects the group’s share of its equity accounted investments, mainly Kibali as well as Morila and the group’s asset leasing joint ventures. Other investments in joint ventures reflect the group’s loans advanced to the group’s asset leasing joint ventures.

 

The increase of $3.2 million in total investment in joint ventures for the quarter mainly reflects the group’s profit share from equity accounted joint ventures ($13.4 million), partially offset by the loan repayment made by Kibali to the joint venture funders (Randgold and AngloGold Ashanti Limited) ($10.0 million attributable share).

 

Current inventories and ore stockpiles of $129.5 million increased by 7% from the balance at 30 June 2015. The increase is the result of an increase in supplies and insurance spares at Loulo with the owner miner agreement being finalised.

 

Trade and other receivables (including the allocation of a portion to non-current) at 30 September 2015 were in line with the balances at 30 June 2015.

 

The total outstanding refundable VAT balances in Mali amount to $102 million (30 June 2015: $100.0 million) (including 100% of the Loulo and Gounkoto VAT receivables and the attributable portion of the Morila VAT receivable of $6.4 million). Morila, Loulo and Gounkoto have the legal right under the terms of their respective mining conventions to offset other taxes payable to the Malian State against these refundable VAT balances. Management continues to pursue the cash settlement of these VAT balances.

 

The portion of the outstanding VAT balances which is not expected to be recovered within a one year time frame, amounts to $6.6 million, and is shown in the long term debtors (30 June 2015: $5.7 million).

 

 

 

 

The group’s share of the VAT balance at Kibali amounted to $55.2 million (30 June 2015: $54.0 million). The Morila and Kibali VAT balances are included in the group’s investment in joint ventures line.

 

The group had received claims for various taxes from the State of Mali totalling $310.0 million (30 June 2015: $310.0 million), in respect of its Mali operations. Having taken professional advice, the group considers the claims to be without merit or foundation and is strongly defending its position, including following the appropriate legal process for disputes within Mali. Accordingly, no provision has been made for the material claims. Loulo, Gounkoto and Morila have legally binding mining conventions which guarantee fiscal stability, govern the taxes applicable to the companies and allow for international arbitration in the event a dispute cannot be resolved in the country. Management continues to engage with the Malian authorities at the highest level to resolve this issue. During the prior year, Loulo submitted a request for arbitration at the International Centre for the Settlement of Investment Disputes against the State of Mali in relation to certain of the disputed tax claims. The arbitration process is ongoing with hearings having taken place in Q1 2015, and the outcome of this process is expected to be concluded before year end.

 

The increase in cash of $59.2 million since 30 June 2015 largely reflects strong operational cash flows from the Loulo-Gounkoto complex and Tongon mines ($109.7 million), and cash returned from Kibali, partially offset by the group’s continued investment in capital expenditure in its subsidiaries ($49.2 million). This includes $16.7 million of down payments for equipment at Loulo related to the owner mining transition.

 

Based on the company's current cash resources and facilities, projected operating cash flows and capital expenditure, the company is confident it will be able to meet its obligations at the prevailing gold price.

 

Trade and other payables of $136.6 million were in line with the balance at 30 June 2015 of $137.4 million.

 

Current tax payable of $15.9 million decreased from 30 June 2015 due to corporation tax payments made at Loulo and Gounkoto during the quarter. Tongon benefits from a five year tax holiday from the start of production in December 2010.

 

CONSOLIDATED CASH FLOW STATEMENT

$000 

3 months

ended

30 Sep

2015

   3 months
ended
30 Jun
2015
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Profit after tax   48 761    59 173    159 248    216 781 
Income tax expense   8 587    12 785    31 036    62 962 
Profit before income tax   57 348    71 958    190 284    279 743 
Share of profits of equity accounted joint ventures   (13 385)   (33 600)   (75 380)   (45 361)
Adjustment for non-cash items   58 360    59 241    169 286    130 690 
Effects of change in operating working capital items   8 575    (27 339)   6 360    (37 722)
Receivables   10 305    (24 503)   (22 935)   (35 355)
Inventories and ore stockpiles   (4 074)   756    1 059   15 761 
Trade and other payables   2 344    (3 592)   28 236    (18 128)
Cash generated from operations   110 898    70 260    290 550    327 350 
Dividends received from equity accounted joint ventures   10 000    20 272    35 272    - 
Income tax paid   (11 220)   (19 086)   (42 978)   (79 061)
Net cash generated from operating activities   109 678    71 446    282 844    248 289 
Additions to property, plant and equipment   (49 247)   (63 428)   (148 021)   (132 051)
Funds invested in equity accounted joint ventures   (174)   175    (2 828)   (51 462)
Loans repaid by equity accounted joint ventures   340    -    340    6 990 
Net cash used by investing activities   (49 081)   (63 253)   (150 509)   (176 523)
Proceeds from issue of ordinary shares   -    -    67    2 035 
Dividends paid to company’s shareholders   -    (38 600)   (38 600)   (43 284)
Dividends paid to non-controlling interests   (1 412)   (1 582)   (8 120)   (5 244)
Proceeds from borrowings   -    -    -    - 
Net cash used by financing activities   (1 412)   (40 182)   (46 653)   (46 493)
Net increase / (decrease) in cash and cash equivalents   59 185    (31 989)   85 682    25 273
Cash and cash equivalents at beginning of period   109 249    141 238    82 752     38 151 
Cash and cash equivalents at end of period   168 434    109 249    168 434    63 424 

