EX-99.2 3 ni43-01_itr.htm NI 43-101 INDEPENDENT TECHNICAL REPORT
(TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project  

 

NATIONAL INSTRUMENT 43-101 Independent Technical Report

 

 

Updated Mineral Resource Estimate for the Buckreef Gold Mine
Project, Tanzania, East Africa

 

 

For Tanzanian Gold Corporation (TSX: TNX)
(NYSE American: TRX)

 

 

(TANZANIAN GOLD CORPORATION LOGO)

 

 

Compiled by:

 

Wenceslaus Kutekwatekwa
BSc Hons (Mining Eng.), MBA, FSAIMM, FIoDZ, PRINCE 2®, MAMMZ, MPMIZ
(Mining Consultant)

 

Dr. Frank K Crundwell
BSc (Eng.) Chem BSc (Financial Maths) MSc (Eng.) PhD FSAIMM, FIChemE
(Metallurgical Consultant)

 

(VIRIMAI PROJECTS LOGO)

Reference No: VPTRX002-2020
Effective Date: May 15, 2020

30 Tunsgate Road, P.O. Box 1022, Mount
Pleasant, Harare, Zimbabwe
Telephone +236 4 853 271-2
Mobile: +263 77 225 9821

www.virimaiprojects.co.zw

 
 (VIRIMAI PROJECTS LOGO)Page 1
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

DATE AND SIGNATURES

 

This Report titled “NATIONAL INSTRUMENT 43-101 Independent Technical Report - Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa” prepared for Tanzanian Gold Corporation has an effective date of May 15, 2020, and has been prepared and signed on June 8, 2020 by the following author, as shown in the Appendices:

 

QUALIFIED PERSONS:

 

Wenceslaus Kutekwatekwa (Mining Engineer, Mining and Project Management Consultant)

 

BSc Hons (Mining Eng.), MBA, FSAIMM, FIoDZ, PRINCE 2®, MAMMZ, MPMIZ

 

(-s- WENCESLAUS KUTEKWATEKWA)

 

Dr. Frank K Crundwell (Metallurgical Consultant, Director CP Solutions Private Limited)

 

BSc (Eng.) Chem BSc (Financial Maths) MSc (Eng.) PhD Pr Eng. FSAIMM, FIChemE

 

(-s- DR. FRANK K CRUNDWELL)

 
 (VIRIMAI PROJECTS LOGO)Page 2
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

CONTENTS

 

1. SUMMARY 14
     
1.1 Introduction 14
     
1.2 Location, Property Description and Ownership 14
     
1.3 Geology and Mineralization 15
     
1.4 Exploration, Drilling, Sampling and QA/QC 16
     
1.5 Mineral Processing and Metallurgical Testing 16
     
1.6 Mineral Resource Estimation 16
     
1.6.1 Exploration Targets 17
     
1.7 Mineral Reserves 18
     
1.8 Interpretations and Conclusions 19
     
1.9 Recommendations 20
     
2. INTRODUCTION 22
     
2.1 Scope of Study 22
     
2.2 Qualified Person and List of Consultants 22
     
2.3 Effective Dates and Declaration 23
     
2.4 Sources of Information 23
     
2.5 Site Visit 24
     
2.6 Acknowledgement 24
     
3. RELIANCE ON OTHER EXPERTS 25
     
4. PROPERTY DESCRIPTION AND LOCATION 26
     
4.1 Mineral Tenure 26
     
4.2 Mining Rights in Tanzania 27
     
i. Basis for Mineral Title 27
     
ii. Exploration Permits (Rights and Obligation) 27
     
iii. Project Mining Permits 28
     
4.3 Underlying Agreements 29
     
i. Environmental Considerations 30
     
5. ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 31
     
5.1 Accessibility 31

 
 (VIRIMAI PROJECTS LOGO)Page 3
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

5.2 Climate 31
     
5.3 Physiography 31
     
5.4 Local Resources 32
     
6. HISTORY 34
     
6.1 Previous Exploration Work 34
     
7. GEOLOGICAL SETTING AND MINERALIZATION 36
     
7.1 REGIONAL GEOLOGICAL SETTING 36
     
7.3 DEPOSIT GEOLOGY 41
     
7.3.1 Buckreef Deposit 41
     
7.3.2 Bingwa Deposit 44
     
7.3.3 Eastern Porphyry Deposit 46
     
7.3.4 Tembo Deposit 47
     
7.4 STRUCTURAL SETTING AND MINERALIZATION 47
     
8 DEPOSIT TYPES 51
     
8.1 Regional 51
     
8.2 Buckreef Gold Deposits 51
     
8.3 Buckreef Deposit Model 54
     
8.4 Conclusion 58
     
9 EXPLORATION 59
     
9.1 Buckreef Gold Project 60
     
10. DRILLING 64
     
11. SAMPLE PREPARATION, ANALYSES AND SECURITY 71
     
11.1 Core Sampling Methods 71
     
11.2 RC/RAB Sampling Methods 72
     
11.3 Sample preparation and Analysis 73
     
11.4 QUALITY ASSURANCE & QUALITY CONTROL (QA/QC) PROCEDURE 2019 DRILLING PROGRAMME 74
     
i. Blanks 74
     
ii. Field Duplicates and Pulp duplicates 75
     
iii. Certified Reference Materials (CRM) 76
     
iv. Umpire samples 81

 
 (VIRIMAI PROJECTS LOGO)Page 4
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

12. DATA VERIFICATION 83
     
12.1 Drill Data Review 83
     
12.2 Collar Location Checks 83
     
12.3 Drill hole and Assays Checks 84
     
12.4 Geology Checks 84
     
12.5 Core Assay Checks 84
     
12.6 Verifications by QPs 85
     
13. MINERAL PROCESSING AND METALLURGICAL TESTING 87
     
13.1 Introduction 87
     
13.2 Previous test work 87
     
13.3 Metallurgical Testwork on Buckreef Samples – Geita Gold Mining Ltd 87
     
13.4 Scoping and diagnostic test work – Gallery Gold 88
     
13.5 Phase 2 Metallurgical test work – IAMGOLD 88
     
i. Grinding test work 88
     
ii. Process selection test work 88
     
13.6 Heap leaching test work 89
     
i. Simulated heap tests – SGS 2009 89
     
ii. Heap leaching amenability test work – SGS 2016 89
     
iii. Conclusions concerning heap leaching 89
     
13.7 Conclusions from the test work initiated prior to this study 90
     
13.8 Documentation 90
     
13.9 Metallurgical test work. 90
     
i. Purpose of the test work 90
     
ii. Sample origin 90
     
13.10 Grade and deportment 91
     
i. Head grade 91
     
ii. Gold deportment in the milled material 92
     
13.11 Milling 93
     
i. Bond milling index 93
     
ii. Pilot milling 94

 
 (VIRIMAI PROJECTS LOGO)Page 5
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

13.12 Gravity concentration 96
     
13.13 Cyanidation 97
     
13.14 Conclusions 98
     
13.15 Recommendations 99
     
13.16 Concluding Remarks 99
     
14. MINERAL RESOURCE ESTIMATE 100
     
14.1 Introduction 100
     
14.2 Mineral Resource Modelling 100
     
14.2.1 Sample Distribution and Statistics 104
     
14.2.1 Outlier Analysis 104
     
14.3 Mineral Resource Estimation Models 105
     
14.3.1 Density 108
     
14.4 Mineral Resource Estimation Checks 108
     
14.5 Mineral Resource Classification and Reporting 110
     
14.6 Exploration Targets 112
     
14.7 Mineral Resources and Conclusions 113
     
15. MINERAL RESERVE ESTIMATE 114
     
15.1 Introduction 114
     
15.2 Open Pit Mining 115
     
15.3 Resource Block Model 115
     
15.4 Open Pit Optimization 116
     
15.4.1 Buckreef Pit 117
     
15.4.2 Bingwa Pit 118
     
15.4.3 Eastern Porphyry Pit 119
     
15.4.4 Tembo Pit 120
     
15.5 Detailed Mine Design 121
     
15.6 In-Pit Dilution and Mining Recovery 123
     
15.7 Cut-Off Grade Criteria 124
     
15.8 Open Pit Material Inventory 124
     
15.1 Concluding Remarks 125

 
 (VIRIMAI PROJECTS LOGO)Page 6
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

16. MINING METHOD 126
     
17. RECOVERY METHODS 136
     
17.1 Introduction 136
     
17.2 Description of the ore 136
     
17.2.1 Ore types 136
     
17.2.2 Head grade 136
     
17.3 Processing strategy 136
     
17.4 Overall Design Criteria 137
     
17.5 Mass balance 137
     
17.6 Process Description and Design Criteria 137
     
17.6.1 Ore receipt and scrubbing 139
     
17.6.2 Crushing and milling 140
     
17.6.3 Gravity concentration 141
     
17.6.4 Thickening plant 141
     
17.6.5 Carbon-in-leach plant 142
     
17.6.6 Carbon Acid wash and Elution 143
     
17.6.7 Carbon regeneration 143
     
17.7 Tailings treatment 144
     
i. Reagents 144
     
17.8 Utilities 144
     
17.9 Equipment 145
     
17.9.1 General equipment selection 145
     
17.9.2 EDS Mill 145
     
17.10 Power consumption 147
     
17.11 Summary and Conclusions 147
     
17.1 Concluding Remarks 147
     
18. PROJECT INFRASTRUCTURE 148
     
18.1 Introduction 148
     
18.2 Site Layout 148
     
19. MARKET STUDIES AND CONTRACTS 150

 
 (VIRIMAI PROJECTS LOGO)Page 7
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

19.1 Market Studies 150
     
19.2 Contracts 150
     
20. ENVIRONMENTAL AND SOCIAL IMPACT STUDIES PERMITTING AND SOCIAL AND COMMUNITY IMPACT 151
     
20.1 General Approach 151
     
20.2 Environmental Studies 151
     
20.3 Community and Government Communications 151
     
20.4 Overview 152
     
i. Climate, Air Quality and Sound 152
     
ii. Physiography, Soils and Geology 152
     
iii. Surface Water and Sediment 153
     
20.5 Groundwater Quality 153
     
20.6 Biological Environment 153
     
20.6.1 Vegetation 153
     
20.6.2 Wildlife 154
     
20.6.3 Human Environment 154
     
20.6.4 Population 154
     
20.6.5 Health 155
     
20.6.6 Farming 155
     
20.6.7 Livestock 155
     
20.6.8 Commerce 155
     
20.6.9 Gold Mining 156
     
20.7 Seismicity 156
     
20.8 Environmental Sensitivities 157
     
20.9 Regulatory Context 157
     
21. CAPITAL AND OPERATING COSTS ESTIMATES 158
     
22. ECONOMIC ANALYSIS 168
     
22.1 Cash-flow Model 168
     
22.2 Discount Rate 168
     
22.3 Tax 168
     
22.4 Inflation 169

 
 (VIRIMAI PROJECTS LOGO)Page 8
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

22.5 Revenue 169
     
22.6 Royalty 169
     
22.7 Selling Costs 170
     
22.8 Summary of the Parameters Used in the Financial Model 170
     
22.9 Financial Analysis 171
     
22.10 Financial Analysis Summary 173
     
22.11 Financial Model Sensitivity Analysis 173
     
23. ADJACENT PROPERTIES 175
     
24. OTHER RELEVANT DATA AND INFORMATION 177
     
25. INTERPRETATION AND CONCLUSIONS 178
     
26. RECOMMENDATIONS 180
     
27. REFERENCE 181
     
28. ABBREVIATIONS GENERAL 182
     
29. MEASURES OF QUANTITY 183
     
30. ORGANISATIONS 184
     
31. GLOSSARY 185
     
32. APPENDICES 191
     
32.1 Certificate of Qualified Persons 191
     
32.2 Consent to publish 195
     
32.3 ESIA CERTIFICATION 197
     
32.4 LABORATORIES ACCREDITATION CERTIFICATES 198
     
32.5 PROCESS FLOW DIAGRAMS 201
     
32.6 PROCESSING PLANT MECHANICAL ITEMS 214
     
32.7 TABLES APPENDICES 218
     
     

 
 (VIRIMAI PROJECTS LOGO)Page 9
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

List of Tables  
Table 1.1: Buckreef Project March 2020 Mineral Resource 17
Table 1.2 Exploration targets at the Buckreef Shear Zone 17
Table 1.3: Buckreef Project Pit-Design Optimized Mineral & ROM stockpile Reserves as at 26 June 2018 19
Table 1.4: Buckreef Mineral Reserve Statement as at 26 June 2018 19
Table 2.2 Qualified Person and Contributors Site Visits 24
Table 7.1: Summary of Rock names and mineralogy typical at Buckreef Gold Mine 43
Table 9.1 Summary of Buckreef Project, Historical Exploration Work, Geita District, Tanzania 59
Table 9.2: Mineral Resource Upgrade drilling program statistics, Buckreef Gold Deposit 62
Table 11.1 Range of CRM Used during the 2019 sampling Programme 77
Table 11.2 Pass rate of CRMs used during the 2019 sampling Programme 77
Table 11.2: Comparison of the Nesch Mintech Lab and SGS. 81
Table 13.1. Key results from Gieta Gold test work. 87
Table 13.2. Key results from Gallery Gold test work. 88
Table 13.3. Milling characteristics. 88
Table 13.4. Recoveries for different processing options. 89
Table 13.5. Recommended recovery assumptions for project evaluation. 89
Table 13.6. Head analysis for gold 91
Table 13.7 Bond mill indices for oxide and sulphide ore materials. 93
Table 13.8. Cyanidation results for the oxide and sulphide ores. 97
Table 13.9. Cyanide and lime consumption summary. 98
Table 14.1: Statistics of 1m samples and composites within the resource wireframes 104
Table 14.2 Buckreef Summary Semi-Variogram Parameters 106
Table 14.3: Summary of Buckreef search parameters 107
Table 14.4 Buckreef Project Resource models, Geita District, Tanzania 107
Table 14.5 Buckreef Project Updated Resource Model Density 108
Table 14.6 Buckreef Project Resource models, Geita District, Tanzania 110
Table 14.7: Buckreef Shear Zone March 2020 Mineral Resource Updated Estimates at 0.4g/t Block Cut off 111
Table 14.8: Buckreef Project March 2020 Mineral Resource 111
Table 14.9: Buckreef Project 2020 vs 2018 reconciliation 112
Table 14.10 Exploration targets at the Buckreef Shear Zone 112
Table 15.1: Key Economic Parameters 116
Table 15.2: Main Operating Constraints 116
Table 15.3: Geotechnical Parameters 116
Table 15.4: Processing Parameters 116
Table 15-6 Mine Design Parameters 122
Table 15.7 Open Pit Reserves Summary 124
Table 16.4 Summary of Scheduled Milled Tonnages and Waste Tonnages (Refer Appendix 16.1) 130
Table 16.5 Summary of Scheduled Tonnages by Pit Tonnages 131
Table 16.5 Summary of Waste Dump Volumes at each of the Pits 133
Table 17.1 Design head grade for oxide and sulphide ores 136

 
 (VIRIMAI PROJECTS LOGO)Page 10
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 17.2 Overall design criteria 137
Table 17.3 Design criteria for the scrubber/screen. 140
Table 17.4 Design criteria for the jaw crusher. 140
Table 17.5 Design criteria for the EDS mill and classification circuit. 140
Table 17.6 Design criteria for gravity concentrators. 141
Table 17.7 Design criteria for the shaking table. 141
Table 17.8 Design criteria for the dewatering cyclone. 142
Table 17.9 Design criteria for the thickener. 142
Table 17.10 Design criteria for the carbon-in-leach section. 142
Table 17.11 Design criteria for the tails screening. 143
Table 17.12 Design criteria for carbon elution. 143
Table 17.13 Design criteria for tailings detoxification. 144
Table 17.14 Industrial applications of the EDS mill. 146
Table 17.15 Status of Buckreef design. 147
Table 21.1 Summary of the Capital Costs estimates 159
Table 21.1 Summary of the Mining Operating Costs 163
Table 21.2: Mining rates for the Buckreef 164
Table 21.3: Processing Chemical Consumption & Cost estimation 165
Table 21.4: Annual TSF Management Costs 165
Table 21.5: Summary of Processing Costs estimates 165
Table 21.6: Labour and General Costs Summary 166
Table 21.7: Operating Costs Summary 167
Table 22.1 Summary of Government taxes and levies used in costing and the Financial Model 169
Table 22.2 Summary of the inputs into the Financial Model 170
Table 22.3: Financial Analysis of the Buckreef Gold Project 171
Table 22.4: Results of the After-Tax Financial Analysis of the Buckreef Gold Project 173
Table 25.1 Comparison of Buckreef June 2018 and May 2020 Mineral Resources: 178
Table 32.1: Buckreef Project Full Schedule of Mined Tonnages 218
Table 32.1: Buckreef Project Full Schedule of Mined Tonnages 220
Table 32.2 Buckreef Project Summary of Schedule of Milled Tonnages 221
Table 32.3: Full Schedule of Staffing Requirements of the Buckreef Project 222
Table 32.4: Summary of Capital Costs Estimates 225
Table 32.50: Equipment Operating Costs\ 227
Table 32.7: Buckreef Cash Flow Analysis 229
Figure 32.14. Expert Opinion on Buckreef Gold Project After-Tax Cashflow, NPV & IRR 230
Table 32.1: Buckreef Project Full Schedule of Mined Tonnages 231
Table 32.2 Buckreef Project Summary of Schedule of Milled Tonnages 232
Table 32.3: Full Schedule of Staffing Requirements of the Buckreef Project 233
Table 32.4: Summary of Capital Costs Estimates 236
Table 32.50: Equipment Operating Costs\ 238
Table 32.7: Buckreef Cash Flow Analysis 240

 
 (VIRIMAI PROJECTS LOGO)Page 11
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

LIST OF FIGURES  
   
Figure 1.2.1. Location Map 15
Figure 4.1: Location of the Buckreef Gold Project, Gieta District Tanzania 26
Figure 4.2: Buckreef Gold Project, TRX License Holdings, Geita District, Tanzania 27
Figure 4.3 Buckreef Project: Deposit Locality within Special Mining License Boundaries, Geita District 29
Figure 5.1 Buckreef Project: Physiographic Map of North western districts of Tanzania 32
Figure 7.2 Regional Structural Geology Setting, Buckreef Project, Rwamgaza Greenstone Belt, Geita District, Tanzania 38
Figure 7.3 Local Geological Setting, Buckreef Project, Rwamagaza Greenstone Belt, Geita District, Tanzania 40
Source: TRX 2020 42
Figure 7.3 Local Geological Setting, Buckreef Deposit, Geita District, Tanzania 42
Figure 7.4 Local Geological Setting, Bingwa Deposit, Geita District, Tanzania 45
Figure 7.5 Local Geological Setting, Eastern Porphyry Deposit, Geita District, Tanzania 46
Figure 7.6 Local Geological Setting, Tembo Deposit, Geita District, Tanzania 47
Figure 7.7 Structural Setting, Buckreef Deposit, Geita District, Tanzania 48
Figure 7.8 Structural Setting of the Main Buckreef Prospect, Rwamagaza Greenstone Belt, Geita District, Tanzania 49
Figure 8.1: Buckreef deposit (yellow areas represent projection of mineralized orebodies to surface). 54
Figure 8.2: Inversion of the basin Buckreef structure reactivates as a strike slip transfer fault while original normal faults are now reverse faults. 55
Figure 8.3: Intrusion of Felsic Porphyries controlled by basinal structures. 55
Figure 8.4: Inversion of basin-Buckreef structure reactivates as a strike slip transfer fault while original normal fault are now reverse faults. 55
Figure 8.5: Brecciation of the previously altered zones (Early Stages of Au Mineralisation). 56
Figure 8.7: Continued Cyclic rupturing of the Buckreef fault zone under high fluid pressure conditions resulting in extensive alteration a series of printing brecciation events. 56
Figure 8.8: Illustrates the classic plunge possibilities for classic fault orientations. As Buckreef appears to have been dominantly strike slip we would expect a steep to sub vertical shoot geometry controlled by the  2 direction 57
Figure 9.1: Spatial location of the Mineral Resource Upgrade drill-holes, Buckreef Gold Deposit 2019/2020 63
Figure 10.1 Location of Historical RC/DD exploration and Resource drill-holes, Buckreef Deposit, Geita District, Tanzania 65
Figure 10.2 Location of Historical RC/DD exploration and Resource drill-holes, Bingwa Deposit, Geita District, Tanzania 66
Figure 10.3 Location of Historical RC/DD exploration and Resource drill-holes, Eastern Porphyry Deposit, Geita District, Tanzania 67
Figure 10.4 Location of Historical RC/DD exploration and Resource drill-holes, Tembo Deposit, Geita District, Tanzania 68
Figure 11.1: Drillholes used in 2019 Resource update 73
Figure 11.2: Coarse blanks assessment graph 74

 
 (VIRIMAI PROJECTS LOGO)Page 12
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Figure 11.3: Scatter plots for Field duplicates (left) and Pulp duplicates (right) 75
Figure 11.4: QQ plots for Field duplicates (left) and Pulp duplicates (right) 76
Figures 11.5 CRM ST100302 Nesch Mintech Mwanza Laboratory 77
Figures 11.5 CRM AUOM-3 Nesch Mintech Mwanza Laboratory 78
Figures 11.6 CRM AUOH-5 Nesch Mintech Mwanza Laboratory 78
Figures 11.7 CRM ST37/5340 Nesch Mintech Mwanza Laboratory 78
Figures 11.8 CRM OXE74 Nesch Mintech Mwanza Laboratory 79
Figures 11.9 CRM OXE56 Nesch Mintech Mwanza Laboratory 79
Figures 11.9 CRM AMIS0211-Nesch Mintech Mwanza Laboratory 79
Figures 11.10 CRM AMIS0234-Nesch Mintech Mwanza Laboratory 80
Figures 11.11 CRM OxC72-Nesch Mintech Mwanza Laboratory 80
Figures 11.12 CRM ST07/9258-Nesch Mintech Mwanza Laboratory 80
Figures 11.13 CRM ST07095344-Nesch Mintech Mwanza Laboratory 81
Figure 11.14: Scatter plot and QQ plot for umpire samples 82
Figure 12.1: Virimai Projects Team on Site 84
Figure 12.2: Virimai Team Checking on the Drilling on Site 85
Figure 13.1: Oxide ore before milling and after a single pass of milling in the multi-shaft EDS mill. 91
Figure 13.2: Sulphide ore before milling and after a single pass of milling in the multi-shaft EDS mill. 91
Figure 13.3: Gold grade and deportment by size fraction for the oxide ore, indicating that the gold deportment is higher in the fine fraction, bearing in mind that there is a high fines content of this ore. 92
Figure 13.4. Gold grade and deportment by size fraction for the sulphide ore, indicating that the gold is not concentrated in any one size fraction. 93
Figure 13.5. Principle of the EDS multi-shaft mill. 94
Figure 13.6. Particle-size distribution of the milled (product) oxide ore. (Source: MMSA Report No 15/059 r1) 95
Figure 13.7. Particle-size distribution of the milled (product) sulphide ore. (Source: MMSA Report No 15/059 r1) 95
Figure 13.8. Grade and recovery curves against mass pull for the oxide ore using the Falcon L40 concentrator 96
Figure 13.9. Grade and recovery curves against mass pull for the sulphide ore using the Falcon L40 concentrator. 97
Figure 14.1: Hard boundary illustrations 102
Figure 14.2: Plan View of the Buckreef Main Zone mineralised bodies 103
Figure 14.5: Virimai Projects block grade checks 109
Figure 14.6: Virimai Projects average sample grade compared to average estimated block grade checks 109

 
 (VIRIMAI PROJECTS LOGO)Page 13
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

1.SUMMARY

 

1.1Introduction

 

This report has been prepared by Virimai Projects (“Virimai”) for Tanzanian Gold Corporation (TRX) for the Update of the Mineral Resources Estimates of the Buckreef Gold Mine Project. The Mineral Resources Estimate of the Buckreef discussed in this “Independent Technical Report” has been prepared by Virimai Projects of Harare Zimbabwe at the request of TRX.

 

A press release confirming the definition of an update of the Mineral Resource Estimates for the Buckreef Gold Project was published in 17th March 2020 by TRX and that triggered this Independent Technical Report (ITR) to provide the details of the estimation methodology and results.

 

The contents of this report is based on exploration and drilling data collected by TRX and the results of estimation performed by Virimai Projects utilizing exploration and analytical data as of 28 February 2020. This Technical report was prepared in accordance with the guidelines set out in the National Instrument 43 -101 Standards of Disclosure for Mineral Projects (NI43 -101). The main intent of this study is to provide an update on the mineral resources of the Buckreef Gold Project based on Buckreef’s most recent data on the exploration of the Buckreef prospect. The Update Mineral Resource Estimates detailed in this report is based on drilling data collected by TRX during the period January 2019 to February 2020 period.

 

1.2Location, Property Description and Ownership

 

The Buckreef Gold Project is a description of four gold prospects which are namely Buckreef, Eastern Porphyry Tembo and Bingwa located in the Mnekezi Village in Geita District in north-central Tanzania. The project area is located 40km south west of the town of Geita, which in turn is approximately 110km south-west of the second largest city Mwanza.

 

The Buckreef Gold Project is a gold exploration project comprises, a single Special Mining License covering an area of 16.04km2 and 12 Prospecting Licenses covering 98.19km2. The current Mineral Resources and Mineral Reserves for the Buckreef Gold project are declared over Special Mining License block SML04/1992. In March 2017, the Buckreef gold special mining license (SML04/92) which covers an area of 16.04km2, was successfully renewed for a further 10 years to 16th June 2027. The licenses are operated by Buckreef Gold Company Limited, the Tanzam2000 (a subsidiary company of Tanzanian Gold Corporation).

 
 (VIRIMAI PROJECTS LOGO)Page 14
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(FIGURE 1.2.1)

 

Figure 1.2.1. Location Map

 

1.3Geology and Mineralization

 

The Buckreef Project is situated within the Lake Victoria Greenstone (LVG) belt of northern Tanzania which consists of several east-west trending, linear, Archaean greenstone belts. The LVG is the third largest gold producing region of Africa, surpassed only by the Witwatersrand Basin in South Africa and the Tarkwa region of Ghana. The Buckreef Project is in the regionally east-west trending Rwamagaza greenstone belt and this belt is considered a segment of the larger Sukumaland greenstone belt and is one of the larger greenstone belts in northern Tanzania.

 

Buckreef Gold Company Limited has defined four mineral deposits on the Buckreef Property. As estimated in this technical report, from largest to smallest based on ounces of gold, these include the Buckreef mineralized corridor, Bingwa, Eastern Porphyry and Tembo Deposits. The Buckreef Prospect is a shear zone hosted gold deposit within a sequence of mafic basalts and dolerites, near basement granite. The host rocks at the Buckreef deposit comprise primarily pillowed, amygdaloidal and massive mafic meta-volcanic rocks which have been intruded by medium to coarse grained dolerite sills and dykes. The gold mineralization at Buckreef Prospect is non-refractory in both fresh and oxide material. Gold mineralization at Bingwa is associated with quartz veining in strongly foliated and altered greenstone in a shear zone adjacent to the granitoid contact. The shear zone strikes northeast and dips steeply to the northwest. The Eastern Porphyry mineralization is associated with silicified and weakly pyritised shears, quartz veins and veinlets, and within quartz-feldspar porphyry. The Tembo deposit locates approximately 3km southwest of Buckreef Mine, adjacent to the main Rwamagaza Shear

 
 (VIRIMAI PROJECTS LOGO)Page 15
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Zone. The mineralized zones at Tembo are confined to the east – west trending shears within met-basaltic volcanic package. Gold mineralization is associated with grey quartz thin veins, stringers and boudins parallel to the shear fabric.

 

1.4Exploration, Drilling, Sampling and QA/QC

 

Historical exploration activities include geochemical and geophysical surveys, geologic mapping, and drilling by various operators in the period 2004 to 2020. The most recent drilling programme undertaken by TRX is that from January 2019 to February 2020 in which a total of 17650m of drilling was carried. This brings the total meterage drilled on the project to about 125,750m to date for the project. The recent drilling included reverse circulation holes and diamond core holes.

 

The majority of the assays used for the estimate were fire assay at accredited Nesch Mintech Laboratories in Mwanza. The sample preparation, analyses and security procedures implemented by TRX, Nesch Mintech meet standard practices and were monitored using control samples, blanks, certified reference materials duplicates. On the basis of the quality assurances procedures and the quality control put in place at Buckreef it is the opinion of Wenceslaus Kutekwatekwa that the sampling preparation security and analytical procedures used by TRX are consistent with generally accepted industry best practise and are therefore adequate for use in mineral resource estimation and classification of Mineral Resources in accordance with generally accepted CIM standards.

 

1.5Mineral Processing and Metallurgical Testing

 

No detailed Metallurgical test works have been completed as part of this current mineral resource update study. Virimai’s assumptions on economic recoveries are based on the several previous test work carried out and reported in previous filling by “SEDAR”. The test work conducted by MPC and SGS has shown that more than 90% of the gold can be recovered by a combination of gravity concentration and leaching of the tails. The MMSA test work established that 93% of the gold from the oxide ore can be recovered without gravity concentration by carbon-in-pulp leaching. The work established that 85% of the gold from the sulphide can be recovered in a similar manner.

 

1.6Mineral Resource Estimation

 

The mineral Resource model presented herein represents an update resource evaluation prepared by Virimai Projects following on the drilling programme of 2019 on the Buckreef Prospect. The Mineral Resources of the other three areas, namely Eastern Porphyry, Tembo and Bingwa, were adopted as reported in the 2018 NI-43-101 report as there was no additional drilling on the three deposits. The resources estimates of these three deposits are presented in this mineral resource update report without amendments. The Mineral Resource estimate was informed by both the diamond drilling and reverse circulation drilling results using only samples confined within the Mineral Resource wireframes constructed by Virimai Projects in Datamine™ Studio 3 (version 3.21.7164).

 
 (VIRIMAI PROJECTS LOGO)Page 16
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

In the Resource classification Virimai Projects considered that blocks estimated during the first estimation run considering full variogram ranges can be classified in the Measured category and the second estimation run (at one and half times the search volume) can be classified in the Indicated category. In both cases the classification also took into account kriging efficiency through the slope of regression. For these blocks, Virimai Projects considers that the level of confidence is sufficient to allow appropriate application of technical and economic parameters to support mine planning and to allow evaluation of the economic viability of the deposit. Blocks estimated during the third pass considering search neighbourhoods set at twice or more the variogram ranges were appropriately classified in the Inferred category because the confidence in the estimate is insufficient to allow for the meaningful application of technical and economic parameters or to enable an evaluation of economic viability.

 

The NI-43101 compliant Mineral Resource estimate as revised by Virimai Projects is shown Table 1.1.

 

Table 1.1: Buckreef Project March 2020 Mineral Resource

 

Prospect Measured Indicated Inferred Total Measured + Indicated
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
(Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz)
Buckreef 19.98 1.99 1,281,160 15.89 1.48 755,120 17.82 1.11 635,540 35.88 1.77 2,036,280
Eastern Porphyry 0.09 1.20 3,366 1.02 1.17 38,339 1.24 1.39 55,380 1.10 1.18 41,705
Tembo 0.02 0.99 531 0.19 1.77 10,518 0.27 1.92 16,461 0.20 1.70 11,048
Bingwa 0.90 2.84 82,145 0.49 1.48 23,331 0.22 1.49 10,541 1.39 2.36 105,477
Total 20.99 2.03 1,367,202 17.59 1.46 827,308 19.55 1.14 717,922 38.57 1.77 2,194,510

 

# Buckreef has been updated and reported at 0.40 g/t Au block cut-off

 

# Eastern Porphyry, Bingwa and Tembo Mineral Resources are quoted at 0.50 g/t Au block cut-off as per last update

 

1.6.1Exploration Targets

 

Besides the estimated resources tabulated herein, there are exploration targets within and extending beyond these Mineral Resources. Significant potential lies within the Buckreef Shear Zone that is summarised in Table 1.2. These targets are as such due to the openness of depth and the north eastern strike as well as the consistence of the results from some deep hole drilled to date.

 

Table 1.2 Exploration targets at the Buckreef Shear Zone

 

Target Area Tonnage Range Grade Range Au (g/t) Ounces Range
Minimum Maximum Minimum Maximum Minimum Maximum
Northeast Extension 4,000,000 6,000,000 1.40 2.50 180,000 482,300
Main Zone 25,000,000 35,000,000 1.30 1.50 1,045,000 1,688,000

 

In should be noted that the potential quantity and grade of these exploration targets is conceptual in nature, that there has been insufficient exploration to define a mineral resource and that it is uncertain if further exploration will result in the target being delineated as a mineral resource as per the NI 43-101 reporting standards. The exploration targets include five isolated drill holes and assume projections of mineralized

 
 (VIRIMAI PROJECTS LOGO)Page 17
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

structures to deep levels as well as an extension of the Northeast Zone, and are based a continuation of favourable geological conditions that host mineralized structures that have been encountered in shallower drilling of Phase 2 to deep levels below the limits of the current wireframes used in the estimation of the new resources described herein. The exploration targets assume that the extension of the Northeast Zone along strike will be confirmed by additional drilling.

 

The Phase 3 drilling program is currently underway to further test the continuity of these mineralized structures. Current information from drill holes show high grade intersections including drill-hole BMRCD298 with an intercept average 2.45 g/t from 650 m to 681 m down the hole (NE Extension) and drill-hole BMRCD309 with an intercept average 3.4 g/t from 617 m to 630 m down the hole (Main North).

 

1.7Mineral Reserves

 

The last Mineral Reserves estimate for the Buckreef Gold Project are as reported in the last published ITR titled “Amended NATIONAL INSTRUMENT 43-101 Independent Technical Report Mineral Reserves Estimate and Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” (Virimai 2018). No update Mineral Reserves have been estimated for the Buckreef Gold Project in this current report for Mineral Resources. A new pit optimisation taking into account of the current Mineral Resources update in the Buckreef prospect and the current prevailing economic factors is still to be completed. The mining philosophy for the development of the Buckreef Gold Project still remains that of initial open pit on the Buckreef deposit and possible transitioning into underground mining at depth while it will be purely open pit for the other three smaller deposits as outlined in the ITR (Virimai 2018).

 

The mineral reserves reported in this update report are those in the report titled “Amended NATIONAL INSTRUMENT 43-101 Independent Technical Report Mineral Reserves Estimate and Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa.” June 2018:

 

From the published 2014 Venymn Deloitte NI-43-101 compliant Mineral Resource estimate technical report, Virimai Projects essentially overhauled and improved on the original overall mining philosophy have produced a NI-43-101 compliant Mineral Reserve estimate for Buckreef Gold Project based on the original resource block models, achievable mining shapes, mining recovery, mining dilution and open-pit pre-production development cost considerations.

 

The Buckreef Project Mineral Reserve estimate is based on a gold cut-off grade of 0.37 grams per tonne) which has been calculated from the following parameters:

 

a)Gold Price (pit shell): US$ 1,300 per oz
b)Mining Cost: US$19.00 per ton of ore
c)Process Cost: US$10.24 per ton of ore
d)G & A Cost: US$1.98 per ton of ore
e)Recovery: 92.3% for oxides
f)Recovery 85.0% for sulphides

 

The Mineral Reserve estimate for the Project is tabulated in Table 1.4.

 

 
 (VIRIMAI PROJECTS LOGO)Page 18
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 1.3: Buckreef Project Pit-Design Optimized Mineral & ROM stockpile Reserves as at 26 June 2018

 

Pits Design Reserves Summary COG: Oxide & Trans = 0.38, Fresh = 0.41
Virimai 26th June 2018 Pit Design Reserves Summary
Prospect Reserves Tonnes Grade In Situ Gold Content
Name Category (Mt) Au (g/t) Kg oz
Buckreef Proven 8,174,415 1.64 13,374.06 429,985.66
Probable 8,174,147 1.40 11,435.72 367,666.58
Waste 160,217,840      
Total (Proven + Probable) 16,348,562 1.52 24,809.78 797,652.24
           
Eastern Porphyry Proven 79,385 1.17 93 2,982
Probable 976,281 1.03 1,003 32,242
Waste 9,823,917 0.02    
Total (Proven + Probable) 1,055,666 1.04 1,096 35,224
Tembo Proven - - - -
Probable 70,183 2 165 5,312
Waste 1,354,468 -    
Total (Proven + Probable) 70,183 2.35 111 3,582
Bingwa Proven 1,098,383 2.39 2,366 76,074
Probable 510,154 1.30 377 12,108
Waste 10,311,734      
Total (Proven + Probable) 1,608,536 2.04 2,743 88,182
Grand Total Proven 9,352,183 1.72 16,092 517,358
Probable 9,730,764 1.36 13,265 426,492
Proven +Probable 19,082,947 1.54 16,749 943,851

Source: Virimai Projects 2018

 

(1) Mineral Resource is inclusive of Mineral Reserve shapes, mining recovery, mining dilution and open-pit preproduction development costs. Mineral Reserve estimate includes dilution.

 

(2) Mineral Reserve was estimated using NI43-101F compliant Standards on Mineral Resources and Reserves, Definitions.

 

(3) Ccontained metal may differ due to rounding.

 

The reserve statement for the Buckreef Gold Project is as summarised in table 1.5

 

Table 1.4: Buckreef Mineral Reserve Statement as at 26 June 2018

  

  Tonnes Grade In Situ Gold Content
(Mt) Au (g/t) Kg oz
Buckreef Project Proven -Stockpile 119,726 1.86 223 7,160
Proven 9,352,183 1.72 16,092 517,358
Probable 9,730,764 1.36 13,265 426,492
Mineral Reserves 19,202,673 1.54 29,580 951,010

 

(1) Mineral Resource is inclusive of Mineral Reserve shapes, mining recovery, mining dilution and open-pit preproduction development costs. Mineral Reserve estimate includes dilution.

 

(2) Mineral Reserve was estimated using NI43-101F compliant Standards on Mineral Resources and Reserves, Definitions.

 

(3) Ccontained metal may differ due to rounding.

 

Reserves were calculated from pit design. Full Grade Ore cut-off grade (FGO) calculations rely on inputs from this study and other sections of the Buckreef Prefeasibility study. Reserves are based on a gold price of $1300/oz for pit design, and cut-off grade 0.38g/t. Inferred Mineral Resources are considered geologically speculative and are not used in project economics, nor are they considered for mining plans. The study is only restricted to open pit mining at this stage with.

 

1.8Interpretations and Conclusions

 

TRX has undertaken detailed exploration diamond core drilling and sampling of the Buckreef deposit during the period January 2019 to February 2020 with the aim of upgrading the inferred resources within the pit shell

 
 (VIRIMAI PROJECTS LOGO)Page 19
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

generated by Virimai Projects in 2018 and to test for the mineralisation continuity down dip below the pit shells. These activities have been undertaken by applying industry best standard methods and practices.

 

Sample collection and preparation has been done using industry best practices and analysis have been undertaken by certified laboratory resulting in results that support the Mineral Resource estimates as fully outlined in Chapter 14 of this update report. In light of the results of this resource update Mr W Kutekwatekwa recommend the advancement of the project to a full feasibility study.

 

The project has positive attributes that justify the advancement of the project to the next stage. Some of positive attributes of the project which were fully outlined in the Amended ITR of 2018 (Virimai Projects 2018) include the following:

 

Increased inventory of mineral resources in the Buckreef prospect.
Metallurgical test work provides favourable indications that optimal gold recoveries can be achieved through cyanidation leaching of both oxides and fresh rock mineralization. Test work of samples of the both oxides and sulphides indicates that recoveries in the order of 92% for oxides and 90% for fresh rock can be achieved.
The project can be developed in stages utilizing cash flows from free dig oxides mineralization to capitalize future fresh rock mining and processing of the deposit.
The potential for transitioning from open pit to underground exists as indicated from the down dip mineral resources at depth which cannot be accessed through open pit mining.
The objective of Virimai’s mandate was to prepare an updated mineral resource estimate for the Buckreef Project and prepare a supporting Independent Technical Report (ITR) in compliance with NI43-101 and CIM Definition Standards. After conducting a detailed review of all pertinent information and completing the mandate Mr W Kutekwatekwa concludes as follows:
The data base supporting the 2020 Mineral Resource Estimate for the Buckreef Gold Project is complete, valid, and up to date (including historical drilling and current drilling 2019 program)
The geological and grade continuity of gold mineralization in the Buckreef deposit has been demonstrated and is supported by surface drilling carried out in the area.
The mineral resource estimate is considered to be reliable, thorough and based on quality data and reasonable assumptions in accordance with NI43-101 requirements and CIM Definitions Standards.

 

1.9Recommendations

 

The project appears to have positive attributes that justify the advancement of the project and in that vein, Mr Wenceslaus Kutekwatekwa would recommend the following follow:

 

1.To continue with the ultra-deep drilling programme to increased inventory of mineral resources down dip and the north east strike mineralization’s extend in the Buckreef Main in the identified explorations targets.
2.Complete the metallurgical testing of the fresh rock samples to identify the low costs alternative processing of the ores of the Buckreef Project.

 
 (VIRIMAI PROJECTS LOGO)Page 20
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

3.To carry out rock geo-technical studies to see their impact on the pit slope stability and possible underground mining options.
4.To carry out additional detailed metallurgical test work, on all significant lithological domains, to inform the gold recovery methods and the development of the processing flow sheet.
5.To recomputed the Mineral Reserves on the updated Mineral Resources in this report.
6.To proceed to the project full Feasibility Study.
7.To maintain a strict local legal compliance checklist for the project, in order to close any unreasonable political machinations.

 
 (VIRIMAI PROJECTS LOGO)Page 21
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

2.INTRODUCTION

 

Buckreef Gold Project (“Buckreef”) is an advanced exploration gold project which comprise of four gold deposits namely Buckreef, Eastern Porphyry, Tembo and Bwinga all within 4km of each other. Buckreef deposit is the largest of the four deposits of the area. The gold project is located in the Geita District in Tanzania East Africa. Tanzanian Royalty Exploration Corporation (TRX) a Canadian Listed company owns 55% interest in the Buckreef Project with the other remaining 45% held by State Mining Corporation of Tanzania (Stamico).

 

The Update Independent Technical Report Mineral Resources Estimate of the Buckreef discussed in this “Technical Report” has been prepared by Virimai Projects at the request of TRX. The study was prepared and compiled by Virimai Projects of Harare Zimbabwe as fully defined in this report.

 

A press release confirming the definition of an update of the Mineral Resource Estimates for the Buckreef Gold Project was published in March 2020 by TRX and this Independent Technical Report (ITR) is the supporting technical report providing the details of the estimation methodology and results.

 

The content of this report is based on exploration and drilling data collected by TRX and the results of estimation performed by Virimai Projects utilizing exploration and analytical data as of 28th February 2020. This Technical report was prepared in accordance with the guidelines set out in the National Instruments 43 - 101 Standards of Disclosure for Mineral Projects (NI43 -101). The main intent of this study is to provide an update on the mineral resources of the Buckreef Gold Project based on Buckreef’s most recent data on the exploration of the Buckreef prospect. Technical information including locations, mapping analytical data has been provided by TRX staff with supervision of Mr Kutekwatekwa of Virimai Projects during the exploration period.

 

The report draws some of its information from the previous reports filed with SEDAR (list). Where there has been no change most of the chapters have been reproduced as in the previous or latest filing.

 

2.1Scope of Study

 

Virimai Projects was mandated to compile a technical report regarding the update of the mineral resources of the Buckreef Gold Project located in the Geita District in Tanzania East Africa, based on additional information and data generated during the exploration programme of January 2019 to February 2020. This technical report was prepared to comply with the disclosure and reporting requirements of National Instrument 43-101 (NI 43-101) and form 43-101F1. The mineral resources estimation is based on the CIM standards.

 

2.2Qualified Person and List of Consultants

 

This study was prepared at the request of Mr James Sinclair, President and Chairman of TRX. TRX is a Canadian publicly traded company listed on the Toronto Stock Exchange (TSX) under the trading symbol TRX with its head office situated at:

 

Tanzanian Gold Corporation
82 Richmond Street West
Suite 208
Toronto ON
Canada N5C 1P1

 
 (VIRIMAI PROJECTS LOGO)Page 22
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

This report titled “NATIONAL INSTRUMENT 43-101 Independent Technical Report - Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa” was prepared by Mr Wenceslaus Kutekwatekwa a mining consultant with Virimai Projects for all Items except 13 and 17 for which Dr Frank Crundwell a metallurgical consultant with CP Solutions is responsible for.

 

The QPs acknowledges the contribution of the following personnel in the compilation of the update report.

 

Arimon Ngilazi BSc (Geology & Physics), BSC Hons Geology, CFSG (Mining Geostatistics) MBA, MSAIMM, MAusIMM, MGASA, MGSZ
Wonder Mutematsaka BSc (Mining Engineer), ARSM, MBL(Unisa) Pr Eng. MASME, MZIE, MSAIMM
Clarence Ndunguru (Mining Engineer) BSc (Mining Eng.), MSAIMM, MAusIMM
Peter Zizhou (General Manager / Geologist) MSc (Geology), BSc Hons (Geology), Pri. Sci. Nat

 

2.3Effective Dates and Declaration

 

This Technical Report titled “NATIONAL INSTRUMENT 43-101 Independent Technical Report - Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa” is considered effective as on the 15th of May, 2020. The QP opinion contained herein is based on information collected by Virimai Projects and TRX throughout the course of their investigations, which in turn reflects various technical and economic conditions at the time of writing. Given the nature of the mining business, these conditions can change significantly over relatively short periods of time. Consequently, actual results may be significantly more or less favourable.

 

This Report may include technical information which requires subsequent calculations to derive subtotals, totals and weighted averages. Such calculations inherently involve some degree of rounding and, consequently, introduce some margin of error. Where this occurs, the QP does not consider it to be material.

 

2.4Sources of Information

 

The “NATIONAL INSTRUMENT 43-101 Independent Technical Report - Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa” report is based on information supplied by TRX to Virimai Projects as summarized below and referenced in the text, and included in the reference Section 27 of this Technical Report: -

 

Historic exploration information from previous holders of the exploration rights, IAMGOLD Corporation (IAMGOLD), which surrendered the rights and exploration information to the Tanzanian government in 2009. The historic information is in the possession of TRX by virtue of the joint venture with Stamico;
In-house exploration results from surveys undertaken by IAMGOLD in the course of its tenure;
Published Venmyn independent technical reviews undertaken during the 2014 Mineral Resource update.
Published Virimai Projects, “Amended Independent Technical Mining Reserve Estimate Pre- Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” of June 26,2018.

 
 (VIRIMAI PROJECTS LOGO)Page 23
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

In-house exploration results from exploration surveys undertaken by TRX during the period January 2019 to February 2020.

 

This report titled, “NATIONAL INSTRUMENT 43-101 Independent Technical Report - Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa” (the “Technical Report”) was prepared to provide an update on the mineral resources of Buckreef Gold Mine based on the drilling and analytical results of the 2019-2020 drilling programme.

 

2.5Site Visit

 

Virimai Projects representatives conducted site visit to the Buckreef Gold Project as indicated in the Table 2.2 herein. The intention of the visits to carry out observations of the drilling operations, drill core, collar locations and orientations, drill samples and assessment of the laboratory facilities in Tanzania.