 

 

 

 

CONSOLIDATED STATEMENT OF CHANGES IN EQUITY

  

Number of

ordinary

shares

  

Share

capital

$000

  

Share

premium

$000

  

Other

Reserves1

$000

  

Retained

earnings

$000

  

Total equity

attributable

to owners

of parent

$000

  

Non-

controlling

interests

$000

  

Total

equity

$000

 
Balance - 31 Dec 2013 (audited)   92 245 531    4 612    1 423 513    64 398    1 386 518    2 879 041    178 813    3 057 854 
Share of other comprehensive loss of joint ventures   -    -    -    4    -    4    -    4 
Fair value movement on available-for-sale financial assets   -    -    -    (20)   -    (20)   -    (20)
Other comprehensive expense   -    -    -    (16)   -    (16)   -    (16)
Net profit for the period   -    -    -    -    185 351    185 351    31 430    216 781 
Total comprehensive income / (expense) for the period   -    -    -    (16)   185 351    185 335    31 430    216 765 
Share-based payments   -    -    -    23 097    -    23 097    -    23 097 
Share options exercised   108 300    6    2 029    -    -    2 035    -    2 035 
Reserves transfer on exercise of options previously expensed under IFRS 2   -    -    756    (756)   -    -    -    - 
Shares vested2   283 888    14    21 698    (19 686)   -    2 026    -    2 026 
Dividend relating to 2013   36 366    2    2 988    -    (46 274)   (43 284)   -    (43 284)
Non-controlling interest share of Gounkoto dividend   -    -    -    -    -    -    (5 244   (5 244)
Balance - 30 Sep 2014   92 674 085    4 634    1 450 984    67 037    1 525 595    3 048 250    204 999    3 253 249 
Balance - 31 Dec 2014 (audited)   92 674 085    4 634    1 450 984    67 254    1 575 218    3 098 090    204 864    3 302 954 
Fair value movement on available-for-sale financial assets   -    -    -    (530)   -    (530)   -    (530)
Share of other comprehensive income of joint ventures   -    -    -    (25)   -    (25)   -    (25)
Other comprehensive income / (expense)   -    -    -    (555)   -    (555)   -    (555)
Net profit for the period   -    -    -    -    144 149    144 149    15 099    159 248 
Total comprehensive income / (expense) for the period   -    -    -    (555)   144 149    143 594    15 099    158 693 
Share-based payments   -    -    -    21 334    -    21 334    -    21 334 
Share options exercised   2 000    -    67    -    -    67    -    67 
Reserves transfer on exercise of options previously expensed under IFRS 2   -    -    20    (20)   -    -    -    - 
Shares vested2   297 657    15    25 460    (23 098)   -    2 377    -    2 377 
Dividend relating to 2014   250 635    12    17 132    -    (55 744)   (38 600)   -    (38 600)
Non-controlling interest share of Gounkoto dividend   -    -    -    -    -    -    (8 120   (8 120
Balance - 30 Sep 2015   93 224 377    4 661    1 493 663    64 915    1 663 623    3 226 862    211 843    3 438 705 

1Other reserves includes the cumulative charge recognised under IFRS 2 in respect of share option schemes (net of amounts transferred to share capital and share premium) as well as the foreign currency translation reserve and the movements in available-for-sale financial assets.
2Restricted shares were issued as remuneration to executive directors and senior management. Shares were also issued to executive directors following approval of their annual bonuses and to non-executive directors as fees. The transfer between ‘other reserves’ and ‘share premium’ in respect of the shares vested represents the cost calculated in accordance with IFRS 2.

 

NON-GAAP MEASURES

 

Randgold has identified certain measures that it believes will assist understanding of the performance of the business. As the measures are not defined under IFRS they may not be directly comparable with other companies’ adjusted measures. The non-GAAP measures are not intended to be a substitute for, or superior to, any IFRS measures of performance but management has included them as these are considered to be important comparables and key measures used within the business for assessing performance.