 

Table 2.2 Qualified Person and Contributors Site Visits

 

Company Contributor Status Site Visit
Virimai Projects Wenceslaus
Kutekwatekwa
Qualified Person
Independent
18-21 April 2018
21-28 February 2019
19 to 22 February 2020
Virimai Projects Arimon Ngilazi Contributor Independent 18-21 April 2018
21-28 February 2019
21 to 26 Sep 2019.
19 to 22 February 2020
Virimai Projects Wonder Mutematsaka Contributor Independent 18-21 April 2018,
19 to 22 February 2020
Virimai Projects Clarence Ndunguru Contributor Independent 5 May 2018

 

Dr. Frank Crundwell an independent Metallurgical consultant was contracted to TRX in 2018 to carry out metallurgical test work of the Buckreef ore samples in Johannesburg South Africa for the prefeasibility study is responsible for the preparation of Item 13 and Item 17 included in this update technical report for mineral resource estimate. Dr Crundwell did no visit the project as part of this update report on mineral resource estimates but is the co-author with Mr W Kutekwatekwa of the ITR titled “Amended Independent Technical Mining Reserve Estimate Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” of June 26, 2018.

 

2.6Acknowledgement

 

The QPs would like to extend their gratitude and acknowledge the support provided by Buckreef staff during their various visits to the project. The contributions of these team members are gratefully acknowledged. The Qualified Persons takes full responsibility of any of the contributions that made it into this report.

 
 (VIRIMAI PROJECTS LOGO)Page 24
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

3.RELIANCE ON OTHER EXPERTS

 

This Update Technical Report on the Mineral Resources Estimate of the Buck Reef has been prepared at the request of TRX. The QPs assigned to the current mandate is Wenceslaus Kutekwatekwa BSc Hons (Mining Eng.), MBA, FSAIMM for Items 1 to 12 and 14 to 27, and Dr Frank K Crundwell BSc (Eng.) Chem BSc (Financial Maths) MSc (Eng.) PhD of CP Solutions for Items 13 and 17of this update report. The QPs relied on the following the people or sources of information during the preparation of the technical update report:

 

Environmental Social Impact Assessment (ESIA) February 2014 carried out by Messrs Beatus J Mboya and J Nyaronyo of ENATA Private Limited for the Item 20 which was the basis of the certification of the project in 2014 (see EISA Certificate Appendix 32.3).
Review of after tax NPV Model computations in Item 22 was carried out by Mr John Shimbala a Tanzanian Tax Consultant of ARK Associates July 2018.
QP relied on information supplied by TRX on the legal opinion presented herein with respect to property titles, current ownership or possible litigation for Item 4.0

 
 (VIRIMAI PROJECTS LOGO)Page 25
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

4.PROPERTY DESCRIPTION AND LOCATION

 

The Buckreef Gold Project is a description of four gold prospects which are namely Buckreef, Eastern Porphyry Tembo and Bingwa located in the Mnekezi Village in Geita District in north-central Tanzania. The project area is located 40km south west of the town of Geita, which in turn is approximately 110km south-west of the second largest city Mwanza (Figure 4.1).

 

The area is fully located by the following Geographical co-ordinates:

 

Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN)

 

(Figure 4.1)
Figure 4.1: Location of the Buckreef Gold Project, Gieta District Tanzania

 

4.1Mineral Tenure

 

The Buckreef Gold Project is a gold exploration project comprises, a single Special Mining License covering an area of 16.04km2 and 12 Prospecting Licenses covering 98.19km2 (Figure 4.2).

 
 (VIRIMAI PROJECTS LOGO)Page 26
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 4.2)

 

Figure 4.2: Buckreef Gold Project, TRX License Holdings, Geita District, Tanzania

 

The current Mineral Resources and Mineral Reserves for the Buckreef Gold project are declared over Special Mining License block SML04/1992.

 

In March 2017, the Buckreef gold special mining license (SML04/92) which covers an area of 16.04km2, was successfully renewed for a further 10 years to 16th June 2027. The licenses are operated by Buckreef Gold Company Limited, the Tanzam2000 (a subsidiary company of Tanzanian Gold Corporation).

 

4.2Mining Rights in Tanzania

 

i.Basis for Mineral Title

 

The state owns title to all mineral resources in The Republic of Tanzania. All permits conferring rights to explore and extract mineral resources are granted by the Minister of Energy and Minerals, (“MEM”) in terms of the Tanzania 2010 Mining Act. The Mining Act serves as the legal framework governing mining in the Tanzania.

 

ii.Exploration Permits (Rights and Obligation)

 

The Ministry of Energy and Minerals (MEM) is responsible for guiding the development of the mining industry in Tanzania through the Mineral Division. The Tanzanian Mining Act, 2010, the Explosives Act, 1963, and the Mining (Mineral Rights) Regulations, 2010, regulate the law relating to prospecting and exploiting minerals, including granting, renewals, royalties, fees and other charges.

 
 (VIRIMAI PROJECTS LOGO)Page 27
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Mineral property and control over minerals is vested in The United Republic of Tanzania. Only companies incorporated in Tanzania may hold mineral rights in Tanzania; however, exploration and mining is open to foreign concerns. Royalties are charged on gross value which for precious metals is 6% and district council where a gold mine is located is entitled to collect a 0.3% on the revenues from gold production as service levy. There is no mandatory participation by the State although joint ventures with local companies are encouraged

 

Mineral rights under the Mining Act include Prospecting Licenses (PL), Retention Licenses (RL), Special Mining Licenses (SML), Mining Licenses (ML), Processing Licenses, Smelting Licenses and Refining Licenses. The prospecting license is granted for an initial period of 4 years. Upon 1st renewal, if the area is greater than 20 sq. km then 50% must be relinquished and the license is then valid for a further 3 years. Upon second renewal, if the license is greater than 20sq km then 50% must be relinquished and the license is then valid for a further 2 years. Mining Licenses are granted for an initial period of 10 years for medium scale mining operations with a capital investment between US$100,000 and US$100 million and are renewable. An Environmental Certificate issued by the National Environment Management Council (NEMC) is a prerequisite to the granting of a Mining License.

 

Special Mining Licenses (SML) are granted for large scale mining operations with a capital investment of more than US$100 million and are valid for the estimated mine life determined in the Bankable Feasibility Study (BFS). Holders of special mining licenses may enter into a Mining Development Agreement (MDA) with the Government which is subject to review every five years and at the renewal of the mineral right.

 

MDAs can guarantee fiscal stability for a long-term mining project, cover environmental matters which are project specific and not covered by the Mining Regulations, requirements for the procurement of goods and services available in Tanzania and the employment and training of citizens of Tanzania and the terms of State participation in long-term mining projects.

 

iii.Project Mining Permits

 

The Buckreef Project comprises four gold deposits, namely Buckreef (North, Main & South), Bingwa, Eastern Porphyry and Tembo all located within a single Special Mining License, SML04/1992 (Figure 4.2). Geographical co-ordinates for each respective deposit are:

 

Buckreef North: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN)
Buckreef Main: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN)
Buckreef South: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN)
Bingwa: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN)
Eastern Porphyry: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN) &

 
 (VIRIMAI PROJECTS LOGO)Page 28
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Tembo: Latitude 03ᵒ 5′ 27.69″ S Longitude 032o 1′ 20.65″ E (ARC 1960 UTM Zone 36m: Latitude 391,367.93mE; Longitude 9,658,326.9mN).

 

(Figure 4.3)
Figure 4.3 Buckreef Project: Deposit Locality within Special Mining License Boundaries, Geita District

 

The boundaries of the mining lease (SML04/1992) have been surveyed, whereas the boundaries of other, un-surveyed prospecting licenses are sourced from the Tanzanian Ministry of Energy and Minerals license maps.

 

4.3Underlying Agreements

 

The Buckreef Gold Project is a gold exploration project which was originally held by IAMGOLD prior to July 2009. The “Agreement to Redevelop the Buckreef Gold Mine (ARBGM) between IAMGOLD and the Ministry for Energy and Minerals included at that point, a single Special Mining License and 12 Prospecting Licenses covering 98.19km2.

 

In July 2010, IAMGOLD applied to surrender all licenses relating to the ARBGM, effective 25 October 2009, and the Commissioner for Minerals withdrew all license applications relating to the ARBGM. In 2010, TRX was invited by STAMICO on behalf of the Ministry of Energy and Minerals, to tender for the opportunity to negotiate a joint venture agreement with respect to the Buckreef Gold Project.

 

TRX was awarded the tender, as confirmed in a letter from the Director General of STAMICO dated 16 December 2010. In October 2011, TANZAM2000, a 100% owned subsidiary of TRX signed a joint venture

 
 (VIRIMAI PROJECTS LOGO)Page 29
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

agreement with STAMICO with regards to the Buckreef Gold Project. Through this JV agreement, a Tanzanian registered JV company, Buckreef Gold Company Limited, was formed with an equity holding of 55% Tanzam2000 and 45% STAMICO. In terms of the agreement, TRX through its subsidiary, Tanzam2000 will manage the Buckreef Project and is responsible for providing exploration and mine development financing. TRX expects that the project to be financed through debt or a combination of debt and equity. Net profits will be divided in accordance with the parties’ ownership interests after payment of all project expenses including debt service.

 

i.Environmental Considerations

 

TRX initiated an environmental study of the Buckreef project area in 2012 by commissioning ENATA to undertake a preliminary socio-environmental study. As a result of the socio-environmental studies that were undertaken during the period 2004 to 2014 Buckreef was issued with an EIA certificate in terms of the Environmental Management Act No 20 of 2004 in May 2014 which is valid for the life of the mining project. The EIA certificate was issued with four main conditions which included the following:

 

1)Installation of deep and shallow groundwater monitoring borehole around the waste rock dumps and the tailings storage facilities.
2)Installation of wall monitoring systems for the tailings dam facility to check for any likely movement of the walls.
3)Maintain a data base of the current and previous data on air, dust and noise levels in the Buckreef area.
4)Install water quality monitoring systems for the Nyamanzou River and Dam.
5)Carry out annual environmental audits of the mining area for submission to the EMA.

 
 (VIRIMAI PROJECTS LOGO)Page 30
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

5.ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

 

5.1Accessibility

 

Mwanza is the nearest major population center to the project, the centre is approximately 60km northeast of Buckreef, and is the second largest city in Tanzania with a population of 1million people.

 

Access to the project area is via ferry from Mwanza across Smith’s Sound across Lake Victoria, then via sealed road through the township of Geita. Alternative access is via sealed road through Shinyanga and Kahama, and subsequently via gravel road north to Bulyanhulu and then west to Nyarugusu.

 

The project can also be accessed by scheduled light aircraft flights (Coastal Air Services) from Mwanza to the airstrips located at Bulyanhulu or Geita Gold Mines, or more directly by charter to the bush airstrips located at Buckreef Mine or Nyarugusu Village. Access to the project area can be hampered in the rainy season due to the poor state of the grave road.

 

The project site itself lies 15 km south-east of Katoro Township on a series of unpaved roads. Within the project area, access is via local tracks and paths which are suitable for two-wheel drive vehicles in the dry season and four-wheel drive vehicles in the wet season.

 

5.2Climate

 

The project experiences a temperate climate, with sub-humid moderate temperatures all year round. The mean annual rainfall is 1,264 millimeters (mm) (Veiga, 2004) and the Geita District has a bi-modal summer rainfall distribution, with two main rainy seasons: one from November to December and the other from February to May.

 

The period from June to August is usually dry. The rain occurs as localized storms rather than in a generalized downpour and runoff from the upland ridge and hardpan ferricrete areas on the mine site and its surroundings is very high. The run-off generates rapid response stream-flow and sheet-flow. The water table varies markedly from season to season which can influence drilling conditions. Consequently, the dry season, occurring between May and September is preferable for drilling programs and field operations. During the wet seasons, access is limited across black cotton soils. River drainages are impassable in the wet season without suitable bridge construction.

 

The annual minimum and maximum temperatures for Geita range between 14°C and 30°C. September is the warmest month with an average temperature of 29.2°C at noon, while July is coldest with an average temperature of 14.6°C at night. The area has no distinct temperature seasons and the temperature is relatively constant during the year. July is on average the month with most sunshine (Henning, 2011). The proposed project area is regarded as humid and the climate is classified as a tropical savannah (winter dry season), with a subtropical moist forest bio-zone (Henning, 2011).

 

5.3Physiography

 

The average attitude of the Geita district ranges between 1,300 to 1,100 meters above sea level (m.a.s.l). The Geita district is characterized by hilly topography in the north, west and parts of the south west, with a gentle slope towards the south and southeast (Figure 5.1).

 
 (VIRIMAI PROJECTS LOGO)Page 31
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 5.1)
Figure 5.1 Buckreef Project: Physiographic Map of North western districts of Tanzania

 

There are pediments that are gently sloping towards the drainage depressions which are vulnerable to erosion, particularly where vegetation cover has been removed through cultivation, mining or overgrazing.

 

The Buckreef Project is dominated by very subdued terrain. Low rolling plateaus are cut by incised rivers on north, south and west sides. Major features are long ridges capped by hard iron-rich laterite (“cuirasse”). Where indigenous vegetation has not been cleared is dominated by miombo woodland.

 

There is one dam and one borehole at the Buckreef site at present. Water is relatively enough in supply for the current requirements and will need to be upgraded to meet mine requirement. The current supply is enough for drilling purposes, domestic use at the camp etc.

 

5.4Local Resources

 

Geita town is an established mining community, located 40 km northeast of the Buckreef Project, with a fluctuating population of approximately 2,500 people. The town was established to service AngloGold’s Geita Gold Mine that has been in existence since the early 1930s.

 

Mining supplies, equipment, and services and a skilled mining and mineral exploration workforce are readily available in Mwanza and the mining communities in the Lake Victoria Gold belt (LVG) that has a long history of mining, which helps to attract employees and contractors from throughout Africa.

 
 (VIRIMAI PROJECTS LOGO)Page 32
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The project area is densely populated with individual and/or agglomerations of dwellings related to transient artisanal gold mining activities and pastoral farming. Local small pastoral villages are poor sources of logistical support though communication in the area is provided by a modern cell phone network, which has coverage in virtually all sectors of the LVG.

 

Tanzania National Electricity Supply Company (TANESCO) provides electrical power to site via a single transmission line. Power and water availability are adequate for current requirements and will be upgraded to meet future mining requirements.

 

Fuel is trucked in from the town of Mwanza and the district is well serviced by access roads to various operating large and medium scale mines in the district. The infrastructure surrounding the Buckreef Project area is generally poor and unpaved roads are poorly maintained rendering access during the rainy season difficult but passable.

 

The surface rights and area covered by the Special Mining License are sufficient for future mining operations, processing plant, waste sites and TSF sites. The process plant will be constructed and licensed to operate at up to 2,500t per day. The Company will construct sufficient accommodation on-site for all personnel and provides cafeteria services for employees housed in the Project’s current onsite camp accommodation.

 
 (VIRIMAI PROJECTS LOGO)Page 33
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

6.HISTORY

 

The Lake Victoria Goldfield was discovered in 1894 by German explorers and significant exploitation began in the 1930s at the Geita Gold Mine. Several small gold mines exploiting near surface reefs, operated throughout the Rwamagaza Greenstone Belt, particularly near the village of Rwamagaza. By 1940, Tanzania was producing 4.5tpa of gold (Au).

 

Gold bearing quartz veins were reported from the current Buckreef Mine area in 1945 and reports from the 1950s attest to ongoing production at several localities near Rwamagaza, including the Buckreef area. The extent of the small-scale local and colonial mining activities is evident from the numerous pits and adits covering the entire Buckreef tenement, however no production figures are available.

 

The Buckreef Mine was an underground mine exploited in the name of the Buckreef Gold Mining Company owned by the Tanzanian State Mining Company (STAMICO) in 1972. A brief summary of the more significant exploration and mining activities covering the Buckreef project area is discussed below.

 

6.1Previous Exploration Work

 

i. State Mining Corporation (STAMICO) ERA (1960-1990)

 

Following some artisanal mining activities in the 1960s, a United Nations Development funded 13-hole core drilling program for the government owned Tanzania Mineral Resources Department and this defined 107m long by 8m wide mineralized zone down to a depth of 122m. In 1968, the parastatal, Tanzania Mineral Resources department conducted another 13-hole core drilling program whose results were not made public.

 

The first attempt at underground development was undertaken by Williamson Diamonds Ltd in 1970, when the Buckreef Main shaft was sunk to 75m and lateral developments were done at 30m and 60m depths respectively. The mining results failed to meet expectations and no production records were availed and the mine closed down and the projected reverted back to the Tanzania Mineral Resources department.

 

ii. Comprehensive Exploration ERA (1992-2010)

 

From 1992 to 1994, East Africa Mines Ltd. entered into an exploration agreement with the Tanzania Mineral Resources Department, now renamed STAMICO and commenced regional and project scale reverse air blast (RAB), reverse circulation (RC) and diamond core (DC) drilling centred on the Buckreef main shear structure. The results of their exploration program culminated in the signing of the first Buckreef Redevelopment Agreement (“BRDA”) with Stamico.

 

In 1996, Spinifex Gold, an Australian registered junior exploration company acquired East Africa Mines Ltd and took over responsibility on the BRDA. In 2003, Spinifex Gold was acquired by Gallery Gold, another Australian registered mining and exploration company. In 2006, Gallery Gold was subsequently acquired by IAMGOLD, a Canadian registered mining and exploration company who then entered into the second BRDA with STAMICO.

 

IAMGOLD undertook a 4-year exploration program that included regional airborne geophysical surveys, project scale soil surveys and trenching, exploration and metallurgical and hydrogeological drilling.

 
 (VIRIMAI PROJECTS LOGO)Page 34
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

In early 2010, IAMGOLD then surrendered the project back to STAMICO as part of a corporate decision to relocate and concentrate on projects in Mali.

 
 (VIRIMAI PROJECTS LOGO)Page 35
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

7.GEOLOGICAL SETTING AND MINERALIZATION

 

7.1REGIONAL GEOLOGICAL SETTING

 

The Buckreef Project is situated within the Lake Victoria Greenstone (LVG) belt of northern Tanzania which consists of several east-west trending, linear, Archaean greenstone belts. The LVG is the third largest gold producing region of Africa, surpassed only by the Witwatersrand Basin in South Africa and the Tarkwa region of Ghana. Numerous gold occurrences have been identified in the LVG and new discoveries continue to be made. Since 1998, when the first mine, Golden Pride was commissioned, four additional large scale mines namely, Geita, Bulyanhulu, North Mara, and Tulawaka have come into commercial production. Geita and Bulyhanulu are considered world-class deposits, together representing in excess of 35Moz of gold resources.

 

The Sukumaland Greenstone belt is one of eight Achaean greenstone belts that occur within the Lake Victoria Goldfield of northern Tanzania. The stratigraphy of Lake Victoria Goldfield (LVG) can be divided into three major groups; the Lower Nyanzian, Upper Nyanzian and Kavirondian. The Sukumaland Greenstone Belt has an outer arc (Upper Nyanzian) and inner arc (Lower Nyanzian) stratigraphy cored by granitic rocks (Figure 7.1).

 

(Figure 7.1)

 

Figure 7.1 Regional Geology Map, Buckreef Gold Project, Lake Victoria Greenstone Belt, Tanzania

 

The Rwamagaza greenstone Belt, host to the Buckreef Project, forms the inner arc of Sukumaland Greenstone Belt that comprises dominantly mafic volcanic stratigraphy with minor felsic feldspar porphyry and quartz-

 
 (VIRIMAI PROJECTS LOGO)Page 36
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

feldspar porphyritic, flow-banded rhyolite units. Ultramafic rocks occur in isolated locations in the area to the west of the Busolwa-Buziba prospects.

 

The top of the Lower and upper Nyanzian system is overlain by Kavirondian age rocks. Apart from occurrences in North Mara, Nikonga and BulangaMurwa, the Kavirondian is not widely distributed in the LVG. The Kavirondian rocks are generally coarse clastic molasses that include polymictic conglomerate, gritstones, quartzites, shales and siltstones, metatuffs and intermediate to acidic volcanics and while no clear tectonic setting has been put forward for these rocks, it is speculated that they were deposited in small pull apart basins.

 

The regional metamorphic grade of the Nyanzian is largely low grade, greenschist facies though areas of amphibolite facies are recorded, for example at Msasa and Tulawaka Mine. Local contact metamorphism caused by granite intrusions is also developed, but in general higher grade metamorphic complexes are rare.

 

The greenstone belts are set in a terrain of syntectonic granite, granite gneisses, late kinematic granites and associated felsic intrusives. There is a general lack of detailed regional mapping and standardization of lithological names in the LVG and consequently there is no officially recognized division of this terrain. Quennel (1960) has proposed a fivefold classification for the intrusions (G1 – G5), however subsequent authors, notably Barth (1990) and the UNDP (1986b) adopted a simpler two-fold classification dividing the intrusions into synorogenic and late kinematic cycles.

 

The synorogenic cycle (G1, G2 and G3 granites) is comprised of migmatites, foliated and porphyroblastic granites, biotite – hornblende granite, tronhjenite, granodiorite, tonalite, adamelite, monzanite and quartz diorite. These lithologies include all those formed by interaction with the greenstone belts and the theoretical pre Nyanzian age granitoid basement. It is probable that some of these early units are synvolcanic intrusives that fed the felsic volcanism of the Nyanzian greenstones.

 

The late kinematic granites (G4 and G5) are probably post Nyanzian age and possibly post Kavirondian age intrusive events. Typically, these intrusive include biotite granites, porphyritic biotite granites, microgranite, feldspar porphyries and felsophyric dykes and where mixing with the greenstone belt lithologies occurs the rocks become locally gneissose in texture and granodioritic in chemistry. These late intrusions often appear circular and there is evidence of slight banding suggesting a diapiric origin. However, some are less regular in shape and in the Nzega, Geita and eastern Iramba Sekenke Greenstone belt appear to have an alignment along the 1100 and 0700 or have contacts affected by these directions.

 

Numerous dolerite, gabbro and ultramafic bodies have been intruded in to the Lake Victoria Goldfields. Possibly the most significant phase is related to a system of north south, west southwest trending magnetic dolerite dykes. While they rarely crop out they are often identifiable from magnetic surveys.

 

The trends of the north south dykes maybe divided into two sub sets, 3500 and 0100 (Halls et al, 1984). The 3500 subset is largely confined to the Tanzanian craton area and where they intersect the Proterozoic age Ubendian or Usagaran belts they are highly altered hence have an age pre 2100Ma. In contrast the 0100 subset is largely unaltered and is observed cross cutting the Lower Proterozoic Ubendian belt indicating an age

 
 (VIRIMAI PROJECTS LOGO)Page 37
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

younger than this orogenic event. Barth does not differentiate between the two sets and believes them both to be of Karroo age.

 

The regional structure is poorly understood and the correlation of specific structures from one greenstone belt to another is difficult.

 

Two phases of folding are generally recognized in the Nyanzian System (Barth, 1990). The first phase generated symmetric, east west trending, isoclinal folds. It is likely that this was coincident with tectonic stacking and thickening i.e. thrusting. Following this early phase, a second phase of cross folds with axial planes striking approximately 1000 - 1200 developed. These are coincident with major dextral lineaments that cross cut the LVG area (Figure 7.2).

 

(Figure 7.2)

 Source: SRK Report RS102/02-August 2002,

 

Figure 7.2 Regional Structural Geology Setting, Buckreef Project, Rwamgaza Greenstone Belt, Geita District, Tanzania

 

A key factor in the localization of gold mineralization seems to be where this second phase and/or regional lineaments cross cut the primary east – west phase.

 

The Lake Victoria Goldfield is the third largest gold producing region of Africa, surpassed only by the Witwatersrand Basin in South Africa and the Tarkwa region of Ghana. Numerous gold occurrences have been identified in the LVG, and new discoveries continue to be made. Since 1998, when the first mine, Golden Pride was commissioned, four additional large-scale mines namely, Geita, Bulyanhulu, North Mara, and Tulawaka have come into production. Geita and Bulyanhulu Mines are considered world-class deposits, together representing more than 60Moz of gold resources.

 
 (VIRIMAI PROJECTS LOGO)Page 38
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The Lake Victoria Goldfield has geological and structural similarities to major gold districts in the Canadian Shield (Val d´Or, Kirkland Lake) and the Yilgarn Craton in Western Australia (Kalgoorlie, Laverton, Leonora, Kambalda and Southern Cross). Gold mineralization within the Lake Victoria Goldfield occurs in number of styles including: -

 

quartz veins within minor brittle lineaments, most commonly worked on a small-scale by artisanal workers, due to their limited extent and erratic gold distribution (such as at Bulangamirwa workings in the Nzega Greenstone Belt);

 

mineralization within major ductile shear zones;

 

mineralization associated with replacement of iron formation and ferruginous sediments; and

 

felsic (porphyry) hosted mineralization, such as within the Rwamagaza Greenstone Belt.

 

Nutt (2003) also notes that approximately 19% of known gold occurrences in the LVG are associated with or hosted in part, by felsic intrusives (excluding granitoids) and significantly at least four of the larger gold deposits have known diorite or quartz and/or feldspar porphyry’s in close association i.e.:

 

Geita Group (diorites and felsics),

 

Bulyanhulu (quartz porphyry),

 

Golden Pride (quartz porphyry or rhyolite bodies) and

 

Mobrama deposit – North Mara Group (siliceous felsic rock, protolith: quartz porphyry).

 

Regardless of the geological environment, it is accepted that structural control on the emplacement of the mineralization is critical. The following structural features have proven to be important foci of gold mineralization: -

 

Structural lineaments trending at 120º;
Flexures and splays to the 120º trend (such as at Golden Pride);
Structural lineaments at 70º (such as at Golden Ridge); and
Granite-greenstone contacts (such as at the Ushirombo and Rwamagaza Greenstone belts).

 

7.2LOCAL GEOLOGIC SETTING

 

Buckreef Gold Company Limited’s Buckreef Project is in the regionally east-west trending Rwamagaza greenstone belt. This belt is considered a segment of the larger Sukumaland greenstone belt and is one of the larger greenstone belts in northern Tanzania.

 

Substantial areas of the Buckreef Project are covered by lateritic units, dominantly gravels, mbuga soil and cuirasse. Cuirasse forms some highly indurated upper facies of the lateritic regolith. Several lateralization

 
 (VIRIMAI PROJECTS LOGO)Page 39
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

events have resulted in weathering to depths of up to 40m. The limited bedrock exposure has hampered the development of detailed geologic models for the region.

 

Hill (2006) reported on a geological investigation of the Buckreef Project area for IamGold Ltd. In this PowerPoint presentation, Hill (2006) described the geology of the Buckreef Project as consisting of a tightly folded sequence of lower mafic, upper mafic-ultramafic sequence. The Lower mafic unit appears to be more deformed than upper mafic unit. The two units are separated by magnetic ultramafic flow at unconformity boundary. The mafic –ultramafic units are sandwiched between older granite to the south and young late granite to the north. The margins of granite intrusions have higher magnetic signature suggesting contact metamorphisms (Figure 7.3).

 

(Figure 7.3)

 

Figure 7.3 Local Geological Setting, Buckreef Project, Rwamagaza Greenstone Belt, Geita District, Tanzania

 

The belt is bisected by an East – West trending lineament, that is interpreted as a first-order, crustal scale, sinistral shear zone namely as the Rwamagaza Shear Zone (RSZ). The Rwamagaza greenstone sequences have been affected by at least two deformation events. The deformation D1 forms a weak E - W trending foliation and massive “buck” quartz veins that are weakly prospective for gold mineralization. D2 corresponds to the main phase of deformation and resulted in the progressive development of NE trending shear zones, and a pervasive NE foliation. N to NNE trending dextral shear faults formed during D2 and are associated with stock- work quartz veins and significant gold mineralization.

 
 (VIRIMAI PROJECTS LOGO)Page 40
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Several published data considered that regional gold deposition is tightly constrained to the pre-Lamprophyre intrusion (2697 ±10 Ma) and pre-Kuria volcanic rocks (approx. 2660Ma).

 

7.3DEPOSIT GEOLOGY

 

Buckreef Gold Company Limited has defined four mineral deposits on the Buckreef Property. As estimated in this technical report, from largest to smallest based on ounces of gold, these include the Buckreef mineralized corridor, Bingwa, Eastern Porphyry and Tembo Deposits. In addition to the historical descriptions as summarized from reports by Venmyn (2012; 2014) and IAMGOLD (2003-2009), Tan Gold has further refined the geology of the main Buckreef deposit through interpretation of recent drilling results and historical mineralogical test-work whose interpretation is herein incorporated.

 

7.3.1Buckreef Deposit

 

The Buckreef Prospect is a shear zone hosted gold deposit within a sequence of mafic basalts and dolerites, near basement granite. The host rocks at the Buckreef deposit comprise primarily pillowed, amygdaloidal and massive mafic meta-volcanic rocks which have been intruded by medium to coarse grained dolerite sills and dykes. Slivers of carbonaceous units have been observed in some drill-core sections incorporated in the meta- volcanic assemblages. Minor granitoids (possibly metasomatic) are noted in the north part of the deposit towards the contact with the northern granite (Figure 7.3a).

 
 (VIRIMAI PROJECTS LOGO)Page 41
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

 

(Figure 7.3)

 

Source: TRX 2020

 

Figure 7.3 Local Geological Setting, Buckreef Deposit, Geita District, Tanzania

 

The greenstone rocks for the most part comprise mafic to intermediate volcanic with only a minor sedimentary component. Two major groups of primary lithologies have been distinguished with some confidence, namely formerly glassy quenched mafic lavas and lava breccias (textures suggest basaltic komatiites or magnesian quartz tholeiites), and high-level small intrusive bodies of broadly tonalitic rock. The latter include relatively fine-grained holocrystalline varieties, and less common porphyritic varieties with a very fine groundmass, suggesting either a near-margin very shallow intrusive or a volcanic origin (Crawford, 2005)

 

The table below is an extract from an internal mineralogical report by Mason (220) and Crawford (2005) that classified the dominant rock types and alteration styles prevalent at Buckreef mine.

 
 (VIRIMAI PROJECTS LOGO)Page 42
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

SAMPLE ROCK NAME MINERALOGY*
    Primary** Alteration*** Veins
1101-24 (BMRCD 185) Strongly schistose, veined and chlorite-dolomite- sericite altered meta-basic rock (?quartz dolerite) Qtz Chl, car(dol), ser, leu/rut, opq(?py) Car(dol), qtz, opq(?py), cal
1101-25 (BMRCD 185) Weakly foliated, medium-intensity chlorite-albitealtered meta-dolerite Qtz Alb, chl, cal, leu, opq(?sulp) Cal
1101-26 (BMDD 14) Thinly veined and medium- to high-intensitycalcite-chlorite altered meta-basalt - Cal, chl, py, alb, leu/rut, cpy, hem, gld Cal, chl, py, hem
1101-27 (BMDD 4) Veined foliated high-intensity sericite-dolomite-pyrite altered meta-dolerite - Car(dol), ser, py, qtz, leu, cpy Car(dol), qtz, py, cpy, hem
1101-30 (BMRCD 186) Veined and medium- to high-intensity carbonate-albite-pyrite(-gold) altered meta-dolerite - Alb, car(?dol,?ank), py, ser, leu, cpy, gld Qtz, car(?dol,?ank)
1101-31 (BMDD 5) Fractured and medium- to high-intensity chlorite-calcite-zoisite altered meta-basalt - Chl, cal, alb, zoi, spn, opq(?sulp) Cal, chl, zoi, qtz
1101-33 (BMDD 18) High-intensity epidote-chlorite-calcite - Chl, epi, cal, alb, opq(?mt), spn Cal, chl, epi, opq(?mt)
(-magnetite) altered meta-basic rock
Low-intensity chlorite-magnetite altered meta-porphyritic basalt (dyke) - Alb, opq(?mt), cal, chl, epi Cal, chl
1101-02 (BMRCD 222) Actinolite-chlorite-epidote meta-basalt/?dolerite - Act, alb, chl, epi, cal, leu, qtz, opq(?py) Cal, epi
1101-03 (BMRCD 222) Fractured and high-intensity dolomite-chlorite-sericite altered meta-basic rock (?basalt) - Car(dol), chl, ser, qtz, leu Car(dol), chl, ser, opq(?py, ?cpy)
1101-05 (BMRCD 222) High-intensity carbonate-pyrite-gold altered meta-?basic rock - Car(?dol), py, alb, qtz, ser, chl, leu/rut,cpy, gld -
1101-06 (BMRCD 222) Fractured and medium- to high-intensity chlorite-calcite-quartz altered meta-basalt - Chl, cal, qtz, opq(?py), rut, epi Cal, qtz, chl, opq(?py)
1101-07 (BMRCD 220) Veined and deformed, foliated medium-intensity dolomite-sericite-chlorite altered meta-basaltic conglomerate Qtz Car(dol), ser, chl, alb, qtz, rut, py, cpy Car(dol), qtz, chl, py, cpy
1101-08 (BMRCD 220) Fractured and medium-intensity dolomite-albite-chlorite-sericite altered meta-basalt - Car(dol), alb, chl, ser, rut, opq(?py), tou Car(dol)
1101-16 (BMDD 2) Schistose high-intensity chlorite-calcite-sericite altered meta-quartz dolerite Qtz Chl, cal, ser, qtz, rut, opq(?py) -
1101-20 (BMDD 2) Veined and high-intensity dolomite-albite-pyrite altered, brecciated meta-?basalt - Car(?dol, ?ank), alb, py, ser, rut, po Qtz, car(?dol,?ank)
1101-21 (BMRCD ?203) Veined and deformed, medium-intensity albite- dolomite-sericite-chlorite-sulphide altered meta-basalt - Alb, car(?dol,?ank), ser, chl, opq(?py), leu/rut Car(?dol,?ank), qtz, opq (?py,?hem), chl
1101-22 (BMRCD 208) High-intensity carbonate-sericite-albite altered basaltic breccia (?cataclasite) - Alb, car(?dol,?ank), ser, chl, opq(?py,?cpy), leu/rut Qtz
1101-23 (BMRCD 2) Veined and weakly schistose medium-intensity albite-chlorite-dolomite-sericite-magnetite- hematite altered meta-basalt - Alb, car(dol), chl, ser, mt, hem, leu, py, cpy Car(dol), mt, hem; Hem, qtz, cal

 

Table 7.1: Summary of Rock names and mineralogy typical at Buckreef Gold Mine

 

*: Minerals are listed in each paragenesis according to approximate decreasing abundance.

 

**: Only primary minerals currently present in the rock are listed. Others may have been present, but are altered.

 

***: Earlier parageneses are separated from later parageneses by a semicolon.

 

Mineral abbreviations:

 

Act = actinolite; alb = albite; ank = ankerite; apa = apatite; cal = calcite; car = carbonate minerals (possible mineral in brackets); chl = chlorite; cpy = chalcopyrite; dol = dolomitic carbonate (possibly also including Fe-dolomite or ankerite); epi = epidote; gld = native gold; hem = hematite; leu = leucoxene; mt = magnetite; opq = undifferentiated opaques (possible mineral in brackets); po = pyrrhotite; py = pyrite; qtz = quartz; rut = rutile; ser = sericite; sph = sphalerite; spn = sphene; sulp = undifferentiated sulphides; tou = tourmaline; zoi = zoisite.

 

Altered basic rocks display assemblages ranging from those dominated by chlorite + calcite ± opaques (mainly pyrite), through those dominated by assemblages of dolomite + chlorite + sericite + opaques, to those dominated by dolomite (?Fe-dolomite, ?ankerite) + pyrite + sericite + leucoxene/rutile ± native gold. Thin fracture fillings and veins contain assemblages that reflect the host rock alteration assemblage. The range of alteration assemblages is considered to represent increasing proximity to structures (fractures, shear zones, faults) which facilitated invasion of the rocks by mineralizing hydrothermal fluid(s), and about which alteration zones developed. Thus, the chlorite-calcite assemblages represent lower volume of fluid (distal alteration), and dolomite-pyrite-sericite-gold assemblages represent highest volume of fluid (proximal alteration) (Mason, 2002).

 
 (VIRIMAI PROJECTS LOGO)Page 43
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Alteration of these rocks is complex and variable. The mafic lavas and lava breccias show a silica-chlorite- magnetite+/-albite assemblage with little or no pyrite, and abundant late overprinting carbonate. Sericite and pyrite join this assemblage in the felsic intrusive units and those rocks interpreted as meta-sediments, and magnetite is generally much less prominent than in the mafic metavolcanics. Several generations of carbonate alteration are probably present, including an earlier one broadly contemporaneous with the sericite-chlorite- pyrite assemblage, and a later one that usually manifests as late cross-cutting veinlets.

 

The mineral assemblage includes py, ± po, cpy, mt with associated silica, carbonate and sericite alteration. Gold is associated directly with sulphides as microscopic inclusions. Sulphides are disseminated and may comprise up to 5% of the rock by volume. The gold mineralization at Buckreef Prospect is non-refractory in both fresh and oxide material. Deep drill-holes indicate that high grade mineralized zones plunge steeply to the north. Several narrow, more discontinuous sub-parallel zones of similar alteration and mineralization have been defined both to the west and to the east of the main fault zone.

 

Detailed logging of drill-hole core reveals a prominent deepening of the oxidation profile above portions of both the Main and North Zones. Superimposed on the host rock is an intensely weathered laterite profile up to 40m depth. Gold may be concentrated in the oxide weathering profile by supergene processes. Fresh sulphides generally do not occur shallower than 40m from surface. The base of the oxidation zone occurs between 15m and 40m, with an average depth of 30m, and the overburden consists of both black cotton soils and lateralized duricrusts with an average depth of ±3m-4m, to a maximum of 20m.

 

7.3.2Bingwa Deposit

 

The Bingwa Prospect is located at the northern margin of the RGB, adjacent to a sheared contact with a granitic intrusive and is approximately 4km east of the Buckreef deposit (Figure 7.4) Gold mineralization has been identified in a drilling program over a strike length of 350m and up to 100m below surface, with the main zone of mineralization occurring over a strike length of 150m. Gold mineralization at Bingwa is associated with quartz veining in strongly foliated and altered greenstone in a shear zone adjacent to the granitoid contact. The shear zone strikes northeast and dips steeply to the northwest. The main zone of mineralization is associated with the junction of a northwest striking, shallowly north dipping fault and the northeast striking shear zone.

 
 (VIRIMAI PROJECTS LOGO)Page 44
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 7.4)

 

Source: TRX 2013

 

Figure 7.4 Local Geological Setting, Bingwa Deposit, Geita District, Tanzania

 

Deformation, alteration and gold mineralization appear to be limited to rheological contacts, between basalt and the early quartz veins and along the margin of the granite. The difficulty in constructing continuous grade envelopes may be due to limited continuity of the early quartz vein array, and/or the possibility that the veins are folded, transposed and boudinaged within shear zones.

 

Most the mineralization defined to date occurs within the oxide zone, which extends to 40m-60m below surface. The entire deposit is overlain by 5m to 8m of overburden and transported alluvial. Much of the Bingwa Prospect gold mineralization in the weathered profile occurs in lower saprolite, below the redox boundary.

 

There is negligible upper saprolite below the overburden cover. Given that there is typically limited chemical dispersion of gold in lower mafic saprolite, this may be one of the reasons for poor lateral grade continuity at the Bingwa Prospect. However, recent work at the Bingwa Prospect indicates that mineralization is hosted within the north-northwest to south-southeast trending structures at the intersection with the major northeast-southwest shear zone. The intersection between these structures is considered to play an important role in controlling high grade zones

 
 (VIRIMAI PROJECTS LOGO)Page 45
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

7.3.3Eastern Porphyry Deposit

 

The Eastern Porphyry deposit is located 0.8km east of the Buckreef main deposit and consists of weakly to moderately sheared felsic porphyry and younger fresh feldspar quartz porphyry dykes up to 30m wide within a mafic sequence dominated by medium grained dolerite.

 

The Eastern Porphyry structures occur within sheared basaltic lavas and medium grained dolerite intrusive of the northeast-southwest trending Nyamazama River lineament. The elongated intrusion attains a maximum thickness of 280m, but thins and disperses to the northeast and southwest into a series of relatively narrow quartz-feldspar-porphyry dykes (Figure 7.5).

 

(Figure 7.5)

 

Source: TRX 2013

 

Figure 7.5 Local Geological Setting, Eastern Porphyry Deposit, Geita District, Tanzania

 

The Eastern Porphyry mineralization is associated with silicified and weakly pyritised shears, quartz veins and veinlets, and within quartz-feldspar porphyry. Quartz veining within the felsic unit may contain pyrite with or without low grade mineralization. However, zones of shearing within the dolerite up to 7m in width are associated with silica-carbonate-pyrite alteration. The mineralization has a total strike length of approximately 1,500m. The main intrusion is coincident with a circular magnetic anomaly in the area with a diameter of 350m (Barrett, 2000). In places the quartz-feldspar-porphyry is magnetite bearing, readily deflecting a hand magnet.

 

The gold mineralization occurs in a similar lithological and structural setting as at Buckreef Prospect, but the intensive carbonate-silica-pyrite alteration typical of the Buckreef deposit is lacking or poorly developed. The

 
 (VIRIMAI PROJECTS LOGO)Page 46
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

fact that mineralization on the Nyamazama River lineament is less well developed than at Buckreef may be due to less dilation of the northeast-southwest shear compared to that of Buckreef Prospect or the presence of the porphyry intrusion which inhibited fluid flow and was less chemically reactive than the basalt.

 

7.3.4Tembo Deposit

 

The Tembo deposit locates approximately 3km southwest of Buckreef Mine, adjacent to the main Rwamagaza Shear Zone. The mineralized zones at Tembo are confined to the east – west trending shears within met-basaltic volcanic package. Alteration in the mineralized zones consists of silica-carbonate-pyrite with well-preserved shear fabric (Figure 7.6).

 

(Figure 7.6)

 

Source: TRX 2013

 

Figure 7.6 Local Geological Setting, Tembo Deposit, Geita District, Tanzania

 

Gold mineralization is associated with grey quartz thin veins, stringers and boudins parallel to the shear fabric. At Tembo deposit, the transported and residual soil cover is 7m to 9m deep, below which, completely altered and sheared mafic material occurs to a depth of 50m. Most of the oxidised zone has been exploited by artisanal mining.

 

7.4STRUCTURAL SETTING AND MINERALIZATION

 

The defunct Buckreef Mine is located on a clearly defined, east-northeast/west-southwest trending, 5m-30m wide and 8km long, brittle-ductile shear zone within relatively un-deformed mafic volcanics. Based on preserved slickensides, the dominant displacement vector across the shear zone was sinistral, however the bulk

 
 (VIRIMAI PROJECTS LOGO)Page 47
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

of the ductile fabric is post mineralization. Gold mineralization is associated with intense brecciation and quartz, carbonate, sericite pyrite alteration in at least two phases and is controlled within the regional shear by a fault zone with a 10m true width, drilled continuously for over 1.5km strike length (Figure 7.3a). A late stage veining event characterized by white, buck quartz veins, is evident in the main zone and is barren of gold mineralization but is the only visible sign of the structure in outcrop.

 

Gold mineralization at the Buckreef Mine is controlled by a combination of structure, host lithology, and proximity to the granite contact. The main structure is the NE-SW trending steeply dipping Buckreef Shear Zone that is displaced by a series of two dominant fault sets trending NNW-SSE and ENE-WSW. The ENE lineaments are probably related to the Rwamagaza Shear Zone and have been recently reactivated during the Bukoban and have been intruded by dolerite dykes with a strong magnetic signature even in drill-cores. The NNW trending lineaments appear to be open fractures or fault zones oftentimes host to slivers of late stage vein quartz emplacement (Figure 7.7).

 

(Figure 7.7)

 

Source: TRX 2020

 

Figure 7.7 Structural Setting, Buckreef Deposit, Geita District, Tanzania

 

Crosscutting relationships are not clear, but the offset in the Rwamagaza Shear Zone along the NE Bukoban dykes suggests the Rwamagaza is the older structural event. There is little correlation between topographic lineaments and the interpreted bedrock structures, which suggests a late brittle structural event not reflected in the magnetics.

 

The meta-basaltic volcanic-hosted deposits Buckreef and Tembo, tend to consist of networks of anastomosing and steeply-dipping shear zones, exhibiting multiple, superimposed, phases of veining, alteration and deformation. The intrusive-hosted deposit, Eastern Porphyry, also exhibits multiple phases of veining, alteration and deformation, but tend to develop weak alteration and broader shear zones.

 
 (VIRIMAI PROJECTS LOGO)Page 48
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Bingwa and Eastern Porphyry are associated with intrusive contacts. This could be attributed to thermal aureole effect; however, it may also be controlled by competence contrasts and its effect on structural dilation during deformation and the consequent enhancement of permeability at these sites.

 

The structural setting and interpreted control on the main Buckreef deposit is as shown in the sketch below (Figure 7.8).

 

(Figure 7.8)

Source: Iamgold/SRK 2007

 

Figure 7.8 Structural Setting of the Main Buckreef Prospect, Rwamagaza Greenstone Belt, Geita District, Tanzania

 

Deformation occurred as part of the regional metamorphic event and varied from place to place in the rock sequence (i.e. partitioning of strain). Some samples display massive textures with good preservation of primary textures, but others are variably foliated. Logging in some drill-core samples show distinctive breccias, possibly of cataclastic deformational origin (i.e. fault zone). It is important to note that microtextures support the interpretation that alteration and associated mineralisation occurred during and/or after deformation, that is deformation of the rocks generated conduit systems which allowed invasion of the rocks by hydrothermal fluid(s).

 

The rock types, metamorphism, deformation and alteration are typical of Archaean lode-gold mineralised systems.

 
 (VIRIMAI PROJECTS LOGO)Page 49
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Gold is strongly associated with silica-carbonate alteration and veining. Sulphide minerals associated with mineralization consist predominantly of pyrite and minor chalcopyrite. Gold grains up to 60 microns in size have been reported in both low and high grade zones. Visible gold is known from all deposits but is not common. High amount of gold is found as inclusion in pyrite as well as fracture-filling in pyrite and chalcopyrite. Gangue minerals of interest include clay, feldspar, quartz, dolomite, and hematite and goethite in the oxide and transition material.

 
 (VIRIMAI PROJECTS LOGO)Page 50
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

8DEPOSIT TYPES

 

8.1Regional

 

The Lake Victoria Goldfield hosts numerous small-scale and five large-scale orogenic gold deposits. Term ‘orogenic gold deposit’ is broad in scope and encompasses meso-thermal gold deposits, shear-hosted, lode-gold and metamorphic gold deposits. Orogenic gold is a distinctive class of mineral deposit that has been the source for much of world Au production.

 

The ores are widely recognized in both Phanerozoic mobile belts and older cratonic blocks. Orogenic gold deposits have formed over more than 3 billion years of Earth’s history, episodically during the Middle Archaean to younger Precambrian, and continuously throughout the Phanerozoic.

 

Typically, orogenic gold deposits are formed in regionally metamorphosed terranes, during compressional or transpressional tectonic processes at continental plates margins, in accretionary or collisional orogenic events. In both tectonic regimes, hydrated marine sedimentary sequences are added to continental margins. Subduction related thermal events then drive extensive hydrothermal fluid systems through the hydrated accretionary sequences, which results in the emplacement of gold bearing quartz veins from depths of 15km to 20km to surface (Groves 1997).

 

The mineralization is commonly post the deformation of the host rock but is syn-orogenic with respect to the on-going deep crustal, subduction related thermal processes (Groves 1997). In addition, mineralization has been theorized to be associated with short-lived pulses of metamorphic fluids that are released by the rapid devolatilisation of a rock column undergoing burial in a convergent orogen.

 

The goldfield deposits are hosted by sedimentary units intercalated with volcanics and all are associated with quartz veining. The largest deposit at Geita is hosted by ferruginous chert-pelite units. The Rwamagaza Greenstone Belt hosts numerous small-scale gold deposits exploited by small-scale miners, as well as the Tulawaka Mine that has produced more than 1 Moz at the western limit of the RGB, 56km to the west of the Buckreef Mine.