 

These measures are explained further below:

 

Total cash costs and cash cost per ounce are non-GAAP measures. Total cash costs and total cash cost per ounce are calculated using guidance issued by the Gold Institute. The Gold Institute was a non-profit industry association comprising leading gold producers, refiners, bullion suppliers and manufacturers. This institute has now been incorporated into the National Mining Association. The guidance was first issued in 1996 and revised in November 1999. Total cash costs, as defined in the

 

 

 

 

Gold Institute’s guidance, include mine production, transport and refinery costs, general and administrative costs, movement in production inventories and ore stockpiles, transfers to and from deferred stripping where relevant and royalties. Total cash costs and total cash cost per ounce also include our share of our equity accounted joint ventures’ total cash costs and total cash cost per ounce.

 

Total cash cost per ounce is calculated by dividing total cash costs, as determined using the Gold Institute guidance, by gold ounces sold for the periods presented. Total cash costs and total cash cost per ounce are calculated on a consistent basis for the periods presented. Total cash costs and total cash cost per ounce should not be considered by investors as an alternative to operating profit or net profit attributable to shareholders, as an alternative to other IFRS measures or an indicator of our performance. The data does not have a meaning prescribed by IFRS and therefore amounts presented may not be comparable to data presented by gold producers who do not follow the guidance provided by the Gold Institute. In particular depreciation and amortisation would be included in a measure of total costs of producing gold under IFRS, but are not included in total cash costs under the guidance provided by the Gold Institute.

 

Furthermore, while the Gold Institute has provided a definition for the calculation of total cash costs and total cash cost per ounce, the calculation of these numbers may vary from company to company and may not be comparable to other similarly titled measures of other companies. However, Randgold believes that total cash cost per ounce is a useful indicator to investors and management of a mining company’s performance as it provides an indication of a company’s profitability and efficiency, the trends in cash costs as the company’s operations mature, and a benchmark of performance to allow for comparison against other companies.

 

Cash operating costs and cash operating cost per ounce are calculated by deducting royalties from total cash costs. Cash operating cost per ounce is calculated by dividing cash operating costs by gold ounces sold for the periods presented.

 

Gold sales is a non-GAAP measure. It represents the sales of gold at spot and the gains/losses on hedge contracts which have been delivered into at the designated maturity date. It excludes gains/losses on hedge contracts which have been rolled forward to match future sales. This adjustment is considered appropriate because no cash is received/paid in respect of these contracts. Randgold currently does not have any hedge positions. Gold sales include our share of our equity accounted joint ventures’ gold sales.

 

Profit from mining activity is calculated by subtracting total cash costs from gold sales for all periods presented. Profit from mining includes our share of our equity accounted joint ventures.

 

Gold on hand represents gold in doré at the mines multiplied by the prevailing spot gold price at the end of the period. Gold on hand includes our share of our equity accounted joint ventures’ gold on hand.

 

The group non-GAAP measures presented in the ‘Summarised Financial Information’ in the accompanying table include the group’s share of each operating mine, together with adjustments to eliminate inter-group transactions.

 

The accompanying table reconciles gold sales, total cash costs and profit from mining activity as non-GAAP measures, to the information provided in the statement of comprehensive income, determined in accordance with IFRS, for each of the periods set out therein.

 

 

 

 

NON-GAAP

$000 

Quarter

ended

30 Sep

2015

   Quarter
ended
30 Jun
2015
   Quarter
ended
30 Sep
2014
  

9 months

ended

30 Sep

2015

   9 months
ended
30 Sep
2014
 
Gold sales per IFRS1   250 516    247 590    283 234    729 334    860 433 
Gold sales adjustments for joint ventures2   90 207    107 186    93 562    310 797    234 500 
Gold sales3   340 723    354 776    376 796    1 040 131    1 094 933 
Mine production costs   130 977    127 302    133 100    375 871    395 485 
Movement in production inventory and ore stockpiles1   3 928    981    (6 165)   9 606    (14 160)
Royalties including adjustment for joint ventures   16 911    16 800    17 597    48 829    53 124 
Royalty adjustment for joint ventures2   (4 033)   (3 886)   (3 064)   (11 218)   (8 161)
Total royalties1   12 878    12 914    14 533    37 611    44 963 
Other mining and processing costs1   15 292    15 439    16 340    45 606    48 055 
Cash costs adjustments for joint ventures2   49 225    47 376    46 332    148 393    114 820 
Total cash costs3   212 300    204 012    204 140    617 087    589 163 
Profit from mining activity3   128 423    150 764    172 656    423 044    505 770 
Ounces sold   303 718    298 421    295 018    885 763    850 410 
Total cash cost per ounce sold3   699    684    692    697    693 
Cash operating cost per ounce sold3   643    627    632    642    630 
Gold on hand at period end3   12 812    11 688    11 993    12 812    11 993 
1Figures extracted from IFRS results.
2The group includes the gold sales and cash costs associated with the joint venture results in its non-GAAP measures. The gold sales adjustments per quarter reflect our 40% share of Morila’s gold sales and 45% share of Kibali’s gold sales. The cash costs adjustments per quarter primarily reflect our 40% share of Morila’s cash costs, 45% of Kibali’s cash costs, as well as our 50.1% share in RAL 1 Limited’s (RAL 1) cash cost adjustments.
3Refer to explanation of non-GAAP measures provided.

 

PRINCIPAL RISK FACTORS AND UNCERTAINTIES

 

The group is subject to a variety of risks and uncertainties which are the result of not only the business environment in which it operates but also of other factors over which it has little or no control. The board is responsible for the group’s systems of risk management and internal control as well as reviewing their operational effectiveness on a regular basis. We are continually evaluating risks to ensure the business achieves its strategic objectives; however the principal risks and uncertainties which could impact the group’s long-term performance remain those detailed in the group’s 2014 annual report and financial statements, a copy of which is available on the group’s website www.randgoldresources.com.

 

The group’s strategy takes into account known risks but there may be additional risks unknown to the group and other risks, currently believed to be immaterial, which could develop into material risks. It is recognised that the group is exposed to risks wider than those listed. However, we have disclosed those we believe are likely to have the greatest impact on our business at this moment in time and those that have been the subject of debate at recent board or audit committee meetings. The principal risks and uncertainties may materialise individually, simultaneously or in combination and should be considered in connection with any forward looking statements in this document, the 2014 annual report and the information available on the group’s website.

 

EXTERNAL RISKS   NATURE AND IMPACT
Gold price volatility   Gold price volatility can result in material and adverse movement in the group’s operating results, asset values, revenues and cash flows.  Sustained or significant declines in the gold price will affect earnings and cash flow.  Group planning and forecasting are subject to gold price assumptions and therefore changes to the gold price may have an adverse effect the group’s ability to fund its capital projects.
Country risk   The group operates in jurisdictions where changes may occur to the political environment and governments may seek a greater share of mineral wealth.  Inadequate monitoring of in-country political instability and uncertainty or failure to adapt to changes to terms applicable to the group’s operations may impact the ability to sustain operations, prevent the group from making future investments or result in increased costs for the group.
Corporate, social and environmental responsibility   Some of the group’s current and potential operations are located near communities that may regard these operations as being detrimental to them.  Poor management of stakeholder communication and expectations with a lack of community development activities or regard for environmental responsibility may lead to the inability to sustain operations in the area and impact the group’s ability to expand into other regions.  Failure to understand social and environmental contexts can lead to insufficient planning, resourcing and costing of projects.  Failure to comply with environmental regulations could lead to fines and, in the extreme, loss of operating licence.
Supply routes   Due to the remote location of the operations the disruption of supply routes may cause delays with construction and mine activities.  Supply chain failures, disruptions or significantly increased costs within the supply chain could have an adverse effect on the group’s operations.

 

 

 

 

FINANCIAL RISKS   NATURE AND IMPACT
Operating and capital cost control   Operating cost and capital cost control are a key factor in the group’s profitability.  Failure to control operating cost of production or operational objectives will result in reduced margins and profitability.  Failure or inability to monitor capital expenditure and progress of capital projects may result in financial losses, overspend on projects and cause returns to be eroded.  General cost inflation in the mining sector could affect the operations and projects resulting in significant pressure on operating and capital costs.
In-country tax regimes   The group operates in jurisdictions which may change tax or fiscal regimes and regulations and, failure to adapt to such issues may result in fines and financial losses.  Inability to enforce legislation over tax or incorrectly applied legislation may result in lengthy arbitration and loss of profits.
OPERATIONAL RISKS   NATURE AND IMPACT
Production, reserves and resources   The group’s mining operations may yield less gold under actual production conditions than indicated by its gold reserve figures, which are estimates based on a number of assumptions, including mining and recovery factors, production costs and gold price.  In such instances the group’s profitability may be affected should actual production be lower than indicated reserves.  Should the prevailing gold price not support or sustain the valuation the carrying value of assets may be impaired.
Environmental, health, safety and security incident   The mining sector is subject extensive health, safety and environmental laws, regulations and standards alongside stakeholder expectations.  Failure to maintain environmental, health and safety standards’ may result in significant environmental or safety incidents or deterioration in safety performance standards leading to loss of life or significant loss of time and disruption or damage to operations.  Evolving regulation and standards could result in increased costs, litigation or in extreme cases may threaten the viability of an operation.  
Risks associated with underground mining and geotechnical failure   The group has a number of underground projects which are subject to the extensive risks associated with underground mining.  Failure to monitor or mitigate such risks may affect the profitability of the group and the operational performance.  Failure to consider geotechnical failure in planning and then monitor the impact during operations may impact the geotechnical stability of pits and underground mining operations.  Extreme weather conditions such as high rainfall may also impact the geotechnical stability of the pits and therefore could impact mining operations.
STRATEGIC RISKS   NATURE AND IMPACT
Lack of identification of new exploration targets and exploration failure   The replacement of reserves and resources is key to the long term delivery of the group’s exploration led growth strategy and therefore the lack of identification of new exploration targets may lead to a loss of revenue and an inability to grow and meet strategic objectives.  Exploration and development are costly activities with no guarantee of success, but are necessary for future growth of the group.