 

All the deposits currently being exploited by artisanal miners in the Buckreef Project area consist of narrow discontinuous quartz veins within meta-basalts, shear zones, contact zones with felsic intrusives and metamorphic foliation.

 

Each of the four prospects, whilst generally formed under conditions described above, are unique in the mechanisms which concentrated the mineralization. The exploration programs undertaken have been specifically designed considering the unique set of local structural, lithologic and regional tectonic conditions which created potentially favorable sites for mineralization concentration.

 

8.2Buckreef Gold Deposits

 

The Buckreef Gold mine is hosted within a NE trending mylonitic shear zone, which cross-cuts a mafic volcanic package. The stratigraphy of the Buckreef deposit is dominated by fine grained mafic volcanics, (sub)

 
 (VIRIMAI PROJECTS LOGO)Page 51
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

concordant coarser grained, ±porphyritic doleritic sills or flows with intercalated and interflow sedimentary horizons that occur as rare, thin, massive to finely laminated units within mafic sequence. This mafic package has been intruded by a series of porphyritic felsic dykes that appear to have broadly intruded parallel to the main Buckreef fault zone. The dykes are typically pink in colour and possess both quartz and feldspar phenocrysts phases in a fine-grained ground mass.

 

The Buckreef Prospect is a shear zone hosted gold deposit hosted by mafic basalts and dolerites (referred to locally as a lode), in close proximity to a basement granite. Porphyritic felsic intrusives are typically narrow, steeply dipping bodies, contain abundant quartz and felspar phenocrysts, more abundant in the central and northern region of the Buckreef Main zone (i.e., from approximately mine grid L1600N to at L2600N).

 

Gold mineralisation associated with pyrite-silica-carbonate alteration, with highest grades occurring in intensely altered and fractured host rocks ±quartz veining and appears to be dilation controlled and largely constrained by two cross-cutting sinistral faults, striking ESE-WNW and E-W which displace the Buckreef Shear. Milky to dark grey quartz veining, with higher gold grades generally associated with the (earlier) dark grey quartz,

 

Gold mineralisation is late stage associated with the formation of quartz-rich vein structures, including the steeply dipping lode veins, and related silica carbonate-sericite-pyrite (+Au) dominant alteration. The mineralisation and associated veining / alteration overprint earlier developed fabrics and textures, including the regional greenschist facies metamorphism. Ore-related fabric development (including vein, breccia and secondary foliation development) are more consistent with brittle to brittle-ductile and solution-precipitation processes (including breccia, vein fabrics). Although the dykes are sometimes present within the main mineralised zones they are typically a poor host rock and rarely have economic mineralisation within them. There could be a possible genetic link (hydrothermal?) between the gold mineralisation and quartz-feldspar porphyry intrusions that occur in the area.

 

The dominant (or defining) structural fabrics in the ‘Buckreef Fault’ / Main zone area are a narrow to broad variably foliated / layered zone (termed the ‘main fabric’) and (sub) parallel, (±laterally continuous) quartz vein lode structures; both structures trend broadly to the NE and are steep to near vertical dipping. Structural fabrics / relationships observed in core, are typically not consistent. The ‘main fabric’ varies in foliation intensity from a discrete layer silicate cleavage to a domainal / continuous schistosity. Schistose fabrics are most prominently developed in the finer grained mafic volcanics. Where Au associated alteration is intense, the ‘main fabric’ can be defined by a compositional banding that has (partially) replaced (or been superimposed on) an earlier foliation.

 

Buckreef Main deposit occurs as 3 discrete zones namely, the Buckreef North Zone, the Buckreef Main Zone and the Buckreef South Zone (Figure 8-1) all separated by altered but less well mineralised material. A distinctive ENE-WSW fault break marks the separation between the Main and North zone in the central north while a promininent E-W fault break marks the separation between the Main Zone and South Zone in the central south. The best mineralization occurs between mine grid sections L1800N and L2540N; high grade shoots are SW plunging.

 
 (VIRIMAI PROJECTS LOGO)Page 52
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Buckreef Main Zone

 

has a strike length of 600m and extends to at least 700m below surface
fault-zone hosted, broadly NE trending, with an overall steep to near vertical dip.
close to surface, the lode geometry, displays a near vertical dip to the NW or SE.
Alteration within fault zone characterized pervasive iron-carbonate alteration that has undergone multiple brittle fracturing and brecciation with multiple events of grey to white quartz veining.
Finely disseminated pyrite and also as fracture emplacement associated with Au mineralisation.
Significant development of molybdenite mainly associated with carbonaceous meta-sedimentary units.
Minor amounts of chalcopyrite, pyrrhotite and magnetite occasionally recorded in drill core
Host rock appears to be an important control on higher grade ore blocks or shoots

 

Buckreef North Zone

 

has a strike length of 250m and extends to at least 400m below surface
fault-zone hosted, broadly NNE trending, with an overall steep to near vertical dip.
close to surface, the lode geometry, displays a near vertical dip to the NNW or SSE.
Silica-carbonate-sericite-sulphide (principally pyrite) dominant alteration and related quartz-rich lode vein / breccia and tension fracture emplacement) associated with Au mineralisation.
Host rock varies from mafic volcanics to felsic porphyry.
Porphyry hosted mineralization tends to be wide but generally low grade.

 

Buckreef South Zone

 

has a strike length of 250m and extends to at least 150m below surface
fault-zone hosted, broadly NE trending, with an overall steep to near vertical SE dip at shallow depths.
Mostly occurs close to surface and carrot shaped lode geometry tend to indicate enhancement via secondary re-concentration.
Displays a near vertical dip to the NW or SE and principal all within the weathered zone (mostly oxide and transition material).
Detailed grade control drilling established significantly wider mineralization widths

 
 (VIRIMAI PROJECTS LOGO)Page 53
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 8.1)

 

Figure 8.1: Buckreef deposit (yellow areas represent projection of mineralized orebodies to surface).

 

A preliminary structural interpretation using cross-sectional drilling data, related interpretive plans at various elevations and also the regional aeromagnetic and deposit-scale ground magnetics images covering the project area, the Buckreef Main zone mineralisation appears to show very limited (m-scale) displacements along interpreted E-W to ENE-SWS late stage cross cutting structures, such as dykes and faults. A second but not pervasive N-S set of late stage cross-cutting structures is also evident.

 

The widths of the mineralized zone do show a distinctive tendency to narrow which could reflect less dilationaly favourable inflexion in the fault zone or a typical boudinaging geometry and/or a local change in host rock including intrusion of felsic porphyries that ether diffuse or completely stope out the mineralization.

 

8.3Buckreef Deposit Model

 

In 2005, IamGold engaged a structural geology expert, A. Turks to conduct a detailed structural interpretation of the Buckreef Gold deposit among others. The extract herein described was his summary in point forms on how the Buckreef gold deposit was formed.

 

The section below was an attempt by Turks (2005) to show the evolution of the Buckreef Mineralization in relation to the main structural control so far as follows:

 

ØEruption of mafic volcanic rocks in marine setting
ØCarbonate and chlorite alteration of mafic lithologies during seafloor metamorphism.

 
 (VIRIMAI PROJECTS LOGO)Page 54
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

ØBuckreef fault may have been active a s a transfer fault in original basin. Assuming original basin bounding structures run EW (highly speculative)

 

(Figure 8.2)

 

Figure 8.2: Inversion of the basin –Buckreef structure reactivates as a strike –slip transfer fault while original normal faults are now reverse faults.

 

ØIntrusion of Felsic Porphyries partially controlled by Buckreef fault zone –i.e. Porphyries are not intruded as sills parallel to the bulk of the EW mafic stratigraphy but are broadly intruded NS sub parallel to the Buckreef fault zone.

 

(Figure 8.3)

 

Figure 8.3: Intrusion of Felsic Porphyries controlled by basinal structures.

 

ØInversion of basin reactivating original normal faults as thrusts and Buckreef fault as a strike slip transfer fault

 

(Figure 8.4)

 

Figure 8.4: Inversion of basin-Buckreef structure reactivates as a strike slip transfer fault while original normal fault are now reverse faults.

 
 (VIRIMAI PROJECTS LOGO)Page 55
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

ØEarly quartz – carbonate pyrite veining causing silicification and carbonate alteration (Fe carbonates – ankerite?) of the mafic rocks. There is probably some gold mineralisation associated with this event but it is difficult to interpret how significant this is due to later superimposed deformation and alteration.

 

(Figure 8.5)

 

Figure 8.5: Brecciation of the previously altered zones (Early Stages of Au Mineralisation).

 

Early breccias have a grey quartz matrix with disseminated pyrite? There is definitely gold mineralisation associated with this event. The style of brecciation suggests cyclic high fluid pressures and several episodes of explosive brecciation.

 

(Figure 8.7)

 

Figure 8.7: Continued Cyclic rupturing of the Buckreef fault zone under high fluid pressure conditions resulting in extensive alteration a series of printing brecciation events.

 
 (VIRIMAI PROJECTS LOGO)Page 56
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

ØCyclic formation of carbonate + quartz ± pyrite and brecciation overprinting earlier formed veins and breccias. Additional gold mineralisation again related to sulfidation. Zones that have seen several breccia episodes form the highest-grade intersections. Limited lineation data on quartz veins and breccia zones indicates dominantly sinistral strike slip shear with minor episodes of dip slip reverse shear. Original high-grade shoot geometry would be steep to subvertical, controlled by the orientation of s2 during strike-slip movement along the Buckreef fault zone. Any jogs or transfer zones should have a steep plunge during strike slip deformation.

 

(Figure 8.8)

 

Figure 8.8: Illustrates the classic plunge possibilities for classic fault orientations. As Buckreef appears to have been dominantly strike slip we would expect a steep to sub vertical shoot geometry controlled by the σ2 direction

 
 (VIRIMAI PROJECTS LOGO)Page 57
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

8.4Conclusion

 

The Buckreef Gold mine is hosted within a NE trending mylonitic shear zone, which cross-cuts a mafic volcanic package. In summary, the Buckreef Mine is located on a clearly defined, east-northeast/west-southwest trending, 5m-30m wide and 8km long, brittle-ductile shear zone within relatively undeformed mafic volcanics. Gold mineralisation is controlled within the regional shear by a fault zone with a 10m true width, continuous for over 1.5km strike length, is associated with intense brecciation and quartz, carbonate, sericite pyrite alteration synonymous with typical Archean lode hydrothermal gold deposits.

 

Hydrothermal processes are driven by remnant heat from volcanic activity and or intrusions of regional granitoids and other felsic intrusives such as porphyries in the Rwamgaza greenstone belt. Circulating thermal waters, rising through fissures, eventually reach the “boiling level” where the hydrostatic pressure is low enough to allow boiling to occur. This can impart a limit to the vertical extent of the mineralization as the boiling and deposition of minerals is confined to a relatively narrow band of thermal and hydrostatic conditions. In many cases, however, repeated healing and reopening of host structures can occur, which causes cyclical vertical movement of the boiling zone, resulting in mineralization that spans a much broader range of elevations. This appears to have occurred at the Buckreef Gold Mine.

 
 (VIRIMAI PROJECTS LOGO)Page 58
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

9EXPLORATION

 

The Buckreef project has been the subject of numerous exploration programmes carried out by several companies over more fifty years. As summarized in section 6 of this report the project was originally defined by a 1966 United Nations exploration programme following up artisanal workings. The deposit was subsequently explored by the Tanzanian Mineral Resources Division and developed into a small underground mine by Buckreef Gold Mining Company a wholly owned subsidiary of the State Mining Corporation (Stamico). The mine closed down in 1990 due to low gold prices and lack of working capital resulting in inability to purchase fuel and maintain plant ending in the flooding of the mine.

 

Table 9.1 Summary of Buckreef Project, Historical Exploration Work, Geita District, Tanzania

 

DATE EXPLORATION UNDERTAKEN
1999-2000 EAGM signed an earn-in agreement with Ashanti AngloGold to explore Buckreef Project which was terminated late 2000. 16,324m of drilling in 67 drill holes, 18 of which were RC and 49 drill holes diamond (15,363m)
2001-2003 Spinifex Gold, operating for EAM, ran the project with very limited exploration work based on the follow up recommendations from the final exploration report by Ashanti AngloGold. 610 RC drill holes (49,000m) with 6 diamond drill holes. IP geophysical survey over Buckreef
2004-2005 Following the merger between Spinifex Gold and Gallery Gold in 2003 significant exploration work was concluded on the project and new resources established on the Buckreef Mining licence. Resources were improved at Tembo and Bingwa prospects. Geophysics and geochemical soil surveys completed with additional RAB, RC and diamond drilling.
2006-2009 Following the merger between Gallery Gold and IAMGOLD Corporation of Canada in March 2006 EAM changed names to IAMGOLD Tanzania Ltd. Under IAMGOLDT, Buckreef Project was completed up to commencement of pre-feasibility studies before the company decided to close all its exploration activities in Tanzania in 2009 and in so doing decided to surrender back to the government all its exploration portfolio under the Buckreef Re development Agreement. 2,949 drill holes were drilled for 142,302m including 2,160 aircore, 745 RC and 44 diamond drill holes. Regional soil and termite mound reconnaissance sampling programme. Regional mapping
2010-2012 In March 2010 the government of Tanzania granted afresh all the surrendered licences to Stamico, including the existed applications under IAMGOLDT.

Source: Venmyn Deloitte 2012.

 

Historical exploration work conducted by Tanzanian Gold Corporation (formerly Tanzanian Royalty Exploration Corporation) between 2012 to 2017 has been reported on in detail in several published NI43-101 Technical reports as well as the Prefeasibility report published in June 2018. A brief summary of the historical exploration done on the project is summarized under Sections 9.1 to 9.2 below and is as previously reported in previous publications.

 
 (VIRIMAI PROJECTS LOGO)Page 59
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

In this report, Section 9.3 below, the focus is only on the additional resource drilling that was conducted only on the Buckreef deposit in the period from June 2018 to early 2020. The extensive drilling program (both RC and diamond core drilling) was mainly targeting the down-dip and strike extensions of the three major gold prospects namely, Buckreef North, Buckreef Main and Buckreef South, that make the Buckreef Deposit.

 

9.1Buckreef Gold Project

 

A Section in Chapter 6 briefly summarized the exploration history on the Buckreef Project starting from 1960 soon after the area was designated as a potential strategic deposit by the Tanzanian government following an incursion by local artisanal gold miners. Table 9.1 below summarizes the major exploration work conducted over the decades by the various companies that have been involved with the Buckreef project over the last 50+ years.

 

As reported in the published NI43-101 reported mention in Chapter 6 above, Tanzanian Royalty Exploration Corporation, through its 100% owned subsidiary, Tanzam200 commenced mainly further resource drilling and exploration work covering the five main prospects that make up the Buckreef project in 2012. Most of the exploration work at the Project was completed previously during the IAMGOLD ownership as reported in the SEDAR posted reports.

 

As cited in the published Venymn Independent Technical Reports, regional and detailed exploration by IAMGOLD identified the four major gold prospects as Buckreef (Main, North & South), Bingwa, Tembo and Eastern Porphyry. IAMGOLD then conducted further resource drilling on the Buckreef (Main & North), Bingwa and Tembo prospects. Exploration criteria for the five prospects were essentially based on the normal Archean gold deposit formation criteria listed below:

 

Presence of gold
Favourable structure (shear zones and breccia zones)
Significant quartz vein material
Hydrothermal alteration minerals and assemblages
Proximity to unconformities and disconformities; and
Proximity to oxidation/reduction boundaries of regional scale

 

For detailed descriptions and in-depth discussion of the exploration work, some of whose results are briefly summarized below, the reader is referred to Venymn Independent Projects Preliminary Economic Assessment Technical Report (ITR) completed under NI 43101 standards and amended and filed on the System for Electronic Document Analysis and Retrieval, “SEDAR”, (www.sedar.com), on August 12, 2012.

 

The authors of the Buckreef PEA Independent Technical Report (ITR VIP21), produced for TRX, were Qualified Persons F. Harper (Pri.Sci. Nat.; MGSSA) and A.N. Clay (Pri. Sci. Nat; MSAIMM, FGSSA, FAusIMM). Brief discussions on some of the significant exploration work done are summarized below.

 

9.2Geophysical Survey

 

Because of the limited bedrock exposure in the Buckreef Project area, numerous geophysical surveys have been conducted at the site in the quest for additional ore. These efforts are summarized in report by Venmyn 2014. Geophysical surveys conducted include ground gravity and dipole-dipole IP/resistivity.

 
 (VIRIMAI PROJECTS LOGO)Page 60
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

9.2.1Surveys

 

Spectral Geophysics (Botswana) was contracted during April 2008 to complete ground gravity surveys over 5km2 and the data was interpreted by Southern Geoscience Consultants (SGC) in Australia. The final results were compiled into a 1:20,000 scale geological interpretation delineating twenty-one targets and the Rwamagaza Shear Zone. Gravity surveys proved effective for the location of large first order structures and in 2008 the airborne magnetic data was interpreted into an image atlas for future target definition.

 

9.2.2Induced Polarisation Surveys

 

During 2007, 14 IP survey blocks were completed over the project area by Spectral Geophysics and processed by SGC Australia. The results of these surveys highlighted altered fault/shears zone structures and in conjunction with magnetics can be used for targeting prospective strike extensions of existing ore bodies.

 

9.2.3Geochemistry Surveys

 

Several historical soil and rock chip sampling programs were completed over the Buckreef Project area on a grid of 100m x 100m, with closer spaced grids (80m x 40m) over historical target areas and targets with a high density of lineaments and interpreted mineralized structures. A total of 2,028 rock chip samples, 29,546 soil samples and 481 termite mound samples were taken during the period 1992-2009.

 

Transported laterite, combined with Mbuga soils which cover 60% of the area, hamper geochemical sampling and interpretation and IAMGOLD completed termite mound sampling over the problematic areas. To date the termite sample density is too low for identification of meaningful anomalies. The results of the soil geochemistry results are consistent with the known structures in the area. The largest soils anomalies occur are over the main deposits at Buckreef Prospect.

 

On surface, favourable structures are identified utilizing the 2006 airborne magnetometer survey covering the Rwamagaza greenstone belt. Due to lack of outcrop exposure, very limited ground geological mapping was employed to identify fabrics, offsets and abrupt changes in rock types that indicate structure. Rather detailed geological core logging was used to extrapolate the structural fabrics and hydrothermal assemblages typical for each prospect.

 

9.3Buckreef Deposit: Mineral Resource Upgrade Drilling

 

Based on the recommendations from the June 2018 Pre-Feasibility report, TanGold Corporation conducted further mineral resource drilling on the Buckreef deposit targeting the three specific portions of the deposit, namely South, Main and North. The rationale behind the drilling program included among others:

 

to convert a significant portion of the previous inferred mineral resource category into indicated and measured categories;
to clearly delineate the host structure (shear zones and breccia zones);
to improve understanding of ore-body geometry down dip and along strike;
to identify & confirm the significant potential for underground extension of the Buckreef Main/North deposits and
to update the mineral resource inventory for the Buckreef deposit.

 
 (VIRIMAI PROJECTS LOGO)Page 61
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Towards achieving the goals stated above, the Company conducted the drilling work as summarized in the Table 9.2.

 

Table 9.2: Mineral Resource Upgrade drilling program statistics, Buckreef Gold Deposit

 

Drill-hole Type 2019/2020 Program Pre 2019 Program Grand Total
# of Holes Meters Drilled # of Holes Meters Drilled # of Holes Meters Drilled
RC 43 6,733.00 508 41,994.70 551 48,727.70
RC Pre-Collaring 15 2,713.00     15 2,713.00
Diamond Core 8 4,105.50 213 55,954.00 221 60,059.50
Diamond Core Tailing * 3,936.90 43 10,153.20 43 14,090.10
Metallurgical (core) 1 162.01     1 162.01
Totals 67 17,650.41 764 108,101.90 831 125,752.31
* Note: The DD Tails are already counted as RC percolate hence no figure in the table

 

Some of the deeper diamond drill-holes were first pre-collared with RC drilling after which the drill-hole was then completed with diamond coring. The drilling program was targeted to cover both the strike extension and down-dip projections of the three main portions of the Buckreef deposit and the spatial location of the drill-holes is as shown in the map below.

 
 (VIRIMAI PROJECTS LOGO)Page 62
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 9.1)

 

Figure 9.1: Spatial location of the Mineral Resource Upgrade drill-holes, Buckreef Gold Deposit 2019/2020

 

The 2019/2020 exploration work conducted by the company represents the largest single and continuous drilling program on the Buckreef Gold Deposit and this has allowed the Company to achieve the main goals that included among others the following:

 

Resource conversion within the pre-feasibility pit outlines,
Resource addition immediately below and beyond the last defined pit bottom,
Commence additional Metallurgical test-work &
Set the initial stage for “ultra-deep” underground potential exploration drilling.

 

The detailed findings from this extensive drilling program are described in detail in the following Chapters in this report.

 
 (VIRIMAI PROJECTS LOGO)Page 63
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

10DRILLING

 

As summarized in the various SEDAR posted Technical Reports by Venymn, the majority of the exploration and resource drilling at Buckreef’s four major prospects namely Buckreef, Bingwa, Tembo and Eastern Porphyry was done previously by IAMGOLD.

 

TANZAM2000 then conducted further resource drilling on the Buckreef (Main, South & North), Bingwa, Tembo and Eastern Porphyry prospects based on recommendations from the 2012 Preliminary Economic Assessment report by Venymn.

 

In 2019 the most aggressive drill programme was initiated and a total of 17,650 metres were completed for 67 drill holes as indicated in Table 10.1.

 

Table 10.1 Summaries of the 2019 Drilling Programme on the Buckreef

 

Drill-hole Type 2019/2020 Program
# of Holes Meters
Drilled
RC 43 6,733.00
RC Pre-Collaring 15 2,713.00
Diamond Core 8 4,105.50
Diamond Core Tailing * 3,936.90
Metallurgical (core) 1 162.01
Totals 67 17,650.41

* Note: The DD Tails are already counted as RC percolate hence no figure in the table

 

10.1Buckreef Prospect

 

Surface exploration and resource definition drilling completed, by previous owners, along the NW-SE control lines are shown in Figure 10.1. The Buckreef resource has been drilled on local grid east-west oriented drill traverses at mostly 20 meter intervals along the strike of the gold mineralization above 1100mRL (surface approximately 1225mRL). Below 1000mRL to the base of drill coverage (approximately 700mRL) the deposit has been variably intersected on 100m intervals south of 2600mN and 40-50m intervals north of 2600mN.

 

Many drill holes are angled steep (~60o) towards grid east or west normal to the strike of the main mineralised shear zone. On many sections the drill holes targeting the near surface gold mineralization are spaced at 10m centres providing approximate 20m spaced vertical intercept on the gold mineralization.

 

The RC resource delineation drill spacing was completed on a 40m to 20m x 20m spacing at Buckreef. On sections targeting the near surface gold mineralization, the drill-holes were spaced at 10m centres providing approximate 20m spaced vertical intercepts on the gold mineralization.

 
 (VIRIMAI PROJECTS LOGO)Page 64
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 10.1)
Figure 10.1 Location of Historical RC/DD exploration and Resource drill-holes, Buckreef Deposit, Geita District, Tanzania

Source: Buckreef Gold Mine 2019;

 

Between 2013 and 2014, the TANZAM2000 completed additional resource definition drilling mainly targeting the Buckreef South and North deposits in addition to the mandatory twinning preliminary due-diligence diamond core holes on selected portions of the Buckreef main deposit as part of recommendations from Venymn reports.

 

At Buckreef Prospect, the North and Main Zone mineralization occurs in a shear zone with a true width of about 10m, dipping steeply to the west. As a precaution to minimize interference and sampling by artisanal miners, the RC 1m samples were collected daily and transported to a central sample store where they were sampled and bagged.

 

The 2012 core drilling program was aimed at defining mineralization between 150m and 250m depths at the Buckreef Main deposit. The results identified a wide zone of mineralization, as exemplified by two drill-holes which intersected a mineralized zone 26m wide with a grade of 4.5g/t Au at 215m depth and a zone, 19m wide with a grade of 10.58g/t Au at 155m depth.

 

The same 2012 drilling program also confirmed that the high-grade mineralization extends northwards beyond the previous identified Buckreef North Zone mineralized zone and two significant drill-hole intercepts included a 46m wide mineralized zone with a grade of 2.31g/t Au at a depth of 28m and a 14m wide zone with a grade of 1.75g/t Au at a depth 206m.

 

The diamond drilling core recovery was an average of 93% (Venmyn, 2014). Most of the diamond drill-holes commenced with a tricone roller bit where near surface sampling was not required, followed by HQ diameter, which was reduced to NQ/NQ2 when fresh rock was encountered. Ten HQ core holes were drilled at Buckreef

 
 (VIRIMAI PROJECTS LOGO)Page 65
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

to twin anomalous RC and diamond drill-holes as part of a QA/QC program on historical assay practice and grade continuity. PQ metallurgical samples were collected at Buckreef Prospect.

 

The main objective for the 2019 drill programme was in two folds, one is to drill past 700mrl and test downdip extension of gold mineralisation as well as lateral extension further North east. The second objective was to advance Mineral Resources from Inferred to Indicated and Measured categories. The diamond drilling core recovery for this programme has an average of 99.5%, a good indication of competent rock units in Buckreef. Most of the diamond drill-holes commenced with RC pre-collar or a HQ sized bit, which was reduced to NQ/NQ2 when fresh rock was encountered.

 

10.2Bingwa Prospect

 

Bingwa lies at the northern margin of the RGB adjacent to a sheared contact with a granitic intrusive and approximately 4km east of Buckreef. Surface exploration and resource definition drilling completed, by previous owners, along the NW-SE control lines are shown in Figure 10.2. An additional 1,500m of RC and 180m of diamond core drilling was completed on the prospect in the period 2012 to 2013 by the company.

 

(Figure 10.2)
Figure 10.2 Location of Historical RC/DD exploration and Resource drill-holes, Bingwa Deposit, Geita District, Tanzania

Source: TRX 2013

 

The RC drilling tested the southwest strike and potential down-dip extension of the main Bingwa deposit while the core drilling is to accommodate additional metallurgical and specific gravity analytical test-work. The drilling confirmed gold mineralization over a strike length of 350m and up to 100m below surface with the main zone of mineralisation occurring over a strike length of 150m. The majority of the mineralization defined to date lies in the oxide zone, which extends to 40 to 60m below surface.

 
 (VIRIMAI PROJECTS LOGO)Page 66
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The results of this drilling program were used to advance Mineral Resources from Inferred to Measured and Indicated categories and to increase the Mineral Reserve.

 

10.3Eastern Porphyry Prospect

 

Historical exploration work by IAMGOLD identified the Eastern Porphyry as target with potential to host a significant resource that could be added into the Buckreef Project Resource inventory.

 

Venymn (2012) noted that the historical wide-spaced RC drilling conducted on the Eastern Porphyry Prospect, located on the strike extension of an ENE-WSW trending, 5-30m wide, brittle-ductile fault zone, defined the presence of finely disseminated pyrite and quartz veining slivers of persistent but discontinuous sub parallel zones of quartz porphyry units hosted in the main fault zone over a 300m strike length of continuous gold mineralization associated with quartz veins emplaced in sheared felsic porphyry and dolerite.

 

An additional 10,814m of RC and diamond core drilling was completed on the prospect in the period 2012 to 2013 by the company. The combined historical and additional surface exploration and resource definition drilling along the NW-SE control lines are shown in Figure 10.3.

 

(Figure 10.3)
Figure 10.3 Location of Historical RC/DD exploration and Resource drill-holes, Eastern Porphyry Deposit, Geita District, Tanzania,

Source: TRX 2012

 
 (VIRIMAI PROJECTS LOGO)Page 67
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

10.4Tembo Prospect

 

Venmyn (2012) noted that the historical RC drilling conducted on the Tembo Prospect, defined gold mineralization within grey quartz stringers, veinlets and boudins (tension zones) all tightly constrained by a 3- 5m wide ENE-WSW trending brittle-ductile shear zone hosted in basaltic volcanic units. Historical drilling by IAMGOLD covered a 200m strike length.

 

Tanzam2000 conducted additional RC and diamond core drilling for metallurgical and specific gravity tests to upgrade the deposit resource from inferred to measured + indicated category. The drilling will also test strike continuity of mineralization to the east (Figure 10.4).

 

(Figure 10.4)
Figure 10.4 Location of Historical RC/DD exploration and Resource drill-holes, Tembo Deposit, Geita District, Tanzania

Source: TRX 2013

 

10.52019 Drilling Programme

 

10.5.1Core Handling

 

Drill core is retrieved from the bottom of the hole using a wire-line core barrel double tube setup. Drilling crews then arrange the core in the order from which it is drilled, before it is placed in the core trays. In between each drill run, drill crews place core blocks and mark them with depths (in metres), approximate core loss, or gain. Core trays are marked with the project name, drill hole identity number, the intersection interval (start and final depths in that box), an arrow indicating which direction is down-the-hole, and a sequential box number. In the event of breakage of core is required to fill the box edged tools are used and the end of every run is marked. The

 
 (VIRIMAI PROJECTS LOGO)Page 68
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

core trays are transported to the core storage facility for subsequent core processing only after the supervising geologists has gone the cores to ensure that they are properly laid out, marked correctly and the tray is full.

 

10.5.2Collar Surveys

 

Collar coordinates were captured in the ARC1960 Datum and UTM 36S coordinate system. Independent survey contractor was employed and uses Total station Survey instruments.

 

10.5.3Downhole Surveys

 

The majority of drill holes at the Buckreef Deposit are orientated at a dip angle, commonly -60º to either the northeast or south west depending on accessible drill pad. This is acceptable, as the targeted mineralised shear zone is sub-vertical and interchangeably dip to the SW or NE.

 

In order to monitor the consistency and deviations in drill hole trajectory, multiple downhole surveys were conducted for all drill holes using a Reflex EZ Shot (electronic single shot magnetic survey tool).

 

At the Buckreef Deposit, the down hole surveys were completed at 20 metres intervals and when there was a change from RC pre-collar to Diamond tail.

 

All drill holes were downhole surveyed with the Reflex EZ shot technique. Dip and azimuth readings were recorded, along with temperature, and magnetics data in the project database. A range of magnetics data were used to accept the reliability of azimuth data set. For 2019 drill programme, ranges 32000 to 34000 are acceptable to give a reliable azimuth reading. It was observed that the average deviation was 3.2º for inclined hole and maximum deviation recorded was 12º.

 

10.5.4Orientated Drill Core

 

All diamond drilled core is oriented, for each 3m drill run, by the drilling contractor using the Reflex ACT II RD orientation tool. Where core is sufficiently competent to allow orientation surveys, geologists collected structural information. Orientated core runs (and broken core pieces) were aligned utilising the orientation marks provided by the Reflex ACT II RD system. These core pieces were marked according to the confidence in orientation, with different orientation marks only within 15° of each other to be considered aligned.

 

10.5.5Recovery

 

Core recovery was measured at the core yard by Buckreef technician who reconstructed the core to an intact state within the core tray. The core is measured using a tape measure. This measurement was then compared to the length of the drilled core run, and the percentage of recovery was calculated and recorded.

 

Calculation of the recoveries of RC drill samples is completed by collecting the drill cuttings in a large woven polyethylene bag at the underflow of the RC drill’s cyclone, and weighing the bag and contents using a digital scale. This weight was compared to a theoretical value of a cylinder of 1m length and the diameter of the RC hammer, and an assumed density (based upon measured densities of drill core from similar lithologies). The percentage recovery is then calculated by dividing the weight of the recovered sample, by the theoretical, and then multiplying by 100 to obtain the percentage recovery. This method is considered semi-quantitative as some component of the sample is always lost as airborne dust through the cyclone overflow. No consideration of

 
 (VIRIMAI PROJECTS LOGO)Page 69
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

sample moisture is factored in. This method provides an indicative value to assess whether sample recovery was enough to be considered valid.

 

10.5.6Geological Logging

 

All diamond core holes were logged at the Buckreef core storage facility. The logging was completed by exploration geologists and reviewed by Principal geologist. Industry-standard logging methods, sampling conventions, and geological codes were established for the project. Descriptions of colour, mineralogy, texture, lithology, weathering, alteration and mineralisation were completed using paper logs. Logged data are then entered into Excel spread sheets, using single data entry methods, by Buckreef database officer. Structural features such as bedding, foliation, fold, joints, veins, and faults were recorded for both geological and geotechnical purposes.

 

All drill cores are photographed, when wet and dry, before subsequent core processes in the core storage facility. RC drill chips were logged at site, and representative samples (coarse rejects) are stored in polyweave sacks for each 1m interval. All data, including core photographs, are captured and stored in the project database.

 

10.5.7Comments on Drilling Section

 

The quantity and quality of drilling, geological and geotechnical logging, collar, and downhole survey data collected in the core drill programs is sufficient to support mineral resource update and subsequent use in mine design on the following observations:

 

Drill hole orientations are generally appropriate for the geometry of the orebodies and mineralisation style.
Collar surveys were performed using industry-standard instrumentation.
Downhole surveys provide appropriate representation of the trajectories of the drill holes.
Core recoveries are satisfactory for the estimation of mineral resources.
The accuracy and the level of detail, in both the geological logging and geotechnical logging, is considered sufficient to support the estimation of mineral resources, mining and metallurgical studies; and
No material factors were identified with the data collection from the drill programs that could affect mineral resource estimates.

 
 (VIRIMAI PROJECTS LOGO)Page 70
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

11SAMPLE PREPARATION, ANALYSES AND SECURITY

 

This section of the report briefly summarizes the sampling methods, sample preparation, assay analysis, and security procedures for historical and current 2019 drilling and sampling program. For detailed descriptions and in-depth discussion of on this topic, again the reader is referred to Venymn Independent Projects Technical Reports ITR-VIP21, ITR-VI199R and ITR-VMD1598 completed under NI 43101 standards and amended and filed on the System for Electronic Document Analysis and Retrieval, “SEDAR”, (www.sedar.com).

 

In brief, the procedures for both RC chips and core samples were developed and documented by the previous operator IAMGOLD and were largely adopted by TANZAM2000 to maintain continuity and congruity. The same sampling protocol are maintained in 2019 drill and sampling programme. Any changes made by TANZAM2000 were duly noted within the Independent Technical reports mentioned above.

 

11.1Core Sampling Methods

 

Diamond core drilling at the Project was conducted by contractors under the supervision of a qualified geologist. The drill core was then placed in labelled metal trays and depth marker blocks inserted by drilling contractor personnel prior to the removal of the core from the drill site by the project geologist. Upon arrival at the secure core logging facility, the core boxes were sequentially placed in a core rack and the spatial information on each box of core is checked for accuracy and consistency. Prior to any sampling, the drill core was digitally photographed by a geological technician under the supervision of a geologist.

 

Exploration geologists then logged the core and recorded observations first in a manual log sheet and then subsequently uploaded into a master drill log database. Diamond core is sampled on geological basis such as the presence of mineralization, favourable structure, presence of alteration halos and quartz veining. The samples were then marked and measured for sampling and identified with one part of a three-part assay tag placed at the end of the sample interval. The minimum sampling interval is 0.5m and the maximum is 1m.

 

Venymn noted that the potentially mineralized portion of the drill-core was split in half using a core splitter. One half of the split core was then taken as a sample that was immediately placed in a sample bag by the geologist and identified with an assay tag, whose duplicate copy was kept in the sample book, and the sample number is recorded on the log-sheet prior to entry into the master database. Additional samples on either side of the presumed mineralized section were also collected to close off mineralization as is standard practice.

 

Blind standards were routinely inserted into the sample sequence prior to delivery to the assay laboratory. Blanks (also routinely inserted every 50 samples and after all noted visible gold) consist of either intervals of un-mineralized core which are identified and flagged prior to shipment to the assay lab or were sourced from a commercial laboratory and inserted into the sample stream prior to shipment.

 

Sealed sample bags were then transported to the assay laboratory in a timely manner. Upon arrival at the assay lab, samples are received by laboratory personnel and maintained the laboratory’s chain of custody procedures

 
 (VIRIMAI PROJECTS LOGO)Page 71
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

and protocols. Historical exploration companies including IAMGOLD and TANZAM2000 maintained a chain of custody as well which was updated throughout the process.

 

There were additional requirements for 2019 drill programme samples security and chain of custody. This was introduced in 2016 by the Government of Tanzania through the Ministry of Minerals and it involves government personnel participation in the transportation of samples between site to the laboratory. The government official and Buckreef personnel in the presence of Government police officer verified the samples which are ready packed for dispatch. Weights for each sample is verified through a random check for individual sample weight in the bags and the count is manually done before loaded in the truck and attach a government seal on the truck door. The seal is only opened in the lab premises with government officials and lab crews. This additional security procedure assured that the samples had no chance to be tempered when transported to the laboratory.

 

11.2RC/RAB Sampling Methods

 

The RC/RAB drilling sampling methodology comprised collection through a cyclone at 1m intervals into large plastic bags. An exploration geologist logged the drill-chips on site as each meter sample was riffle split on site, weighed and moisture content recorded for every meter drilled.

 

RC holes were stopped if persistent wet samples were encountered. Most RC samples collected since 1992 were homogenized and reduced to 2kg to 3kg on site by passing reduced samples at least 4 times through a single tier Jones riffle, which is demonstrated to be a more representative sample than that produced by stacked three tier splitters. In later years, the entire length of RC and RAB drill-holes was collected as 1m samples with individual RC samples for assaying taken as 3m composites. During composite sampling, the individual 1m riffle split reduced samples were collected in the field and retained for future analysis if warranted.

 

As with the core samples, unique Sample ID ticket books with corresponding tear off sample tickets were printed and used to record sample details and assay samples.

 

Both drill core and RC pulp samples were submitted to various ISO accredited laboratories who in turn utilized comprehensive in-house QA/QC measures from sample preparation to instrumental finish and reporting of the results. Equipment was cleaned between batches; crushing and pulverizing was monitored by sieve testing. Routine laboratory Quality Control sampling (pulp duplicates and pulp repeats) was also completed on pulps retained at the laboratory. This provided an indication of any sample preparation/sub-sampling/sample digest and assay error at the primary laboratory.

 

Both Hellman & Schofield and Venymn Independent Projects subsequently conducted a very intensive and detailed statistical assessment of the QA/QC Data for project area. They both concluded that the historic (Pre 2019 drill programme) QA/QC data available provided assurance that the data is not flawed by sampling or assaying bias. Further to that, they also considered the QA/QC performance to be good and the data suitable for incorporation in the published Mineral Resource estimates done in 2007, 2012 and 2014.

 
 (VIRIMAI PROJECTS LOGO)Page 72
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

11.3Sample preparation and Analysis

 

Buckreef Gold Project uses Nesch Mintech laboratory as a primary laboratory for sample preparation and analysis. The Laboratory is situated in an industrial area approximately 8 Kms outside Mwanza on Shinyanga road. The Laboratory is divided into two houses, one serves as a sample preparation facility, and the other as a fire assay, wet chemistry, instrumentation facility and administration office. The laboratory is ISO 17025 certified. Accreditation certification of the laboratory is appended hereto. The laboratory operation follows and maintains the standards supported by this accreditation.

 

In the laboratory, samples are sorted into numeric sequence and referenced to the clients’ submission documents. Once confirmed, the batch data is entered in the computer. And a new work sheet is created to go with sample batches at every laboratory workstation.

 

Samples received are crushed to ensure appropriate sample size (<2mm) before milling. Jones Riffle Splitters are used to further split samples to get a reasonable size (about 0.5kg) for milling using Labtechs LM2 pulverisers machines. Milling of samples is performed to attain 95% passing 75 micron. The Buckreef samples are fire assayed using 50g aliquot and gold results are read on Atomic Absorption spectrometry machine.

 

The following chapter gives details on the Quality control and quality assurance results for samples generated in 2019 drill programme.

 

(Figure 11.1)

 

Figure 11.1: Drillholes used in 2019 Resource update

 
 (VIRIMAI PROJECTS LOGO)Page 73
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

11.4QUALITY ASSURANCE & QUALITY CONTROL (QA/QC) PROCEDURE 2019 DRILLING PROGRAMME

 

Figure 11.1 shows additional drill holes completed in 2019, this section deals with samples and assays quality control and quality assurance generated from this programme. Analytical performance was determined by analysis of control samples to determine precision, accuracy, bias and cross contamination. This included the analysis of certified reference materials (CRMs), coarse blanks and duplicates within sample stream batches. A review of the Buckreef QA/QC procedures were completed by a team from Virimai Projects and the staff of TRX.

 

i.Blanks

 

Coarse blank material from the granitic quarry has been used in the sample streams for all Buckreef samples for both Reverse circulations and diamond drilled samples. The material was sourced approximately 10km from deposit area on a granitic borrow pit. Prior to using the blank material, a number of sub-samples were taken, and these were submitted for assay at the Nesch Mintech laboratory to confirm that the material is not mineralised.

 

Material used for coarse blanks was crushed to -2 mm to be used as a blank in the crushing pulverising stage of the sample preparation. The coarse blanks are inserted into the sample preparation stage at an average rate of one in every 20 samples. It is in discretion of a sampling geologist to locate a position in the sample stream where to insert a coarse blank sample, mainly with preference to start/ end of mineralised zone or a start of a sample batch.

 

(Figure 11.2)

 

Figure 11.2: Coarse blanks assessment graph

 

The acceptable limit for Au on blanks was set at 0.05g/t, this is 5 times detection limit. At least 90% of blanks should be within the acceptable limits for a satisfactory performance. Au values are plotted against the order of analysis on a control chart for visual assessment (See Figure 11.2).

 
 (VIRIMAI PROJECTS LOGO)Page 74
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

From the data, a total of 253 blank samples that were taken to the lab, and only five six returned results above pass limit, this equates to 98% of blanks within pass limits.

 

In general, the contamination levels of the 2019 drill holes analyzed by the Nesch Mintech Laboratory can be said to be within satisfactory limits. There is an indication of some level of contamination of samples or sample swapping at the Lab, these were investigated and where required, re-analyzed.

 

ii.Field Duplicates and Pulp duplicates

 

Assay results from field and pulp duplicates are compared with the original results of primary assay data to assess the quality of the various subsampling procedures and repeatability of laboratory analysis at various stages. The frequency of these duplicates for 2019 drilling programme is a minimum of 1:20. The location of duplicated samples is on geologist discretion, where, he sees potential for gold mineralization. Duplication of samples around detection limit, does not serve the purpose of checking precision of the results.

 

In Figure 11.2 a Duplicate analyses are plotted against the original analysis. A line of X=Y (i.e. 1:1) is plotted. A correlation coefficient from linear regression line depicting actual trend of the distribution of the sets is also shown in the plot. Allowable error margins plotted are +/-20% for field duplicates and +/-10% for Pulp duplicates.

 

Pulp duplicate samples in Buckreef 2019 drill programme originate from Diamond drilled samples which were previously assayed by the same laboratory. As a result a pulp duplicate is thus used to check repeatability of original assaying at a later date. The pulp scatter plot shows a significant bias toward pulp duplicate results. Although this is a concern, most of the results are below 0.2g/t Au which is below a reported cutoff grade for resource update, and therefore may not have material impact on the Resource numbers reported. Nevertheless, these results were communicated to the lab to avoid potential future bias.

 

(Figure 11.3)

 

Figure 11.3: Scatter plots for Field duplicates (left) and Pulp duplicates (right)

 

Figure 11.3 is a graphical technique for determining if two data sets come from populations with a common distribution (as should be in the case of duplicate assay samples). The q-q plot is a plot of the quantiles of the original samples against the quantiles of the duplicates/repeats.

 
 (VIRIMAI PROJECTS LOGO)Page 75
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

A 45-degree reference line is also plotted. If the two sets come from a population with the same distribution, the points should fall approximately along this reference line. The greater the departure from this reference line, the greater the evidence for concluding that the sub-sampling was erroneously done and therefore precision of sampling protocols (whether in the field or lab as the case may be) is not satisfactory. This method also helps to physically look for the relationship between various grade ranges and precision.

 

Field duplicates indicates a bias toward duplicate assays at a grade range of up to 1g/t Au, and pulp duplicates indicates a bias towards a second assay to up to 0.4 g/t Au.

 

(Figure 11.4) 

 

Figure 11.4: QQ plots for Field duplicates (left) and Pulp duplicates (right)

 

iii.Certified Reference Materials (CRM)

 

A total of 368 certified reference materials were submitted together with the 16,624 drill core samples to determine assay accuracy and precision of the analyses. Eight CRMs were reported without valid CRM ID, these were excluded in the evaluation due to sample mislabelling.

 

Reference materials from various suppliers were used, to cater for various grades ranges that is high, medium and low grades as shown in Table 11.2.

 

A failure is defined as results outside ±3 certified standard deviations. At least 90% of the population of each standard reference material should pass the said criteria for the assay data to be considered to have a satisfactory accuracy level. During the 2019 drilling programme average CRMs achieved an average of 93.3% pass.

 
 (VIRIMAI PROJECTS LOGO)Page 76
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 11.1 Range of CRM Used during the 2019 sampling Programme

 

CRM
Category
CRM_ID Au (g/t) Mean
value
Standard
Deviation
High Grade AUOM-3 3.229 0.082
ST10/0302 3.660 0.150
ST10/0301 3.400 0.150
AMIS 0441 2.440 0.230
Medium Grade AMIS 0211 0.620 0.080
AMIS 0440 1.740 0.080
AMIS 0221 1.140 0.080
AUOH-5 1.319 0.027
ST 37/5340 0.730 0.030
OXE 74 0.615 0.006
OXE 56 0.611 0.006
Low grade ST 70/5344 0.099 0.010
ST 07/9258 0.220 0.020
OxC 72 0.205 0.003
AMIS 0234 0.229 0.030

 

Table 11.2 Pass rate of CRMs used during the 2019 sampling Programme

 

CRM ID No of
CRMS
Reported
CRMs
within
Certified
mean
(g/t Au)
Reported
mean
(g/t Au)
% Within
Pass
ST100302 38 35 3.66 3.67 92.1%
AMIS0221 36 36 0.62 0.61 100.0%
AMIS0234 17 16 0.23 0.23 94.1%
AUOM-3 42 38 3.23 3.16 90.5%
OxC72 44 38 0.21 0.2 86.4%
OxE56 33 32 0.61 0.61 97.0%
OxE74 52 48 0.62 0.62 92.3%
ST70/5344 25 25 0.1 0.1 100.0%
ST100302 38 35 3.66 3.67 92.1%
AUOH-5 10 35 1.32 1.29 100.0%
ST07/9258 25 10 0.22 0.2 100.0%
ST37/5340 8 6 0.73 0.67 75.0%
Average Pass Rate       93.3%

 

(Figures 11.5)

 

Figures 11.5 CRM ST100302 Nesch Mintech Mwanza Laboratory

 
 (VIRIMAI PROJECTS LOGO)Page 77
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figures 11.5)

 

Figures 11.5 CRM AUOM-3 Nesch Mintech Mwanza Laboratory

 

(Figures 11.6)

 

Figures 11.6 CRM AUOH-5 Nesch Mintech Mwanza Laboratory

 

(Figures 11.7)

 

Figures 11.7 CRM ST37/5340 Nesch Mintech Mwanza Laboratory

 
 (VIRIMAI PROJECTS LOGO)Page 78
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figures 11.8)

 

Figures 11.8 CRM OXE74 Nesch Mintech Mwanza Laboratory

 

(Figures 11.9)

 

Figures 11.9 CRM OXE56 Nesch Mintech Mwanza Laboratory

 

(Figures 11.9)

 

Figures 11.9 CRM AMIS0211-Nesch Mintech Mwanza Laboratory

 
 (VIRIMAI PROJECTS LOGO)Page 79
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figures 11.10)

 

Figures 11.10 CRM AMIS0234-Nesch Mintech Mwanza Laboratory

 

(Figures 11.11)

 

Figures 11.11 CRM OxC72-Nesch Mintech Mwanza Laboratory

 

(Figures 11.12)

 

Figures 11.12 CRM ST07/9258-Nesch Mintech Mwanza Laboratory

 
 (VIRIMAI PROJECTS LOGO)Page 80
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figures 11.13)

 

Figures 11.13 CRM ST07095344-Nesch Mintech Mwanza Laboratory

 

iv.Umpire samples

 

In 2019 drilling and sampling campaign, Umpire samples in Buckreef were generated by resubmitting a pulp sample from which an aliquot has been previously assayed for assay to a different laboratory. A total of 200 samples were sent to SGS laboratory in Mwanza which is ISO17025 certified laboratory. Results for Umpire samples are statistically summarized and compared with those analyses carried out at Nesch Mintech Laboratory the Primary Laboratory used for Buckreef see table 11.2.

 

Table 11.2: Comparison of the Nesch Mintech Lab and SGS.

 

  Nesch Mintech Aug/t SGS Au g/t  
No of samples 200   200  
Minimum 0.005   0.005  
Lower quartile 0.31   0.09  
Median 0.86   0.61  
Mean 1.65   1.42  
Upper quartile 1.72   1.54  
Maximum 29.43   27.80  
Coefficient of Variation 2.06   2.23  
Standard Deviation 3.40   3.17  
Variance 11.57   10.03  

 
 (VIRIMAI PROJECTS LOGO)Page 81
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Scatter plots of the primary versus umpire re-assay (Figure 11.14) demonstrate a restricted dispersion with the majority of data plotting within or close to the +/- 10% limits. Linear correlation of primary Nesch lab assays against SGS lab assays is at 96.7%, which is very good correlation. However a close look at the scatter plot, a tendency for the primary assay to be overstated relative to the umpire is common. Quintile - Quintile plots (Figure below) supplement the scatter plots and demonstrate consistent bias toward Nesch laboratory assay results. Grade range between 0 to 1.2 g/t Au is outside 10% correlation window and biased toward the primary laboratory. The bias trend remains in higher grades but within or close to 10% correlation margins refer to Figure 11.14.

 

(Figure 11.14)

 

Figure 11.14: Scatter plot and QQ plot for umpire samples

 
 (VIRIMAI PROJECTS LOGO)Page 82
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

12DATA VERIFICATION

 

This section of the report outlines the checks carried out during the campaign on the quality of the data collected during the period to see if it meets with industry practise and supports the estimation of the resources. Data verification relates to work undertaken by Virimai Projects whose technical team conducted several visits to the mine site in 2019 and in 2020. This section of the report summarizes the verification and validation of the results of the 2019 exploration campaign carried out by people from Virimai Projects on the Buckreef.

 

12.1Drill Data Review

 

The Historical data for the Buckreef Gold Project was provided to Virimai Projects in 2018 during the compilation of the Amended NATIONAL INSTRUMENT 43-101 Independent Technical Report Mineral Reserves Estimate and Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” completed under NI 43-101 standards and filed on the System for Electronic Document Analysis and Retrieval, “SEDAR”, (www.sedar.com).

 

The drill hole database and resource models were supplied as Datamine Studio 3 files with the drill hole files consisting of collar, down-hole survey and interval tables. The resource models were as 3D Datamine Studio 3 wireframe files encompassing discrete mineral zones identified by a zone number in the file name. Block models of the grade estimates were also supplied for these zones.

 

Surface Digital Terrain Models (DTMs) were supplied for each area and this also included the DTMs at (1) the interface of the oxide and intermediate material and (2) the interface of the intermediate and fresh material.

 

Virimai Projects’ team then reviewed the data and models to verify the findings as previously reported and published by Venymn Independent Projects. Messrs Wenceslaus Kutekwatekwa, Wonder Mutematsaka and Arimon Ngilazi then visited the site from the 17th to the 19th April 2018 in the company of Mr. Peter T. Zizhou.

 

12.2Collar Location Checks

 

Mr Kutekwatekwa and a team from Virimai Projects carried out field checks of pre-selected borehole collars on the Buckreef, Eastern Porphyry and Tembo anomalies from the 18th to the 19th of April 2018. The recorded co-ordinates of 20 collars were entered into a hand-held GPS and used to track to the positions in the field. Some of the collars at Buckreef anomaly have since been destroyed during pre-stripping but even so, some evidence was available through residual cement works. Using this method collar location for the surface diamond drill holes are considered to be reliable.

 
 (VIRIMAI PROJECTS LOGO)Page 83
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 12.1)

Figure 12.1: Virimai Projects Team on Site

 

12.3Drill hole and Assays Checks

 

Virimai Projects randomly selected several diamond and RC drill holes, and deliberately selected portions of holes with intersections of mineralization were selected by the Virimai Project team and the Buckreef project personnel and availed the core trays and pulp for inspection and verification logging in the core-shed.

 

12.4Geology Checks

 

Several randomly chosen manual log-sheets for drill-core availed at site were first manually logged to acquaint the Virimai Projects team with the geological units as described in the log-sheets. A comparison with the lithology database then revealed congruency as previously established by Venymn Deloitte. The diamond core drill-hole lengths and lithologic coding for the core drill-holes is thus considered to be reliable.

 

12.5Core Assay Checks

 

During the 18th to May 19th 2018 site visit, Mr Kutekwatekwa and Mr Ngilazi of Virimai Projects carried out geology and assay checks as a single exercise. Pre-selected holes were laid out by Buckreef staff for verification logging to validate geology, depth of intersections and mineralisation. Comparison was made with the database entries and Mr Kutekwatekwa and Ngilazi found the geological and assay data to be representative of the observed geology and mineralisation.

 

No assay check samples were collected for this report. Mr Kutekwatekwa and Mr Ngilazi conducted verification of the randomly chosen drill holes to check assay entries against the assay certificates. The assay certificates were obtained in both digital and manual formats directly from the assay laboratories. Mr Ngilazi’s finding was that the assay database was considered to be reliable.

 
 (VIRIMAI PROJECTS LOGO)Page 84
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

On the basis of the verified collar, geology and assay data, Mr Kutekwatekwa deems the data fit for use in resource modelling, grade estimation and subsequent business use.

 

(Figure 12.2)

 

Figure 12.2: Virimai Team Checking on the Drilling on Site

 

From the recommendations of Messrs Kutekwatekwa and Ngilazi, TRX employed a full-time resource geologist and Database and GIS officer to help manage the 2019 exploration programme. The Database and GIS officer is responsible for receiving logging and lab results sheets for entry into the digital data base. The data officer is the only person with authority of importing assay results into the database. On receipt of each batch of results of assays for the exploration drilling the QA/QC samples are checked to accept or reject the batch. If there is a problem the senior Geologist is notified and he requests the lab to identify and solve the problem if possible or carry out reanalysis. If re-assaying is required then the whole batch or sample tray between the good QC samples is re-assayed. Excel spread sheets and graphs are used to check QC results and update this batch so that the whole program is monitored progressively.

 

12.6Verifications by QPs

 

Mr Kutekwatekwa has been working with TRX geological team since 2018 initially for the Prefeasibility Study and were further appointed to management the 2019 drilling program by TRX. Since then weekly meetings on skype have been held between the staff of TRX and Virimai Projects to assess on progress and monitor adherence to set protocols during drilling, assaying and analysis of the results. A number of visits to the mine site were carried out by a team of Virimai Projects, in order to independently verify the information incorporated in the latest drill program were in adherence to the set protocols. In accordance with NI 43 101 guidelines Mr Kutekwatekwa most recent visit to the mine site was a weeklong from the 19th to 22nd February 2020. The primary aim of the visits was to witness the extent of the exploration work completed to date, inspect drill core, inspect core logging and sample storage facilities, review data in the database, hold discussions with geologists on the project

 
 (VIRIMAI PROJECTS LOGO)Page 85
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

On the basis of the quality assurances procedures and the quality control put in place at Buckreef it is the opinion of QPs that the sampling preparation security and analytical procedures used by TRX are consistent with generally accepted industry best practise and are therefore adequate for use in mineral resource estimation and classification of Mineral Resources in accordance with generally accepted CIM standards.

 
 (VIRIMAI PROJECTS LOGO)Page 86
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

13MINERAL PROCESSING AND METALLURGICAL TESTING

 

13.1Introduction

 

No new detailed Metallurgical test work has been completed as part of this current update study. Virimai Projects assumptions on economic recoveries are based on the several previous test work carried out and reported in previous filling.

 

The following section summarizes the results of the historical metallurgical test work completed between 2001 and 2017 which were reported in the published reports.

 

Chemical analysis, mineralogy, comminution, gravity separation and cyanidation tests have been completed that support the process design criteria for the proposed metallurgical operations. The results of these tests are summarised in this section.

 

13.2Previous test work

 

The following reports of work on the Buckreef deposits have been issued and reviewed:

 

Metallurgical Testwork on Buckreef Samples – Geita Gold Mining Ltd, 15th September 2001;
Scoping and Diagnostic Testwork on Tanzania Samples for Gallery Gold Ltd – IML (Pty) Ltd, September 2003;
Phase 2 Metallurgical Testwork Summary – IAMGOLD, MPC Project 6011, February 2007
Metallurgical Test Programme: IAMGOLD, SGS Southdale, 9 March 2009
Heap leach Amenability Test work - SGS Southdale Metmin Report No 13/527, 16 April 2014

 

The relevant sections of each of these reports is summarised in order in the sections that follow.

 

13.3Metallurgical Testwork on Buckreef Samples – Geita Gold Mining Ltd

 

Three samples from three drill holes were prepared. For each drill, a composite sample was prepared from 53 sub-samples taken at one-metre intervals along the drill core. The results for these three holes is summarised in Table 13.1.

 

Table 13.1. Key results from Gieta Gold test work.

 

Sample
  Units BMRCD 185 BMRCD 191 BMRCD 204
Head grade g/t 11.7 4.9 2.7
Recovery (direct cyanidation) % 84 86 77
Recovery (CIL) % 91 91 77
Cyanide consumption kg/t 1.0 0.72 1.09
Lime consumption kg/t 1.17 0.50 0.87

 

Key observations from this work were the following:

 

the gold is leached rapidly, with 80% dissolved within the first two hours;
the gold is liberated with grinding,
diagnostic leaching and analysis indicated that the residual gold is refractory, associated with pyrite.
Arsenic is present at about 22 g/t.

 
 (VIRIMAI PROJECTS LOGO)Page 87
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

13.4Scoping and diagnostic test work – Gallery Gold

 

Leaching tests, diagnostic leaching tests, and mineralogy were conducted by Independent Metallurgical Laboratory (IML), based in Perth, Australia. The leaching results are summarised in the Table 13.2.

 

Table 13.2. Key results from Gallery Gold test work.

 

Sample
  Units BMDD023 BMDD222
Head grade g/t 3.16 6.05
Recovery (direct cyanidation) % 71.6 87.0
Cyanide consumption kg/t 0.83 0.58
Lime consumption kg/t 1.31 1.47

 

13.5Phase 2 Metallurgical test work – IAMGOLD

 

IML performed further test work for IAMGOLD, with MPC acting as consultants. The results of this test work that are relevant to the current project plan are discussed in the sections that follow.

 

i.Grinding test work

 

The bond rod mill and ball mill work indices (BRWI and BBWI, respectively) are given in Table 13.3.

 

Table 13.3. Milling characteristics.

 

Item Unit Oxide     Primary  
    Buckreef
Main Clay
Buckreef
Main Rock
Buckreef
Main 92
Buckreef
Main
Buckreef
North
BRWI kWh/t 10.6 11.4 19.5 21.2 24.3
BBWI kWh/t 9.9 12.9 22.3 17.5 17.2
Ai   0.014 0.154 0.586 0.424 0.042
Classification   Soft Soft to moderate Hard Moderately hard Moderately hard

 

ii.Process selection test work

 

Process selection test work was undertaken to determine the relative advantages of whole ore leaching, gravity/leaching or gravity/flotation/fine grinding/leaching.

 

The results of this test work suggested that a gravity/leaching circuit was best suited to this orebody. The comparison of the different options is shown in Table 13.4. The test work indicated that in order to get high recoveries of gold, the flotation tailings must be leached. The consumptions of cyanide and lime were significantly higher in the flotation/fine grinding option.

 
 (VIRIMAI PROJECTS LOGO)Page 88
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 13.4. Recoveries for different processing options.

 

Recovery from Process Unit Buckreef Main
Oxide
Buckreef North
Primary
Buckreef Main
Primary
Whole Ore Leaching % 92.7 88.6 85.3
Gravity/Leaching % 95.5 92.9 92.4
Gravity/Flotation/Leaching %   81.3 80.2
Gravity/Flotation/Tailings leaching %   92.1 94.5

 

The report recommended that the recoveries for the gravity and leaching sections that should be used in the project evaluation are those shown in Table 13.5.

 

Table 13.5. Recommended recovery assumptions for project evaluation.

 

Item Unit Buckreef Main
Oxide
Buckreef North
Primary
Buckreef Main
Primary
Gravity recovery % 30 37 41
Leaching recovery % 65 55 51
Total recovery % 95 92 92

 

13.6Heap leaching test work

 

The process selection test work conducted summarised in Table 13.4 did not consider heap leaching as a possible option. Consequently, SGS was contracted to performed these tests. The first set of tests were “simulated heap tests’ using a bottle roll technique, and the second set were column tests at various column heights. These tests are discussed in the following sections.

 

i.Simulated heap tests – SGS 2009

 

Simulated heap leaching tests were conducted using a bottle roll technique. The 7-day simulated heap leaching tests indicated that the extractions varied between 50.2% and 88.9%. The cyanide consumptions varied between 1.08 kg/t and 3.11 kg/t.

 

ii.Heap leaching amenability test work – SGS 2016

 

The recommended height of the heap was determined by pressure percolation tests. The results indicated that the heights are 4.0, 8.2 and 16.5 m for the oxide, transition and primary orebodies, respectively.

 

Column tests conducted using 4.0 m columns yields leaching extractions of 67.7%, 51.0% and 52.4% for the oxide, transition and primary orebodies, respectively.

 

iii.Conclusions concerning heap leaching

 

The heap leaching results were not sufficiently promising compared with those achieved using a gravity recovery and leaching process to justify this process option.

 
 (VIRIMAI PROJECTS LOGO)Page 89
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

13.7Conclusions from the test work initiated prior to this study

 

The process selection test work indicated that the optimal process is a combination of gravity concentration with leaching of the gravity tails. This is the process route that has been proposed in the current study.

 

13.8Documentation

 

Apart from the historical test work that has been summarized in the previous section, test work has been undertaken to specifically support the metallurgical design of the plant for the project. This section is a summary of that supporting documentation. The relevant documents are the following:

 

(i)REPORT NO 15/059 r1, prepared by Juan van der Merwe of MMSA, dated 11 January 2016; and,
(ii)Project 6011, prepared by Peter Banovich of Metallurgical Project Consultants Pty Ltd, dated February 2011.

 

These documents are attached as Appendix 13.1 and 13.2, respectively, to this chapter.

 

13.9Metallurgical test work.

 

i.Purpose of the test work

 

The process selection work conducted by MPC on behalf of IAMGOLD (attached as Appendix 13.2 to this chapter) indicated that the optimal process for this material is a gravity circuit followed by leaching of the gravity tails. The test work conducted in this study is aimed to specifically provide confirmatory information for design purposes. As a result, the test work does not simulate the process, because that was done and reported in Appendix 13.2. Instead, the test work was intended to determine the design parameters, which are discussed in the sections that follow.

 

ii.Sample origin

 

A sample of 3.9 t of material was shipped to Emisha Mining Innovations. This sample consisted of the following two bulk samples:

 

(i)a composite sample of 2 t of material from Buckreef South and Buckreef Main oxide/transition ore, and
(ii)a composite sample of 1.9 t of material from Buckreef Main sulphide ore.

 
 (VIRIMAI PROJECTS LOGO)Page 90
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

These samples are referred to here as “oxide” and “sulphide”, respectively. The oxide ore is more weathered, as can be seen in Figure 13.1, while the sulphide ore is more competent, as can be seen in Figure 13.2.

 

(Figure 13.1)

 

Figure 13.1: Oxide ore before milling and after a single pass of milling in the multi-shaft EDS mill.

 

(Source: Emisha Mining Innovations)

 

(Figure 13.2)

 

Figure 13.2: Sulphide ore before milling and after a single pass of milling in the multi-shaft EDS mill.

 

(Source: Emisha Mining Innovations)

 

13.10Grade and deportment

 

i.Head grade

 

The head grade of the oxide and sulphide ores is given in Table 13.6. The oxide ore is lower in grade than the sulphide ore, and possibly displays greater variability.

 

Table 13.6. Head analysis for gold

 

(Source: MMSA Report No 15/059 r1)

 

Gold analysis, g/t      
Sample Replicate 1 Replicate 2 Replicate 3 Average
Oxide ore 1.76 2.12 1.91 1.93
Sulphide ore 4.73 4.51 4.55 4.60

 
 (VIRIMAI PROJECTS LOGO)Page 91
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

ii.Gold deportment in the milled material

 

The deportment of gold by size fraction in the milled product was determined. The results of this analysis are shown in Figures 13.3 and 13.4 for the oxide and sulphide ores, respectively.

 

The results for the oxide ore indicate that the grade of gold is slightly lower in the fine fractions. Because of the large mass of fine material in the oxide ore, this fraction accounts for most of the gold. These results indicate that there is no justification for discarding a particular size fraction.

 

The results for the sulphide ore indicate that the grade of gold is relatively evenly distributed with size fraction. A similar conclusion to that reached for the oxide ore is applicable, that is, that these results indicate that there is no justification for discarding a particular size fraction.

 

(Figure 13.3)

 

Figure 13.3: Gold grade and deportment by size fraction for the oxide ore, indicating that the gold deportment is higher in the fine fraction, bearing in mind that there is a high fines content of this ore.

 

(Source: MMSA Report No 15/059 r1)

 
 (VIRIMAI PROJECTS LOGO)Page 92
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 13.4)

 

Figure 13.4. Gold grade and deportment by size fraction for the sulphide ore, indicating that the gold is not concentrated in any one size fraction.

 

(Source: MMSA Report No 15/059 r1)

 

13.11Milling

 

i.Bond milling index

 

The bond mill indices for the different ore type is given in Table 13.7. The oxide ore is soft, while the sulphide ore is moderately hard.

 

Table 13.7 Bond mill indices for oxide and sulphide ore materials.

 

(Source: Phase 2 Metallurgical Test work Summary Project 6011)

 

Domain Description BRWI
kWh/t
BBWI
kWh/t
AI Classification
Oxide
  Buckreef Main Clay 10.6 9.9 0.014 Soft
  Buckreef Main Rock 11.4 12.9 0.154 Medium
  Buckreef Main 92 19.5 22.3 0.586 Hard
  Busolwa Oxide 9.1 8.9 0.052 Soft
  Busolwa Quartz 12.8 19.0 0.335 Soft
  Buziba Oxide 11.1 9.2 0.103 Soft
Sulphide
  Buckreef Main 21.2 17.5 0.424 Moderately hard
  Buckreef North 24.3 17.2 0.042 Moderately hard
  Busolwa 19.1 15.1 0.131 Moderately hard
  Buziba 23.2 17.6 0.339 Moderately hard

 
 (VIRIMAI PROJECTS LOGO)Page 93
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

ii.Pilot milling

 

Both the oxide and sulphide bulk samples were milled in a demonstration-scale multi-shaft EDS mill. This is a unique mill, which is designed to maximize the number of particle-particle impact events to achieve milling. The mill does not require media (balls, rods or ceramics). As a consequence, the weight of mill and the associated infrastructure requirements are substantially reduced. The principle of the EDS multi-shaft mill is shown in Figure 13.5.

 

(Figure 13.5)

 

Figure 13.5. Principle of the EDS multi-shaft mill.

 

The material before and after the milling is shown in Figures 13.1 and 13.2 for the oxide and sulphide ores, respectively. These photographs indicate the effectiveness of a single pass through the EDS multi-shaft mill.

 

The particle-size distribution for the oxide material after a single milling stage is given in Figure 13.6, and that for the sulphide material is shown in Figure 13.7. These results indicate that the oxide material has a d50 of less than 25 µm, while that of the sulphide ore is about 250 µm. This is a direct consequence of the differences in the intrinsic hardness and the feed distribution of the two materials.

 
 (VIRIMAI PROJECTS LOGO)Page 94
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 13.6)

 

Figure 13.6. Particle-size distribution of the milled (product) oxide ore. (Source: MMSA Report No 15/059 r1)

 

(Figure 13.7)

 

Figure 13.7. Particle-size distribution of the milled (product) sulphide ore. (Source: MMSA Report No 15/059 r1)

 
 (VIRIMAI PROJECTS LOGO)Page 95
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

13.12Gravity concentration

 

Gravity concentration test work was undertaken using a laboratory-scale Falcon L40 concentrator. These tests were conducted as sequential separations with inter-stage grinding. The grinding stages were as received, 50% less than 75 µm and 70% less than 75 µm.

 

The results of these tests are shown in Figures 13.8 and 13.9 for the oxide ore and the sulphide ore, respectively.

 

The gravity concentration tests for the oxide ore indicates that more than 50% of the gold can be concentrated in about 4% of the mass with a grade of about 25 g/t.

 

The gravity concentration tests for the sulphide ore indicates that about 20% of the gold can be concentrated in about 4% of the mass with a grade of about 25 g/t.

 

(Figure 13.8)

 

Figure 13.8. Grade and recovery curves against mass pull for the oxide ore using the Falcon L40 concentrator.

 

(Source: MMSA Report No 15/059 r1)

 
 (VIRIMAI PROJECTS LOGO)Page 96
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 13.9)

 

Figure 13.9. Grade and recovery curves against mass pull for the sulphide ore using the Falcon L40 concentrator.

 

(Source: MMSA Report No 15/059 r1)

 

13.13Cyanidation

 

Samples of the as-received ores were ground to a p80 of 75 µm and tested with and without the addition of carbon. The results of these tests for the oxide ore and the sulphide ore are shown in Table 13.8. The other conditions of these cyanidation tests are as follows: pH 10.5; NaCN 5 kg/t; cyanidation time 48 hours. The cyanide and lime additions are excessive, and the expected cyanide and lime consumptions are closer to those determined in previous test work. See section 2 of this chapter.)

 

These results indicate that a leach efficiency of 93.8% can be achieved with the addition of carbon for the oxide ore, and 85.4% for the sulphide ore. These results suggest that a carbon-in-leach circuit will be beneficial in the processing of these ores.

 

Table 13.8. Cyanidation results for the oxide and sulphide ores.

 

(Source: MMSA Report No 15/059 r1)

 

Domain Carbon
addition,
g/L
NaCN
addition,
kg/t
CaO
addition,
kg/t
Leach
efficiency,
%
Oxide
  0 5 1.3 82.4
  20 5 1.3 93.8
Sulphide
  0 5 0.6 79.8
  20 5 0.6 85.4

 

The MMSA test work summarised in Table 13.8 did not establish the residual concentrations of cyanide and lime after leaching, which means that an accurate estimate of the cyanide and lime consumptions cannot be

 
 (VIRIMAI PROJECTS LOGO)Page 97
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

determined from this test work. Previous work has established the cyanide and lime consumption, and these results are summarised in Table 13.9.

 

Table 13.9. Cyanide and lime consumption summary.

 

(Source: MMSA Report No 15/059 r1)

 

Report
Name
Ore Type Source Milled Particle size (Microns) Lime Consumption (kg/t) NaCN Consu (kg/t) Recovery (%)
MPC Buckreef Main Gravity 80% - 106 3.84 1.14 *L=62.3
IAMGOLD oxide tailings       *G+L=96.9
Phase 2 Met
Testwork
Summary
Project 6011
Feb 2007
Buckreef North
Primary
Gravity
tailings
80% - 106 1.05 0.59 *L=56.7
*G+L=94.4
Buckreef Main
Primary
Gravity
tailings
80% - 106 0.36 0.36 *L=55.9
*G+L=93.9
Busolwa Main Gravity 80% - 106 3.05 1.58 *L=37.2
  Oxide tailings       *G+L=98.0
  Busolwa Main Gravity 80% - 75 0.78 0.55 *L=53.8
  Primary tailings       *G+L=98.9
  Buziba Oxide Gravity 80% - 106 3.19 1.07 *L=43.3
    tailings       *G+L=97.9
  Buziba Primary Gravity 80% - 75 0.74 0.34 *L=54.0
    tailings       *G+L=97.6
MMSA Sulphides Ore As Received 0.6 4.98 71.7
15/059r1 (48 hours)          
Report
Jan 2016
Oxides
(48 hours)
Ore As Received 1.3 4.98 62.7
  Sulphides Ore 80% - 75 0.6 *5 79.8
  No Carbon          
  Sulphides with Ore 80% - 75 0.6 *5 85.4
  Carbon          
  Oxides Ore 80% - 75 1.3 *5 82.4
  No Carbon          
  Oxides Ore 80% - 75 1.3 *5 93.8
  with Carbon          
  Sulphides Ore As Received 0.6 4.98 70.0
  (24 hours)          
  Oxides Ore As Received 1.3 4.98 61.1
  (24 hours)          
   

 

* L = Leaching

 

* G+L = Combined recovery for gravity concentration and cyanidation of gravity tailings

 

* 5 = Cyanide added at the beginning of the testwork and residual cyanide after the testwork was not provided

 

13.14Conclusions

 

Process selection: The test work conducted by MPC and SGS has shown that more than 90% of the gold can be recovered by a combination of gravity concentration and leaching of the tails. The MMSA test work established that 93% of the gold from the oxide ore can be recovered without gravity concentration by carbon-in-pulp leaching. The work established that 85% of the gold from the sulphide can be recovered in a similar manner.

 

Gold deportment: There does not appear to be a concentration of gold with size fraction.

 
 (VIRIMAI PROJECTS LOGO)Page 98
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Gold head grade: The gold head grade for the metallurgical tests varied between 1.5 and 6 g/t Au. For the bulk samples supplied that were milled using the EDS mill, the oxide head grade was about 1.9 g/t and the sulphide head grade was 4.6 g/t.

 

Milling: The bond mill index for the oxide ore is in the range of 9-12 kWh/t, while that for the sulphide ore is in the range of 19 to 24 kWh/t.

 

Gravity concentration: The gravity concentration test work confirmed that 50% of the gold can be recovered from the oxide ore, and 20% of the gold from the sulphide ore. The mass pulls in both cases is about 4%.

 

Leaching: The cyanidation test work confirmed that the gold recovery in the presence of activated carbon for the oxide ore was about 93% and for the sulphide ore was about 85%, without gravity concentration at a grind size of 80% less than 75 µm. The expected cyanide consumption is 1.1 kg/t, and the expected lime consumption is 1.5 kg/t.

 

13.15Recommendations

 

The test work has established the basic process parameters. There is no data on settling and thickening test work, and no data on the tailings storage facility. These aspects should be addressed.

 

It is recommended that the following test work is conducted:

 

A process simulation run of the EDS mill in recirculation mode using a screen size of 100 micron, followed by bulk gravity concentration and bulk leaching of the tailings;
Site water characterization;
Settling and thickening test work;
Tailings characterization;
Variability test work.

 

13.16Concluding Remarks

 

In April 2020 TRX commissioned SGS Canada Inc of Lakefield Ontario to carry out further metallurgical test work on the fresh rock ores to confirm the prefeasibility flow sheet that includes either Gravity Separation with Gravity Tailing Cyanidation, or Gravity Separation, followed by sulphide Flotation of the gravity tailing, with regrinding and cyanide leaching of reground sulphide concentrate along with possible leaching of flotation tailing. These flow sheets constitute low cost and attractive alternatives for the Buckreef Project. The current round of testing is expected to take approximately five to six months, following which some additional sampling and variability testing may be required that would arise from the design of a new open pit which will be initiated shortly. This large plant will be the basis for the Company’s Final Feasibility NI 43-101 Report.

 
 (VIRIMAI PROJECTS LOGO)Page 99
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

14MINERAL RESOURCE ESTIMATE

 

14.1Introduction

 

CIM’s Definition Standards for Mineral Resources and Mineral Reserves (May 2014) defines a mineral resource as a “concentration or occurrence of solid material of economic interest in or on the Earth’s crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge.”

 

Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no guarantee that all or any part of the Mineral Resource will be converted into Mineral Reserve. Confidence in the estimate of Inferred Mineral Resources is insufficient to allow the meaningful application of technical and economic parameters or to enable an evaluation of economic viability worthy of public disclosure.

 

The Buckreef Main Mineral Resource estimates reported in this section were carried out by Virimai Projects. The other three areas, namely Eastern Porphyry, Tembo and Bingwa, were adopted as reported in the 2018 NI- 43-101 update report and are presented in this report without amendment. The Buckreef Main resources estimates are an update necessitated by the infill and extension drilling done in 2018 and 2019 with Virimai Projects providing technical support including the location of the new drill holes.

 

14.2Mineral Resource Modelling

 

The Buckreef Main comprises several mineralised bodies within a broad shear zone. Each one of these bodies was delineated along cross sections and wireframed. The construction of resource envelopes along sections nominally 25 m apart was done using a “natural” cut-off due to the hard boundary between potentially economic mineralisation and waste. This natural sample cut-off is variable but the lower limit is approximately 0.40 g/t in the oxides and 0.6 g/t in the sulphides with lower external grades being accepted where geological continuity warranted it. Internal waste within the resource envelopes was accepted without further definition. This is tighter than the 0.34 g/t reserve block cut off for oxides and transitional material and 0.37 g/t block cut off for fresh rock obtained from open pit optimisation obtained using the following parameters:

 

(a)Long Term Gold price: USD $1,300 per troy ounce.
(b)Nominal metallurgical recoveries 92.3% Oxides and fresh 85% using conventional gravity and cynidation process.
(c)Mining costs for oxides $1.88/t
(d)Mining costs for fresh rock $2.78/t
(e)Processing costs $10.90/t
(f)Administrative and General Costs -$1.98/t

 

The future prospects indicate at least higher prices (besides higher efficiencies and economies of scale or lower costs) and therefore the resource cut off should be lower than 0.34 g/t. However, the natural hard boundary cut- off keeps the economically mineralised zone largely unchanged except to merge some discontinuous zones. At

 
 (VIRIMAI PROJECTS LOGO)Page 100
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

the grade control stage it is possible to realise extra ore from low grade pods that may have been excluded from the resource models for lack of defined shape and spatial continuity.

 

Illustrations of the hard boundaries from Buckreef are shown in Figure 14.1 the nominal surface elevation is 1225 m.a.s.l and the sections should give an indicative view of intersections depth below surface. As can be seen from these figures, the resource boundaries are self-defining in the sense that the boundary between potentially economic and uneconomic mineralisation (generally background value or below laboratory detection limit) is quite distinct.

 
 (VIRIMAI PROJECTS LOGO)Page 101
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 14.1)

 

Figure 14.1: Hard boundary illustrations

 

The sections were the linked to form wireframes for each mineralised body.

 
 (VIRIMAI PROJECTS LOGO)Page 102
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 14.2)

 

Figure 14.2: Plan View of the Buckreef Main Zone mineralised bodies

 
 (VIRIMAI PROJECTS LOGO)Page 103
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

14.2.1Sample Distribution and Statistics

 

This section presents the sample statistics within each mineralised body as wireframed. There are eighteen zones of which the Main Zone and South Pit areas form the core around which there are several narrow parallel including a SSW-trending splay. After selection within the wireframes, the samples were composited to 1m to cater for narrow zones which may be as narrows as 2 m to 3 m. The limit to two metres was taken considering that an initial open pit is considered before underground mining where as narrow as 1.5 m reef widths can be mined.

 

Table 14.1: Statistics of 1m samples and composites within the resource wireframes

 

Area Sub-domain Records Missing
Values
Samples Min
Au(g/t)
Max
Au(g/t)
Mean Au
(g/t)
Std.
Deviation
Standard
Error
Skewness Geomtric
Mean Au
(g/t)
Log
Estimate
of the
Mean
Main Zone Extension 3636 157 3479 0.01 207.50 2.16 4.88 0.08 25.69 0.98 2.78
Central 5001 319 4682 0.01 77.50 2.74 5.49 0.08 6.03 0.94 3.66
South 67 0 67 0.06 6.08 1.28 1.19 0.14 1.86 0.87 1.35
Main Zone
Extension
Parallels
Footwall 1 725 146 579 0.01 41.57 0.52 1.93 0.08 17.37 0.12 0.64
Footwall 2 541 209 332 0.01 4.95 0.25 0.57 0.03 4.51 0.05 0.28
Footwall 3 1329 565 764 0.01 49.50 0.56 2.30 0.08 15.07 0.08 0.64
Hangingwall 1 429 100 329 0.01 10.80 0.80 1.50 0.08 3.18 0.13 1.22
Hangingwall 2 294 115 179 0.01 8.48 0.41 1.14 0.09 5.01 0.06 0.40
Hangingwall 3 210 60 150 0.01 4.06 0.36 0.68 0.06 2.96 0.08 0.47
Main Zone
Central and
South
Parallels
Footwall 1 980 299 681 0.01 57.80 0.98 3.59 0.14 11.47 0.22 1.06
Footwall 2 745 227 518 0.01 111.21 1.01 5.35 0.24 17.40 0.12 1.11
Footwall 3 691 189 502 0.01 416.50 1.64 18.65 0.83 21.97 0.16 1.12
Hangingwall 1 1882 852 1030 0.01 9.58 0.58 0.90 0.03 3.79 0.16 1.02
Hangingwall 2 415 149 266 0.01 10.22 0.87 1.54 0.10 3.05 0.15 1.71
Hangingwall 3 323 192 131 0.01 3.76 0.30 0.59 0.05 3.10 0.05 0.32
Hangingwall 4 225 129 96 0.01 7.68 0.68 1.39 0.14 2.62 0.06 1.02
Hangingwall 5 94 25 69 0.01 2.79 0.29 0.47 0.06 2.78 0.07 0.34
South Pit All 456 7 449 0.01 58.40 1.72 3.59 0.17 9.71 0.71 2.18
West Splays All 690 161 529 0.01 43.05 1.05 3.48 0.15 7.27 0.12 0.92

 

Compared to the mean and log estimate of the mean, the lower geometric mean indicates the disproportionate effect of the relatively few extreme high grades, but the closer the classical mean is to the log estimate indicates the robustness of the mean. Very high grades area evident for the Main Zone Extension (207.50 g/t) Main Zone Central and South Parallels Footwall 2 (111.21 g/t) and Footwall 3 (416.50 g/t). An analysis of the sample grade was done to determine whether these are outliers.

 

14.2.1Outlier Analysis

 

Outlier analysis of the Buckreef grades was done by comparing the difference between ranked samples starting with the highest grades. The expectation is that there would be a significant jump in difference between non- outlier grades and potential outliers. The magnitude of the jump relative to the whole data set is important. In this case, a difference of less than 30% was not considered significant. The result of this exercise is shown in Figure 14.3. The results shows successive differences are less than 15% up to 77.5 g/t after which there is a 35.38% jump to 105 g/t. This put the cap at 100 g/t for non-outlier grades (calculated 30% jump from 77.7g/t is 100.75 g/t). Note that these are potential outliers until their spatial positions are verified. If a resource boundary can be delineated around the samples then these are not outliers and should be treated as a separate domain. However if they are found at random among much lower-grade samples then they qualify as true outliers.

 
 (VIRIMAI PROJECTS LOGO)Page 104
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 14.3)

 

Figure 14.3: Plan View of the Buckreef Main Zone mineralised bodies

 

All the four grades above 100 g/t are located in Main Zone and Main Zone Extension where high grades are predominant. Two of them (105 g/t and 207.5 g/t) are in the Main Zone Extension within the same 27 m down- the-hole intersection 80 m below surface and contiguous to grades in the 20 g/t to 70 g/t Au range. The 111.206 g/t composite is in the footwall of the Main Zone Extension in a narrow 3 m zone, about 155 m below surface. The highest grade of 416.5 g/t is contiguous to an 18.2 g/t sample approximately 16 m below surface within a 4 m wide supergene-enriched zone in the footwall of the Main Zone Extension. These samples are all in settings which are expected for such high grades and are not outliers.

 

14.3Mineral Resource Estimation Models

 

The Mineral Resource estimate was informed by both the diamond drilling and reverse circulation drilling results using only one-metre samples and composites confined within the Mineral Resource wireframes constructed by Mr Ngilazi of Virimai Projects in Datamine™ Studio 3 (version 3.21.7164). Experimental semi-variograms were calculated and model semi-variograms fitted for each zone.

 
 (VIRIMAI PROJECTS LOGO)Page 105
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 14.4)

 

Figure 14.4: Variogram Model

 

For the hard boundary grade estimation, Virimai Projects applied the Ordinary Kriging (OK) method in Datamine™ Studio 3 (version 3.21.7164).

 

Table 14.2 Buckreef Summary Semi-Variogram Parameters

 

  Nugget
Co
Range 1 Spatial
Variance
C1
Range 2 Spatial
Variance
C2
Total
X1 Y1 Z2 X2 Y2 Z2
Main 0.368 22 15 15 0.479 70 25 70 0.153 1.0
South 0.350 28 14 22 0.481 65 20 75 0.169 1.0
Parallels 0.368 22 15 15 0.479 70 25 70 0.153 1.0

 

The search parameters used in conjunction with these semi-variogram models are in Table 14.3.

 
 (VIRIMAI PROJECTS LOGO)Page 106
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 14.3: Summary of Buckreef search parameters

 

  Main South Parallels Splays
Search Rotation (X,Y,Z) (-65,5,0) (-65,5,0) (-65,5,0) (-30,5,0)
Search Ranges (X,Y Z) (75,25,70) (65,20,75 (75,25,70) (75,10,75
Samples Minimum 4 4 2 2
Maximum 30 30 10 20
Second search range multiplier 1.5 1.5 1.5 1.5
Third search range multiplier 3.0 3.0 4.0 3.0

 

Table 14.4 Buckreef Project Resource models, Geita District, Tanzania

 

Mineralisation Area Block Model Model Type Comment
1 Buckreef Main mod_br_upd2020 OrdinaryKriging Updated resource
2 Eastern Porphyry mod_ep_mixed OrdinaryKriging As per last update
3 Tembo mod_tb_mixed OrdinaryKriging As per last update
4 Bingwa mod_bw_supercap OrdinaryKriging As per last update

 

The block models reflect the general dimensions of the drilling grid that covers each prospect and consist of separate zones with fields for ordinary kriging grade estimate, number of samples used in the estimate, estimation variance, the check inverse distance grade estimate, oxidation code, density, search volume, domain numeric identifier, domain alphanumeric identifier, and classification.

 
 (VIRIMAI PROJECTS LOGO)Page 107
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

14.3.1Density

 

In keeping with the existing model, densities for this update report Virimai relied on bulk density measurements made during prior 2014 by Venmyn. The bulk densities were determined by “weight in air versus weight in water” determinations for 2,209 samples. Detailed analysis of the bulk density is given in Venmyn ITR 2014 titled “Update National Instrument 43-101 Independent Technical Report on the Buckreef Project in Tanzania for Tanzanian Royalty Exploration Corporation”. The average densities used in this update mineral resource estimates are summarised in Table 14.5.

 

Table 14.5 Buckreef Project Updated Resource Model Density

 

Mineralisation Area Density (t/m3)
1 Oxide 2.2
2 Transition 2.5
3 Sulphide/Fresh Rock 2.8

 

14.4Mineral Resource Estimation Checks

 

For historical estimates, Mr Ngilazi carried out inverse distance squared estimate out as a high-level check of the global and local (block by block) of the Venmyn Deloitte ordinary kriging estimates. The comparison is shown in Figure 14.5. Although the estimates are spread around the line of equality, the high-level check validates the robustness of the Venmyn Deloitte estimates.

 

Virimai Projects also validated the block models using swath analysis where the average of length weighted sample grades within a 100 m wide corridor for Buckreef and 50 m for the other prospects were compared to block model grades within the same swathe. This was done in order to verify that the block models correctly reflected the average of the sample grades within the same swath (Figure 14.6). The results generally show the same trend as the sample grades and the expected smoothening effect of the ordinary kriging process with very high/low sample grades being moderated by the low/high sample grades in the neighbourhood.

 

The inverse distance squared method as a check method and swath analysis for comparison between block grades and samples were also used for the Buckreef upgrade.

 

(Figure 14.5)

 
 (VIRIMAI PROJECTS LOGO)Page 108
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 14.5)
Figure 14.5: Virimai Projects block grade checks

 

(Figure 14.5)
Figure 14.6: Virimai Projects average sample grade compared to average estimated block grade checks

 
 (VIRIMAI PROJECTS LOGO)Page 109
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

It is pertinent to note that the Bingwa average grades drop below 0.50 g/t from the easting X+396200 (Figure 14.6). The model checks showed that in the north-eastern half of the strike, continuity is poor and resource grades only start at about 40 m below surface.

 

14.5Mineral Resource Classification and Reporting

 

Virimai Projects considers that blocks estimated during the first estimation run considering full variogram ranges can be classified in the Measured category and the second estimation run (at one and half times the search volume) can be classified in the Indicated category. For these blocks, Virimai Projects considers that the level of confidence is sufficient to allow appropriate application of technical and economic parameters to support mine planning and to allow evaluation of the economic viability of the deposit. Blocks estimated during the third pass considering search neighbourhoods set at twice or more the variogram ranges should be appropriately classified in the Inferred category because the confidence in the estimate is insufficient to allow for the meaningful application of technical and economic parameters or to enable an evaluation of economic viability.

 

Based on the knowledge that due to nugget effect, kriging variance does not necessarily get lower nor does the regression slope get better as the grid tightens Virimai found it appropriate to use an additional filter for classification as shown in Table 14.6.

 

Table 14.6 Buckreef Project Resource models, Geita District, Tanzania

 

Search Volume Nominal Grid Regression Slope Class
1 25-30 m by 25-30 m 0.7+ Measured
2 >30 m by 50-75m 0.5 - 0.7 Indicated
3 >75 m-100m <0.5 Inferred

 

Application of the further filters resulted in the downgrading from the Measured category to the Indicated category of approximately 30% of the tonnage classified as Measured using search volume only.

 
 (VIRIMAI PROJECTS LOGO)Page 110
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 14.7: Buckreef Shear Zone March 2020 Mineral Resource Updated Estimates at 0.4g/t Block Cut off

 

  Measured Indicated Inferred
Resource Sub Zone Tonnes Grade Au(g/t) Ounces Tonnes Grade Au(g/t) Ounces Tonnes Grade Au(g/t) Ounces
Main Zone Extension 8,388,927 2.23 601,323 1,625,876 2.07 108,388 1,121,343 1.90 68,449
Central 6,722,737 2.30 498,003 1,462,286 3.35 157,552 849,220 3.41 93,217
South 392,033 1.36 17,080 163,260 1.61 8,437 156,280 1.63 8,176
Main Zone
Extension
Parallels
Footwall 1 736,723 0.89 21,055 110,263 0.86 3,065 89,449 0.67 1,937
Footwall 2 0 0.00 0 482,810 0.99 15,399 161,974 0.55 2,871
Footwall 3 0 0.00 0 1,939,691 0.86 53,369 2,664,877 0.60 51,382
Hangingwall 1 243,490 1.66 12,983 3,838 1.26 155 0 0.00 0
Hangingwall 2 0 0.00 0 421,517 1.09 14,721 196 1.40 9
Hangingwall 3 0 0.00 0 927,600 0.68 20,263 1,284,930 0.55 22,638
Main Zone
Central and
South
Parallels
Footwall 1 1,456,084 1.41 66,137 489,783 0.71 11,240 1,059,305 0.52 17,574
Footwall 2 0 0.00 0 1,605,278 1.52 78,457 2,685,932 1.13 97,867
Footwall 3 0 0.00 0 2,916,865 1.32 123,439 5,848,828 1.03 193,510
Hangingwall 1 1,622,131 0.88 45,673 339,079 0.89 9,676 336,033 0.84 9,110
Hangingwall 2 0 0.00 0 1,340,142 1.62 69,888 1,309,019 1.40 58,887
Hangingwall 3 0 0.00 0 254,733 0.72 5,927 4,882 0.57 90
Hangingwall 4 0 0.00 0 271,919 1.43 12,494 84 0.52 1
Hangingwall 5 0 0.00 0 171,657 0.67 3,702 2,279 0.84 61
South Pit All 421,866 1.39 18,906 94,054 0.92 2,786 0 0.00 0
West Splays All 0 0.00 0 1,273,935 1.37 56,161 247,407 1.23 9,764
Grand Total 19,983,991 1.99 1,281,161 15,894,585 1.48 755,119 17,822,036 1.11 635,541

 

The NI43-101 compliant Mineral Resource estimate as revised by Virimai Projects is shown Table 14.8. To reflect the uncertainty in the shape of mineralisation as wireframed, the summary total tonnage for the Buckreef Shear Zone been rounded off to the nearest 50 tonnes while the grades has been rounded off to two decimal places Contained gold has been rounded off to the nearest 10 ounces.

 

Table 14.8: Buckreef Project March 2020 Mineral Resource

 

Prospect Measured Indicated Inferred Total Measured + Indicated
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
(Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz)
Buckreef 19.98 1.99 1,281,160 15.89 1.48 755,120 17.82 1.11 635,540 35.88 1.77 2,036,280
Eastern Porphyry 0.09 1.20 3,366 1.02 1.17 38,339 1.24 1.39 55,380 1.10 1.18 41,705
Tembo 0.02 0.99 531 0.19 1.77 10,518 0.27 1.92 16,461 0.20 1.70 11,048
Bingwa 0.90 2.84 82,145 0.49 1.48 23,331 0.22 1.49 10,541 1.39 2.36 105,477
Total 20.99 2.03 1,367,202 17.59 1.46 827,308 19.55 1.14 717,922 38.57 1.77 2,194,510

 

# Buckreef has been updated and reported at 0.40 g/t Au block cut-off

# Eastern Porphyry, Bingwa and Tembo Mineral Resources are quoted at 0.50 g/t Au block cut-off as per last update

 
 (VIRIMAI PROJECTS LOGO)Page 111
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 14.9 Shows the reconciliation between this update and the last report in 2018.

 

Table 14.9: Buckreef Project 2020 vs 2018 reconciliation

 

Buckreef 2018 NI43-101 2020 NI43-101 Update 2020 Update - 2018 Report
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
Tonnes Grade In Situ
Content
(Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz) (Mt) Au
(g/t)
Au (Oz)
Measured 8.90 1.72 491,368 19.98 1.99 1,281,160 11.09 2.22 789,792
Indicated 13.09 1.41 594,097 15.89 1.48 755,120 2.80 1.79 161,023
Inferred 7.52 1.33 322,819 17.82 1.11 635,540 10.30 0.94 312,721
                   
Measured + Indicated 21.99 1.54 1,085,465 35.88 1.77 2,036,280 13.89 2.13 950,815
                   
Measured + Indicated + Inferred 29.52 1.48 1,408,284 53.70 1.55 2,671,820 24.19 1.62 1,263,536

 

The largest tonnage and grade increase has been in the Measured Resources mainly due to the down dip and extension drilling in the central and north extension of the Main Zone where grades are high. The down dip limits which used to be to 650 m.a.s.l is now 400 m.a.s.l or about 100 m from the deepest intersection which contributes to most of the Inferred. The 2018 model assumed that mineralised was narrowing down to 650 m.a.s.l but the latest drilling incorporated in this report indicates that the mineralisation is still open ended. In addition, several parallel narrow reefs have been incorporated with lower confidence levels.