 

GENERAL

During the quarter, Randgold performed well across all its operations and projects. At Kibali, production is now expected to exceed the annual guidance provided at the start of the year, while at Loulo-Gounkoto, the complex may fall short of its annual target, given the lower grades achieved during the quarter. As such, the group continues to forecast production and cash costs within the guidance range set out at the start of the year. Capital expenditure for the year is now expected to be slightly less than the previous guidance, owing to the timing of commitments and payments, with the balance rolling over into 2016.

 

As is customary, Randgold will be finalising its 2016 budget during the fourth quarter and guidance for 2016 will be given with the year end results. The group remains focused on its strategy to deliver value for all its stakeholders through the discovery and development of world class orebodies and has a pipeline of high quality projects and exploration targets. Notwithstanding this core strategy, management routinely reviews corporate and asset acquisition opportunities, focused on Africa.

 

On 16 September 2015, Randgold announced that it had concluded an investment agreement (the ‘Agreement’) with AngloGold Ashanti Limited (‘AngloGold Ashanti’) aimed at the formation of a joint

 

 

 

 

venture to redevelop and operate AngloGold Ashanti’s Obuasi gold mine in Ghana. In terms of the Agreement, Randgold will lead and fund a development plan study designed to rebuild Obuasi as a viable long-life mining business with an attractive cost structure and returns.

 

Obuasi, located in the Ashanti region of Ghana, 320km northwest of the capital, Accra, is a large, high grade deposit with proven and probable ore reserves (as reported by AngloGold Ashanti in their 2014 Annual Report) of 24.53Mt at 6.70g/t for 5.29Moz, part of a substantial mineral resource base. In 2012, AngloGold Ashanti initiated a programme to modernise the mine, principally by starting to develop a ramp access that will ultimately run from surface to high grade blocks of ore underground. The ramp will supplement current vertical hoisting infrastructure and help debottleneck the underground operation by allowing for greater ease in transporting people and materials underground, and transporting ore to surface. This was considered by AngloGold Ashanti to be a necessary step ahead of the envisaged transformation of the mine into a modern, mechanised operation. At the end of 2014, AngloGold Ashanti converted Obuasi to limited operations, ceasing underground production, retrenching the workforce but continuing to process tailings, and starting a feasibility study on the redevelopment of the mine. Development of the decline ramp has continued over this period.

 

The development plan will build on the feasibility study work completed with the intention of establishing a more focused, efficient, mechanised high grade operation, and is expected to take about four months to complete. If Randgold completes due diligence to its satisfaction and the development plan meets both parties’ investment criteria, and assuming all other conditions are satisfied, Randgold and AngloGold Ashanti will form a new joint venture company.

 

Randgold and AngloGold Ashanti will then be jointly responsible for funding the redevelopment of Obuasi in line with the agreed development plan. A Randgold group entity will be appointed as operator of the mine, and Randgold and AngloGold Ashanti will appoint an equal number of directors to the board of the joint venture company, with board and shareholder decisions to be approved by both parties.

 

Randgold is expected to complete and deliver a new development plan to both parties’ boards by 31 January 2016, should its work demonstrate a viable plan. Consequently, the Randgold team together with a multi-disciplinary team of experts managed by Randgold, are currently on site at Obuasi undertaking this work. Randgold expects to be in a position to update the market further on this opportunity by the next quarterly report.

 

The directors confirm to the best of their knowledge that:

a)These third quarter results have been prepared in accordance with IAS 34 as adopted by the European Union; and
b)The interim management report includes a fair review of the information required by the FCA’s Disclosure and Transparency Rules (4.2.7R and 4.2.8R).