 

14.6Exploration Targets

 

Besides the estimated resources tabulated herein, there are exploration targets within and extending beyond the delineated and estimated Mineral Resources. Exploration targets within the delineated and estimated Mineral Resources refer to gaps in grade estimation within the strike and depth extent of the delineated resources resulting in islands of blocks with no grade estimates. It also refers to interpreted fault zones that need to be explored further to firm up on the mineral resource losses that were accepted for the current estimate.

 

Significant potential lies within the Buckreef Shear Zone that is summarised in Table 14.10.

 

Table 14.10 Exploration targets at the Buckreef Shear Zone

 

Target Area Tonnage Range Grade Range Au (g/t) Ounces Range
Minimum Maximum Minimum Maximum Minimum Maximum
Northeast Extension 4,000,000 6,000,000 1.40 2.50 180,000 482,300
Main Zone 25,000,000 35,000,000 1.30 1.50 1,045,000 1,688,000

 

In should be noted that the potential quantity and grade of these exploration targets is conceptual in nature, that there has been insufficient exploration to define a mineral resource and that it is uncertain if further exploration will result in the target being delineated as a mineral resource as per the NI 43-101 reporting standards. The exploration targets include five isolated drill holes and assume projections of mineralized structures to deep levels as well as an extension of the Northeast Zone, and are based a continuation of favourable geological conditions that host mineralized structures that have been encountered in shallower drilling of Phase 2 to deep levels below the limits of the current wireframes used in the estimation of the new

 
 (VIRIMAI PROJECTS LOGO)Page 112
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

resources described herein. The exploration targets assume that the extension of the Northeast Zone along strike will be confirmed by additional drilling.

 

The Phase 3 drilling program is currently underway to further test the continuity of these mineralized structures. Current information from drill holes show high grade intersections including drill-hole BMRCD298 with an intercept average 2.45 g/t from 650 m to 681 m down the hole (NE Extension) and drill-hole BMRCD309 with an intercept average 3.4 g/t from 617 m to 630 m down the hole (Main North)

 

14.7Mineral Resources and Conclusions

 

Since the last update, June 2018, the Buckreef Shear Zone Measured Mineral Resources have more than doubled in terms of tonnage but increased by two and half times in terms of contained ounces mainly due to the high grades intersected in the Main Zone Central and North East extension during the last campaign. Indicated Mineral Resources have increased by approximately 20% with a corresponding nearly 30% increase in contained ounces. Inferred Mineral Resources have also more than doubled with but contained ounces just fall short of being double. This is due to the deeper drilling that reflects the open–ended nature of the mineralisation.

 
 (VIRIMAI PROJECTS LOGO)Page 113
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

15.MINERAL RESERVE ESTIMATE

 

The last Mineral Reserves estimate for the Buckreef Gold Project are as reported in the last published ITR titled “Amended NATIONAL INSTRUMENT 43-101 Independent Technical Report Mineral Reserves Estimate and Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” (Virimai 2018). No update Mineral Reserves have been estimated for the Buckreef Gold Project in this update report for Mineral Resources. A new pit optimisation taking into account of the current Mineral Resources update in the Buckreef prospect and the current prevailing economic factors is still to be completed. The mining philosophy for the development of the Buckreef Gold Project still remains that of initial open pit on the Buckreef deposit transitioning into underground mining at depth while it will be purely open pit for the other three smaller deposits as outlined in the ITR (Virimai 2018).

 

The following section is a full extract from the report titled “Amended NATIONAL INSTRUMENT 43-101 Independent Technical Report Mineral Reserves Estimate and Pre-Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa.” June 2018:

 

15.1Introduction

 

This section describes the Mineral Reserves estimation process completed by Virimai Projects in June 2018. By definition a Mineral Reserve is the economically mineable part of a Measured or Indicated Mineral Resource demonstrated by at least a Preliminary Feasibility Study. The Study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. The Mineral Reserve takes into account diluting material that will be mined in conjunction with the economic mineralized rock and delivered to the processing plant also takes into account the likely unrecoverable material that will be either left in the ground or will be associated with disposed waste rock.

 

Further, the Mineral Reserves are classified as only Proven and/or Probable in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) classification of NI 43-101 Resource and Reserve definitions, and the Companion Policy 43-101CP.

 

In the calculation of reserves the most important step is to ascertain the portion of mineral resource that can be mined economically. Various parameters are put together and used as inputs for the purpose of carrying out criteria-based computations, in the process of defining economic limits of the orebody. In case of surface mining, these computations are done through a process known as Pit Optimization which is performed by using a well-known Lerch’s-Grossman algorithm. The algorithm is implemented in various mine planning software applications such as Geovia Whittle, NPV Scheduler and many others. Given the right input parameters such as geological block model grades, rock classification, mining and processing costs, metal recoveries, geo-technical parameters and the metal price, the software generates a series of nested pit shells. For the purposes of pit optimization, costs are grouped into five key categories as mining, processing, selling, rehabilitation/reclamation and general/administration costs.

 

From optimization results, final pit shell is selected usually on the basis that it in general maximizes undiscounted or discounted cash flow at the given economic parameters and the applied physical constraints;

 
 (VIRIMAI PROJECTS LOGO)Page 114
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

however, it can also be selected by considering other factors such as the maximum quantity of metal product being able to realistically produce without adversely affecting the overall economic outcome of the project.

 

Once the optimal pitshell is selected, it is necessary to carry out designs for the purpose of putting into consideration various practical aspects such as access ramps, benched pit walls, geotechnical berms, minimum mining widths and pit phasing. Using the created pit designs, mineral reserves are calculated within those designs to determine tonnage and grade only of the indicated and measured part of the mineral resources, which are respectively converted to probable and proven mineral reserves. An economic cut-off grade is usually applied in the calculation to discriminate ore and waste that fall within the designed pit. Mined rock material of grade below cut-off grade would not be profitable if processed basing on the prevailing economic and technological conditions; these materials together with completely barren rock are reported as waste. Reserves estimates presented in this report followed this process and include four deposits that are Buckreef, Eastern Porphyry, Bingwa and Tembo. These deposits contain gold mineralization starting from near the ground surface with generally continued spatial distribution in a manner that is suitable for surface mining particularly open pit mining method.

 

15.2Open Pit Mining

 

Considering that all the four deposits somehow start from or near the ground surface, Open Pit mining method was a logical choice made by Virimai Projects in completing reserves preparation.

 

Open pit mining involves cutting vertical or subvertical faces in the ground with reasonable step-ins technically known as benches. Access between benches to the lowest one, is via inclined ramps wrapping around the wall of the pit. Ramps are developed progressively as the pit continues to develop downward. Open pit design follows as closely as possible the selected pit shell in order to stay within expected economic limits. Design also follows geotechnical recommendations in order to ensure long term stability of the mine and reduced risks wall failures .

 

15.3Resource Block Model

 

Virimai Projects used resources models discussed in chapter 14 of this report for completing mine planning. The model contains among many others important attributes including gold grade field, rock type coding, ore zones coding, mineral resources classification field etc.

 
 (VIRIMAI PROJECTS LOGO)Page 115
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

15.4Open Pit Optimization

 

Pit optimisations were done using Lerch-Grossman algorithm available in Whittle software. The geological block models were imported into the software considering no depletion of any mined surfaces. The input parameters used in running pit optimisations are shown in Tables below.

 

Table 15.1: Key Economic Parameters

 

Parameters Value Units
Long Term Gold Price - Reserves 1,300 $/Oz
Long Term Gold Price - Resources 1,600 $/Oz
Gov. Royalties 6.00 %
Export Fee 1.00 %
Other Applicable Fees (Local Service Levy) 0.30 %
Discount Rate 8.00 %
Other Selling Costs (Smelting, Insurance, Security etc) 4.40 $/Oz
Exchange Rate 2,250 TZS/USD
Fuel/Diesel Price 1.20 $/L

 

Table 15.2: Main Operating Constraints

 

Parameters Value Units
Maximum Mining Limit 14.00 Mtpa
Processing Limit 1.45 Mtpa
Ore Dilution (External) 5.00 %
Ore Loss 5.00 %
Call factor 100.00 %

 

For running optimizations geotechnical parameters are an integral part and must be understood and applied correctly. Since optimization shells do not include access ramps and/or geotechnical berms, it is vital that sufficient allowance is made to account for these berms and possible geotechnical stability step offs.

 

Table 15.3: Geotechnical Parameters

 

Inter-ramp Slope Angle Weathered/Soft Transitional Fresh Rock
For Pit Design (Degrees) 29 46 52
For Optimization (Degrees) 28 44 47
Flattening for Ramps (Degrees) -1 -2 -5

 

It is noted that the hard rock part has been penalized with higher IRA flattening in order to account for ramps wrapping around the pit walls several times. Geotechnical berms are also taken into consideration.

 

Table 15.4: Processing Parameters

 

Processing Units Oxide Trans Hard
Recoveries % 92.33% 92.33% 85.50%
Processing Cost ($/t) 10.09 10.09 10.24
Rehabilitation Cost ($/t) 0.03 0.03 0.03
G&A Costs ($/t) 1.98 1.98 1.98
Total Ore Cost ($/t) 12.10 12.10 12.25

 
 (VIRIMAI PROJECTS LOGO)Page 116
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The following is a summary of the outcome of pit optimization for the four deposits.

 

There are in total 4 possible push-backs for Buckreef Pit.
Bingwa is a single pushback to the final limits
Eastern Porphyry is also a single pushback to the final limits
Tembo is mined to the ultimate pit limits in one single phase also.

 

Optimizations were carried out based on $1300/Oz gold price where by nested pit shells were create using a range of revenue factors between 0.3 and 2 at $20 increments for each deposit.

 

Analysis for each of the pits was completed resulting in cashflow summaries and charts showing various metrics including discounted and undiscounted cashflow useful for decision making in shell selection.

 

Guided by the corporate policy where by the company intends to maximize gold production at the best possible economic value, pitshells selected were not necessarily of highest undiscounted cash flow as shown in the charts for each deposit. Selected pits strike a balance between best pit value and gold ounces produce to also maximize mine life which give optionality for developing other potential targets within the area.

 

15.4.1Buckreef Pit

 

Due to its relatively larger size, Buckreef pit was split into a total of four phases; as a result, its overall value improved significantly by differing waste stripping and improves cash flow in the early years of its life.

 

(Figure 15-1)
Figure 15-1: Pit by Pit Graph for Buckreef Pit

 

Buckreef has been determined to be mineable in 4 phases; which by doing so would allow for deferment of waste stripping hence improve cashflow in the earlier years. Pit shell number 12 was selected to be Phase One or the starter pit, Pit shell number 19 Phase Two, pit shell 29 phase three and the final pit shell was 49. By

 
 (VIRIMAI PROJECTS LOGO)Page 117
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

looking at pit by pit graphs, usually at step changes represent significant pits shell size change hence suitable for picking pit phases.

 

Isometric view of the selected pit shells with ore blocks as presented below, depict that Buckreef pits is generally high stripping pit due to its sub vertical ore body.

 

(Figure 15-2)
Figure 15-2: Buckreef Selected Ultimate Pit

 

In view of the changes in the mineral resource estimates of this prospect the shape general extent of this pit will change once the new pit optimisation taking into account the additional resources is done into account.

 

TRX commissioned SGS of Canada to complete a conceptual study of the underground operation at Buckreef Prospect for the exploitation of the underground. The report provides recommendations to guide stope, underground infrastructure, and crown pillar designs. Key recommendations are:

 

a. A crown pillar with a minimum thickness of 15 m between the open pit and underground workings

 

b. Unsupported long hole longitudinal stopes have been assessed for widths of 7.5, 10, and 12.5 m for both single 25 m sub-level interval heights, using Q’ median values. These conceptual or Level 1 underground stope designs will be advanced to the next level of mine design as the basis for a possible underground operation below the planned Buckreef open pit. The presented open pit is based on the June 26, 2018 43-101 Pre- Feasibility Report.

 

15.4.2Bingwa Pit

 

Bingwa is the second in size on tonnage basis, it however is not large enough to warrant phasing. And is also a short life pit which as a result phasing would not bear any beneficial outcome. Therefore, only the ultimate pit was selected.

 
 (VIRIMAI PROJECTS LOGO)Page 118
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 15-3)
Figure 15-3: Pit by Pit graph for Bingwa

 

(Figure 15-4)
Figure 15-4: Bingwa Selected Ultimate Pit

 

15.4.3Eastern Porphyry Pit

 

Eastern Porphyry is a small pit just next to the main Buckreef pit, similar to Bingwa it is a small satellite pit that cannot be practically phased. Ultimate pit shells was selected to be shell number 38

 
 (VIRIMAI PROJECTS LOGO)Page 119
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 15-5)
Figure 15-5: Pit by Pit graph for Eastern Porphyry

  

(Figure 15-6)
Figure 15-6: Eastern Porphyry Pit Selected Ultimate Pit

 

 

15.4.4Tembo Pit

 

Tembo is the smallest of all the four deposits, and follows the same trend as other satellite pits being too small for any possible phasing. Ultimate selected shell is number 13.

 
 (VIRIMAI PROJECTS LOGO)Page 120
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 15-7)
Figure 15-7: Pit by Pit graph for Tembo

 

(Figure 15-8)
Figure 15-8: Tembo Pit Selected Ultimate Pit

 

15.5Detailed Mine Design

 

Open pit mine designs followed the selected economic limits represented by the selected pit shells. Considering that, the deposits are made up of weathered/soft, Transitional and fresh rocks which differ in competency, the design parameters differed based on rock type. Detailed geotechnical study is yet to be completed which may optimize these parameters. However, present assumptions are quite reasonable and are within the limits of

 
 (VIRIMAI PROJECTS LOGO)Page 121
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

parameters applied by mines around the Buckreef project with similar rock characteristics. Pit design parameters used for design of all the four pits are summarised in Table 15-6

 

Table 15-6 Mine Design Parameters

 

Design Criteria Weathered/Soft Transitional Fresh Rock
Bench Height (m) 5 10 10
Berm Width (m) 6 8 6
Batter Angle (Degrees) 60 80 80
Ramp Width (m) 10 10 10
Stack Height (m) 40 40 40
Stack Berm Width (m) 10 10 10
Inter-ramp Slope Angle (Degrees) 29 46 52

 

Additionally, waste rock dumps were designed taking into account the final footprint after rehabilitation shaping for rehabilitation purposes. A summary of waste rock dump design parameters are as follows: -

 

Lift Height 15m

 

Ramp Width 10m

 

Ramp Gradient 10%

 

Tipping Angle 32 degrees

 

Final Angle of Rehab 18 degrees

 

(Figure 15-8)
Figure 15-8: Buckreef and Eastern Porphyry Pit and Waste Dump

 
 (VIRIMAI PROJECTS LOGO)Page 122
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 15-9)
Figure 15-9: Buckreef Pit Design Plan and Sections

 

15.6In-Pit Dilution and Mining Recovery

 

Dilution is the term used to describe the grade drop of mined ore in relation to the originally computed insitu grade due to addition of lower grade material or completely barren material. Technically there are two types of dilution, these are internal and external dilution.

 

Internal dilution is usually a result of averaging material grade to include waste lenses that may be within the ore zone. This is taken care off during resource modelling and so the estimated grade has already accounted for internal dilution. Of particular concern for mine planning purpose is external dilution which is taken into account in order to a consider practical limitations of mining the ore without mixing it with lower grade or barren material. In real life it is not practically possible to completely avoid the mixing consequently the ore grade is diluted due to mining practices. For this project, no extensive mining has taken place hence estimation of dilution is based on experience from other deposits of similar characteristics. It is further expected that responsible mining will be practiced in order to minimize ore dilution. For the purpose of this study it was therefore assumed that 5% will be the applicable dilution.

 

On the other hand, ore loss is a result of poor recovery from especially ore body contacts where by part of the ore is left in the ground or the split in waste and ore boundaries is not precise enough as a result portion of the ore is sent to the waste rock disposal areas. This is also an outcome of mining practices. With application of leading practices, it can be controlled and reduced. An ore loss of 5% was also considered.

 
 (VIRIMAI PROJECTS LOGO)Page 123
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

15.7Cut-Off Grade Criteria

 

In order to determine ore and waste within the pit designs, fixed cut-off grades by rock type were computed based on break-even analysis. In this analysis, all materials with grades equal or above the prescribed cut-off were classified as ore, whereas the rest with grades lower than the cut-off were considered as waste.

 

The breakeven calculation formula is used is as follows: -

 

Cut − Off =  (Processing Cost − Rehabilitation Costs)
(Gold Price x Recovery)

 

Where

 

Cut-Off is expressed in grams per tonne (g/t)
Processing cost is in dollars per tonne of ore processed ($/t)
Rehabilitation cost is in dollars per tonne of mined ($/t)
Gold price in dollars per gram recovered ($/gm)
And recovery in percentage or fraction of contained gold in the ore fed to the process.

 

15.8Open Pit Material Inventory

 

After completing all the steps in preparation as described in this section for computation of reserves pit design and cut off grades were used to calculate reserves for each deposit. The obtained Cut off grade was used to classify ore and waste but also resource class Indicated and Measured were used to convert ore tonnes in those categories into Probable and Proven reserves respectively.

 

Table 15.7 Open Pit Reserves Summary

 

Pits Design Reserves Summary Round 3 COG: Oxide & Trans = 0.34, Fresh = 0.37
Virimai June 2018 Pit Design Reserves Summary
Prospect Name Reserves Category Tonnes Grade In Situ Gold Content
(Mt) Au (g/t) Kg oz
Buckreef Proven 8,174,415 1.64 13,374 429,986
Probable 8,174,147 1.40 11,436 367,667
Total (Proven + Probable) 16,348,562 1.52 24,810 797,652
Eastern Porphyry Proven 79,385 1.17 93 2,982
Probable 976,281 1.03 1,003 32,242
Total (Proven + Probable) 1,055,666 1.04 1,096 35,224
Tembo Proven - - - -
Probable 70,183 2.35 165 5,312
Total (Proven + Probable) 70,183 2.35 165 5,312
Bingwa Proven 1,098,383 2.39 2,625 84,390
Probable 510,154 1.30 662 21,271
Total (Proven + Probable) 1,608,536 2.04 3,286 105,661
           
Grand Total Proven -Stockpile 119,726 1.86 223 7,160
Proven 9,352,183 1.72 16,092 517,358
Probable 9,730,764 1.36 13,265 426,492
Total Ore (Proven + Probable) 19,202,673 1.54 29,580 951,009

 

1.CIM definitions were followed for Mineral Resource Estimates
2.Mineral Reserve is estimated at gold price of US$1,300/oz
3.Cutoff grade of Oxides 0.34g/t and fresh rock of 0.37g/t
4Metallurgical recoveries of 92% for oxides and 85% for fresh rock

 
 (VIRIMAI PROJECTS LOGO)Page 124
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

15.1Concluding Remarks

 

As stated in section 15.1 of the report the Mineral Reserves stated herein are based on the optimisation of the Mineral Resources as at June 2018. Virimai expects a change in the Mineral Reserves inventory of the Buckreef Prospect in view of the May 2020 update of the Mineral Resources of the Buckreef Prospect on completion of the new pit optimisation and design work and the planned feasibility study of the underground mine to exploit the deep Mineral Resources of the prospect as identified through this update report. The Mineral Reserves of the other smaller pits of Bingwa, Tembo and Eastern Porphyry will remain as defined in the 2018 ITR.

 
 (VIRIMAI PROJECTS LOGO)Page 125
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

16.MINING METHOD

 

16.1Introduction

 

In the 2018 update study it was assumed that only open pit mining methods will be used for the resource extraction and any resource falling below the pit will be subject of future studies. The mining methods and production capacity have been tailored to match the milling throughput of 0.5Mtpa in year 1 ramping up in year 2 to 1.0Mtpa and then to 1,5Mtpa when in full production in year 4 of project start up. The open pit operations will deliver mined ore to the primary crusher for sizing and delivery into the processing plant.

 

The project consists of four deposits that are Buckreef, Eastern Porphyry, Tembo and Bingwa. These are near to the surface and are suitable for open pit mining method. The deposits consist of weathered zones/soft, transition and fresh zones. Selection of mining method is usually dictated by among other aspects the nature of the orebody which ultimately dictates the economics. For near surface orebodies, usually the first choice is to look for possibility to mine by surface method. Deep seated orebodies are commonly considered for underground mining. At Buckreef project all the deposits are near surface, consequently Open Pit mining method was chosen as the highest-ranked option for consideration. Validation of this selection was verified by running pit optimization to see if the larger portion of the orebody would be mineable economically by means of open pit.

 

16.2Open Pit Mining Method

 

Open pit mining is a method of extracting ore from the ground by mean of excavating a series of vertical or sub vertical faces while leaving wide horizontal ledges to make what is commonly know is mining benches. Mining will involve conventional drilling, blasting load and haul of both waste and ore using Articulated Dump Trucks (ADT) and Excavators R966 Liebherr. This will be a owner mining meaning the owner will acquire the mining fleet an operate using own crew to carry out mining activities.

 

In order to appropriately schedule waste stripping in a manner that improves project economics, Buckreef main pit will be mined by a series of four pushback starting with a small cut and increasing in size by step of each pushback to the final pit.

 

(Figure 16-1)
Figure 16-1. Key Mining Equipment

 
 (VIRIMAI PROJECTS LOGO)Page 126
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

16.3Open Pit and Stockpiles Geotechnical Designs

 

Long term mine stability is a critical component in consideration during design, especially when a pit has to operate for several years. Therefore, as mining continues, the walls must be able to hold in place while going through changes in seasons and excavation continue to the bottom. The pit wall will be subjected to various forces including vibrations due to blasting, wetting due to rains, gravitational forces due to changing shape of the ground also possible seismic activities. In order to achieve the intended wall stability, detailed geotechnical study is required that will identify key rockmass characterizations and establish design parameters for suitable mining without rock failures.

 

For purpose of pre-feasibility study, a preliminary rockmass characterization was carried out using existing core samples taken from drilling around the site. Rock core sample as shown in figure 16-2, appear to be good based on what can be seen as superior Rock Quality Designation (RQD) Index.

 

Using this information preliminary recommendation for stability design were completed and have been used in the current pit designs.

 

(Figure 16-2)
Figure 16-2: Buckreef Rock Core Sample (Source Geology of the Rwamagaza Greenstone Belt and Au prospects therein. Andrew Tunks & Jamie Rogers September 2006)

 

 

16.4Open Pit Mine Planning

 

16.4.1Open Pit Mine Production Schedule

 

Open pit mine production schedule was developed for each of the pit by Virimai for the operation of the Buckreef Gold Project. The schedule is summarised in Table 16.4.

 
 (VIRIMAI PROJECTS LOGO)Page 127
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 16-3)
Figure 16-3 Mining Annual Summary

 

(Figure 16-4)
Figure 16-4 Mill Feed Annual Summary

 
 (VIRIMAI PROJECTS LOGO)Page 128
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 16-5)
Figure 16-5 Gold Production Annual Profile

 
 (VIRIMAI PROJECTS LOGO)Page 129
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

 

Table 16.4 Summary of Scheduled Milled Tonnages and Waste Tonnages (Refer –Appendix 16.1)

 

Total                                  
Tonnes of Oxide Ore 274 256 80 110 39 31 159 65 321 118 16 1 41 - - - 1,510
AUMI of Oxide Ore 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - - 1.78
Tonnes of Oxide Waste 2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - - 20,155
Tonnes of Oxide Ore & Waste 2,988 1,699 2,166 707 230 1,581 2,245 2,205 2,299 3,440 935 83 1,086 - - - 21,665
Tonnes of Trans. Ore 92 192 150 93 93 91 40 21 82 341 256 52 17 - - - 1,520
AUMI of Trans. Ore 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - - 1.92
Tonnes of Trans. Waste 1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - - 20,346
Tonnes of Trans. Ore & Waste 1,388 1,289 2,284 1,504 825 1,616 1,970 1,298 1,711 3,041 3,134 1,420 385 - - - 21,866
Tonnes of Hard Ore 43 187 346 555 1,247 1,522 1,269 1,263 1,060 1,122 1,092 1,440 1,497 1,386 1,110 915 16,053
AUMI of Hard Ore 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70 1.48
Tonnes of Hard Waste 508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102 141,207
Tonnes of Hard Ore & Waste 551 1,953 4,401 7,379 9,028 8,361 9,254 10,557 15,700 13,283 15,641 16,930 13,645 14,274 14,286 2,017 157,260
Tonnes of Oxide, Trans and Hard Ore 409 635 575 758 1,378 1,644 1,469 1,349 1,462 1,581 1,364 1,493 1,555 1,386 1,110 915 19,083
AUMI of of Oxide, Trans and Hard Ore 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70 1.54
Tonnes of of Oxide, Trans and Hard Waste 4,518 4,306 8,276 8,833 8,705 9,914 12,000 12,712 18,248 18,183 18,346 16,940 13,562 12,888 13,176 1,102 181,708
Tonnes of of Oxide, Trans and Hard Ore & Waste 4,927 4,941 8,851 9,590 10,083 11,558 13,469 14,060 19,710 19,764 19,710 18,432 15,117 14,274 14,286 2,017 200,791
SR (w/o) 11.04 6.79 14.38 11.66 6.32 6.03 8.17 9.42 12.48 11.50 13.45 11.35 8.72 9.30 11.87 1.20 9.52

 
 (VIRIMAI PROJECTS LOGO)Page 130
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The production schedule was developed with the aim of delivering the highest ore grades to the mill as early as possible in order to maximize the near term cash flow of the project and maximize the net present value. This was guided by mining the Buckreef pit in four phases in a value sequence per the price sensitivity of the pits and phases from the pit optimization exercise.

 

Production of ore and waste will begin in the first year of operation at the Buckreef open pit. The mining schedule is based upon all proven and probable reserves located within pits defined using only measured and indicated resources.

 

Virimai adopted a value based (cash-generation capacity) pit ranking as well as proximity to process plant and ease of mine development approach to come up with an optimal production schedule. This strategy should be revisited and reviewed annually in the development of the next life of mine business plan considering available information and evolving business climate.

 

To assist the sequencing, cash cost per recovered ounce for each cutback or pit was calculated and ranked from lowest to highest. To maximize the return on investment, pits with the lowest cash cost (or in other words highest cash margins) are sequenced first. Other considerations were:

 

Percentage of oxidation,

 

Plant capacity,

 

Satellite Haulage capacity, and

 

Bench turnover rate.

 

Table 16.5 Summary of Scheduled Tonnages by Pit Tonnages

 

    Buckreef Bingwa Eastern
Porphyry
Tembo
Waste t 160,217,803 10,311,730 9,823,912 1,424,651
Ore t 16,348,562 1,608,536 1,055,666 70,183
Grade g/t 1.52 2.04 1.04 2.35
Ounce Mined g/t 797,664.77 105,660.16 35,223.36 5,312.10
Stripping Ratio t:t 9.80 6.41 9.31 20.30
Distance to Plant km 1.2 5 1.3 3
Ranking   1 2 3 4

 

Based on the total in pit reserves available the open pit mine life is estimated at 16 years using the production rate of 0.5Mtpa for the first year 1.0Mtpa for year 2-3 and then 1.497Mtpa from the fourth year to end of mine life.

 

Major considerations for the mining schedule included:

 

The bench by bench mining approach is considered for this type of ore body. The ore body is vertical so ore body selectivity is limited in almost all the pits. This approach brings more benefits in the middle of the life of mine.

 

Mining production operations commence at and continue at the Buckreef Main Pit for the first four (4) years, the focus will be treating the oxide material at the process plant in that period. The production rate is gradually increased from ~300,000tpa to ~480,000tpa by end of 4th year.

 
 (VIRIMAI PROJECTS LOGO)Page 131
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Year-0 includes pit pre-development including waste stripping, haul road and infrastructure construction with the process plant mainly processing ROMPAD material already on-hand for commissioning.

 

In Year-4 production rate is ramped up to ~1.497Mtpa from the Buckreef main pit while in Year-4, production from the Bingwa pit will commence with production rates set around ~120,000tpa during its first years of operation. Production from Bingwa will be mostly be saprolite material while sulphide ores will commence being mined at the main Buckreef pit.

 

In Year-10 production from the Eastern Porphyry pit will commence with production rates set around ~20,000-87,000tpa.

 

In Year -10, the Tembo pit also comes online with overall mine production rates approximating 20ktpa to 25ktpa until LOM in Year-11. This is a small pit with a life of one year.

 

The production schedule applies a stockpiling strategy in order to elevate the feed grade to the mill early on. Saprolite and fresh rock ores are divided into low grade, medium grade and high grade categories with high and medium grades being prioritized in the mill feed. Low grade saprolite and rock ores are stockpiled separately until required to “fill the mill” when insufficient high grade and medium grade are being mined.

 

The Buckreef main pit remains the backbone of the mine over current LOM. The pit has ore of higher tonnages. Therefore, it is of strategic importance that the ore supply from this pit flows constantly. The Bingwa project is mostly oxide and it contains a larger amount of low grade as well. Enough time is given to this pit to allow grade control to take place. The grade control will turn this project into a pit of higher value because its ore body is thick and consistence as compared to the rest of the pits.

 

The ore treatment philosophy is that all material above the cut off is treated first. The grade control is potentially very important to increase the confidence of the ore body and increase the tonnage. It is very important to note that marginal material is separately stockpiled for treatment at the end of life after all pit mining has stopped, i.e. under reduced cost structure. The full detailed of mining and plant schedule is as indicated in Appendix 16.1

 

16.4.2Material Management

 

During mining operations ore from the various pits will be tipped direct into the grizzlies of the three modular plants or will be stockpiled on the feed stockpile or on low grade stockpile for material with grades below cut- off. Both the RoM ore and the low grade stockpiles will be placed close to the primary crusher to reduce the re- handling costs. The low grade stockpile will be depleted after the pits have been depleted. It must however be noted that in this study all material below cut off grade has been considered as waste.

 

16.4.3Waste Dump Design

 

The waste rock piles have been designed according to the waste requirements of each of the pit and are located around the periphery of the pits to minimize the haulage distance. The material properties assumptions used for the design of the waste rock piles are an in-situ waste rock density of 2.75t/m3 and a swell factor of 35%. The waste dumps are located and sized to fit entirely within Buckreef’s mining claims or leasing area and are kept at an adequate distance from all major water basins.

 

Each of the waste dumps for the four pits are estimated to hold waste volumes as summarised in table 16.5.

 
 (VIRIMAI PROJECTS LOGO)Page 132
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 16.5 Summary of Waste Dump Volumes at each of the Pits

 

Area Waste Waste dumps
Volumes
(t) Mm3
Buckreef 160,217,803 96.52
Bingwa 10,311,730 6.21
Eastern Porphyry 9,823,912 5.92
Tembo 1,354,467 0.82
Totals 181,707,912 109.46

 

The dumps will be built in 5 m lifts, with 15 m bench heights. Dumping has been sequenced in phases to allow for shorter hauls during earlier years of operation.

 

16.4.4In-Pit Dumping

 

The Buckreef pit is a elongated pit of about 1.5km in total length as the pit gets to the lower depth in order to reduce the cycle times for waste haulage and maintain the quantity of dump trucks at reasonable levels an in-pit dumping regime is considered. These in pit dumps will be located to the south of the pit and to the north. These in-pit dumps will only be considered after further drilling to sterilise the zones below those currently defined by the current drilling in the south and north of Buckreef.

 

16.5Operating Time Assumptions

 

The operating regimes for the Buckreef Gold Project have been set in two categories as follow:

 

Primary Plant operating times

 

Open Pit Mining operating times.

 

The two have been separated in order to take into account the extra scheduled hours typically associated with mining operation such as blasting times, inspection and refuelling of earthmoving equipment and shift change. The plant is planned to operate on 3 -8hour shifts per day, 7 days per week while the mining operations are planned on 2 -10 hour shifts per day, 7 days per week. The 2 hour in between shifts is allowed for blasting, inspection and refuelling of earthmoving equipment.

 

16.6Mine Equipment and Operations

 

Selection and sizing of mining fleet was done by computational simulations using Talpac fleet management software. Ancillary equipment also included in the list of machines require for the operation.

 

The full schedule of mining equipment employed to meet its current requirements is given below.

 

Item Machine Type Model Make Units
1 ADT B40E Bell 17
2 Excavator R966 Liebherr 3
3 Dozer PR754 Liebherr 3
4 Wheel Dozer PR755 Liebherr 1
5 Grader 770G Bell 1
6 ADT Water Bowser B30E - 27,000L Bell 1
7 ADT Fuel Bowser B25E - 23,000L Bell 1
8 Drilling Rig     3

 
 (VIRIMAI PROJECTS LOGO)Page 133
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The loading equipment are backhoe hydraulic excavators equipped with 4.5m3 bucket capacity and these will be supported by a fleet of articulated dump trucks with 40tonne payload capacity which is a good match for the 4m3 bucket excavator. The truck fleet will start with 6 in year 1 and will increase to 17no in year 4 when the mine reaches steady production. The support equipment such as dozer and grader tend to follow the increase in the profile of the prime earthmovers.

 

An analysis was performed to evaluate and determine the optimum size and configuration of the truck and excavator fleet. Various sizes, brands of haul trucks, excavators, and drill rigs were evaluated. Given the close availability and relatively lack of power in the area diesel powered equipment were chosen as the most cost effective for the project. Due to the changing production requirements of the mine over the period varying numbers of key production equipment will be required. The annual requirements of the trucks, loaders/excavator and drill rigs for the project in order to meet the plant production requirements and be able to expose the same amount of ore material are summarised in Table 16.3. In addition to the key equipment auxiliary equipment such as tracked dozers for pit cleaning, rubber tyred dozers for stockpile management graders for haul roads etc will be required.

 

16.6.1Drilling Requirement

 

The initial drill requirements would consist of two diesel-powered hydraulic percussion track drill rigs capable of drilling 110mm diameter blast holes. A 2.5m x 3.0m pattern has been selected for fresh rock ore material and a 3.70m x 4.00m pattern for fresh waste material.

 

16.6.2Blasting

 

Overall explosive consumption was based on using a 70% ANFO and 30% emulsion mix product. Some blasting parameters may be seen in Table 16.6. Where possible drill hole liners will be used in wet holes to maximise the use of ANFO however in the study it has been assumed that mixture of ANFO/Emulsion will be the predominate explosive material. The selected explosive supplier is to erect a plant and storage facility on site. All Blasting operations will be carried out under the supervision of the mine blasting foreman, the supplier will be contracted to supply, deliver, and load explosives into the blast holes. The estimate explosive powder factor (PF) in waste has been estimated at 0.75kg/bcm (0.3kg/t) in waste material and 1.2kg/bcm (0.4kg/t) in ore material.

 

16.7Mine Personnel Requirements

 

In view of the mining philosophy adopted by the mine of owner mining a full schedule of personnel required to maintain the pits producing at the required rate to feed the plant will include earthmoving operative and support technical support. The mine personnel requirement will cater for the operation and repair of the mining equipment, supervision, grade control and technical services. Summarised in Appendix 16.6 is the full schedule of mine staff required to support the operation of the Buckreef Gold Project.

 

16.8Concluding Remarks

 

In view of the material change in the change in the Mineral Resource inventory of the Buckreef the overall design and scheduling of the Buckreef Prospect will to take into account the increase in Mineral Resource

 
 (VIRIMAI PROJECTS LOGO)Page 134
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

through the proposed new optimisation and design and the underground mining of the deep sitting resources of the resources.

 

Virimai envisages that the overall mining philosophy would remain the same for the smaller deposits of Bingwa, Tembo and Eastern Porphyry which would consist of a number of conventional open pit layouts with access to the orebodies provided via a series of ramps into the pits. However, for the Buckreef prospect the mining philosophy will start with open pit accessed by a series of ramps transitioning into underground mining accessed through a decline into the orebody leaving a crown pillar between the underground working and the pit. This work is the subject of the next level of study for the Buckreef Gold Project.

 
 (VIRIMAI PROJECTS LOGO)Page 135
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

17.RECOVERY METHODS

 

17.1Introduction

 

In April 2020 TRX started mining the oxide ores and processing them through a small pilot oxide gravity CIL plant installed at the Buckreef Prospect. The small plant is to confirm the proposed flow-sheet that includes either Gravity Separation with Gravity Tailing Cyanidation outlined in the Prefeasibility Study of 2018. TRX has commissioned SGS Canada Inc, to carry out metallurgical testing of several large fresh rock samples at its Lakefield, Ontario, Canada facilities. These samples were collected from holes recently drilled in the area of the Pre-Feasibility Study open pit to collect critical flow sheet and design information for a large plant that will process the primary ores of the Buckreef. This large plant will be the basis for the Company’s Final Feasibility 43-101 Report that is still to be commissioned.

 

The design of the processing facilities described in the “Amended NI43-101 Independent Technical Mining Reserves Estimate and Feasibility Study on the Buckreef Gold Mine Project Tanzania East Africa” is reproduced in this section of this update. The test work conducted on the ores of the Buckreef indicated that both the oxide (and transition) ore and the sulphide ore are amenable to conventional gold recovery techniques, namely, crushing, milling, gravity concentration and cyanidation. The proposed process is outlined in this section, starting with the overall design criteria, and finishing with the process description.

 

17.2Description of the ore

 

17.2.1Ore types

 

The ore body consists of oxide material that overlies sulphide material, with a transition zone in between these two ore types. The oxide ore is weathered, has a clay consistency, and can be classified as a ’saprolite’. Ore from the transition zone will, for the purposes of this design section, be included with oxide ore. The depth of the oxidised layer varies between about 18 and 33 m. The sulphide ore is hard-rock, composed predominantly of quartzite.

 

The deportment of gold in both the oxide and sulphide ore types is ‘free-milling’, in the sense that it is amenable to gravity concentration and cyanidation with high recoveries.

 

17.2.2Head grade

 

The design head grade for the ore is given in Table 17.1.

 

Table 17.1 Design head grade for oxide and sulphide ores

 

Gold analysis,
Sample g/t
Oxide ore 3.25
Sulphide ore 3.16

(Source: MMSA Report No 15/059 r1)

 

17.3Processing strategy

 

The mining plan calls for the stripping of overburden, and the mining of the oxidised ore. Feed to the plant and hence production of gold will be ramped up over a period of time. To enable this, the plant will be built in modules, each with a capacity of 60t/h. In the first two years, feed material will be fed to one module,

 
 (VIRIMAI PROJECTS LOGO)Page 136
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

consisting of crushing, milling, carbon-in-leach, elution, doré production and tailings detoxification. Each module has been designed to accommodate both oxide and sulphide materials.

 

In the third year, the fed rate will increase to 120t/h, and the type of material will change to predominantly sulphide. A second processing module will be added to accommodate this increased production rate. This second processing module will be a replica of the first, that is, it will consist of crushing, milling, carbon-in- leach, elution, dore production and tailings detoxification.

 

In the fourth year, a third module will be added, raising the capacity of the processing facilities to180 t/hr. As with the second module, this will be a replica, consisting of an entire production train.

 

17.4Overall Design Criteria

 

The overall process criteria are given in Table 17.2. The process is design to treat 60t/hr of oxide ore in years 1 to 2 of the mining and beneficiation plant development. In total, the processing of the oxide will take a year and quarter. In year 3, a second module will increase the production to 120t/hr, treating sulphide ore. The front end will be modified in this phase to accommodate the sulphide ore. A third module will be installed in year 5 to increase production to 180t/hr. The process is designed to produce 78000 oz of gold per annum, bearing in mind that the lower throughput in the first four years.

 

Table 17.2 Overall design criteria

 

Criteria Units Year 1-2 Years 3 Years 4 on
Dry feed rate (design) t/h 60 120 180
Feed rate (nominal) tpa 483 552 967 104 1 450 656
Overall availability % 97 97 97
Recovery % 86 94 94
Gold Production oz pa 27 700 51 621 80 678

 

17.5Mass balance

 

A mass balance has been prepared, and the mass flows expected through each price of equipment in the process are presented with the equipment list in Appendix 13.1.

 

17.6Process Description and Design Criteria

 

The process consists of scrubbing, crushing, milling, gravity concentration, carbon-in-leach, elution and regeneration, and electrowinning and smelting. A model of the gold processing is shown in Figure 17.1, and a block flow diagram of the process is shown in Figure 17.2.

 

Each of the process sections will be described in further detail. The individual process flow diagrams are given in Appendix 13.1 and the list of mechanical items is given in Appendix 13.2.

 
 (VIRIMAI PROJECTS LOGO)Page 137
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 17.1)

 

Figure 17.1. Model of the gold processing plant.

 
 (VIRIMAI PROJECTS LOGO)Page 138
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 17.2)

 

Figure 17.2. Block flow diagram of the process.

 

17.6.1Ore receipt and scrubbing

 

The ore is stockpiled on a run-of-mine (ROM) pad and then fed to the ROM bin. The ore is conveyed from the ROM bin to a Rotaspiral. An electromagnet is used to remove tramp iron from the conveyor belt.

 

The oxide material is screened at 1 mm and scrubbed with water in the Rotaspiral. The minus 1 mm fraction and the water used in scrubbing drains to the underflow sump, from where it is pumped to the milling section. Water addition is controlled so that the specific gravity of the underflow is 1.3. The plus 1 mm fraction, which is now scrubbed of clay-type material, is discharged onto a conveyor and transported to the crushing section.

 

The design criteria for the Rotaspiral scrubbing unit are given in Table 17.3.

 
 (VIRIMAI PROJECTS LOGO)Page 139
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 17.3 Design criteria for the scrubber/screen.

 

Criteria Units Value
Dry feed rate per unit t/h 30
Screen size µm 1000
Oversize - 40%

 

17.6.2Crushing and milling

 

The material is conveyed to the jaw crushers. The discharge from the crushers is collected in a crusher bin, from where it is conveyed to the milling plant. Tramp iron is removed from the conveyor using an electromagnet.

 

The design criteria for the crusher are given in Table 17.4. The close-side setting of the crusher is 40 mm in order to create a feed of the optimal size to the EDS mill.

 

Table 17.4 Design criteria for the jaw crusher.

 

Criteria Units Value
Plant availability % 65%
Effective operating hours hr/y 5694
Effective operating hours hr/d 16
Dry solids feed rate per unit t/hr 92
Feed top size Mm 200

 

The crushed ore is combined with the oversize material from the mill on the feed conveyor to the mill. The feed from the conveyor is split in a two-way splitter chute, which discharge directly into the EDS multi-shaft mills. Each of the mills discharges directly into the feed chute of a Rotaspiral. The Rotaspirals are fitted with a sizing screen of 100 µm (90 x 400 µm). The oversize from the Rotaspiral is discharged onto a conveyor that feeds it back onto the mill feed conveyor as a recirculating load. Thus, the mill product will be 100% passing 100 microns.

 

The undersize forms the product from the milling sections and is pumped at a specific gravity of about 1.4 to the gravity concentrators.

 

The design criteria for the EDS mill are given in Table 17.5.

 

Table 17.5 Design criteria for the EDS mill and classification circuit.

 

Criteria Units Value
    Oxide ore Sulphide ore
Bond work index kWh/t 22 12
Classification screen microns 100 100

 
 (VIRIMAI PROJECTS LOGO)Page 140
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

For the treatment of the oxide ore, about 50% of ore will report to the undersize in the scrubber and will not be fed to the crushing and milling section. Consequently, the production through the mill will only be 50% of capacity.

 

The design of the mill anticipates that 20% of the material fed to the mill will be oversize on a single pass. Thus, the re-circulating load to the mill will be 120%.

 

17.6.3Gravity concentration

 

The underflow from the Rotaspirals is pumped to the gravity feed tank. Two Knelson concentrators are configured in series. Concentrate from the two gravity concentrators collected in a sump, and then fed to a Deister concentrating table. The concentrate is collected and bagged.

 

The tailings from the gravity circuit are pumped to the thickening plant.

 

The design criteria for the gravity concentrators are given in Table 17.6.

 

Table 17.6 Design criteria for gravity concentrators.

 

Criteria Units Value
Configuration No 2 units in series
Mass recovery – Unit 1 % 2.8%
Mass recovery – Unit 2 % 1.4%
Gold recovery – Unit 1 % 34.6%
Gold recovery – Unit 2 % 8.7%

 

The design criteria for the shaking table are given in Table 17.7.

 

Table 17.7 Design criteria for the shaking table.

 

Criteria Units Value
Type   Deister No 6
Gold recovery   75%
Gold grade g/t 300

 

17.6.4Thickening plant

 

The tailings from the gravity concentration plant are pumped to a dewatering cyclone. The cyclone underflow is fed to a pre-leach thickener, where the slurry stream is thickened.

 

The overflow from the cyclone and the thickener are pumped to the settling pond. The underflow from the thickener is pumped to the leaching (carbon-in-leach plant).

 

The design criteria for the dewatering cyclone are given in Table 17.8.

 
 (VIRIMAI PROJECTS LOGO)Page 141
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 17.8 Design criteria for the dewatering cyclone.

 

Criteria Units Value
Underflow percentage solids % 43%

 

The design criteria for the thickener are given in Table 17.9.

 

Table 17.9 Design criteria for the thickener.

 

Criteria Units Value
Underflow density kg/m3 1480
Underflow percent solids w/w 50%

 

17.6.5Carbon-in-leach plant

 

The thickened slurry is pumped to a pre-conditioning tank, where the pH is adjusted to a value greater than 10 by the addition of lime. The slurry flows by gravity from the pre-conditioning tank into the first of the carbon- in-leach (CIL) tanks.

 

The preconditioned slurry flows by gravity into the first of the 6 CIL tanks. The residence time of the slurry in each tank is 4 h. A solution of NaCN is pumped into the first tank. The slurry flows by gravity through from the first tank to the sixth tank. A screen with an aperture of 630 µm on each tank allows the slurry to pass while withholding the carbon.

 

Carbon is pumped from the regeneration circuit to the regenerated-carbon screen (sieve-bend), and into the sixth CIL tank. Each tank has a Kemix pump cell agitator for the transfer of carbon counter-current to the flow of slurry. Loaded carbon from the first CIL tank is pumped to the carbon acid wash area.

 

The design criteria for the carbon-in-leach section are given in Table 17.10.

 

Table 17.10 Design criteria for the carbon-in-leach section.

 

Criteria Units Value
Slurry feed rate m3/h 81
Pre-oxidation residence time h 3.5
CIL residence time h 21
Leach efficiency   91%
NaCN consumption kg/t 1.4
CaO consumption kg/t 4.0
Carbon loading g/t 800
Carbon residence time per stage h 24
Carbon flowrate t/h 0.17
Carbon concentration g/L (slurry) 14.42
Carbon pumping   16.7%
Soluble gold recovery   90%

 
 (VIRIMAI PROJECTS LOGO)Page 142
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

17.6.6Carbon Acid wash and Elution

 

Loaded carbon from the CIL circuit is pumped to the loaded carbon screen, where the ore solids are screened from the ore solids. The underflow from the screen is pumped back to the first tank of the CIL. The carbon from the loaded carbon screen is collected in the loaded carbon tank, slurried with water and pumped the acid wash column. The carbon is collected in the column, and the water is drained from the carbon.

 

A solution of dilute hydrochloric acid is pumped from the acid wash tank into the acid wash column and drained to the acid wash tank. The purpose of the acid wash is to remove impurities like Ca from the carbon. The carbon is then washed in water and transferred to the elution column.

 

The carbon is loaded into the elution column. The method of elution is of the Zadra type. Gold is eluted from the carbon using a dilute caustic soda/sodium cyanide eluent solution at an elevated temperature and pressure. The eluent is pumped through a series of heat exchangers to elevate the temperature to 135°C using a combination of the exiting eluent and boiler steam.

 

The eluent from the elution column is pumped from the elution column through a heat exchanger, which cools the solution to 35°C, to the electrowinning cells. Spent electrolyte from the electrowinning cells is returned to the eluent tank. Recycling continues until the gold in solution is depleted to a sufficiently low level.

 

The design criteria for tails screening is given in Table 17.11.

 

Table 17.11 Design criteria for the tails screening.

 

Criteria Units Value
Screen aperture µm 500

 

The design criterion for carbon elution is given in Table 17.12.

 

Table 17.12 Design criteria for carbon elution.

 

Criteria Units Value
Elution frequency per day No 1
Carbon mass per elution t 4.08
Eluant volume BV 4
Eluted carbon grade g/t 50
NaOH concentration % 2.5%
NaCN concentration % 3.0%

 

17.6.7Carbon regeneration

 

Carbon from the elution column is transferred to a dewatering screw, and then thermally regenerated at 700°C. Regenerated carbon is discharged into a quench tank, where it is mixed with process water, and pumped to the elution circuit.

 
 (VIRIMAI PROJECTS LOGO)Page 143
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

17.7Tailings treatment

 

The slurry from CIL is pumped to the tailings treatment plant, where it passes over a screen for the collection of carbon that might pass through the final tank screen. Any carbon collected on this screen is transferred to the elution section. The underflow from the screen is pumped to the cyanide detoxification section.

 

The cyanide detoxification section consists of a single tank into which the slurry is pumped. A solution containing ferrous sulphate is added to complex the free cyanide and a dilute solution of HCl is added to lower the pH. The slurry is pumped from this tank to the existing tailings dams.

 

The design criteria for the tailings detoxification are given in Table 17.13.

 

Table 17.13 Design criteria for tailings detoxification.

 

Criteria Units Value
FeSO4 consumption kg/kg NaCN 1.6
HCl consumptions m3/h 0.1

 

i.Reagents

 

The reagents to the process are NaCN, NaOH, CaO, FeSO4, and HCl.

 

The cyanide required in operation is made up by mixing solid NaCN supplied in bulk reagent in a make-up tank with process water. The cyanide solution is pumped into a holding tank and then pumped into with a ring main to the CIL and carbon elution areas.

 

Caustic soda is made up by mixing solid NaOH bulk supplied in reagent bags in with process water. This solution of caustic soda is pumped to the elution area.

 

Lime is required for neutralisation. It is made up by mixing CaO supplied in bulk reagent bags with process water. The resulting lime slurry is pumped into a holding tank and pumped from there to a ring main that supplies the CIL area.

 

Ferrous sulphate used for cyanide detoxification. A solution of ferrous sulphate is made up by mixing solid ferrous sulphate supplied bulk reagent bags with process water. The ferrous sulphate solution is pumped into a ring main to tailings treatment area.

 

Concentrated hydrochloric acid, supplied in from the isotainer, is pumped into a tank where it is diluted with process water. The dilute acid is pumped in a ring main that supplies the elution and tailings treatment areas.

 

17.8Utilities

 

Water is used as potable water, process water, cooling water and carbon transfer water in the elution section. Separate supply systems are provided for each of these uses.

 
 (VIRIMAI PROJECTS LOGO)Page 144
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

17.9Equipment

 

17.9.1General equipment selection

 

The equipment and its design capacity is listed in Appendix13. 2. This equipment list has bene costed to construct a capital cost estimate.

 

17.9.2EDS Mill

 

The process has been designed using tried and tested equipment, except for the EDS multishift mill.

 

Attention should be drawn to the selection of the EDS multishaft mill. This mill is of a vertical mill consisting of several horizontal shafts at various levels. The shafts drive internal fingers or flingers that accelerate the particles. The particles break due to impact with the rotating flingers, with the wall, or with the mill liners attached to the body.

 

The mill is shown in Figure 17. 3, and a view of the internal rotating flingers is shown in Figure 17.4. The mill has been tested both industrially and academically. The mill offers positive benefits in terms of plant footprint, high reduction ratio, and high throughput. Powell et al. (2016) concluded that their “study proved the mills’ ability to continuously sustain operation and product size for two different ore types under various configurations”.

 

(Figure 17.3)

 

Figure 17.3. The EDS multishift mill (Source: Jeff Wain, EDS).

 
 (VIRIMAI PROJECTS LOGO)Page 145
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 17.4)

 

Figure 17.4. A view of the internals of the EDS multishift mill seen from the feed chute. (Source: Jeff Wain, EDS).

 

The industrial applications of the EDS mill are listed in Table 17.14.

 

Table 17.14 Industrial applications of the EDS mill.

 

Criteria Units Value
Operation Site   Kalgold

WCM Mooi Nooi

De Hoek Rayton Marble hall
Owner   Harmony Samancor PPC Randquip Afrimat
Material   Gold ore Chrome ore Limestone Kimberlite Limestone
Start date   ~Apr 2013 ~Nov 2014 ~Dec 2014 ~Jan 2017 ~Sept 2016
Date ended   ~Oct 2013 ~Apr 2015 ~June 2015 ~July 2017 ~Nov 2016
Feed rate t/h 20 – 100 65 80 80 120
Feed size F80 Mm 26 18 28 15 12
Product size P80 Mm 1-5 2-3 2-3.5 1 2-3
Power consumption kWh/t 5 1.5 to 2 3-4 <2 <2
Availability   Unknown 85% 91 88% 6
Maintenance cost R/t Unknown 45 20 20  

 
 (VIRIMAI PROJECTS LOGO)Page 146
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

17.10Power consumption

 

The installed power is calculated from the installed equipment. The installed power for the oxide circuit is 1215 kW, and for the sulphide ore is 1428 kW.

 

17.11Summary and Conclusions

 

A feasibility level design (class 3, -15%/+20%) has been prepared for the Buckreef project. The status of the following items for this design is summarised in Table 17.15.

 

Table 17.15 Status of Buckreef design.

 

Item Requirement for
Class III estimate
Current Status
Plant capacity Fixed defined
Process selection optimised defined
Test work Finalised Defined – items that may be
considered are listed in Chapter 13.
Design basis Final defined
Process flowsheets Detailed completed
Process design criteria Detailed completed
Mass balances optimised completed
Process equipment completed list/sizied completed
Specifications Major equipment only completed
Layout optimised completed
GA drawings Full outlines completed

 

17.1Concluding Remarks

 

The current metallurgical testing being carried out by SGS Canada Inc will help incoming up with low cost gold processing flow sheets alternatives for the Buckreef Gold Project. The flow sheets alternatives will form the basis of the design and selection of the large processing plant for the project. This large processing plant will be then form the basis for the Company’s Final Feasibility 43-101 Report. Furthermore new approaches will need to be adopted with respect to the mill throughput and equipment selection and sizes in light of the increased resource level.

 
 (VIRIMAI PROJECTS LOGO)Page 147
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

18.PROJECT INFRASTRUCTURE

 

18.1Introduction

 

Buckreef being the largest pit, it will be most cost effective to setup the processing facility near the Buckreef pit. All satellite pits many times smaller than the main pit will result in long haulage of ore makes more economic sense if the processing infrastructure is setup at the Buckreef pit area. Presently, some of the basic infrastructure is present as left over from previous mining activities and from exploration camps. Most importantly also, there is a natural depression that can be modified and become suitable location for storing fresh water. There is an existing airstrip, but this will have to be relocated as it is situated at the edge of the current Buckreef main pit designed..

 

18.2Site Layout

 

Mine infrastructure at the mine will be required for smooth operation of the mine and the plant. Figure 18-1 shows overall site layout depicting major infrastructure.

 

Main additional infrastructures required for the project include the following: -

 

a.Primary Access Primary access to the site is via the Katoro Rwamagaza road which passes through the mine lease area. The road is a gravel road with a number of small bridges. This link road will need to be diverted away from the mining area.
b.Power Supply: The project is serviced by Tanesco the national power distribution company of Tanzania. The substation is currently being upgraded to provide power to the small oxide plant and back-up generators are being acquired to provide uninterrupted power for the plant.
c.Tailings Storage Facility (TSF) – The construction of the initial tailing storage facility to handle tailings from the small plant treating oxides from the Buckreef plant has been completed in compliance to the environmental standards of the country.
d.Fresh water dam – old water storage dam from previous mining has been rehabilitated for process water supply makeup water is supplied from the old underground mine through a submersible pump and line to the plant. Portable water for the mine complex is supplied from three boreholes sunk within the mine lease area.
e.Haulage Roads - Provisional siting shown in figure 18-1 illustrate haulage routes from the two distant satellite pits of Bingwa and Tembo which are respectively 5.6km and 4.2km in length. The haulage roads will follow existing local roads and will be upgraded to suit for frequent heavy trucks passage. Shorter haulage roads will be connecting Buckreef main pit and the near stockpile, waste and plant.
f.Waste Rock Dumps – Each mining pit site will have its own waste rock dump except that Buckreef and Eastern Porphyry will have a common waste rock dumping site.

 
 (VIRIMAI PROJECTS LOGO)Page 148
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(Figure 18.1)

 

Figure 18.1: Buckreef Project Infrastructure Layout (Emisha 2016; MaSS 2017)

 
 (VIRIMAI PROJECTS LOGO)Page 149
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

19.MARKET STUDIES AND CONTRACTS

 

19.1Market Studies

 

Neither Virimai Projects nor TRX has conducted a market study in relation to the gold market which will be produced by Buckreef Gold Project. Gold is a freely traded commodity on the world market for which there is a ready and steady demand from buyers worldwide.

 

19.2Contracts

 

There are no refining agreements or sales contracts currently in place that are relevant to this update Technical Report.

 
 (VIRIMAI PROJECTS LOGO)Page 150
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

20.ENVIRONMENTAL AND SOCIAL IMPACT STUDIES PERMITTING AND SOCIAL AND COMMUNITY IMPACT

 

20.1General Approach

 

TRX is committed to excellence in the management of health, safety environment and sustainability in the conduct of its operations. The company’s objectives are as follows:

 

Ensure the health and safety of its employees, contractors and visitors in the workplace.
Responsible management of the impact that its mineral exploration and development operation may have on the environment and the community.
Demonstrate its commitment to having sustainable development in the communities in which it is operating.

 

20.2Environmental Studies

 

Several environmental and environmental management plan studies have been performed on the project area. The environmental Scoping Studies for the project was conducted by URS from Australia in collaboration with MTL Consulting a local company. A Social Impact Assessment (SIA) was undertaken by Social Sustainability Services Ltd of Australia and the University of Dar es Salaam in 2006.

 

The environmental and socio-economic baseline for the project is documented in the Environmental and Social Impact Assessment (ESIA) performed by Enata Ltd 2014. This document was submitted to the NATIONAL ENVIRONMENT MANAGEMENT COUNCIL (NEMC). This report was approved by NEMC and an EIA certificate was awarded on 19th May 2014. The Enata Ltd ESIA was subsequently updated by Sphere Envirotech & Engineering Ltd, to reflect changes which were implemented from 19th May 2014 after the issuance of the Environmental Impact Assessment Certificate in compliance with Section 92 (1) of the Environmental Management Act No.20 of 2004 and the proposed future changes following mining operations changes.

 

The approved ESIA for the Buckreef Project covers areas which encompass the Buckreef Main, South and North, Eastern Porphyry, Tembo and Bingwa deposits.

 

20.3Community and Government Communications

 

Tanzam200 is an active member of the local community in Geita and Mwanza area and is in constant contact with the local and government leadership about developments on the Buckreef. The local leadership and the government leadership have been engaged in the planning activities for the project. This has been done through meetings with members of the local communities and ministry of mines

 
 (VIRIMAI PROJECTS LOGO)Page 151
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

20.4Overview

 

The Buckreef Project is primarily an undeveloped exploration project, although the project area includes the defunct Buckreef Mine area that was exploited by STAMICO until the mine closed in 1994. The historic mine site will ultimately form part of the future operation developed within the Buckreef Prospect. A couple of years of environmental baseline investigation have been completed on the project in support of the Buckreef Gold Project.

 

A summary of existing environment is provided herein and the intent of this summary is to give the reader a familiarization local setting of the area where the gold project is located. Further details of the baseline reports herein referred to are given in the referenced Environmental Assessment Reports.

 

i.Climate, Air Quality and Sound

 

The Buckreef Project is in the northwest region of Tanzania. The area has a moderately warm tropical climate with minimal variation through the year. Daily temperatures vary between 22oC and 30oC with a mean annual daily temperature of 25oC.

 

The region gets an average of 900 mm – 1200 mm of rainfall per annum. There are two distinct rainy seasons; the long rains or Masika from March to May and the short rains or Vuli from late September to December. The rainy seasons are characterized by short storm events, which lead to highly localized variations in rainfall. Storm events are often interspersed with relatively long dry spells. Between the two rainy seasons, is a long dry spell, occurring from June to August, which makes the area drought prone? During hot and rain season the humidity ranges between 35% and 60% respectively.

 

Evaporation remains relatively high throughout the year although daily evaporation rates decrease during the rainy seasons because of increased cloud cover. Average daily evaporation throughout the year varies between 4.5 and 7.2 mm/day (1,642.5 mm/yr.).

 

ii.Physiography, Soils and Geology

 

The project area topography consists of gently rolling hills at an elevation of 1200 to 1250 above sea level (amsl), with flat alluvium deposits and black cotton soil filled valleys. The average elevation difference is 50m on profiles north-south and east-west over 5km. This equates to an average elevation slope of 0.01m per km or 1%.

 

Most of the soils in the area are iron-rich due to the widespread presence of “cuirasse” or hard laterite on the property. In river valleys and drainages saturated, clay-rich soils known as Mbuga can be found but account for only a small proportion of all soils present.

 

In general, soils in the project area which have not been exposed to artisanal mining activities show no pollution in the form of mercury, cyanide, or heavy metals while soils located where artisanal mining has been conducted are often found to possess contaminant levels higher than established guidelines.

 
 (VIRIMAI PROJECTS LOGO)Page 152
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

A study was conducted on the stream water and sediment quality as well as on the groundwater quality in 2009 (Sphere, 2016). In terms of geochemistry the stream water and sediment quality concluded that:

 

Arsenic and Cr were above probable effects levels in stream sediments,
Sediment quality showed no enrichment in metals;
Mercury in sediment samples were below guideline values; and
Natural elevation of F, NO3, Al, Cr, Cu and Pb were above Canadian guidelines for aquatic life.

 

iii.Surface Water and Sediment

 

Surface water is scarce in the Project area but wetlands are developed in drainage channels. The main surface water flow in the project area is a dammed Nyamazovu River, a small stream to the west of the BRMA, which was used historically as a fresh water supply for the Buckreef process plant. Another important drainage channel is that of the Nyamazama stream, which forms a confluence with the Nyikonga approximately 12km to the southeast of Buckreef mine. Due to the low topographic relief of the area the river is extremely shallow, typically no more than 1-2 m in depth, but may reach a width of 50 m during the height of flow each year.

 

Considering the proximity of the rivers course within the Project area, Plans including the treating and recycling water from storm water storage have been considered. This is to save the wastage of water and ensure the surface run-off are directed and kept away from the operation consequently reducing chances of the interference to the mining activities as well as the stability of the Pit walls. A storm water management plan will be implemented for the Mine Project area to ensure that water resources are protected from pollution and that run- off is managed in accordance with the applicable environmental legal requirements. Storm water will be a valuable water resource and can be effectively used to decrease water use from water sources and thus potentially decrease costs.

 

20.5Groundwater Quality

 

Tests from the drill-holes show that ground water level depth is shallow at an average of 6.34meters below ground level (6.34mbgl). This suggests that only shallow structures and perhaps the unconfined aquifers were intersected. Nevertheless, assessment will focus on understanding the impact of excavating the open pit and abstracting groundwater on the hydro geological regime. The three pits (Buckreef, Bingwa and Eastern Porphyry) and the ROM Pad may be affected by the ground water from the two main rivers (Nyamazama and Nyamazovu). It is therefore important to make a frequent follow up on the soil behaviour and its contribution to the charge of the ground water.

 

20.6Biological Environment

 

20.6.1Vegetation

 

There are several vegetation zones in the project area. Their presence is strongly related to proximity to water and human activities. Barren land, shrub-steppe, grassland, and forest zones all occur naturally and generally correspond to the increasing presence of water.

 
 (VIRIMAI PROJECTS LOGO)Page 153
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The project area is still covered with categories of natural vegetation types with diversity of life forms including trees, shrubs, herbs, climbers, grasses, sedges and reeds. The most common vegetation in the project area is Acacia polyacantha woodland and Miombo woodland. Human activities in the form of agriculture, pastoralism, artisanal mining, and settlements areas to generate firewood have had a distinct impact on the vegetation in the project area.

 

Pastoralism is practiced widely with cattle, sheep, and goats foraging in the woods and plain areas as they are able, however, the quality of feed is poor. The potential for damage to an already fragile ecosystem from overgrazing is high.

 

20.6.2Wildlife

 

The area like most of the savannah areas is a very good habitat for several species of animals and birds. DikDik (Madoquaswaynei), lesser kudu (Strepsicerosimberbis) and greater kudu (Strepsicerosstrepsiceros) can all be found in the project area. It also includes the reedbuck, bushbuck, orb, hyena, serval cat, jackal, Nile crocodiles, short snouted crocodiles, baboons etc. Bird species include the shoebill (Balaenicepsrex). Other species are wattled crane (Bugeranuscarunculatus), ducks, geese, guinea fowls, bastards, plovers, vultures, Spur winged goose (Plectroptermsgumbensis).

 

20.6.3Human Environment

 

The Buckreef Project lies entirely within the Geita District in Geita region. The area is by large undeveloped tracts of land, poor infrastructure, and a largely rural population. There are three villages immediate to project area. The villages are Mnekezi located at the northwest and Kaseme at the west end of the project. Rwamagaza village which is the center for artisanal miners is located around five kilometres southeast of Buckreef mine.

 

The political environment in the country is stable with a growing influence of opposition parties in a country traditionally run on single party basis for decades. The parliamentary and presidential elections were held in October 2015. Generally, the elections were peacefully and successfully held in the country.

 

Currently there is no incident reported regarding the trespassing or intruding into the mine area.

 

The mine drilled a bore hole of water as one the community engagement project and the project has been handled over to the Mnekezi village authority.

 

The social license to operate will be greatly enhanced judging by the current response from different stakeholders that include villagers and their leaders, interfaith organizations, local and regional government and the government leaders at a national level.

 

20.6.4Population

 

Most of the residents in the project area belong to the Sukuma tribe. Rwamagaza village has many ethnic groups than Mnekezi. Apart from Sukuma tribe other tribes available in Rwamagaza are Waha, Wasumbwa,

 
 (VIRIMAI PROJECTS LOGO)Page 154
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Wachaga, Wakurya, Wajaluo and Wazinza whereas in Mnekezi village Wasumbwa and Wazinza make minor population. The local language spoken in the project area is Sukuma.

 

In 2012, the total population of Mnekezi village was approximately 1820. The largest village is Rwamagaza with a population of 3,202. These are the immediately villages which will be impacted by the proposed Buckreef mine.

 

It is notable that among the residents of the project area, 75% are under the age of 35 and more than 50% have an age less than 20. There are slightly more women than men. This demographic is amplified in the dry season when lack of rain makes it impossible to farm and young men of working age engage themselves in artisanal gold mining activities.

 

20.6.5Health

 

The most prevalent disease in the project area is malaria. Over 50% of all sickness treated in the region is malaria. HIV/AIDS is not only the threat to the health of the region’s population but also to the economic and social well-being of the people. Available statistics shows that the rate of HIV & AIDS infections in the region has been decreased from 8.2% to 4.5% in December 2011. The leading group due to infections is the youth group age aging between 15-24 years. Geita district had the highest number of reported AIDS cases accounting to 40.8% of all reported cases in the region. Nyang’hwale district had 872 cases equivalent to 4.1%.

 

Mnekezi has a dispensary staffed by four nurses and one doctor which serves residents of the project area. At Rwamagaza village there is a dispensary with one doctor and four nurses as well.

 

20.6.6Farming

 

Agriculture is by far the most prevalent form of employment in the project area. More than 77% of the labour force is engaged in subsistence farming. Crops most commonly grown are maize, paddy, cassava, beans, groundnuts, sorghum and sweet potatoes while the major cash crops are cotton and tobacco. Where sufficient water is available, rice and vegetables are also grown (in mbuga soil); both for personal consumption and as cash crops. Issues affecting the successes of farming in the project area include poor soil, and lack of equipment.

 

20.6.7Livestock

 

Livestock is the second most important economic activity in Geita Region. The climate of the region also favours growth of improved dairy breed particularly promotion of dairy cattle through cross breeding. The livestock kept in the region are cattle, goats, sheep, donkeys, pigs, chicken and ducks. Overgrazing is a common occurrence. Lack of pasture and veterinarians, and poor knowledge of sound livestock management practices all present challenges to cattle keepers.

 

20.6.8Commerce

 

Trade and commerce are an important activity. Rwamagaza market is held twice in a week, Tuesday and Friday. There are small shops, a crop and second-hand clothes market in Rwamagaza-CCM. For the surrounding

 
 (VIRIMAI PROJECTS LOGO)Page 155
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

villages, this is really a town with its several bars, eating places (migahawa) and guest houses. The centre is always full of people engaged in trading.

 

Katoro Township in the north is a big business centre providing manufactured goods as well as produce from local farmers.

 

20.6.9Gold Mining

 

Gold mining is a popular and well-organized activity regionally. Artisanal mining is an important and growing source of income in the project area. Miners are of two types: residents and migrants. Residents are local people, mostly women and children, who work local deposits by hand during the dry season when agriculture is limited or not possible. Migrants may be individuals who drift through the area hoping to find a likely spot to work or more often, bands of workers, organized, and financed by gold buyers.

 

Artisanal mining practices have already been hampered by the proposed Project, and illegal miners on the project will have to be removed once the project is implemented. Several small-scale operations in the area operating under Primary Mining Licenses provide employment to the local populations, and TRX will offer employment to the local population.

 

20.7Seismicity

 

Buckreef Gold Mine Project is located approximately 360 km north-east of the seismically active Lake Tanganyika Rift seismic zone. According to the Global Seismic Hazard Map produced by the Global Seismic Hazard Assessment Program (GSHAP, 2015), the site is in an area of low seismicity but borders an area of moderate seismicity about 67km in the Southwest.

 

The risk of catastrophic failure during a seismic event because of liquefaction of top soils and saprolite material is negligible as the natural water table lies well below the clay and saprolite zones. Nevertheless, potential instability because of seismic ground acceleration and loading on low shear strength defects cannot be ruled out. The seismic acceleration coefficient applicable to the site is between 0.04g and 0.08g for a return period of 475 years (10% chance of exceedance in 50 years). Further study at the final design stage is recommended to ensure the hazard from the nearby source zone of moderate seismicity to the east of the site does not warrant an increase in the peak accelerations quoted above.

 

A search of seismic events (from the USGS/NEIC 1973 – present database) indicated that there have been 16 earthquakes of magnitude 3 or above since 1973 within a 300-km radius of the site. The most significant event was a M5.3 event in December1983, the epicentre of which was 92 km from site. The most recent earthquake event in September 2016 in Bukoba, was a 5.9 magnitude in Richter scale and the epicentre was 40km deep. This area is about 240km northwest of the Buckreef Mine Area. It is considered that these peak accelerations experienced at Buckreef Gold Mine from this event would have been negligible.

 
 (VIRIMAI PROJECTS LOGO)Page 156
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

20.8Environmental Sensitivities

 

Based on information available there are no known Endangered Species within the Buckreef area. There are no wild life parks or protected land within the project footprint and as such no special permits will be required to proceed with the project. Further there no areas of natural scientific and archaeological interest to inhibit the development of the gold project.

 

20.9Regulatory Context

 

Mining operations has been taking place at Buckreef since 1990 until the underground mine closed down in 1994. Mining although on a small scale is the major source of income for the local communities in the area. Currently the Buckreef project site is fully compliant with the existing environmental laws of Tanzania. A copy of the EIA issued to Buckreef Gold Project is annexed in Appendix 20.1.

 
 (VIRIMAI PROJECTS LOGO)Page 157
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.CAPITAL AND OPERATING COSTS ESTIMATES

 

The capital estimates presented in this update report relate to the estimates presented in the prefeasibility study report of June 2018. No new capital and operating costs estimates could be developed for this ITR at this stage as new and processing flow designs for the Buckreef Prospect are still to be developed. The current prevailing economic factors have changed considerably from those presented in 2018 study. This will call for the revision of the costs in light of the material change in the mineral resources and the operating environment.

 

The capital and operating costs estimates developed for the update prefeasibility study are based on the development of an open pit mine and processing plant facility having a nominal processing capacity of 2880tpd ramped up to 4320tpd of ore feed at steady production in year 4. The estimates presented in this study relates to the open pit, processing plant and surface infrastructure developed by Virimai Projects with consultation with TRX. Capital and operating costs related to the gold processing plant have been developed by Emisha Solutions while costs for the TSF were developed by Epoch. Virimai Projects consultants consolidated the costs information from various sources to determine the project capital and operating costs.

 

21.1Capital Costs estimates

 

The capital costs estimates (CAPEX) for the Buckreef Gold Project has been prepared in accordance with industry practise for prefeasibility studies to intended accuracy of -15% to 20%. This estimate includes direct costs estimates based on current pricing for the common items required for the project of this nature. To establish current market pricing, various contractors, freight forwarders vendor and service providers were consulted in the process of compiling the capital estimates for the project.

 

21.1.1Pricing

 

The pricing of the capital costs build up for the supply of equipment are budgetary and not based upon binding quotations. These budgetary quotes where obtained from reputable vendors and contractors who provide unit rates or prices. The capital costs estimates are inclusive of all local tax components as applicable.

 

21.1.2Project Currency

 

All capital costs are expressed in US Dollars with costs based on the June 2018 market conditions with no escalation from that date. Costs submitted in Tanzanian Shillings were converted into US Dollars at the prevailing exchange rate of TZS 2,250 =US$1.00 used in this study.

 

21.1.3Capital Costs Summary

 

The projected capital cost estimates for the project are estimated to be US$76.336Million inclusive of a 15% contingency sum for the Buckreef Gold Project. Taxes and land acquisition permitting licensing are included. The project capital costs summary is outlined in table 21.1 with all the capital cost breakdown descriptions.

 
 (VIRIMAI PROJECTS LOGO)Page 158
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 21.1 Summary of the Capital Costs estimates

 

Item Capital Description No Unit Cost Total
Capex
1 Mining      
1.1 Mining Equipment ( Fleet) 1   17,531,424
1.2 Loader 3 265,500 796,500
1.3 Water Truck 1 100,000 100,000
1.4 Service Truck 1 100,000 100,000
1.5 Light Trucks & Cars 8 41,500 332,000
1.6 Dewatering Pump 4 40,000 160,000
1.7 Survey Tools 1 45,000 45,000
1.8 Pit Optimisation 1 75,000 75,000
1.9 Mining Offices/Shop 1 300,000 300,000
1.1 Haul Roads 1 100,000 100,000
1.11 HME - Workshop Construction 1 700,000 700,000
1.12 Explosive magazine 1 150,000 150,000
1.13 Fuel Tanks with a Capacity to hold 400klt 1 240,000 240,000
  Subtotal Mining     20,629,924
2 Processing Plant      
2.1 TSF Construction & Design 1 1,750,000 1,750,000
2.2 Portable Water Plant 1 600,000 600,000
2.3 Laboratory 1 500,000 500,000
2.4 Process Plant Development 1 35,284,625 35,284,625
2.5 Generators 4No x 2.5MVa 1 1,100,000 1,100,000
2.6 Substation and Power Reticulation 1 500,000 500,000
2.7 Engineering Workshop for Plant +tools 1 400,000 400,000
  Subtotal Processing Plant     40,134,625
3 Human Resources & Community      
3.1 Camping Facilities 1 250,000 250,000
3.2 Camp Houses (2Bx20+4Bx30) 50 15,000 750,000
3.3 Relocation of Mnekezi road 1 250,000 250,000
3.4 Airport/Aerodrome 1 35,000 35,000
3.5 Helicopter Pad 1 10,000 10,000
3.6 Compensation - Relocation from SML 1 2,500,000 2,500,000
3.7 Sewer Ponds & Facilities 1 350,000 350,000
3.8 Security fencing 1 520,000 520,000
  Subtotal Human Resources & Community     4,665,000
4 HSE      
4.1 Clinic 1 100,000 100,000
4.2 Waste Handling Facilities 1 75,000 75,000
  Subtotal HSE     175,000
5 Finance + IT      
5.1 Computer & Server 1 40,000 40,000
5.2 Desktop 1 45,000 45,000
5.3 Laptop 1 30,000 30,000
5.4 Networking & Communication 1 40,000 40,000
5.5 Process Plant Insurance - 6% Plant Cost 1 600,000 600,000
5.6 Mining Equipment Insurance - 2.5% Equip Cost 1 19,913 19,913
  Subtotal Finance +IT     774,913
6 Contingency 15% 15%   9,956,919
7 Total Capex     76,336,381

 

21.1.4Open Pit Mining Capital Cost Estimate

 

Open pit mining equipment will be owned and operated by the mine to carry out all the mining operations and related activities at Buckreef. Virimai Projects has not carried out an option analysis on owner mining versus contractor mining as the client preferred owner mining to contract mining. The acquisition of the mobile mining equipment is phased in line with the ramp up in production of the Buckreef project. The total capital for mobile

 
 (VIRIMAI PROJECTS LOGO)Page 159
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

equipment is estimated at US$20Million. The quotes for the supply of the earthmoving equipment are based on quotes from Bell Equipment a major equipment supplier in Tanzania.

 

21.1.5Process Plant Capital Costs

 

The design of the processing plant and associated infrastructure was carried out by Emisha Metallurgical Consultants (Emisha). Using their experience and the general layout and drawings Emisha developed estimates capital costs in the sum of US$35.285million for the procurement and installation of the processing plant facilities as defined in the flow sheet diagrams in Appendix 13. Other plant related costs and equipment as itemised in table 21.1 have been included the costs to bring it to a sum total of US$39Million.

 

21.1.6Tailings Storage Facility

 

Tailings Storage Facility is the other major component required to support the Buckreef Gold project. In coming up with the capital estimates for the facility the following philosophy was adopted in guiding the design of the tailings storage facility (TSF).

 

Economical Stage 1 development of the TSF
Efficient use of area and use of local construction materials
Maximum water recovery; and
Minimum environmental impacts (location relative to streams, dams)

 

The estimate design costs are included in the TSF Capital costs and the construction costs are estimated by DE Cooper Associates Geotechnical Engineers as a sum of US$1.75Million for stage 1. Stage 2 and subsequent TSF facilities have been assumed in this study to be financed from operating capital.

 

21.1.7Surface Infrastructure

 

In support of the mining operation Buckreef will aim at housing its employees in camping facilities to be built on the project premises. Most of the project employees will be recruited from the nearby surrounding villages and town centres. The surface infrastructure required to support the Buckreef Project is fully outlined in section 18.3 of this report. The total estimate for these facilities is given in table 21.1.

 

21.1.8Primary Access Roads

 

The capital costs estimates for the road works were based on the preliminary BOQ of the earthworks and storm water drainage systems required to divert the road which currently passes through the mine. The Geita District Council had put plans for the diversion of the gravel road away from the mine site. However, Buckreef have set aside funds to assist the council in expediting the construction work. Quotes received for the works put the total upgrading and diversion costs at US$250,000.00.

 

21.1.9On-Site Roads

 

All site road construction within the mine will be constructed as part of the pit excavations and utilising hard waste material from the pits. A provision has been made for a sum of $100,000 to cater for some roads which are not related to the mining activities.

 

21.1.10Airstrip

 

The cost of US$45k for the construction of a new gravel airstrip is based on the use of current mine equipment in clearing and compacting the runway.

 
 (VIRIMAI PROJECTS LOGO)Page 160
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.1.11Office Buildings and Workshops

 

The costs of building up the camp facilities, operations and maintenance buildings, plant and open pit buildings are based on the Tanzanian rebuilding costs of the defined structures. The estimate rebuilding costs for the steel structure with brick cladding under IBR roofing in Geita Town range from US$500/m2 to 750/m2 while that for camp and housing facilities range from US$250 to US$350/m2. Using these factors Virimai Projects was able to estimate the capital costs for putting up the proposed infrastructure at Buckreef as itemised in table 21.1.

 

21.1.12Laboratory

 

In addition to the cost of putting up the building there will be the cost of equipping the laboratory with state of the art equipment for use in assaying samples from the plant and for grade control in the pits. The full estimate costs for the construction and equipping is a total of US$0.5Million.

 

21.1.13Fuel Storage facilities

 

The cost of the fuel tanks is based on installation of above ground fuel storage tanks of 50,000lt capacity each at $30,000 each.

 

21.1.14Explosives Magazine

 

The magazine construction is based on reinforced concrete structure under a reinforced concrete roof for storage of explosive material. In view of the amount of oxides ore material to be mined at Buckreef a view was taken that this capital cost will come late in the life of the project in year 2 or 3.

 

21.1.15Power Plant and Distribution

 

The total requirement for the mine at peak production is estimated at 4.5MVA supplied from the national grid and backed up with a number of diesel generators. A total of 5No 1.6MVA generators will be purchased to back up power supply to the project TRX has been assured that enough grid power will be available for the mine requirements. The estimate costs for the power plant and the substation for the mine is summarised as sum of US$1.1Million. This cost is inclusive of power lines used to deliver power to various locations within Buckreef Gold Project area.

 

21.1.16Fresh Water Supply, Fire Suppression Water and Distribution

 

Buckreef portable water supply will be met through additional boreholes drilled on mine site including an additional water purification unit for the mine complex. The total cost of the new system is US$300,000 with the total for the two units coming to $600k.

 

21.1.17Sewage Collection and Disposal

 

In keeping with the environmental philosophy of the mine capital estimates for modern collection of all mine sewer through sewer line to the stabilisation ponds has been provided for. The treatment process facility consisting of stabilisation ponds catering for a mine population of say 500 people at a time have been estimated at US$350,000

 

21.1.18Site Security

 

A high-level security fence will be constructed to enclose the main Buckreef operations which include the camp site, process facility and open pits and tailings storage facility. In view of the local invasion of mining areas by

 
 (VIRIMAI PROJECTS LOGO)Page 161
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

small scale miners the need for security perimeter fencing around the pits becomes more critical. The total perimeter fencing for the Buckreef main is 16km and for Tembo and Bingwa pits the perimeter fencing is 2km each. The estimate cost of installation of 1.8m high diamond mesh security fence at US$26/m for the project is a sum of US$520,000.

 

21.1.19Rehabilitation and Mine Closure Costs

 

It has been assumed in the study that progressive rehabilitation will be carried out as development of the mine is been carried out. These costs have been considered as part of the mine operating costs at a unit rate of $0.03per tonne of waste mined. However some capital costs have been factored in to come in two or so years from the end of life of the mine for the removal of some of the mine infrastructure, equipment and plant at the end of the project. This capital sum has been estimated at US$4.5Million. To reduce the overall costs of plant and equipment removal, scrap steel dealers will be engaged to recover most of the steel on site for resale.

 

21.1.20Sustaining Costs

 

Sustaining capital is the periodic addition of capital required by the gold project to maintain operations at existing levels of production. The main components of sustaining capital required for the Buckreef relates to the replacement of aging equipment during the life of the project. With TRX concurrence, this capital has been pegged at 7.5% of start-up capital per year.

 

21.2Operating Costs

 

21.2.1Introduction

 

The operating costs estimates include all recurring costs for labour, service contractors, mine operation maintenance parts and supplies, consumables supplies, freight transport etc to operate the facilities as described in the study. Operating costs is defined as any recurring expenditure which can be expensed in the tax year in which it is incurred.

 

The Buckreef mine and plant operating regime schedule is summarised as follows:

 

Two 12 hour shifts daily for the mining operation.
Salaried staff will be paid monthly including vacation
Hourly personnel will be paid hourly excluding vacation

 

Operating expenses commence with the introduction of feed into the plant in year 1

 

The operating costs are summarised as follows:

 

Mining
Process
Power
Tailings
Labour
General & Administration (G&A)

 

All costs details were developed for a typical year and extended over the years of operation. The estimates are considered complete in terms of the scope and allowances for all the planned and anticipated events, activities and occurrences throughout the life of the Buckreef project. The level of estimate detail was determined by the general significance of the item and its cost and the degree of definition available.

 
 (VIRIMAI PROJECTS LOGO)Page 162
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.2.2Scope

 

The recurring annual operating expense estimate includes all labour, spares supplies, services, logistical and turnaround costs to mine, process and service the operation for a nominal 1.5Mt ore per year operation. It includes all costs to be incurred by TRX management organisation and includes all activities from the start of mining operations through to gold product transfer to the buyer.

 

21.2.3Mining Operating Costs

 

The Buckreef Mine operating costs encompass the labour material/supply/power costs incurred in the mining and haulage of RoM ore to the processing plant. These mine operating costs include the costs associated with the typical surface mining activities (such as drilling, blasting, load and haul of waste and ore), maintenance and operational support for the mining operations, grade control, rehabilitation and direct supervision of the mining operation.

 

To allow for a more thorough analysis and reporting of the mining operations expenses, costs were aggregated separately for each of the primary mine functions, drill and blast, load and haul and rehabilitation.

 

Table 21.1 Summary of the Mining Operating Costs

 

Description Unit Rate $/t Comment
Drilling and Blasting Waste $/t 0.74 Based on Virimai Estimation
Drilling and Blasting Ore $/t 0.90 Based on Virimai Estimation
Load and Haul Ore $/t 1.13 Based on Virimai Estimation
Load and Haul waste $/t 1.03 Based on Virimai Estimation
Overhaul rate $/t/km 0.08 Based on Virimai Estimation
Mine Rehabilitation (Pits & Dumps) $/t 0.03 Based on Virimai Estimation
Note 0.1 km per 10m bench at 10% grade.

 

21.2.4Labour Costs

 

Buckreef Mine labour requirements were estimated using a zero-based approach with the annual staffing levels for the mine determined by the level of deployment of staff to manning various sections of the operations of the Buckreef Gold Project. Most of the labour will be employed in the pits and in the processing plant. The main departments of the Buckreef will comprise of the following sections each headed by a departmental head.

 

Management
Open Pit Operations
Engineering
Technical Services
Processing Plant and Metallurgy
Safety Health and Environment
Human Resources Management
Administration and Accounts

 

A total staffing level estimated for the Buckreef operation is about 307 employees ranging from salaried staff to hourly paid employees. The annual cost labour costs at full production is estimated at USD$2.87Million which works out at US$1.98/t based on annual ore production of 1. 497Mt.The full schedule of assumed staffing levels of the project over the life of the project is summarized in table 21.2.

 
 (VIRIMAI PROJECTS LOGO)Page 163
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.2.5Security Costs & Other Licenses

 

Mine security will be provided by Tanzanian local company which has provided security over the exploration projects of the company over the last 10years. In addition to the local security company the Tanzanian national police will be contracted for periodic security duties for the security of the gold product. The annual costs of security in Tanzanian shillings are in the sum of TZS1, 007 Million and have been converted to US$448k at the current exchange rate of TZS2,250 to 1US$. This equates to about US$0.29/t of ore milled at full production.

 

21.2.6SHE & Licenses

 

During the operation of the mine a number of licenses are required for the abstraction of water, landfill permits etc and the operation of aerodrome to the Tanzanian Government air traffic control authority and annual audits stipulated by the Environmental Management Agency of Tanzania in the Buckreef EIA certificates. These costs are estimated at about at TSZ580Million per year which at current rate of exchange is US$0.17/t milled at the planned production rate of 1.5Mtpa.

 

21.2.7Open Pit Mining

 

Mine operating costs were estimated assuming all mining functions would be directly performed by the owner using company owned equipment and company employees. All mining will be carried out using a fleet of hydraulic excavators loading into 40tonne capacity articulated dump truck. The mining costs relate to the running cost of the mining mobile equipment which include for the fuel, maintenance (spares and labour), operators and other consumables.

 

Table 21.2: Mining rates for the Buckreef

 

Item Description Unit Rate
3 Load and Haul Ore $/t 1.13
4 Load and Haul waste $/t 1.03
5 Overhaul rate $/t/km 0.08

 

21.2.8Power

 

The power supply estimate is based on the use of combination of grid power from Tanesco and diesel generators powered by diesel fuel at an assumed ratio of 80% and 20% respectively. The current grid power cost from Tanesco is 159TZS /kWhr which equates to US$0.07/kWhr. The inclusion of generators is to provide backup power for the operations in the case of power outages. The operating load estimate for the plant and other mine facilities has been developed based mostly on equipment sized in the study. Price of power used in this update study for the Buckreef is a weighted average of the grid and generator power at ratio of 80% to 20% grid supply and diesel power supply respectively.

 

21.2.9Fuel Cost

 

The fuel cost includes selling price at source plus taxes and transport cost for delivery at the mine site. The current delivery price of diesel fuel to the mine from the Mwanza is at US$1.20/lt. All fuel costs have being captured in the other respective costs centres like mining and processing.

 
 (VIRIMAI PROJECTS LOGO)Page 164
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.2.10Process

 

The processing operating cost estimates were prepared from quotes presented by various suppliers and on metallurgical test results on reagent consumption levels. The metallurgical test results on which the costs are based on are from Emisha Metallurgical Solutions and the metallurgical tests results from CN Solutions. Based on the current test results and reagent consumption levels this update study has estimated the process operating costs at US$ 10.24 /t of ore milled. The process plant has been designed in three modules of 60tphr capacity each sized to process 3888tpd in total with an availability of 90%. The costs include the costs of direct process operations, labour, consumables and reagents maintenance and laboratory assay costs. A detailed process operating reagent cost estimate is provided in table 21.3.

 

Table 21.3: Processing Chemical Consumption & Cost estimation

 

Item Description Unit Cons
Kg/t
Unit price
$/kg
Costs
$/tRoM
1 Flocculent kg/t 1.085 0.2 0.217
2 Lime kg/t 1.01 3 3.031
3 Cyanide kg/t 0.007 0.68 0.005
4 HCL kg/tc 0.213 1.27 0.27
5 NaOH kg/tc 0.001 3.78 0.004
6 Carbon kg/tc 0.036 22.73 0.814
7 Ferrous Sulphate kg/t 8E-04 1.2 0.001
8 Diesel kg/t 1.085 0.2 0.217
9 Total Consumable Costs $/tRoM 4.39

 

21.2.11Tailing Storage Facility (TSF)

 

The TSF operating costs were developed and provided by Fraser Alexander of South Africa and the estimate operating costs cover routine maintenance and servicing of the TSF infrastructure which include the earthworks related tailings and water handling systems presented in the update study report.

 

Table 21.4: Annual TSF Management Costs

 

Description Annual Costs
$/yr
Unit Cost $/t
TSF management 84,375 0.06

 

The prices of liners and steel balls in the crushing and grinding section of the plant are based on vendor data and industry standards. In summary the processing costs estimates are given in table 21.5.

 

Table 21.5: Summary of Processing Costs estimates

 

Item Description Unit Rate
1 Processing reagents $/t 4.39
2 General spares & mechanical consumables $/t 0.52
3 General spares and consumables $/t 1.66
4 Power $/t 1.56
5 Process Labour $/t 1.76
6 TSF management $/t 0.06
7 RoM Ore Re-handle $/t 0.28
8 Processing Costs $/t 10.23

 
 (VIRIMAI PROJECTS LOGO)Page 165
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

21.2.12Labour Costs

 

Buckreef Mine labour requirements were estimated using a zero-based approach with the annual staffing levels determined by the level of manpower requirements dictated by the production sequence. The manpower requirements necessary for the operation which is inclusive of supervising the mining operations in the pits, running the processing plant and the other production support facilities were based on the respective operating shifts. The engineering staffing levels were based on Virimai Projects engineering experience in the allocation of manning levels to maintain the facilities and the equipment on the project. Support labour and mine supervisory personnel were assigned in accordance with manning conventions at other Tanzanian mines and as deemed necessary to adequately support the production requirements of the Buckreef Project.

 

The total annual salaries and wage for labour at the mine were based on salary information provided by TRX and Table 21.6 is the summarised annual cost by section of the mine.

 

Table 21.6: Labour and General Costs Summary

 

ITEM CATEGORY NO Annual USD
1 Management 3 162,000
2 Mine Operation 111 385,800
3 Mining Engineering 42 558,000
4 Technical Services 15 297,600
5 Process Plant 18 60,000
6 Safety, Health & Environment 8 201,600
7 Metallurgical Laboratory 6 80,400
8 Human Resources 12 132,000
9 Purchasing 7 74,400
10 Accounting 11 210,000
11 Camp 28 127,200
12 TOTAL 261 2,289,000
13 Skills Development Levy 5% 103,005
14 Workers Compensation Fund 1% 22,890
15 Company social contribution 10% 228,900
16 SUB TOTAL   2,643,795
17 Other Non-Labour G& A 10% 228,900
18 GRAND TOTAL   2,872,695
19 Annual Tonnage   1,450,656
20 UNIT LABOUR COSTS $/t 1.98

 

21.2.13Summary

 

On the basis of estimated steady state production of 1,497,000tpa of ore milled the average operating costs for the mine at Buckreef are summarised in table 21.7. This cost is not inclusive of additional costs required for exploration for the addition of more resources to the reserve pipeline in order to sustain the mine to the end of the life of the station. Further these costs are not inclusive of the overhead costs incurred by the head office in Toronto.

 
 (VIRIMAI PROJECTS LOGO)Page 166
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 21.7: Operating Costs Summary

 

Item Description Unit Rate
1 Mining Rates    
1.1 Mining Drilling and Blasting Waste $/tw 0.90
1.2 Mining Drilling and Blasting Ore $/to 1.20
1.3 Load and Haul Ore $/to 1.88
1.4 Load and Haul waste $/tw 1.88
1.5 Overhaul rate $/t/km 0.08
2 Processing Rates    
2.1 Processing reagents $/to 5.07
2.2 General spares & mechanical consumables $/to 2.05
2.3 RoM Ore Re-handle $/to 0.28
3 Power (Diesel Generators) $/to 3.11
4 TSF Management $/to 0.06
5 Labour Costs & General Costs $/to 1.98

 

Note: to = tonnes of ore material tw =tonnes of waste material

 

In the cash flow model, the unit costs of material were used in determining the net annual cash-flows based on the scheduled tonnages of materials from the each of the pits of Buckreef Project.

 
 (VIRIMAI PROJECTS LOGO)Page 167
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

22.ECONOMIC ANALYSIS

 

The new mine optimisation and design on the Buckreef Prospect based on the updated Mineral Resources is still to be commissioned. The metallurgical testing of the fresh rock samples at SGS Canada Inc to provide critical flow sheet and design information for a large plant is will take up to six months. These two exercises will form the basis economic analysis of the Final feasibility NI43-101 Report to be commissioned by TRX on the Buckreef Gold Project. Notwithstanding that the full feasibility study is still to be commissioned Mr Kutekwtekwa outlines the economic analysis carried out in 2018 in support of the Mineral Reserves estimated in 2018 Prefeasibility study.

 

22.1Cash-flow Model

 

A cash flow model was developed by Virimai Projects to allow a after-tax economic evaluation of the Buckreef Gold Project to be carried out. The model was subsequently reviewed by TRX to ensure that all cost considerations were catered for. As noted elsewhere all costs are stated in US Dollars and the cash flow and financial analysis are presented in June 2018 dollars and no provision of inflation was made in the model.

 

The capital and operating costs that were developed during the study were entered into the model and the annual cash flow forecasts were made on the basis of the scheduled tonnages and these cash-flows are shown in Table 22.1

 

As described elsewhere in the study report the mine is planned to operate for 15 years or more utilising surface mining. The surface mining operations begins in year 1 producing from the outcrops of the oxide ore areas in the pits. Surface mining reaches full production of 1.497Mtpa RoM in year four of starting operation.