 

By order of the board  
D M Bristow G P Shuttleworth
Chief Executive Financial Director
   
5 November 2015
 
   

 

 

 

  

RANDGOLD RESOURCES NEWS UPDATES

 

KIBALI SHAFT SIGNALS SUCCESS OF ‘OWNER’S TEAM’ DEVELOPMENT APPROACH

 

Towering incongruously over the African jungle, the shaft headgear at Kibali marks the spot where the Randgold ‘owner’s team’ is rapidly progressing the development of the complex’s underground mine. The underground system is based on a vertical and twin decline shaft with a 3.0 million tonne per annum hoisting capacity, and the mine is scheduled to hoist ore through the shaft in 2017.

 

Kibali undertook the sinking of the shaft on an owner’s team basis, contrary to the normal industry practice of contracting out the management, in order to retain full control of the project. The team is made up of highly skilled operators with extensive experience of shaft sinking throughout Africa and South America.

 

“The team achieved a sinking rate that was 50% higher than the industry norm and consequently managed to reach the shaft bottom at 751 metres almost three months ahead of plan,” says GM operations Central and East Africa Willem Jacobs. “What makes this performance even more special is that the programme included horizontal development on three levels as well as 730 metres of wide diameter raise-boring.”

 

Randgold decided in 2005 to start building its underground mining skills set, and with the Loulo mines already well advanced towards full owner-operator status, the success of the Kibali shaft project has demonstrated its growing expertise in this field.

 

RESEARCH AND TECHNOLOGY ADD IMPETUS TO DISCOVERY DRIVE

 

Randgold Resources has joined the West African Exploration Initiative (WAXI) to tap into its research programme, now in its ninth year, for additional information which its generative team can leverage to expand its data foundation.

 

Group exploration manager Joel Holliday says that there is still a dearth of basic geological knowledge about Africa’s most prospective gold regions, so Randgold is investing in fundamental research to improve its understanding of mineralisation controls and other exploration factors.

 

“We know we’re looking in the right areas, but we want to sharpen up our ability to spot the unique anomalies that signal world-class deposits,” he says.

 

“We’re using large scale remote programmes and applied geology to identify key structures. Starting November, we’ll be flying a multi-sensor survey which will collect electromagnetic, magnetic and radiometric data, over a large area in the north of Côte d’Ivoire. Similar surveys at Loulo, Tongon and Kibali greatly improved our understanding of these structures and is one of the key tools that led to the discovery of Gounkoto.”

 

Chief executive Mark Bristow says Randgold’s exploration drive underscores its belief that the only real way to create value in the mining industry is through discovery and development of world class deposits. At a time when the rest of the industry is cutting back we see enhanced opportunity to expand our footprints and intensify our efforts to add to our past successes.

 

“West Africa, where we have long had a substantial presence, has been a prolific source of major discoveries and we believe its potential is matched by Central Africa, which we entered through Kibali,” he says.

 

LAUNCH OF AGRI-TRAINING CENTRE MARKS MAJOR NEW LEGACY INITIATIVE

 

The Loulo-Gounkoto agribusiness training centre, a project designed by Randgold Resources to provide the local community with a sustainable source of economic activity, was officially launched on 30 October in a ceremony attended by two Malian cabinet ministers and local government officials.

 

The centre will provide a 12-month agricultural and entrepreneurial training programme on a five hectare farm, close to the mines, for 100 students selected by the local community development committee and sponsored by their villages. The concept and the programme were devised in conjunction with the SDDR, the National Malian Strategy for Rural Development.

 

At the launch, chief executive Mark Bristow said agribusiness was the core initiative in Randgold’s commitment to creating viable local economies as a legacy to the communities which host its operations. In addition to the Loulo-Gounkoto project, it is also developing agribusinesses at its Morila, Tongon and Kibali mines.

 

“A mine is relatively short-lived but a successful farm is forever, and that is why we are focusing on an agricultural heritage for our operations. Agribusiness will not only create employment but will also provide food security, which is one of the prime requirements of any community,” he said.

 

 

 

 

After completion of their 12-month course, groups of trainees will be set up as profit-sharing micro-enterprises under the supervision of the centre management, and those who complete this incubation period successfully will be equipped and funded to start their own ventures. Each of them by then will have the ability to manage a productive, profitable and sustainable farm.

 

Bristow said it was intended to involve government and local investors in the development of agricultural manufacturing units and distribution systems.

 

Group community and environmental officer Hilaire Diarra said while conventional aid programmes merely propped people up for a while, Randgold’s investment in agribusinesses was providing local communities with a real opportunity to build a better future for themselves.

 

West African operations officer Chiaka Berthe said the agribusiness would also provide alternative employment opportunities to people currently engaged in illegal mining which was rife in the area as elsewhere in Africa’s mining countries. “We are working closely with the Malian government in an effort to stamp this out and to regulate small-scale or artisanal mining more effectively,” he said.