 

A summary of the unit average operating costs used in the model are given in Table 21.4 in section 21 of the report.

 

22.2Discount Rate

 

The cash flow in the model was discounted at 3%, 5% and 8% per annum after tax. The current commercial lending rates worldwide are relatively low. TRX has been operating for many years in Tanzania without difficulty; and had good relations with all levels of authority. It has a partnership with Stamico, a state mining company; it has provided access to its properties to artisan miners and it has active and positive relations with local communities. After all the foregoing considerations, the base case discount rate for the project is therefore pegged at 5%.

 

22.3Tax

 

The financial analysis for the study was performed on after-tax basis. The Buckreef Project is subject to income tax at 30% of taxable income. Virimai Projects compiled the tax calculations for the

 
 (VIRIMAI PROJECTS LOGO)Page 168
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Buckreef with the assistance of Mr John Shimbala, a tax consultant and partner/director with Ark Associates Limited of Tanzania. Ark’s consent is shown in Figure 32.14 in the Appendices

 

The summary of Government taxes and levies used, where appropriate, in the computation of costs and the financial model is listed below for the record:

 

Table 22.1 Summary of Government taxes and levies used in costing and the Financial Model

 

Corporate Tax 30%  
VAT 18%  
Capital Gains Tax 10% Resident
Capital Gains Tax 15% Non-resident
Withholding Tax on Services 5% Local
Withholding Tax on Services 15% Foreign
Stamp Duty 1%  
Skills Development Levy 5%  
Workmen’s Compensation 1%  
Company Social Contribution 10%  
Gov. Royalties 6%  
Export Fee 1%  
Other Applicable Fees (Local Service Levy) 0.3%  

 

22.4Inflation

 

No inflation factor was applied to the analysis. The escalation of costs and revenues were assumed to be equal throughout the life of the project.

 

22.5Revenue

 

The projections of revenue are based on the quantity of gold produced at Buckreef based on the production scheduling as fully outlined in the study over the life of the project LoM at constant gold price of $1300/oz.

 

22.6Royalty

 

The Government of Tanzania has established that the state and district are entitled to receive royalties for the exploitation of mineral resources by holders of mining concessions. The government royalty rate for gold is currently at 6% arising from the sale of the gold product and the district council service levy is pegged at 1.3% of revenue.

 
 (VIRIMAI PROJECTS LOGO)Page 169
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

22.7Selling Costs

 

The gold selling costs as levied by the government is US$40/oz which is deducted directly from the proceeds of sales.

 

22.8Summary of the Parameters Used in the Financial Model

 

The following data was fed into a financial model built by Virimai Projects to carry out an economic assessment of the Buckreef Gold Project.

 

Table 22.2 Summary of the inputs into the Financial Model

 

DESCRIPTION UNIT VALUE
Total Ore (Mineral Reserves) (tonnes) 19,202,000
Grade (Mineral Reserves) (g/t) 1.54
Waste (In Pit) (tonnes) 180,707,000
Average Stripping Ratio   9.54
Production Rate Mtpa 1.497
In Situ Ounces (oz) 943,850
Mining Dilution % 5
Gold Price (USD/oz) 1,300
Discount Rate (%) 5%
Royalty Rate (%) 7.3%
Capital Costs USD($Million) 76.5
Expansion Year 1 USD($Million) 36.8
Expansion Year 2 USD($Million) 5.8
Expansion Year 3 USD($Million) 14.3
Expansion Year 4 USD($Million) 19.6

 
 (VIRIMAI PROJECTS LOGO)Page 170
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

22.9Financial Analysis

 

Table 22.3 below shows the full after-tax financial analysis:

 

Table 22.3: Financial Analysis of the Buckreef Gold Project

 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Ore Mining                                      
Oxide Ore (Tonnes) kt   349 188 57 209 73 30 159 66 309 118 21 - 41 2 8 - 1,629
Oxide Ore (g/t) g/t   2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 -  
Trans Ore (Tonnes) kt   92 151 136 133 106 78 40 28 82 309 270 52 17 6 21 - 1,520
Trans Ore (g/t) g/t   2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 -  
Hard Ore (Tonnes) kt   43 146 290 625 1,271 1,347 1,251 1,356 1,060 1,028 1,160 1,399 1,392 1,446 1,323 915 16,053
Hard Ore (g/t) g/t   1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70  
Oxide Waste kt   2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - - 20,155
Trans Waste kt   1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - - 20,346
Hard Waste kt   508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102 141,207
Oxide & Trans Ore Recovery % 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%  
Sulphide Ore Recovery   85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%  
Mining Dilution % 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%  
Gold produced                                      
Fine (kg) kg   876 869 677 1,208 1,878 1,621 1,468 2,225 1,989 2,405 1,599 1,433 1,595 1,924 1,535 1,258 24,559
Fine (oz) (1oz =31.1034768grams) koz   28,162 27,944 21,752 38,837 60,375 52,111 47,181 71,532 63,956 77,320 51,412 46,069 51,295 61,851 49,347 40,448 789,593
Gold price (US$000) $/oz 1300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300  
                                       
Gross revenue US ($000) 0 36,610 36,327 28,277 50,488 78,487 67,744 61,336 92,992 83,143 100,516 66,835 59,890 66,684 80,406 64,151 52,583 1,026,471
Less Royalties & Selling Costs                                     -
: Royalties 7.3% on Revenue   7.3% (2,673) (2,652) (2,064) (3,686) (5,730) (4,945) (4,478) (6,788) (6,069) (7,338) (4,879) (4,372) (4,868) (5,870) (4,683) (3,839) (74,932)
: Selling Costs per oz of gold   4.40 (124) (123) (96) (171) (266) (229) (208) (315) (281) (340) (226) (203) (226) (272) (217) (178) (3,470)
Net revenue     33,814 33,553 26,117 46,631 72,492 62,570 56,651 85,889 76,792 92,838 61,730 55,315 61,590 74,264 59,251 48,566 948,064

 
 (VIRIMAI PROJECTS LOGO)Page 171
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Capital Costs US ($k)                                    
Start up Capital     36,799 5,804 14,334 19,563                         76,501
Closure Costs U$                                 4,507 4,507
Sustaining Costs U$ 7.5% - - -   5,738 - - 5,738 - - 5,738 - - 5,738   - 22,950
Total Capital Costs U$ - 36,799 5,804 14,334 19,563 5,738 - - 5,738 - - 5,738 - - 5,738 - 4,507 103,958
Operating expenditure U$                                    
Mining Rates US ($k)                                    
Drill & Blast Waste $/tw 0.74 1,337 2,122 3,796 6,103 6,310 6,198 7,348 7,834 12,057 11,013 12,916 12,493 9,276 9,551 9,764 817 118,936
Drill & Blast Ore $/to 0.90 122 269 385 685 1,244 1,287 1,166 1,250 1,031 1,208 1,291 1,310 1,274 1,312 1,213 827 15,876
Load and Haul Ore $/to 1.13 544 546 544 1,088 1,632 1,637 1,632 1,632 1,632 1,637 1,632 1,632 1,632 1,637 1,520 1,030 21,609
Load and Haul waste $/tw 1.03 4,663 4,444 8,541 9,115 8,983 10,231 12,384 13,118 18,831 18,764 18,933 17,481 13,996 13,300 13,597 1,138 187,519
Overhaul rate $/t/km 0.08                                  
Mine Rehabilitation $/tw 0.03 136 129 248 265 261 297 360 381 547 545 550 508 407 387 395 33 5,451
Processing Rates                                      
Processing reagents $/to 10.24 4,952 4,966 4,952 9,905 14,853 14,894 14,853 14,853 14,853 14,894 14,853 14,853 14,853 14,894 13,836 9,370 196,646
Labour Costs $/to 1.98 958 960 958 1,915 2,872 2,880 2,872 2,872 2,872 2,880 2,872 2,872 2,872 2,880 2,675 1,812 38,023
Total operating costs US ($k)   12,712 13,436 19,424 29,076 36,156 37,425 40,616 41,942 51,825 50,941 53,048 51,151 44,310 43,960 43,001 15,026 584,048
Opex +Capex US ($k) - 49,511 19,240 33,758 48,639 41,894 37,425 40,616 47,679 51,825 50,941 58,786 51,151 44,310 49,698 43,001 19,533 688,006
Pre Tax Net Cash Flows US ($k) - (15,697) 14,313 (7,641) (2,008) 30,598 25,145 16,035 38,210 24,967 41,897 2,944 4,165 17,280 24,567 16,250 29,033 260,058
Taxable Income US ($k)   12,644 27,206 16,607 31,338 50,119 33,483 23,247 48,350 25,515 42,444 9,229 4,712 17,828 30,852 16,797 34,088 424,457
Tax Payable US ($k)   3,793 8,162 4,982 9,401 15,036 10,045 6,974 14,505 7,654 12,733 2,769 1,414 5,348 9,255 5,039 10,226 127,337
Net Cashflows after Tax US ($k)   (19,490) 6,151 (12,623) (11,409) 15,563 15,100 9,061 23,705 17,313 29,164 176 2,751 11,932 15,311 11,211 18,807 132,721
Add back Depreciation US ($k)   5,955 7,090 9,913 13,783 13,783 8,338 7,212 4,403 547 547 547 547 547 547 547 547 74,854
Net Cashflow after tax adjusted for tax dep US ($k)   (13,536) 13,240 (2,709) 2,373 29,346 23,438 16,273 28,107 17,860 29,711 723 3,298 12,479 15,859 11,758 19,354 207,575
After Tax NPV @ ( 3%) US ($k) 3%   156,552                              
After Tax @ NPV (5%) US ($k) 5%   130,964                              
After Tax @ NPV (8%) US ($k) 8%   101,495                              
After Tax IRR %     74%                              
Cash cost per oz $/oz   451 481 893 749 599 718 861 586 810 659 1,032 1,110 864 711 871 371 735
All in cash costs $/oz   1,758 689 1,552 1,252 694 718 861 667 810 659 1,143 1,110 864 804 871 483 933

 
 (VIRIMAI PROJECTS LOGO)Page 172
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

22.10Financial Analysis Summary

 

The results of the Buckreef Project’s economic analysis based on mining the identified open-pit Mineral Reserve, indicate a positive after-tax Net Present Value (NPV) of $130.96 million at a discount rate of 5% pa with an Internal Rate of Return (IRR) of 74% as summarized in Table 22.4 using a 30% Corporate tax rate.

 

Table 22.4: Results of the After-Tax Financial Analysis of the Buckreef Gold Project

  

Item Description Units Amount
1 Mining Profile    
1.1 Mineral Reserves (Prove +Probable) Mt 19.202
1.3 In situ Grade g/t 1.54
1.4 Waste in Pit Shell Mt 181
1.5 Mine Dilution % 5
2.4 Stripping Ratio in Area 1 waste/ore 9.54
2 Processing    
2.1 Annual Ore Milling Mtpa 1.497
2.1.1 Year 1-2 Mtpa 0.486
2.1.2. Year 3-4 Mtpa 0.972
2.1.3 Year 4-16 Mtpa 1.497
2.2 Life of Mine in Years Years 16
2.3 Gold Production    
2.3.1 Average Gold Production per year (oz) 51,000
2.3.2 Total Gold Production (LoM) (oz) 822,000
3 Capital Expenditure    
3.1 Start-up Capital Plant etc USD$ M 76.5
3.2 Sustaining capital costs USD$ M 22.95
3.3 Closure Costs (in Opex) USD$M 4.500
4 Financial Modelling Result    
4.1 Average LoM Cash Costs USD$/oz 735
4.2 After Tax NPV @ 5%pa USD$M 130.96
4.3 IRR % 74

 

22.11Financial Model Sensitivity Analysis

 

A financial sensitivity analysis was conducted on the base case cash flow net present value (NPV) and internal rate of return on the following variable: capital costs, operational costs, gold price, and recoveries. A deterministic sensitivity analysis was carried out by varying the input values and calculating the new net present value at discount rate of 5% pa. The input values where varied by up to plus and minus 20% on the follows:

 

Price of gold (revenue parameters)
Operating costs
Capital costs

 
 (VIRIMAI PROJECTS LOGO)Page 173
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

 
(LINE GRAPH)
 
 
Figure 22.1 Buckreef After-tax Sensitivity Analysis on NPV @ 5%

 
 (VIRIMAI PROJECTS LOGO)Page 174
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

23.ADJACENT PROPERTIES

 

The Buckreef project is situated within the Lake Victoria Gold Belt (LVGB), which is host to numerous small and a number of large scale gold mining operations as illustrated in figure 23.1.

 

 
(MAP)
 
 
Figure 23.1 Location of adjacent Gold Properties to Buckreef

 

The nearest large-scale gold mines projects are outlined as follows:

 

Geita Gold Mine: Located on the outer arc of the Lake Victoria Greenstone belt, Geita mine is an open pit and underground mine and is one of AngloGold Ashanti’s flagship mines. The mine has been in operation as a large-scale mine since the 1930s. Geita is an Archaean mesothermal, mainly banded ironstone formation (BIF)-hosted, deposit. Mineralization is found on sheared BIF-diorite contacts and in the diorite as well.
Tulawaka Mine (now Stamigold): Located on the western end of the inner arc of the Lake Victoria Greenstone ~50km due west of Buckreef Gold Mine, the Tulawaka gold deposit is hosted in a complex upper greenschist to amphibolite facies metamorphic terrain comprised of meta-sediments, including a minor component of meta-silicate-iron formation and meta-gabbro dykes or sills. The local stratigraphy has been folded into a large-scale Z-shaped fold that plunges to the south. The anticline portion of the fold has been cut by a thrust fault sub-parallel to the south-dipping fold axial plane. Gold occurs principally as free gold within quartz veins or stockworks, often associated with felsic intrusives.an exploration project and gold mine currently owned by STAMIGOLD a subsidiary of STAMICO.

 
 (VIRIMAI PROJECTS LOGO)Page 175
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Bulyanhulu Mine: Located ~50km east of the Buckreef Mine on the inner arc of the Lake Victoria Greenstone, the geology consists of mafic volcanic flows overlain by a series of pyroclastics and ash tuffs. Argillite is present at the contact between the mafic and felsic rocks. The gold, silver and copper mineralization on the property occurs in mineralized “reefs” or quartz veins localize along steeply dipping northwest striking structures, generally localized in the argillite units. The mine is owned by Barrick Gold Corporation.

 

The LVGB represents an important, large scale gold province in which regional mineralising systems have utilised rheologic, chemical and structural boundaries to remobilise and concentrate gold to produce economic deposits. Buckreef Project occurs in the LVG context with similarly suitable lithologic and structural features and theoretically therefore, could prove as potentially prospective.

 

The QP has not verified the public domain information with regards the Geita, Tulawaka and Bulyanhulu Mines and the information provided is not necessarily indicative of the mineralisation at Buckreef Project.

 
 (VIRIMAI PROJECTS LOGO)Page 176
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

24.OTHER RELEVANT DATA AND INFORMATION

 

Not applicable

 
 (VIRIMAI PROJECTS LOGO)Page 177
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

25.INTERPRETATION AND CONCLUSIONS

 

TRX has undertaken further detailed exploration diamond core drilling and sampling of the Buckreef deposit during the period January 2019 to February 2020 with the aim of upgrading the inferred resources within the pit shell generated by Virimai Projects in 2018 and to test for the mineralisation continuity down dip below the pit shells. All these activities have been undertaken by applying industry best standard methods and practices.

 

Sample collection and preparation has been done using industry best practises and analysis have been undertaken by certified laboratory resulting in results that support the Mineral Resource estimates as fully outlined in Chapter 14 of this update report. In light of the results of this resource update the QP recommend the advancement of the project to full Feasibility Study.

 

The project has positive attributes that justify the advancement some of which were fully outlined in the Amended ITR of 2018 (Virimai Projects 2018). These attributes include the following:

 

Increased inventory of mineral resources in the Buckreef Main.
Project location in the highest gold producing region of East Africa.
Metallurgical test work provides favourable indications that optimal gold recoveries can be achieved through cyanidation leaching of both oxides and fresh rock mineralization. Test work of samples of the both oxides indicates that recoveries in the order of 92% for oxides and 90% for fresh rock can be achieved.
The project can be developed in stages utilizing cash flows from free dig oxides mineralization to capitalize future fresh rock mining and processing of the deposit. The potential for transitioning from open pit to underground exists as indicated from the down dip mineral resources at depth which cannot be accessed through open pit mining.

 

The objective of Virimai’s mandate was to prepare an up Mineral Resource estimate for the Buckreef Project and prepare a supporting Independent Technical Report (ITR) in compliance with NI43-101 and CIM Definition Standards. After conducting a detailed review of all pertinent information and completing the mandate Virimai Projects concludes as follows:

 

Table 25.1 Comparison of Buckreef June 2018 and May 2020 Mineral Resources:

 

Prospect Measured Indicated Inferred Total Measured + Indicated
Tonnes Grade In Situ Content Tonnes Grade In Situ Content Tonnes Grade In Situ Content Tonnes Grade In Situ Content
(Mt) Au (g/t) Au (Oz) (Mt) Au (g/t) Au (Oz) (Mt) Au (g/t) Au (Oz) (Mt) Au (g/t) Au (Oz)
Buckreef June 2018 8.90 1.72 491,529 13.10 1.41 594,456 7.53 1.33 322,902 22.00 1.54 1,085,978
Buckreef May 2020 19.98 1.99 1,281,160 15.89 1.48 755,120 17.82 1.11 635,540 35.88 1.77 2,036,280

 

The data base supporting the 2020 Mineral Resource Estimate for the Buckreef Gold Project is complete, valid, and up to date (including historical drilling and current drilling 2019 program)
The geological and grade continuity of gold mineralization in the Buckreef deposit has been demonstrated and is supported by surface drilling carried out in the area.

 
 (VIRIMAI PROJECTS LOGO)Page 178
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

The mineral resource estimate is considered to be reliable, thorough and based on quality data and reasonable assumptions compliant with NI43-101 requirements and CIM Definitions Standards.
Mr Kutekwatekwa is of the opinion that the Mineral Resource Estimates results of the Buckreef Project support the recommendations to advance the project to a full feasibility stage.
Opportunities exist for new discoveries and to potentially add more mineral resources to the project.

 
 (VIRIMAI PROJECTS LOGO)Page 179
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

26.RECOMMENDATIONS

 

The project appears to have positive attributes that justify the advancement of the project and in that vein, that QPs would recommend the following follow:

 

8.To continue with the ultra-deep drilling programme to increased inventory of mineral resources down dip and the north east strike mineralization’s extend in the Buckreef Main in the identified explorations targets.
9.Complete the metallurgical testing of the fresh rock samples to identify the low costs alternative processing of the ores of the Buckreef Project.
10.To carry out rock geo-technical studies to see their impact the pit slope stability and possible underground mining options.
11.To carry out additional detailed metallurgical test work, on all significant lithological domains, to inform the gold recovery methods and the development of the processing flow sheet.
12.To recomputed the Mineral Reserves on the updated Mineral Resources in this report.
13.To proceed to the project full Feasibility Study.
14.To maintain a strict local legal compliance checklist for the project, in order to close any possible unreasonable political machinations.

 

Effective dated: May 15, 2020.

 

(-s- Wenceslaus Kutekwatekwa)    (-s- Frank K Crundwell)  
Wenceslaus Kutekwatekwa  Frank K Crundwell
BSc (Hons) Ming Eng. MBA  BSc(Hons) BSc(Maths) MSc(Eng) PhD. MBA 
FSAIMM, FIoDZ, MPMZ  FSAIMM, FChemI
    
CONSULTING DIRECTOR  METALLURGICAL CONSULTANT

 
 (VIRIMAI PROJECTS LOGO)Page 180
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

27.REFERENCE

 

Virimai Projects-Update National Instrument 43-101 Independent Technical Mining Reserve Estimate and Prefeasibility Study on the Buckreef Gold Project, Tanzania East Africa, June 2018

 

RSG Global, - Metallurgical Test-work Review and Recommendations for the Buckreef Project, July 2004

 

Metallurgical Project Consultants Pty Limited, - Phase 2 Metallurgical Test-work Summary, February 2007

 

Hellman & Schofield Pty Ltd (H&S), Estimates of the Gold Resources at Buckreef Prospect – Tanzania, June 2007

 

Sound Mining (SMS), Buckreef Gold Project Mining Study, - Preliminary Economic Assessment, January 2012

 

Venmyn Independent Projects (Pty) Limited, - National Instrument 43-101 Preliminary Economic Assessment of Tanzania Royalty Exploration Corporation’s Buckreef Gold Mine, Re-development Project in Tanzania, May 31st, 2012

 

ENATA LTD, - Environmental Impact Assessment for Gold Mining Project at Mnekezi Village in Geita District, Geita Region, Tanzania; February 2014

 

Venmyn Deloitte, - Update National Instrument 43-101, Independent Technical Report on the Buckreef Project in Tanzania for Tanzanian Gold Corporation; February 24th, 2014

 

Mark Noppe, - Reporting Mineral Resources and Ore Reserves – How Confident are we? – MINERAL RESOURCE & ORE RESERVE ESTIMATION bulletin, June 2014

 

Sphere Envirotech & Engineering (T)Ltd – Buckreef Gold Mine, Environment Management Plan (EMP) Update, January 2016

 

Tanzania Minerals Audit Agency: https://www.tmaa.go.tz - Accessed on 23rd January 2017.

 

MMSA Report No 15/059 r1 “Metallurgical testwork on oxide and sulphide gold bearing ore samples” by Juan van der Merwe, MMSA, 11 January, 2016.

 

Project 6011 “Phase 2 Metallurgical Test work Summary Project 6011” prepared by Peter Banovich of Metallurgical Project Consultants Pty Ltd, dated February 2011.

 
 (VIRIMAI PROJECTS LOGO)Page 181
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

28.ABBREVIATIONS GENERAL

 

ADT  as in ADT Truck, referring to rear articulated dump
    
ANFO  a site-mixed blend of Ammonium Nitrate (prills) & Fuel Oil (predominantly diesel, used as a
    
CoG  Cut-off Grade
    
CAPEX  Capital Costs Expenditure
    
DTM  Digital Terrain Model
    
EDS  Energy and Densification Systems
    
EIA  Environmental Impact Assessment
    
EPC  refers to Engineering, Procurement and Construction management of a project by a contractor
    
EMP  Environmental Management Plan
    
ESIA  Environmental and Social Impact Assessment
    
Hex  Hydraulic Excavator
    
JV  Joint Venture
    
IRR  Internal Rate of Return
    
NPV  net present value of a cash flow at a stated discount rate
    
OPEX  Operating Costs Expenditure
    
PFS  Preliminary Feasibility Study
    
ROMPAD  Run of Mine Ore Stockpile
    
RL  Reduced Level, referring to the height of a point above datum
    
ROM  Run of Mine, referring to excavated material that has not been further treated
    
RT  as in RT Dozer, referring to rubber tired Dozer
    
SR  Strip Ratio, being the tonnes of waste to be moved to expose a tonne of ore
    
TSF  Tailings Storage facility
    
TZS  Tanzanian Shilling

 
 (VIRIMAI PROJECTS LOGO)Page 182
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

29.MEASURES OF QUANTITY

 

bcm  bank cubic metre, being a volumetric measure of (undisturbed) rock
    
cm  cubic metre, used to classify the volume of loader buckets, truck size etc
    
ha  hectare, or 10,000 square metres
    
in-situ  refers to undisturbed (un-blasted, un-dug) material
    
k  as a suffix to a number refers to a thousand (103) units
    
kg  kilogram
    
km  kilometre
    
lcm  loose cubic metre, being a volumetric measure applied to, broken rock
    
m  as a suffix to a number refers to a metre length
    
M  as a suffix to a number refers to a million (106) units
    
m2  as a suffix to a number refers to a square metre of area
    
mm  as a suffix to a number refers to a millimeter
    
pa  as a suffix to a number refers to a value per annum
    
PF  Powder Factor, a measure of the kg of explosive to be blasted per tonne of rock
    
t  tonne, being a metric tonne of 1,000 kg
    
m.a.m.s.l  metres above mean sea level

 
 (VIRIMAI PROJECTS LOGO)Page 183
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

30.ORGANISATIONS

 

ARSM   Associate of the Royal School of Mines
     
CM   Commissioner of Minerals
     
GOT   Government of Tanzania
     
FSAIMM   Fellow of South African Institute of Mining and Metallurgy
     
LBMA   London Bullion Market Association
     
MEM   Ministry of Energy and Minerals
     
MSAIMM   Member of South African Institute of Mining and Metallurgy
     
MAusIMM   Member of Australian Institute of Mining and Metallurgy
     
MZIE   Member of the Zimbabwe Institution of Engineer
     
NEMC   National Environment Management Council
     
TRX   Tanzanian Gold Corporation
     
STAMICO   State Mining Corporation of Tanzania
     
USGS   United States Geological Survey
     
UNISA   University of South Africa

 
 (VIRIMAI PROJECTS LOGO)Page 184
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

31.GLOSSARY

 

Archaean  Geological eon – subdivision of the Precambrian 2.5Ga to 3.8Ga
    
Assay  A chemical test performed on a sample of ore or minerals to determine the amount of valuable metals contained.
    
Basalt  Fine grained mafic volcanic rock
    
Borehole  A hole drilled from surface or underground, in which core of the rock is cut by a diamond drill bit as the cutting edge.
    
Bulk sample  A large sample of mineralized rock, frequently hundreds of tonnes, selected in such a manner as to be representative of the potential orebody being sampled. Used to determine metallurgical characteristics. Large sample which is processed through a small-scale plant, not a laboratory.
    
Carbon-in-leach  The recovery process in which Au is leached from Au ore pulp by cyanide and simultaneously adsorbed onto activated carbon granules in the same vessel. The loaded carbon is then separated from the pulp for subsequent Au removal by elution. The process is typically employed where there is a naturally occurring Au adsorbent in the ore.
    
Conglomerate  Sedimentary rock comprising of pebbles in a finer grained matrix
    
Cross section  A diagram or drawing that shows features transacted by a vertical plane drawn at right angles to the longer axis of a geologic feature.
    
Cyanidation  Method of extracting gold by dissolving in potassium cyanide solution
    
Density  Measure of the relative “heaviness” of objects with a constant volume, density = mass/volume
    
Deposit  Any sort of earth material that has accumulated through the action of wind, water, ice or other agents.
    
Diamond drilling  A drilling method, where the rock is cut with a diamond bit, to extract cores.
    
Dip  The angle that a structural surface, i.e. a bedding or fault plane, makes with the horizontal measured perpendicular to the strike of the structure.
    
Dyke  Intrusive igneous rock vertically or sub-vertically emplaced.
    
Estimation  The quantitative judgement of a variable.
    
Exploration  Prospecting, sampling, mapping, diamond drilling and other work involved in the search for mineralization.

 
 (VIRIMAI PROJECTS LOGO)Page 185
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Exploration License/ Property  A Mineral Asset which is being actively explored for Mineral deposits or petroleum fields, but for which economic viability has not been demonstrated.
    
Facies  An assemblage or association of mineral, rock, or fossil features reflecting the environment and conditions of origin of the rock.
    
Fault  A fracture in earth materials, along which the opposite sides have been displaced parallel to the plane of the movement
    
Feasibility study  A definitive engineering estimate of all costs, revenues, equipment requirements and production levels likely to be achieved if a mine is developed. The study is used to define the economic viability of a project and to support the search for project financing.
    
Grade  The relative quantity or percentage of gold within the rock mass. Measured as grams per tonnes in this report.
    
Greenstone Belt  Archaean sequence of mafic and ultramafic rocks
    
Hanging wall  The overlying unit of a stratigraphic horizon, fault ore body or stope
    
In situ  In its original place, most often used to refer to the location of the mineral resources.
    
Indicated Mineral Resource  That part of a mineral resource for which tonnage, densities, shape, physical characteristics, grade and average mineral content can be estimated with a reasonable level of confidence. It is based on exploration sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are too widely or inappropriately spaced to confirm geological and/or grade continuity but are spaced closely enough for continuity to be assumed and sufficient minerals have been recovered to allow a confident estimate of average mineral value.
    
Inferred Mineral Resource  That part of a mineral resource for which tonnage, grade and average mineral content can be estimated with a low level of confidence. It is inferred from geological evidence and assumed but not verified by geological and/or grade continuity. It is based on information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that may be limited or of uncertain quality and reliability.
    
Laterite  Residual soil in humid climates form the leaching of silica and aluminium and enrichment in iron
    
Lava  Molten silicate material extruded by a volcano.

 
 (VIRIMAI PROJECTS LOGO)Page 186
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

License, Permit, Lease or other similar entitlement   Any form of license, permit, lease or other entitlement granted by the relevant Government department in accordance with its mining legislation that confers on the holder certain rights to explore for and/or extract minerals that might be contained in the land or ownership title that may prove ownership of the minerals.
     
Life-of- Mine/LoM   Expected duration of time that it will take to extract accessible material.
     
Liberation   Release of Au from the host rock through processing.
     
Lithologies   The description of the characteristics of rocks, as seen in hand-specimens and outcrops based on colour, grain size and composition.
     
Lode   Metalliferous ore that fills a fissure
     
Mineral Reserve   The economically mineable material derived from a Measured and/or Indicated Mineral Resource. It is inclusive of diluting materials and allows for losses that may occur when the material is mined. Appropriate assessments, which may include feasibility studies, have been carried out, including consideration of and modification by, realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction is reasonably justified. Mineral Reserves are sub-divided in order of increasing confidence into Probable Mineral Reserves and Proven Mineral Reserve.
     
Mineral Resource   A concentration of material of economic interest in or on Earth’s crust in such form, quality and quantity that there are reasonable and realistic prospects for eventual economic extraction. The location, quantity, grade, continuity and other geological characteristics of a Mineral Resource are known, estimated from specific geological evidence and knowledge, or interpreted from a well constrained and portrayed geological model. Mineral Resources are subdivided, in order of increasing confidence in respect of geoscientific evidence, into Inferred, Indicated and Measured categories.
     
    A deposit is a concentration of material of possible economic interest in, on or near the Earth’s crust. Portions of a deposit that do not have reasonable and realistic prospects for eventual economic extraction must not be included in a Mineral resource.
     
Measured Mineral Resource  

That part of a mineral resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a high level of confidence. It is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill-holes. The locations are spaced closely enough to confirm geological and grade continuity.

 
 (VIRIMAI PROJECTS LOGO)Page 187
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

MEM   Ministry of Energy and Minerals
     
Mineralization   The presence of a target mineral in a mass of host rock.
     
Mining Property   A Mineral Asset which is in production.
     
National Instrument 43-101   Canadian National Instrument on the reporting of exploration, mineral resources and mineral reserves for the TSX.
     
Opencast / Open pit   Surface mining in which the ore is extracted from a pit. The geometry of the pit may vary with the characteristics of the ore body.
     
Orebody   A continuous well-defined mass of material of sufficient ore content to make extraction economically feasible.
     
Overburden   The alluvium and rock that must be removed in-order to expose an ore deposit.
     
Porphyry   Fine grained igneous rock with large feldspar crystals
     
Probable reserves   The economically mineable material derived from a Measured and/or Indicated Mineral Resource. It is estimated with a lower level of confidence than a Proven Reserve. It is inclusive of diluting materials and allows for losses that may occur when the material is mined. Appropriate assessments, which may include feasibility studies, have been carried out, including consideration of, and modification by, realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction is reasonably justified.
     
Prospect   A deposit with the potential for economic extraction.
     
Pyrite   Fool’s gold a common yellow sulphide mineral, FeS. Pyrite forms under a wide range of pressure-temperature conditions, and so is found in many geological environments.
     
Quartzite   A metamorphic rock consisting primarily of quartz grains, formed by the recrystallisation of sandstone by thermal or regional metamorphism or a sandstone composed of quartz grains cemented by silica.
     
Recovered grade/Yield   The actual grade of ore realised after the mining and treatment process.
     
Reef   Mineralized lode.

 
 (VIRIMAI PROJECTS LOGO)Page 188
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Rehabilitation   The process of restoring mined land to a condition approximating to a greater or lesser degree its original state. Reclamation standards are determined by the Russia Federation Department of Mineral and Energy Affairs and address ground and surface water, topsoil, final slope gradients, waste handling and re-vegetation issues.
     
Rhyolite   One of a group of extrusive rocks commonly showing flow texture, and typically porphyritic, with phenocrysts of quartz and potassium feldspar in a glassy to microcrystalline groundmass.
     
Sample   The removal of a small amount of rock pertaining to the deposit which is used to estimate the grade of the deposit and other geological parameters.
     
Sampling   Taking small pieces of rock at intervals along exposed mineralization for assay (to determine the mineral content).
     
Saprolite   In situ weathered profile on laterite terrane where the soil comprises mostly clays
     
Sedimentary   Formed by the deposition of solid fragmental or chemical material that originates from weathering of rocks and is transported from a source to a site of deposition.
     
Specific gravity/S.G.   Measure of quantity of mass per unit of volume, density.
     
Stockpile   A store of unprocessed ore or marginal grade material.
     
Stripping   Removal of waste overburden covering the mineral deposit.
     
Stripping ratio   Ratio of ore rock to waste rock.
     
Subduction   The movement of one crustal plate (lithospheric plate) under another so that the descending plate is consumed.
     
Tailings   The waste products of the processing circuit. These may still contain very small quantities of the economic mineral.
     
Tailings dam   Dams or dumps created from waste material from processed ore after the economically recoverable metal or mineral has been extracted.
     
Tonnage   Quantities where the tonne is an appropriate unit of measure. Typically used to measure reserves of metal-bearing material in-situ or quantities of ore and waste material mined, transported or milled.
     
Trenching   Making elongated open-air excavations for the purposed of mapping and sampling.

 
 (VIRIMAI PROJECTS LOGO)Page 189
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Veins   A tabular or sheet like body of one or more minerals deposited in openings of fissures, joints or faults, frequently with associated replacement of the host rock.
     
Yield/Recovered grade   The actual grade of ore realised after the mining and treatment process.

 
 (VIRIMAI PROJECTS LOGO)Page 190
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.APPENDICES

 

32.1Certificate of Qualified Persons Certificate of Wenceslaus Kutekwatekwa

 

I, Wenceslaus Kutekwatekwa of Block 4, Tunsgate Office Park, 30 Tunsgate Road, Mount Pleasant, Harare, Zimbabwe, as author of the report (the “NATIONAL INSTRUMENT 43-101 Independent Technical Report, Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa For Tanzanian Gold Corporation (TRX)” with an effective date of May 15, 2020 (the “Effective Date”) and with an amendment date of June 8, 2020, do hereby certify that:

 

I am a senior mining engineer in Zimbabwe with Virimai Projects and hold the designation of Consulting Director.

 

I graduated with a BSc (Hons) degree in Mining Engineering from University of Zimbabwe in 1989.

 

I am a member/fellow of the following professional association

 

a.Fellow Southern African Institute of Mining and Metallurgy (SAIMM), membership number 703812.

 

b.Fellow Institute of Directors Zimbabwe (IoDZ), membership number ZW11768/13

 

c.Member Project Management Institute of Zimbabwe (PMIZ) membership number PMH132

 

I have worked as a mining engineer for 31 years since my graduation from university.

 

I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional organization (as described in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purpose of NI 43-101.

 

I visited the Buckreef property and spent a total of 96 hours, in three separate visits, visiting mine sites, test pit, test processing plant, analysing core and general ground truthing, looking at plans and technical data.

 

My latest, and third, visit of my personal inspection to the Buckreef property was from 19 to 22 February 2020.

 

I am responsible for all sections of this NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project Report, excluding Sections 13 and 17.

 

I have not received and do not expect to receive any interest, either direct or indirect, in any properties of Tanzanian Gold Corporation (the “Issuer”) and I do not beneficially own, either directly or indirectly, any securities of the Issuer.

 

I am independent of the Issuer as set out in section 1.5 of NI 43-101.

 

I have had prior involvement with the Buckreef property that is the subject of this NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project in 2018, when I co-authored the “Amended Independent Technical Mining Reserve Estimate Pre-Feasibility Study on the Buckreef Gold Mine

 
 (VIRIMAI PROJECTS LOGO)Page 191
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Project, Tanzania, East Africa” prepared for the then Tanzanian Royalty Exploration Corporation with an effective date of 26th June 2018.

 

I have read NI 43-101 and Form 43-101F1 and this NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project Report has been prepared in compliance with NI 43-101 and Form 43-101F1.

 

As at the Effective Date of this NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project Report, to the best of my knowledge, information and belief, the Report contains all scientific and technical information that is required to be disclosed to make the NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project not misleading.

 

I consent to the filing of the Technical Report with any stock exchange and other regulatory authority and any publication by them for regulatory purposes, including electronic publication in the public company files on their websites accessible by the public, of the Technical Report.

 

Dated June 8, 2020.

 

(-s Wenceslaus Kutekwatekwa)

 

 

 

Wenceslaus Kutekwatekwa

 

BSc (Hons) Ming Eng. MBA

 

FSAIMM, FIoDZ, MPMZ

 

CONSULTING DIRECTOR

 

Summary of Recent Experience

 

YEAR CLIENT COMMODITY TYPE OF
STUDY
PROJECT DESCRIPTION
2019 Mimosa Mining Company Platinum PFS Review on DRA, North Hill Projects
2018 Hanzu Gold DFS EPCM
2018 Anglo Platinum Unki Platinum Scoping Decline Access and
2018 Metallon Gold Gold PEA Scoping Study of Corporate Growth Strategy
2017 Samrec Vermiculite Vermiculite LOM Pit Optimisation Scheduling and LoM Planning
2017 Prospect Resources Lithium PFS Open Pit Optimisation design and Scheduling
2016 Global Platinum Resources Platinum PFS Green Field Project PFS
2015 Mimosa Mining Company Platinum LOM Scoping Study of the Mtshingwe expansion

 
 (VIRIMAI PROJECTS LOGO)Page 192
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Certificate of Frank K Crundwell

 

I, Frank K. Crundwell of 89J Victoria Drive, London, SW196PT, United Kingdom, am the author of the sections for metallurgical test work and recovery methods for the report (the “NATIONAL INSTRUMENT 43-101 Independent Technical Report, Updated Mineral Resource Estimate for the Buckreef Gold Mine Project, Tanzania, East Africa For Tanzanian Gold Corporation (TRX)” with an effective date of May 15, 2020 (the “Effective Date”) and with an amendment date of June 8, 2020, do hereby certify that:

 

1.I am a Director of CM Solutions (Pty) Ltd, a company registered in South Africa, and I am a Consulting Engineer with Crundwell Metallurgy Limited, a company registered in the United Kingdom.

 

2.I graduated with a BSc Engineering degree in Chemical Engineering from the University of the Witwatersrand, Johannesburg in 1983. I also hold MSc (Eng) and PhD degrees from the same university.

 

3.I am a member/fellow of the following professional association

 

i.Fellow of the Southern African Institute of Mining and Metallurgy (SAIMM), membership number 56496.

 

ii.A Registered Professional Engineer with Engineering Council of South Africa, registration number 20040172.

 

iii.Fellow of the Institution of Chemical Engineers, membership number 99963109.

 

4.I have worked as a metallurgical engineer for 36 years since my graduation from university in 1983.

 

5.I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional organization (as described in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purpose of NI 43-101.

 

6.I witnessed the bulk milling test work conducted using the EDS mill pilot rig in Johannesburg, South Africa.

 

7.I am responsible for the “Metallurgical test work” (item 13) and the “Recovery methods” (item 17) sections of the Updated Mineral Resources Estimates Buckreef Report.

 

8.I have not received and do not expect to receive any interest, either direct or indirect, in any properties of Tanzanian Gold Corporation (the “Issuer”) and I do not beneficially own, either directly or indirectly, any securities of the Issuer.

 

9.I am independent of the Issuer as set out in section 1.5 of NI 43-101.

 

10.I have had prior involvement with this Buckreef property that is the subject of this NI43-101 ITR - Updated Mineral Resources Estimate Buckreef Gold Project in 2018, when I

 
 (VIRIMAI PROJECTS LOGO)Page 193
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

co-authored the “Amended Independent Technical Mining Reserve Estimate Pre- Feasibility Study on the Buckreef Gold Mine Project, Tanzania, East Africa” prepared for the then Tanzanian Royalty Exploration Corporation with an effective date of 26th June 2018.

 

11.I have read NI 43-101 and Form 43-101F1 and the Amended Buckreef Report has been prepared in compliance with NI 43-101 and Form 43-101F1.

 

12.As at the Effective Date of the Amended Buckreef Report, to the best of my knowledge, information and belief, the Amended Buckreef Report contains all scientific and technical information that is required to be disclosed to make the Amended Buckreef Report not misleading.

 

13.I consent to the filing of the Technical Report with any stock exchange and other regulatory authority and any publication by them for regulatory purposes, including electronic publication in the public company files on their websites accessible by the public, of the Technical Report.

 

Dated June 8, 2020.

 

(-s- Frank Crundwell)

 

 

 

Frank Crundwell

 

BSc (Eng) Chem, BSc (Hons) Financial Maths, MSc (Eng) Chem, PhD,

 

Pr Eng, FSAIMM, FIChemE

 

DIRECTOR

 

Summary of Recent Experience

 

YEAR CLIENT COMMODITY TYPE OF STUDY PROJECT DESCRIPTION
2018 Horizon Mining Copper/cobalt DFS EPCM
2018 Anglo Platinum Platinum FS Pressure leaching
2018 Sumitomo Cobalt Scoping Optimization
2018 Undisclosed Nickel Consulting Board document
2017 Undisclosed Gold Metallurgical dispute Analysis, assessment
2017 Kansanshi Copper/gold Metallurgical test work Test work
2017 Undisclosed Gold/Sb Metallurgical test work Test work

 
 (VIRIMAI PROJECTS LOGO)Page 194
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.2Consent to publish

 

Frank K. Crundwell

 

I Frank K Crundwell consent to the filing of the Technical Report titled “National Instrument 43-101 Independent Technical Report Update Mineral Resource Estimate for the Buckreef Gold Mine Project Tanzania East Africa.”

 

I Frank K Crundwell certify that I have read (i) the “National Instrument 43-101 Independent Technical Report Update Mineral Resource Estimate for the Buckreef Gold Mine Project Tanzania East Africa” dated 15th May 2020 by Virimai Projects and (ii) the news release of Tanzanian Gold Corporation dated March 17, 2020, and confirm they fairly and accurately represents the information in sections of the technical report for which I am responsible.

 

Dated June 8, 2020

 

(-s- Frank Crundwell)

 

 

 

Frank K. Crundwell

 

BSc (Eng) Chem, BSc (Hons) Financial Maths, MSc (Eng) Chem, PhD,

 

Pr Eng, FSAIMM, FIChemE

 

DIRECTOR

 

89J Victoria Drive, London, SW196PT, United Kingdom

 
 (VIRIMAI PROJECTS LOGO)Page 195
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Wenceslaus Kutekwatekwa

 

I Wenceslaus Kutekwatekwa consent to the filing of the Technical Report titled “National Instrument 43- 101 Independent Technical Report Update Mineral Resource Estimate for the Buckreef Gold Mine Project Tanzania East Africa.”

 

I Wenceslaus Kutekwatekwa certify that I am responsible for the compilation of the ITR titled “National Instrument 43-101 Independent Technical Report Update Mineral Resource Estimate for the Buckreef Gold Mine Project Tanzania East Africa” dated 15th May 2020 by Virimai Projects and I have read the news release of Tanzanian Gold Corporation dated March 17, 2020, and confirm they fairly and accurately represents the information in sections of the technical report for which I am responsible.

 

Dated June 8, 2020

 

(-s- Wenceslaus Kutekwatekwa)

 

 

 

Wenceslaus Kutekwatekwa

 

BSc (Hons) Ming Eng. MBA

 

FSAIMM, FIoDZ, MPMZ

 

CONSULTING DIRECTOR

 
 (VIRIMAI PROJECTS LOGO)Page 196
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.3ESIA CERTIFICATION

 

(CERTIFICATE)

 
 (VIRIMAI PROJECTS LOGO)Page 197
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.4LABORATORIES ACCREDITATION CERTIFICATES

  

(GRAPHIC)

 
 (VIRIMAI PROJECTS LOGO)Page 198
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 
 (VIRIMAI PROJECTS LOGO)Page 199
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 
 (VIRIMAI PROJECTS LOGO)Page 200
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.5PROCESS FLOW DIAGRAMS

 

(GRAPHIC)

 

Figure 32.1: Process flow diagram for Area 100.

 
 (VIRIMAI PROJECTS LOGO)Page 201
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.2. Process flow diagram for Area 200

 
 (VIRIMAI PROJECTS LOGO)Page 202
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.3. Process flow diagram for Area 250

 
 (VIRIMAI PROJECTS LOGO)Page 203
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.4. Process flow diagram for Area 300

 
 (VIRIMAI PROJECTS LOGO)Page 204
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.5. Process flow diagram for Area 310

 
 (VIRIMAI PROJECTS LOGO)Page 205
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.6. Process flow diagram for Area 350.

 
 (VIRIMAI PROJECTS LOGO)Page 206
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.7. Process flow diagram for Area 400.

 
 (VIRIMAI PROJECTS LOGO)Page 207
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.8. Process flow diagram for Area 410.

 
 (VIRIMAI PROJECTS LOGO)Page 208
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.9. Process flow diagram for Area 420

 
 (VIRIMAI PROJECTS LOGO)Page 209
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.10. Process flow diagram for Area 500

 
 (VIRIMAI PROJECTS LOGO)Page 210
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.11. Process flow diagram for Area 600

 
 (VIRIMAI PROJECTS LOGO)Page 211
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.12. Process flow diagram for Area 610

 
 (VIRIMAI PROJECTS LOGO)Page 212
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(GRAPHIC)

 

Figure 32.13. Process flow diagram for Area 700.