 

INVESTMENT IN TRAINING AND DEVELOPMENT YIELDS HIGH HUMAN RETURNS

 

Randgold Resources’ extensive training programmes, run in conjunction with leading educational institutions, are designed to produce a workforce with world-class skills, says group human resources executive Philip Pretorius.

 

The programmes start at feeder level, where operators and unskilled workers are given training on site as well as at technical schools. The aim, says Pretorius, is not only to give them the necessary work-related competencies but to imbue them with an understanding of Randgold’s business culture.

 

Then there is the Stagiaire project, which provides work experience to students in mining-related disciplines at African universities. At present, more than 120 of these students are engaged in three-month practical training programmes at Randgold mines, with a new intake every quarter. As well as rendering a service to the community and the industry, this project allows Randgold to identify particularly promising candidates for its bursary programme, which currently has recipients studying at universities in South Africa, Morocco, the UK and the USA. Randgold also runs sponsorship schemes to assist talented undergraduates studying at university in our host countries, and is also currently funding two students to complete PhD research programmes in geological sciences at Kingston University in the UK.

 

The continuing education of senior employees, in terms of technical skills as well as business acumen, is structured in partnership with internationally renowned institutions, notably the University of Pretoria engineering and mining faculty and the University of Cape Town’s business school. Senior group and operational executives – some of whom have come up through every tier of the training structure, from the entry level up – are also enrolled in executive development programmes which makes use of a number of the leading business schools in South Africa, USA and UK.

 

“In line with Randgold’s policy of local employment, the aim of our investment in education and development is essentially to ensure that our world-class operations can be run by competent in-country managers, supported by skilled locally recruited workforces – and, beyond that, to cultivate the future leaders of the company,” says Randgold’s CEO Mark Bristow.

 

SENIOR APPOINTMENTS IN MALI

 

Chiaka Berthe, formerly GM of the Loulo-Gounkoto mine complex, has been promoted to West African operations officer. Chiaka has a Master’s degree in geological engineering from the Malian National School of Engineering and began his career with Randgold as a young graduate 20 years ago. He has been involved in the exploration, evaluation and production phases of the Loulo project, having served as production and resources geologist before being appointed mineral resources manager in 2006. Chiaka was appointed GM of Loulo-Gounkoto in 2012 and is a member of AusIMM and GASA. In 2015, Chiaka attended the Senior Executive Programme at the London Business School.

 

 

 

 

Tahirou Ballo, the former mine manager at Gounkoto, has assumed the position of GM at the Loulo-Gounkoto complex. He is a mining economics engineer with 21 years’ experience and served as mining superintendent for Randgold at the Syama mine from 1999. In 2009 Tahirou underwent the Randgold executive training programme. In 2010, he was promoted to operations manager at Loulo and then appointed GM at Gounkoto in 2011.

 

ACCOLADES

 

·Tongon has received the President’s Award as the best mine in Côte d’Ivoire for the second year running.
·At the DRC Mining Industry awards in October CEO Mark Bristow was honoured with a Lifetime Achievement Award and Randgold Resources was named Best Performer in Occupational Health and Safety.
·Mark was also the highest-ranking mining CEO in the Harvard Business Review’s 2015 list of the top 100 best-performing CEOs in the world.

 

KIBALI SUSTAINS MOMENTUM AND EXPANDS LOCAL ECONOMIC DEVELOPMENT PROGRAMME

 

The Kibali gold mine in the north-east of the Democratic Republic of Congo is sustaining its operating momentum, and at this point looks set to exceed its 2015 production target of 600 000 ounces of gold, Randgold chief executive Mark Bristow said at the quarterly update for local media in Kinshasa.

 

Bristow said the recent completion of the vertical shaft sinking, ahead of schedule, marked a major advance in the development of the underground mine which will complement Kibali’s existing open pit operation. The other remaining capital projects were also making good progress, with the mine’s second hydropower station in the process of commissioning the first of two phases.

 

“With the mine settling down, we have been able to intensify our focus on sustainability issues such as the mine’s ISO certifications in the field of the environment, health and safety,” Bristow said.

 

“Despite tough market conditions, Kibali also continues to invest in its extensive local development programme, which includes the introduction of the region’s first free-to-air television station, an entrepreneurship training programme led by the University of Cape Town’s Graduate School of Business and a local economic development facility to give loans to smallholding farmers and local entrepreneurs. The latter is a product of the recent cooperation agreement between Kibali, the local community and the local authorities.”

 

In related initiatives, a proposal on the development of a palm oil business in the region has been submitted to the DRC government and an 82 hectare maize project trial has been successfully launched.

 

Bristow said he hoped that both these projects would be backed by the state, and that the government would also roll out more support for Kibali’s efforts to promote economic activity in this remote and deprived region. He noted that the delay in implementing the DRC’s current move to a more federal structure was causing some dysfunction in the provincial administration and appealed for this issue to be addressed.

 

“Together with the other mining companies operating in the DRC we applaud the government’s decision to take another look at the proposed changes to the country’s mining code, which in our view are deeply flawed. The DRC possesses enormous mineral resources, and has the potential to become one of Africa’s wealthiest countries. With the drop in commodity prices, however, international capital providers will need the security of a transparent and equitable mining code before they invest further in what we believe could grow into a world-class mining industry,” he said.

 

TONGON PASSES MAJOR MILESTONE AS RANDGOLD CONTINUES TO HUNT FOR MORE

 

Randgold’s Tongon mine has repaid its shareholder’s loans of $448 million, used to partially fund its capital investment of $580 million, thereby moving it into a dividend-paying position.

 

 

 

 

Speaking at the mine’s quarterly briefing for local media, chief executive Mark Bristow described this as a significant achievement, particularly in the context of a global gold mining industry currently characterised by capital write-downs and impairments.

 

“Tongon has already paid close to $90 million to the Ivorian state in the form of royalties and taxes and the country will now benefit even more from the dividends the government will receive through its 10% carried interest in the mine as well as the increased revenue when Tongon starts paying full corporate tax at the end of this year,” Bristow said. He noted that since its commissioning five years ago, Tongon had also contributed more than $600 million to the Ivorian economy in the form of payments to local suppliers and had invested almost $6 million in community upliftment projects.

 

“Ongoing exploration around Tongon has increased its reserves after depletion by 18% since 2009, extending its remaining life by another year. We also continue to look for more multi-million ounce deposits elsewhere in this highly prospective country, and we are about to launch our biggest-ever exploration drive in Côte d’Ivoire. This will include a fresh look at the Nielle permit, which hosts Tongon, and a geophysical survey, followed by a diamond drilling programme, across our holdings in the north of the country,” he said.

 

He also cited Tongon as a particularly good example of the success of Randgold’s policy of recruiting, training and empowering nationals of its host countries to run world-class mines in Africa. The mine’s workforce is 97% Ivorian and only two members of its management team are not Ivorians.

 

Tongon has won the President’s Award as the best mine in Côte d’Ivoire for two successive years.

 

 

 

REGISTERED OFFICE 3rd Floor, Unity Chambers, 28 Halkett Street, St Helier, Jersey, JE2 4WJ, Channel Islands

REGISTRARS Computershare Investor Services (Jersey) Limited, Queensway House. Hilgrove Street, St Helier, Jersey JE1 1ES, Channel Islands

TRANSFER AGENTS Computershare Services PLC, PO Box 663, 7th Floor, Jupiter House, Triton Court, 14 Finsbury Square, London EC2A 1BR

INVESTOR AND MEDIA RELATIONS For further information contact Kathy du Plessis on telephone: +44 20 7557 7738, e-mail:  randgold@dpapr.com

 

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS: Except for the historical information contained herein, the matters discussed in this news release are forward-looking statements within the meaning of Section 27A of the US Securities Act of 1933 and Section 21E of the US Securities Exchange Act of 1934, and applicable Canadian securities legislation. Forward-looking statements include, but are not limited to, statements with respect to the future price of gold, the estimation of mineral reserves and resources, the realisation of mineral reserve estimates, the timing and amount of estimated future production, costs of production, reserve determination and reserve conversion rates. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'will', 'plans', 'expects' or 'does not expect', 'is expected', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates' or 'does not anticipate', or 'believes', or variations of such words and phrases or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur' or 'be achieved'. Assumptions upon which such forward-looking statements are based are in turn based on factors and events that are not within the control of Randgold Resources Limited (‘Randgold’) and there is no assurance they will prove to be correct. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Randgold to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to mining operations, including political risks and instability and risks related to international operations, actual results of current exploration activities, conclusions of economic evaluations, changes in project parameters as plans continue to be refined, as well as those factors discussed in Randgold’s filings with the US Securities and Exchange Commission (the 'SEC'). Although Randgold has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Randgold does not undertake to update any forward-looking statements herein, except in accordance with applicable securities laws. CAUTIONARY NOTE TO US INVESTORS: The SEC permits companies, in their filings with the SEC, to disclose only proven and probable ore reserves. We use certain terms in this report, such as 'resources', that the SEC does not recognise and strictly prohibits us from including in our filings with the SEC. Investors are cautioned not to assume that all or any parts of our resources will ever be converted into reserves which qualify as 'proven and probable reserves' for the purposes of the SEC's Industry Guide number 7.