 
 (VIRIMAI PROJECTS LOGO)Page 213
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.6PROCESSING PLANT MECHANICAL ITEMS

 

      Volumetric Design    
Equipment Tag Description Total feed flow volume Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
100 BIN 01 Feed Bin 1 31 17.6 22.0    
100 BIN 02 Feed Bin 2 31 17.6 22.0    
100 BIN 03 Jaw Crusher Discharge Overflow Bin 67 35.3 43.0    
100 CHT 01 Rotaspiral 1 Feed Chute 63 43.8   52.5  
100 CHT 02 Rotaspiral 2 Feed Chute 63 43.8   52.5  
100 CRU 01 Jaw Crusher 1 67 35.3     103
100 CRU 02 Jaw Crusher 2 67 35.3     103
100 CON 01 Feed Bin 1 Conveyor 31 17.6     38
100 CON 02 Feed Bin 2 Conveyor 31 17.6     38
100 CON 03 Scrubbing Rotaspiral Oversize Conveyor 67 35.3     80
100 CON 04 Jaw Crusher Discharge Conveyor 67 35.3     80
100 CON 05 Mill Feed Conveyor 89 45.8     107
100 CON 06 Classification Rotaspiral Oversize Conveyor 22 10.5     27
100 FEL 01 ROM Front End Loader          
100 FEL 02 ROM Front End Loader          
100 MGT 01 Feed Bin 1 Conveyor Magnet 31        
100 MGT 02 Feed Bin 2 Conveyor Magnet 31        
100 MGT 03 Jaw Crusher Discharge Conveyor Magnet 67        
100 MIL 01 EDS Mill 1 42       51
100 MIL 02 EDS Mill 2 42       51
100 MMT 01 Feed Bin 1 Conveyor Weightometer 31        
100 MMT 02 Feed Bin 2 Conveyor Weightometer 31        
100 PMP 01 Scrubbing Rotaspiral 1 Underflow Pump 50 38.5   47  
100 PMP 02 Scrubbing Rotaspiral 2 Underflow Pump 50 38.5   47  
100 PMP 03 Classification Rotaspiral 1 Underflow Pump 75 55.5   67  
100 PMP 04 Classification Rotaspiral 2 Underflow Pump 75 55.5   67  
100 RSP 01 Scrubbing Rotaspiral 1 63 43.8   53 76
100 RSP 02 Scrubbing Rotaspiral 2 63 43.8   53 76
100 RSP 03 Classification Rotaspiral 1 82 55.9   68 99
100 RSP 04 Classification Rotaspiral 2 82 55.9   68 99
100 SPL 01 Jaw Crusher 2-way Splitter 67 35.3     103
100 SPL 02 EDS Mill 2-way Splitter 89 45.8     107
100 PMP 05 Standby 100-PMP-01/02          

 

      Volumetric    
Equipment Tag Description Total feed flow Design Flow
Area Description Sequential number   t/h m3/h m3/h t/h
200 AGT 01 Gravity Feed Tank Agitator        
200 AGT 02 Gravity Concentrate Tank Agitator        
200 BAG 1 Gravity Concentrate 2      
200 CNC 01 Gravity Concentrator 1 150 110.9 134 180
200 CNC 02 Gravity Concentrator 2 150 110.9 134 180
200 PMP 01 Gravity Feed Pump 150 110.9 134  
200 PMP 02 Gravity Concentrate Pump 5 3.1 4  
200 PMP 03 Shaking Table Sump Pump   10.0 12  
200 PMP 04 Gravity Tails Pump 153 108.3 131  
200 SMP 01 Shaking Table Sump        
200 TBL 01 Shaking Table 2.5      
200 TNK 01 Gravity Feed Tank 150.0 110.9    
200 TNK 02 Gravity Tails Tank 148.0 110.0    
200 TNK 03 Gravity Concentrate Tank 5.0 3.1    

 

Equipment Tag Description Total feed Volumetric
flow
Design
volume
Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
250 BOX 01 Thickener Feed Box 137.3 93.4 0.5    
250 CYC 01 Dewatering Cyclone 150.4 106.5      
250 MXR 01 Flocculant Mixer          
250 PMP 01 Thickener Underflow Pump 118.1 79.8   96  
250 PMP 02 Thickener Underlow Pump (Standby) 118.1 79.8   96  
250 PMP 03 Thickener Overflow Pump 32.3 32.3   39  
250 THK 01 Hi-rate Thickener 137.3 93.4      
250 TNK 01 Thickener Overflow Tank 32.3 32.3 19.4    

 
 (VIRIMAI PROJECTS LOGO)Page 214
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Equipment Tag Description Total feed Volumetric
flow
Design
volume
Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
310 BAG 01 CIL Tails Fine Carbon Collection Bag     1.0    
310 BOX 01 CIL Tails Screen Feed Box 122 77.9 3.1    
310 PMP 01 CIL Tails Transfer Pump 130 85.6   103  
310 SCR 01 CIL Tails Carbon Fine Screen 122 77.9      
310 STN 01 CIL Tails Bag Stand     1.0    
310 TNK 01 CIL Tails Tank 122 77.9 6.2    
                 
      Volumetric Design  
Equipment Tag Description Total feed flow volume Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
350 AGT 01 Detox Tank2pt Agitator     344.7    
350 PMP 01 Detox Tank Discharge 131 91.7   111  
350 PMP 02 Detox Spillage Pump   10.0   12  
350 SSH 01 Detox Safety Shower          
350 SMP 01 Detox Spillage Sump          
350 TNK 01 Detox Tank 130 85.6 344.7    
350 PMP 03 Standby 310/350          
                 
      Volumetric Design  
Equipment Tag Description Total feed flow volume Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
400 AGT 01 Loaded Carbon Tank Agitator     11.3    
400 CLM 01 Acid Wash Column     4.4    
400 PMP 01 Acid Wash Pump   3.7   4.4  
400 PMP 02 Loaded Carbon Transfer Pump   9.2   13.8  
400 PMP 03 Slurry Return Pump   79.7   96  
400 PMP 04 Acid Wash Spillage Pump   10.0   12  
400 PMP 05 Column Pump 14.73 7.37   9  
400 PMP 06 Wash Water Pump   3.7   5  
400 SCR 01 Loaded Carbon Screen   69.8      
400 SMP 01 Acid Wash Spillage Sump          
400 SSH 01 Safety Shower          
400 TNK 01 Acid Wash Tank 3.68 3.6 21.1    
400 TNK 02 Wash Water Tank 7.4 7.4 8.8    
400 TNK 03 Loaded Carbon Tank 0.4 0.4 11.3    
400 TNK 04 Slurry Return Tank 113.2 79.7 34.0    
                 
Equipment Tag Description Total feed Volumetric
flow
Design
volume
Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
410 AGT 01 Eluate Agitator     21.1    
410 BLR 01 Elution Boiler 1          
410 BLR 02 Elution Boiler 2          
410 CLM 01 Elution Column     4.40    
410 HTE 01 Primary Heat Exchanger          
410 HTE 02 Secondary Heat Exchanger          
410 HTE 03 Tertiary Heat Exchanger          
410 PMP 01 Elution Pump 3.68 3.7   4.4  
410 PMP 02 Transfer Water Pump 14.73 14.7   17.7  
410 PMP 03 Elution Spillage Pump   10.0   12.0  
410 SMP 01 Elution Spillage Sump          
410 SSH 01 Safety Shower          
410 TNK 01 Elution Tank     21.1    
410 TNK 02 Transfer Water Tank 7.37 7.4 4.4    
                 
Equipment Tag Description Total feed Volumetric
flow
Design
volume
Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
420 AGT 01 Eluted Carbon Tank Agitator     20.1    
420 AGT 02 Regenerated Carbon Agitator     21.7    
420 BAG 01 CIL Tails Carbon Bag     1.0    
420 FDS 01 Regeneration Kiln Screw Feeder 0.4 0.4      
420 MBG 01 Kiln DC Drive          
420 PMP 01 Kiln Carbon Pump 0.4 0.4   0.56  
420 PMP 02 Regeneration Carbon Pump 0.4 0.4   0.56  
420 PMP 03 Water Transport Pump 7.4 7.4   8.84  
420 PMP 04 Carbon Regeneration Sump Pump   10.0   12.00  
420 RGK 01 Carbon Regeneration Kiln 1.8 1.7      
420 SMP 01 Carbon Regeneration Sump          
420 STN 01 CIL Tails Carbon Bag Stand     1.0    
420 TNK 01 Eluted Carbon Tank 9.2 8.4 20.1    
420 TNK 02 Regenerated Carbon Tank 9.2 9.0 21.7    
420 TNK 03 Transfer Water Tank 9.2 9.0 43.4    

 
 (VIRIMAI PROJECTS LOGO)Page 215
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

      Volumetric Design  
Equipment Tag Description Total feed flow volume Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
500 EWC 01 Electrowinning Cell 1 1.8 1.8 26.5    
500 EWC 02 Electrowinning Cell 2 1.8 1.8 26.5    
500 PMP 01 Electrowinning Discharge Pump   1.8   2.2  
500 REC 01 Electrowinning Rectifier 1 1.8 1.8      
500 REC 02 Electrowinning Rectifier 2 1.8 1.8      
500 TNK 01 Electrowinning Overflow Discharge Tank   1.8 26.5    
500 PMP 02 Standby 500/420          

 
 (VIRIMAI PROJECTS LOGO)Page 216
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

      Volumetric Design  
Equipment Tag Description Total feed flow volume Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
600 AGT 01 Cyanide Make-up Agitator     14.8    
600 AGT 02 Caustic Make-up Agitator     15.8    
600 AGT 03 Lime Make-up Agitator     24.9    
600 AGT 04 Cyanide Tank Agitator     14.8    
600 AGT 05 Lime Tank Agitator     24.9    
600 BAG 01 Sodium Cyanide Reagent 12.0        
600 BAG 02 Caustic Reagent 6.0        
600 BAG 03 Lime (Calcium Oxide) Reagent 6.0        
600 BBR 01 Bag Breaker Cyanide          
600 BBR 02 Bag Breaker Caustic          
600 BBR 03 Bag Breaker Lime          
600 PMP 01 Cyanide Make-Up Pump   3.1   3.39  
600 PMP 02 Caustic Pump   6.6   7.92  
600 PMP 03 Lime Make-Up Pump   20.7   24.88  
600 PMP 04 Cyanide Pump          
600 PMP 05 Lime Pump          
600 PMP 06 Base Sump Pump   10.0   12.00  
600 SMP 01 Base Sump          
600 SSH 02 Base Safety Shower          
600 TNK 01 Cyanide Make-up Tank   0.5 14.8    
600 TNK 02 Caustic Make-up Tank   1.1 15.8    
600 TNK 03 Lime Make-up Tank   3.5 24.9    
600 TNK 04 Cyanide Tank     14.7744 0 0
600 TNK 05 Lime Tank     24.8832 0 0
610 AGT 01 Ferrous Sulphate Agitator     22.9    
610 AGT 02 Acid Agitator     8.7    
610 BAG 01 Ferrous Sulphate Reagent 12.0        
610 BBR 01 Bag Breaker Ferrous Sulphate          
610 PMP 01 Ferrous Sulphate Tank Pump   1.6   1.91  
610 PMP 02 Dilute Acid Pump   3.6   4.37  
610 PMP 03 Concentrate Acid Pump   1.1   1.34  
610 PMP 04 Acid Sump Pump   10.0   12.00  
610 SMP 01 Acid Sump          
610 SSH 01 Acid Safety Shower          
610 TNK 01 Ferrous Sulphate Make-Up Tank   0.8 22.9    
610 TNK 02 Dilute Acid Tank   3.6 8.7    

 

Equipment Tag Description Total feed Volumetric
flow
Design
volume
Design Flow
Area Description Sequential number   t/h m3/h m3 m3/h t/h
700 PMP 01 Process Water Pump   107   128.9  
700 PMP 02 Process Water Pump (Stand-by)   107   128.9  
700 PMP 03 Transfer Water Pump   7   8.84  
700 PMP 04 Potable Water Pump          
700 PMP 05 Gland Water Pump          
700 PMP 06 Cooling Water Pump          
700 PMP 07 Cooling Tower Feed Pump          
700 PMP 08 Cooling Tower Return Pump          
700 PMP 09 Anti-Scalant Pump          
700 TNK 01 Process Water Tank 107 107 257.7    
700 TNK 02 Transfer Water Tank 7 7 8.8    
700 TNK 03 Potable Water Tank     20    
700 TNK 04 Gland Water Tank     5    
700 TNK 05 Cooling Water Tank     20    
700 TNK 06 Anti-Scalant Tank     5    

 
 (VIRIMAI PROJECTS LOGO)Page 217
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

32.7TABLES APPENDICES

 

Table 32.1: Buckreef Project Full Schedule of Mined Tonnages

 

 TRX Mine Plan 2019                                  
 YEAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Total
 MINING Summary                                  
Oxide Ore (Tonnes) 274,483 256,217 79,578 109,536 38,713 30,525 159,318 64,833 320,880 117,506 16,298 1,232 40,585 - - - -
Oxide Ore (g/t) 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - - -
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Oxide Ore & Waste 2,987,867 1,699,167 2,166,326 707,445 229,881 1,581,042 2,245,162 2,205,193 2,299,065 3,440,074 934,664 82,939 1,086,332 - - - -
                                   
Trans Ore (Tonnes) 91,927 191,820 149,582 93,467 92,763 91,086 40,183 21,171 81,587 341,223 255,904 51,915 17,472 - - - -
Trans Ore (g/t) 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Trans Ore & Waste 1,388,387 1,289,207 2,283,879 1,503,798 825,459 1,615,673 1,969,973 1,297,984 1,710,757 3,041,416 3,134,227 1,419,675 385,177 - - - -
                                   
Hard Ore (Tonnes) 42,968 186,569 346,182 554,797 1,246,759 1,522,363 1,269,055 1,262,780 1,059,983 1,122,314 1,091,578 1,439,843 1,496,521 1,386,337 1,110,020 915,073 -
Hard Ore (g/t) 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70 -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Hard Ore & Waste 551,246 1,952,626 4,401,044 7,379,132 9,027,784 8,361,405 9,253,780 10,557,224 15,700,177 13,282,510 15,641,109 16,929,886 13,645,153 14,273,999 14,285,570 2,017,443 -
                                   
Total Ore (Tonnes) 409,378 634,606 575,342 757,800 1,378,235 1,643,974 1,468,556 1,348,784 1,462,450 1,581,043 1,363,781 1,492,990 1,554,578 1,386,337 1,110,020 915,073 -
Total Ore (g/t) 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70 -
Total Waste 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370 -
Total Ore & Waste 4,927,500 4,941,000 8,851,250 9,590,375 10,083,125 11,558,119 13,468,915 14,060,401 19,709,999 19,763,999 19,709,999 18,432,500 15,116,663 14,273,999 14,285,570 2,017,443 -
 MILL FEED Summary                                  
Oxide Ore (Tonnes) 348,730 187,710 57,425 208,941 73,014 29,574 159,318 66,452 308,940 117,506 21,063 - 40,585 2,241 7,930 - 1,629,430
Oxide Ore (g/t) 2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 - 1.79
Trans Ore (Tonnes) 91,927 150,814 136,218 133,167 106,462 77,843 40,183 27,971 81,587 308,576 269,834 51,538 17,472 5,842 20,668 - 1,520,100
Trans Ore (g/t) 2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 - 1.92
Hard Ore (Tonnes) 42,968 146,426 289,982 625,143 1,271,034 1,347,066 1,251,009 1,356,088 1,059,983 1,028,401 1,159,613 1,398,972 1,392,453 1,446,401 1,322,530 915,073 16,053,143
Hard Ore (g/t) 1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70 1.48
  483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 - - -
Total Ore (Tonnes) 483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,351,128 915,073 19,202,673
Hard Ore (g/t) 1.98 2.02 1.64 1.48 1.58 1.37 1.23 1.88 1.63 1.90 1.33 1.22 1.35 1.64 1.40 1.70 1.54
Oz Fed to Plant 30,748 31,540 25,534 45,975 73,767 64,004 57,394 87,814 75,987 88,989 61,959 56,839 62,911 76,537 60,916 50,091 951,012
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Total 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370 -
SR 9.34 8.88 17.11 9.13 6.00 6.82 8.27 8.76 12.58 12.50 12.65 11.68 9.35 8.86 9.75 1.20 9.56

 
 (VIRIMAI PROJECTS LOGO)Page 218
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.1: Buckreef Project Full Schedule of Mined Tonnages

 

 TRX Mine Plan 2019                                  
 YEAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Total
 MINING Summary                                  
Oxide Ore (Tonnes) 274,483 256,217 79,578 109,536 38,713 30,525 159,318 64,833 320,880 117,506 16,298 1,232 40,585 - - - -
Oxide Ore (g/t) 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - - -
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Oxide Ore & Waste 2,987,867 1,699,167 2,166,326 707,445 229,881 1,581,042 2,245,162 2,205,193 2,299,065 3,440,074 934,664 82,939 1,086,332 - - - -
                                   
Trans Ore (Tonnes) 91,927 191,820 149,582 93,467 92,763 91,086 40,183 21,171 81,587 341,223 255,904 51,915 17,472 - - - -
Trans Ore (g/t) 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Trans Ore & Waste 1,388,387 1,289,207 2,283,879 1,503,798 825,459 1,615,673 1,969,973 1,297,984 1,710,757 3,041,416 3,134,227 1,419,675 385,177 - - - -
                                   
Hard Ore (Tonnes) 42,968 186,569 346,182 554,797 1,246,759 1,522,363 1,269,055 1,262,780 1,059,983 1,122,314 1,091,578 1,439,843 1,496,521 1,386,337 1,110,020 915,073 -
Hard Ore (g/t) 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70 -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Hard Ore & Waste 551,246 1,952,626 4,401,044 7,379,132 9,027,784 8,361,405 9,253,780 10,557,224 15,700,177 13,282,510 15,641,109 16,929,886 13,645,153 14,273,999 14,285,570 2,017,443 -
                                   
Total Ore (Tonnes) 409,378 634,606 575,342 757,800 1,378,235 1,643,974 1,468,556 1,348,784 1,462,450 1,581,043 1,363,781 1,492,990 1,554,578 1,386,337 1,110,020 915,073 -
Total Ore (g/t) 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70 -
Total Waste 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370 -
Total Ore & Waste 4,927,500 4,941,000 8,851,250 9,590,375 10,083,125 11,558,119 13,468,915 14,060,401 19,709,999 19,763,999 19,709,999 18,432,500 15,116,663 14,273,999 14,285,570 2,017,443 -
 MILL FEED Summary                                  
Oxide Ore (Tonnes) 348,730 187,710 57,425 208,941 73,014 29,574 159,318 66,452 308,940 117,506 21,063 - 40,585 2,241 7,930 - 1,629,430
Oxide Ore (g/t) 2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 - 1.79
Trans Ore (Tonnes) 91,927 150,814 136,218 133,167 106,462 77,843 40,183 27,971 81,587 308,576 269,834 51,538 17,472 5,842 20,668 - 1,520,100
Trans Ore (g/t) 2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 - 1.92
Hard Ore (Tonnes) 42,968 146,426 289,982 625,143 1,271,034 1,347,066 1,251,009 1,356,088 1,059,983 1,028,401 1,159,613 1,398,972 1,392,453 1,446,401 1,322,530 915,073 16,053,143
Hard Ore (g/t) 1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70 1.48
  483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 - - -
Total Ore (Tonnes) 483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,351,128 915,073 19,202,673
Hard Ore (g/t) 1.98 2.02 1.64 1.48 1.58 1.37 1.23 1.88 1.63 1.90 1.33 1.22 1.35 1.64 1.40 1.70 1.54
Oz Fed to Plant 30,748 31,540 25,534 45,975 73,767 64,004 57,394 87,814 75,987 88,989 61,959 56,839 62,911 76,537 60,916 50,091 951,012
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Total 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370 -
SR 9.34 8.88 17.11 9.13 6.00 6.82 8.27 8.76 12.58 12.50 12.65 11.68 9.35 8.86 9.75 1.20 9.56

 
 (VIRIMAI PROJECTS LOGO)Page 219
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.2 Buckreef Project Summary of Schedule of Milled Tonnages

 

 Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
 MINING Summary                                
Oxide Ore (Tonnes) 274 256 80 110 39 31 159 65 321 118 16 1 41 - - -
Oxide Ore (g/t) 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - -
Oxide Waste 2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - -
Oxide Ore & Waste 2,988 1,699 2,166 707 230 1,581 2,245 2,205 2,299 3,440 935 83 1,086 - - -
                                 
Trans Ore (Tonnes) 92 192 150 93 93 91 40 21 82 341 256 52 17 - - -
Trans Ore (g/t) 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - -
Trans Waste 1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - -
Trans Ore & Waste 1,388 1,289 2,284 1,504 825 1,616 1,970 1,298 1,711 3,041 3,134 1,420 385 - - -
                                 
Hard Ore (Tonnes) 43 187 346 555 1,247 1,522 1,269 1,263 1,060 1,122 1,092 1,440 1,497 1,386 1,110 915
Hard Ore (g/t) 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70
Hard Waste 508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102
Hard Ore & Waste 551 1,953 4,401 7,379 9,028 8,361 9,254 10,557 15,700 13,283 15,641 16,930 13,645 14,274 14,286 2,017
                                 
Total Ore (Tonnes) 409 635 575 758 1,378 1,644 1,469 1,349 1,462 1,581 1,364 1,493 1,555 1,386 1,110 915
Total Ore (g/t) 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70
Total Waste 4,518 4,306 8,276 8,833 8,705 9,914 12,000 12,712 18,248 18,183 18,346 16,940 13,562 12,888 13,176 1,102
Total Ore & Waste 4,927 4,941 8,851 9,590 10,083 11,558 13,469 14,060 19,710 19,764 19,710 18,432 15,117 14,274 14,286 2,017
                                 
 MILL FEED
Summary
                               
Oxide Ore (Tonnes) 349 188 57 209 73 30 159 66 309 118 21 - 41 2 8 -
Oxide Ore (g/t) 2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 -
Trans Ore (Tonnes) 92 151 136 133 106 78 40 28 82 309 270 52 17 6 21 -
Trans Ore (g/t) 2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 -
Hard Ore (Tonnes) 43 146 290 625 1,271 1,347 1,251 1,356 1,060 1,028 1,160 1,399 1,392 1,446 1,323 915
Hard Ore (g/t) 1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70
  484 485 484 967 1,451 1,454 1,451 1,451 1,451 1,454 1,451 1,451 1,451 1,454 1,351 915
Total Ore (Tonnes) 484 485 484 967 1,451 1,454 1,451 1,451 1,451 1,454 1,451 1,451 1,451 1,454 1,351 915
Hard Ore (g/t) 1.98 2.02 1.64 1.48 1.58 1.37 1.23 1.88 1.63 1.90 1.33 1.22 1.35 1.64 1.40 1.70
Oz Fed to Plant 31 32 26 46 74 64 57 88 76 89 62 57 63 77 61 50
Oxide Waste 2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - -
Trans Waste 1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - -
Hard Waste 508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102

 
 (VIRIMAI PROJECTS LOGO)Page 220
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.3: Full Schedule of Staffing Requirements of the Buckreef Project

 

      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
MANAGEMENT   (US$)                                  
Chief Operating Officer M 120,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
General Manager   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Executive Secretary S 42,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL   162,000 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
MINE OPERATION                                      
Mine /Production Manager M 72,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Pit Superintendent   0   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Shift Supervisor S 12,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Driller-Contractor/Supervisor C 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Blasters-Contractor/Supervisor C 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Loader Operator S 9,600   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Excavator Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Truck Driver /Dumper S 8,400 1 10 10 10 5 10 10 10 10 10 10 10 10 10 10 10 10
Wheel Dozer Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Track Dozer Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Water Truck Operator S 8,400 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Grader Operator S 9,600   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Lube Fuel Truck Operator S 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Ore Spotter S 9,000 2 2 2 2 6 2 2 2 2 2 2 2 2 2 2 2 2
Pit Pump Operator S 9,000 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Laborer L 9,000 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
TOTAL   202,800 12 36 36 36 35 36 36 36 36 36 36 36 36 36 36 36 36
MINING ENGINEERING                                      
Engineering Manager   60,000 0 0 0 0 1 0 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Shift Supervisor S 30,000 2 3 4 5 4 7 4 3 3 3 3 3 3 3 3 3 3
Mine Engineers S 24,000 1 2 2 2 2 2 1                    
Fitters and Mechanics S 12,000 10 20 20 20 20 10 10                    
Fuel Bay Attendants Fitter Asst L 6,000 4 4 4 4 14 4 4 2 2 2 2 2 2 2 2 2 2
Data Clerks L 6,000 1 1 1 1 1 1 1 11 7 7 7 7 7 7 7 7 7
TOTAL     18 30 31 32 42 24 20 16 12 12 12 12 12 12 12 12 12
                                       
TECHNICAL SERVICES                                      
Geology Manager   0 0 0 0 0 0 0 0 0.0                  
Mine Surveyor S 30,000 2 2 2 2 3 3 3                    
      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

 
 (VIRIMAI PROJECTS LOGO)Page 221
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Geotechnical Engineer L 21,600 1 1 1 1 1 1 1                    
Survey Technician L 10,800 1 3 3 3 4 4 4                    
Geotechnical Technicisn L 10,800 1 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1
Mine/Exploration Geologist S 36,000 2 2 2 2 2 2 1                    
Resource Geologist   0 0 0 0 0 0 0 0                    
Geology Technician L 10,800 4 2 4 4 4 4 4                    
Data Clerk L 6,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     12 13 15 15 17 17 16 2 2 2 2 2 2 2 2 2 2
                                       
PROCESS PLANT                                      
Plant Manager/Supritendent M 72,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Process/Maintanance Engineer S 30,000   1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1
Shift Supervisor S 30,000   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Gold Room Supervisor S 30,000   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Operators L 10,800   20 20 20 0 20 20 20 20 20 20 20 20 20 20 20 20
Fitters and Mechanics S 10,800   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Metallurgist S 24,000 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1
Effluent Treatment Operator L 8,400   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 31 31 31 1 31 31 31 31 31 31 31 31 31 31 31 31
                                       
SAFETY, HEALTH & ENVIRONMENT                                      
SHE Manager M 60,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Medical Doctor S 36,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety/Environment Officer S 30,000 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Nurse S 11,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Lab Technician S 11,400 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     2 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
METALLURGICAL LABORATORY                                      
Chief Chemist S 36,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Assayers S 8,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Sample Preparation L 8,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Instrumentation Techn. S 10,800   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     0 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
HUMAN RESOURCES                                      
Human Resource Manager   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
HR Officer S 30,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Community Relations Officer S 18,000 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

 
 (VIRIMAI PROJECTS LOGO)Page 222
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Administration Officer S 18,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
PURCHASING                                      
Chief Buyer S 48,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Procurement Officer S 12,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Receiving Supervisor   0   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Data Clerks L 7,200   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
ACCOUNTING                                      
Chief Accountant M 72,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Accountant/Payroll Officer S 36,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Accountant/Accounts payable officer S 36,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Cost accountant/PPE S 48,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
IT Technician S 18,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
CAMP                                      
Camp Manager S 42,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Chief Cook S 30,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Assistant Cook L 10,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Kitchen Assistant L 10,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Office Cleaners L 7,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8

 
 (VIRIMAI PROJECTS LOGO)Page 223
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.4: Summary of Capital Costs Estimates

 

    60tph Prod   120tph Prod

180tph Prod 

   
Item Capital Description No Unit Cost Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
  Capital Plan   USD USD              
1 Mining                    
1.1 Mining Equipment ( Fleet) 1 17,531,424 17,531,424 8,737,653 4,581,271   4,212,500    
1.2 Loader 3 265,500 796,500 796,500            
1.3 Water Truck 0 100,000 100,000 100,000            
1.4 Service Truck 1 100,000 100,000 100,000            
1.5 Light Trucks & Cars 8 41,500 332,000 166,000 166,000          
1.6 Dewatering Pump 4 40,000 160,000 160,000            
1.7 Survey Tools 1 45,000 45,000 45,000            
1.8 Pit Optimisation 1 75,000 75,000 75,000            
1.9 Mining Offices/Shop 1 300,000 300,000 300,000            
1.1 Haul Roads 1 100,000 100,000 100,000            
1.11 HME - Workshop Construction 1 700,000 700,000 700,000            
1.12 Explosive magazine 1 150,000 150,000   150,000          
1.13 Fuel Tanks with a Capacity to hold 400klt 1 240,000 240,000 240,000            
  Subtotal Mining     20,629,924 11,520,153 4,897,271 0 4,212,500      
2 Processing Plant                    
2.1 TSF Construction & Design 1 1,750,000 1,750,000 1,250,000   250,000 250,000      
2.2 Portable Water Plant 1 600,000 600,000 300,000   300,000        
2.3 Laboratory 1 500,000 500,000 500,000            
2.4 Process Plant Development 1 35,284,625 35,284,625 11,500,000 150,000 11,500,000 12,134,625      
2.5 Generators 4No x 2.5MVa 1 1,243,000 1,243,000 414,333 - 414,333 414,333      
2.6 Substation and Power Reticulation 1 500,000 500,000 500,000            
2.7 Engineering Workshop for Plant +tools 1 400,000 400,000 400,000            
  Subtotal Processing Plant   40,277,625 40,277,625 14,864,333 150,000 12,464,333 12,798,958      
3 Human Resources & Community                    
3.1 Camping Facilities 1 250,000 250,000 250,000            
3.2 Camp Houses (2Bx20+4Bx30) 50 15,000 750,000 750,000            
3.3 Relocation of Mnekezi road 1 250,000 250,000 250,000            
3.4 Airport/Aerodrome 1 35,000 35,000 35,000            
3.5 Helicopter Pad 1 10,000 10,000 10,000            
3.6 Compensation - Relocation from SML 1 2,500,000 2,500,000 2,500,000            
3.7 Sewer Ponds & Facilities 1 350,000 350,000 350,000            
3.8 Security fencing 1 520,000 520,000 520,000            
  Subtotal Human Resources & Community   3,930,000 4,665,000 4,665,000 0 0 0      
4 HSE                    
4.1 Clinic 1 100,000 100,000 100,000            

 
 (VIRIMAI PROJECTS LOGO)Page 224
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

    60tph Prod   120tph Prod

180tph Prod

   
Item Capital Description No Unit Cost Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
4.2 Waste Handling Facilties 1 75,000 75,000 75,000            
  Subtotal HSE   175,000 175,000 175,000 0 0 0      
5 Finance + IT                    
5.1 Computer & Server 1 40,000 40,000 40,000            
5.2 Desktop 1 45,000 45,000 45,000            
5.3 Laptop 1 30,000 30,000 30,000            
5.4 Networking & Communication 1 40,000 40,000 40,000            
5.5 Process Plant Insurance - 6% Plant Cost 1 600,000 600,000 600,000            
5.6 Mining Equipment Insurance - 2.5% Equip Cost 1 19,913 19,913 19,913            
  Subtotal Finance +IT   774,913 774,913 774,913 0 0 0      
6 Contingency 15% 15%   9,978,369 4,799,910 757,091 1,869,650 2,551,719      
7 Total Capex     76,500,831 36,799,309 5,804,362 14,333,983 19,563,177      
                       
  For Depreciation     Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
1 Plant and Equipment US$   64,707,681 26,873,384 5,876,725 14,657,200 20,113,750      
2 Building and Infrastructure US$   11,059,500 10,887,000 3,952,500 3,780,000 3,780,000      
3 Office & Computers Equipment US$   891,150 891,150 0 0 0      
4 Total US$   76,658,331 38,651,534 9,829,225 18,437,200 23,893,750      

 
 (VIRIMAI PROJECTS LOGO)Page 225
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.50: Equipment Operating Costs\

 

FUEL PRICE USD 1.20 Type TRACKED
BULL
DOZER
TRACKED
BULL
DOZER
MOTOR GRADER HYDRAULIC
EXCAVATOR
HYDRAULIC
EXCAVATOR
ARTICULATED
DUMP TRUCK
FUEL
BOWSER
WATER
BOWSER
TRACKED
DRILL
RIG
ENGINE OIL USD 4.60 Make BELL CAT CAT CAT LIEBHEER BELL BELL BELL Sandvik
TRANS OIL USD 7.17 Model PR754 D8R 140H 374 R966 B40D B25E B30E  
HYD OIL USD 4.60 kW   123 112            
F / DRIVE OIL USD 5.10 kg 32,000 17,083 13,529           32,000
Delivery Price DP   USD 683,771.00 USD 850,000.00 USD 385,000.00 USD 855,000.00 USD 855,000.00 USD 540,000.00 USD 343,000.00 USD 385,000.00 USD 675,750.00
Residual Value At Replacement RVR   USD 0.00 USD 85,000.00 USD 38,500.00 USD 85,500.00 USD 85,500.00 USD 54,000.00 USD 34,300.00 USD 38,500.00 USD 0.00
Value To Be Recovered
Through Work
VRTW   USD 683,771.00 USD 765,000.00 USD 346,500.00 USD 769,500.00 USD 769,500.00 USD 486,000.00 USD 308,700.00 USD 346,500.00 USD 675,750.00
Estimated Ownership N years 5 5 5 5 5 6 10 5 5
Estimated Usage H hours/year 7,200 7,200 7,200 7,200 7,200 7,200 4,500 7,200 7,200
Ownership Usage T hours 36,000 36,000 36,000 36,000 36,000 43,200 45,000 36,000 36,000
Cost Per Hour CPH USD/hr USD 18.99 USD 21.25 USD 9.63 USD 21.38 USD 21.38 USD 11.25 USD 6.86 USD 9.63 USD 18.77
Simple Interest Rate SI % 12% 12% 12% 12% 12% 12% 12% 12% 12%
Interest Costs SIC USD/hr USD 6.84 USD 8.50 USD 3.85 USD 8.55 USD 8.55 USD 5.25 USD 5.03 USD 3.85 USD 6.76
Insurance Rate IN % 2% 2% 2% 2% 2% 2% 4% 4% 2%
Insurance Costs INSC USD/hr USD 1.14 USD 1.42 USD 0.64 USD 1.43 USD 1.43 USD 0.88 USD 1.68 USD 1.28 USD 1.13
                       
TOTAL OWNING COSTS TOC USD/hr USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
                       
Fuel Consumption Rate F litres/hour 35 35 20 60 60 28 20 27 28
Fuel Price FP USD/litre USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20
Dry (D) Or Wet (W) Rate D/W w w w w w w w w w w
Fuel Consumption FC USD/hour USD 42.00 USD 42.00 USD 24.00 USD 72.00 USD 72.00 USD 33.60 USD 24.00 USD 32.40 USD 33.60
                       
Engine Oil Price EOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60
Engine Oil Consumption Rate EOCR litres/hour 0.160 0.140 0.140 0.300 0.200 0.150 USD 0.15 0.150 0.160
Transmission Oil Price TOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60
Transmission Oil Consumption Rate TOCR litres/hour 0.150 0.144 0.047 0.000 0.000 0.040 USD 0.04 0.040 0.150
Final Drives Fluid Price FDFP USD USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 0.00
Final Drives Fluid Consumption
Rate
FDFCR litres/hour 0.015 0.013 0.065 0.150 0.040 0.050 USD 0.05 0.050 0.015
Hydraulic Oil Price HOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 0.00
Hydraulic Oil Consumption
Rate
HOCR litres/hour 0.075 0.050 0.019 1.000 1.000 0.250 USD 0.25 0.250 0.075
Grease Price GP USD USD 6.20 USD 6.20 USD 6.20 USD 6.20 USD 6.20 6.200 USD 6.20 USD 6.20 USD 6.20
Grease Consumption Rate GCR kg/hour 0.140 0.139 0.139 0.200 0.200 0.140 0.140 0.140 0.140
Engine Oil Cost EOC USD/hour USD 0.74 USD 0.64 USD 0.64 USD 1.38 USD 0.92 USD 0.69 USD 0.69 USD 0.69 USD 0.74
Transmission Oil Cost TOC USD/hour USD 0.69 USD 0.66 USD 0.22 USD 0.00 USD 0.00 USD 0.18 USD 0.18 USD 0.18 USD 0.69
Final Drives Fluid Cost FDFC USD/hour USD 0.08 USD 0.07 USD 0.33 USD 0.77 USD 0.20 USD 0.26 USD 0.26 USD 0.26 USD 0.00
Hydraulic Oil Cost HOC USD/hour USD 0.35 USD 0.23 USD 0.09 USD 4.60 USD 4.60 USD 1.15 USD 1.15 USD 1.15 USD 0.00
Grease Cost GC USD/hour USD 0.87 USD 0.86 USD 0.86 USD 1.24 USD 1.24 USD 0.87 USD 0.87 USD 0.87 USD 0.87
Filter Cost [From Tables] FILC USD/hour USD 2.00 USD 1.50 USD 1.50 USD 2.50 USD 2.50 USD 2.00 USD 2.00 USD 2.00 USD 2.00
Total Lubricants, Oils And
Filter Cost
LC USD/hour USD 6.51 USD 6.51 USD 3.72 USD 11.16 USD 11.16 USD 5.04 USD 3.72 USD 5.02 USD 5.21
                       
Number Of Wheels NW     0 6 0 0 6 6 6 0
Tyre Size TS     0 17.5x25 0 0 26.5R25 26.5R25 26.5R25 0
Tyre Price CT     USD 0.00 USD 2,500.00 USD 0.00 USD 0.00 USD 6,500.00 USD 6,500.00 USD 6,500.00 0
Life Of Tyre LT hours   0 2,000 0 0 4,500 6,000 3,000 0
Tyre Replacement Cost TRC     USD 0.00 USD 7.50 USD 0.00 USD 0.00 USD 8.67 USD 6.50 USD 13.00 USD 0.00
                       
FUEL PRICE USD 1.20 Type TRACKED TRACKED MOTOR HYDRAULIC HYDRAULIC ARTICULATED FUEL WATER TRACKED

 
 (VIRIMAI PROJECTS LOGO)Page 226
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

      BULL
DOZER
BULL
DOZER
GRADER EXCAVATOR EXCAVATOR DUMP
TRUCK
BOWSER BOWSER DRILL
RIG
ENGINE OIL USD 4.60 Make BELL CAT CAT CAT LIEBHEER BELL BELL BELL Sandvik
TRANS OIL USD 7.17 Model PR754 D8R 140H 374 R966 B40D B25E B30E  
Impact Factor IF   0.4 0.4 0.0 0.5 0.4 0.0 0.0 0.0 0.4
                       
Abrasiveness A   0.6 0.6 0.0 0.6 0.6 0.0 0.0 0.0 0.6
“Z” Factor Z   0.5 0.5 0.0 1.0 1.0 0.0 0.0 0.0 0.5
Undercarriage Basic Factor Ba   10.0 10.0 0.0 10.0 10.0 0.0 0.0 0.0 6.0
Extended Use Multiplier EM   1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Basic Repair Factor BF   10 10 5.0 10.0 10.0 10.0 6.0 6.0 4
Undercarriage Repair Costs URC USD/hour USD 15.00 USD 15.00 USD 0.00 USD 21.00 USD 20.00 USD 0.00 USD 0.00 USD 0.00 USD 9.00
Repair Reserve RR   USD 10.00 USD 10.00 USD 5.00 USD 10.00 USD 10.00 USD 10.00 USD 6.00 USD 6.00 USD 11.00
                       
Price Of Cutting Edges/Bucket PCE USD USD 400.00 USD 460.00 USD 248.39 USD 20,000.00 USD 20,000.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Ripper Tips/Picks PRT USD USD 200.00 USD 230.00 USD 16.16 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Bucket Tips/Pick Holders PBT USD USD 0.00 USD 0.00 USD 0.00 USD 400.00 USD 400.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Bin Liners/Corner
Piece/End Ring
PEB USD USD 350.00 USD 402.50 USD 281.54 USD 0.00 USD 0.00 USD 3,000.00 USD 2,000.00 USD 2,000.00 USD 0.00
No. Of Cutting Edges NCE   2 2 2 1 1 0 0 0 0
No. Of Ripper Tips/Picks NRT   1 3 3 0 0 0 0 0 0
No. Of Bucket Tips/Pick Holders NRT   0 0 0 4 4 0 0 0 0
No. Of Bin Liners/Corner Piece/Endrings NEB   2 2 2 1 0 1 1 1 0
Life Of Cutting Edges/Bucket LCE hours 200 200 200 2,000 2,000 0 0 0 0
Life Of Ripper Tips/Picks LRT hours 200 200 200 0 0 0 0 0 0
Life Of Bucket Tips/Pick
Holders
LBT hours 0 0 0 150 150 0 0 0 0
Life Of Bin Liners/Corner
Piece/End Ring
LEB hours 200 250 0 0 0 2,500 4,000 4,000 0
Cost Of Cutting Edges CCE USD/hour USD 4.00 USD 4.60 USD 2.48 USD 10.00 USD 10.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Ripper Tips CRT USD/hour USD 1.00 USD 3.45 USD 0.24 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Bucket Tips CBT USD/hour USD 0.00 USD 0.00 USD 0.00 USD 10.67 USD 10.67 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Bin Liners CEB USD/hour USD 3.50 USD 3.22 USD 0.00 USD 0.00 USD 0.00 USD 1.20 USD 0.50 USD 0.50 USD 0.00
Special Wear Items SWI USD/hour USD 8.50 USD 11.27 USD 2.73 USD 20.67 USD 20.67 USD 1.20 USD 0.50 USD 0.50 USD 0.00
                       
Operator Costs OPC USD/hour USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
                       
TOTAL OPERATING CXOSTS TOC USD/hour USD 82.01 USD 84.78 USD 42.95 USD 134.83 USD 133.83 USD 58.51 USD 40.72 USD 56.92 USD 58.81
                       
    USD/hour USD 82.01 USD 84.78 USD 42.95 USD 134.83 USD 133.83 USD 58.51 USD 40.72 USD 56.92 USD 58.81
                       

 
 (VIRIMAI PROJECTS LOGO)Page 227
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.7: Buckreef Cash Flow Analysis

 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Ore Mining                                      
Oxide Ore (Tonnes) kt   349 188 57 209 73 30 159 66 309 118 21 - 41 2 8 - 1,629
Oxide Ore (g/t) g/t   2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 -  
Trans Ore (Tonnes) kt   92 151 136 133 106 78 40 28 82 309 270 52 17 6 21 - 1,520
Trans Ore (g/t) g/t   2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 -  
Hard Ore (Tonnes) kt   43 146 290 625 1,271 1,347 1,251 1,356 1,060 1,028 1,160 1,399 1,392 1,446 1,323 915 16,053
Hard Ore (g/t) g/t   1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70  
Oxide Waste kt   2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - - 20,155
Trans Waste kt   1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - - 20,346
Hard Waste kt   508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102 141,207
Oxide & Trans Ore Recovery % 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%  
Sulphide Ore Recovery   85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%  
Mining Dilution % 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%  
Gold produced                                      
Fine (kg) kg   876 869 677 1,208 1,878 1,621 1,468 2,225 1,989 2,405 1,599 1,433 1,595 1,924 1,535 1,258 24,559
Fine (oz) (1oz =31.1034768grams) koz   28,162 27,944 21,752 38,837 60,375 52,111 47,181 71,532 63,956 77,320 51,412 46,069 51,295 61,851 49,347 40,448 789,593
Gold price (US$000) $/oz 1300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300  
                                       
Gross revenue US ($000) 0 36,610 36,327 28,277 50,488 78,487 67,744 61,336 92,992 83,143 100,516 66,835 59,890 66,684 80,406 64,151 52,583 1,026,471
Less Royalties & Selling Costs                                     -
: Royalties 7.3% on Revenue   7.3% (2,673) (2,652) (2,064) (3,686) (5,730) (4,945) (4,478) (6,788) (6,069) (7,338) (4,879) (4,372) (4,868) (5,870) (4,683) (3,839) (74,932)
: Selling Costs per oz of gold   4.40 (124) (123) (96) (171) (266) (229) (208) (315) (281) (340) (226) (203) (226) (272) (217) (178) (3,470)
Net revenue     33,814 33,553 26,117 46,631 72,492 62,570 56,651 85,889 76,792 92,838 61,730 55,315 61,590 74,264 59,251 48,566 948,064

 
 (VIRIMAI PROJECTS LOGO)Page 228
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Capital Costs US ($k)                                    
Start up Capital     36,799 5,804 14,334 19,563                         76,501
Closure Costs U$                                 4,507 4,507
Sustaining Costs U$ 7.5% - - -   5,738 - - 5,738 - - 5,738 - - 5,738   - 22,950
Total Capital Costs U$ - 36,799 5,804 14,334 19,563 5,738 - - 5,738 - - 5,738 - - 5,738 - 4,507 103,958
Operating expenditure U$                                    
Mining Rates US ($k)                                    
Drill & Blast Waste $/tw 0.74 1,337 2,122 3,796 6,103 6,310 6,198 7,348 7,834 12,057 11,013 12,916 12,493 9,276 9,551 9,764 817 118,936
Drill & Blast Ore $/to 0.90 122 269 385 685 1,244 1,287 1,166 1,250 1,031 1,208 1,291 1,310 1,274 1,312 1,213 827 15,876
Load and Haul Ore $/to 1.13 544 546 544 1,088 1,632 1,637 1,632 1,632 1,632 1,637 1,632 1,632 1,632 1,637 1,520 1,030 21,609
Load and Haul waste $/tw 1.03 4,663 4,444 8,541 9,115 8,983 10,231 12,384 13,118 18,831 18,764 18,933 17,481 13,996 13,300 13,597 1,138 187,519
Overhaul rate $/t/km 0.08                                  
Mine Rehabilitation $/tw 0.03 136 129 248 265 261 297 360 381 547 545 550 508 407 387 395 33 5,451
Processing Rates                                      
Processing reagents $/to 10.24 4,952 4,966 4,952 9,905 14,853 14,894 14,853 14,853 14,853 14,894 14,853 14,853 14,853 14,894 13,836 9,370 196,646
Labour Costs $/to 1.98 958 960 958 1,915 2,872 2,880 2,872 2,872 2,872 2,880 2,872 2,872 2,872 2,880 2,675 1,812 38,023
Total operating costs US ($k)   12,712 13,436 19,424 29,076 36,156 37,425 40,616 41,942 51,825 50,941 53,048 51,151 44,310 43,960 43,001 15,026 584,048
Opex +Capex US ($k) - 49,511 19,240 33,758 48,639 41,894 37,425 40,616 47,679 51,825 50,941 58,786 51,151 44,310 49,698 43,001 19,533 688,006
Pre Tax Net Cash Flows US ($k) - (15,697) 14,313 (7,641) (2,008) 30,598 25,145 16,035 38,210 24,967 41,897 2,944 4,165 17,280 24,567 16,250 29,033 260,058
Taxable Income US ($k)   12,644 27,206 16,607 31,338 50,119 33,483 23,247 48,350 25,515 42,444 9,229 4,712 17,828 30,852 16,797 34,088 424,457
Tax Payable US ($k)   3,793 8,162 4,982 9,401 15,036 10,045 6,974 14,505 7,654 12,733 2,769 1,414 5,348 9,255 5,039 10,226 127,337
Net Cashflows after Tax US ($k)   (19,490) 6,151 (12,623) (11,409) 15,563 15,100 9,061 23,705 17,313 29,164 176 2,751 11,932 15,311 11,211 18,807 132,721
Add back Depreciation US ($k)   5,955 7,090 9,913 13,783 13,783 8,338 7,212 4,403 547 547 547 547 547 547 547 547 74,854
Net Cashflow after tax adjusted for tax dep US ($k)   (13,536) 13,240 (2,709) 2,373 29,346 23,438 16,273 28,107 17,860 29,711 723 3,298 12,479 15,859 11,758 19,354 207,575
After Tax NPV @ ( 3%) US ($k) 3%   156,552                              
After Tax @ NPV (5%) US ($k) 5%   130,964                              
After Tax @ NPV (8%) US ($k) 8%   101,495                              
After Tax IRR %     74%                              
Cash cost per oz $/oz   451 481 893 749 599 718 861 586 810 659 1,032 1,110 864 711 871 371 735
All in cash costs $/oz   1,758 689 1,552 1,252 694 718 861 667 810 659 1,143 1,110 864 804 871 483 933

 
 (VIRIMAI PROJECTS LOGO)Page 229
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

(ARK LOGO)

 

Reference: 2018-L01

 

16 July 2018

 

Buckreef Gold Company Limited
Plot No. 263, Chato Street, Regent Estate
P O Box 33407
Dares Salaam - Tanzania

 

Buckreef Gold Company Limited; TIN: 116-448-459
Expert Opinion on Net Present Value (NPV) Model for Buckreef Project covering a 16 years period

 

We have reviewed the NPV Model for the Buckreef project in accordance with our understanding of the taxation laws as currently applicable in Tanzanian. Based on our review, we confirm as experts in the taxation field in Tanzania that the parameters in the summary below for the 16 years model period (model attached) represent a true and fair view of the cash flow and project cost assumptions.

 

Table of NPV model results for Buckreef project

 

Description Years 1 to 16
(US$(k))
Gross revenue 1,026,471
Royalties and selling costs (78,402)
Net revenue 948,069
Capital costs (103,958)
Operating costs (584,048)
Pre-tax net cash flows 260,062
Tax (127,337)
Net cash-flow after Tax 132,725
Add back tax depreciation 74,854
Net cash-flow after tax & depreciation adjustments 207,579
After Tax NPV @ (3%) – US ($k) 156,552
After Tax NPV @ (5%) – US ($k) 130,964
After Tax NPV @ (8%) – US ($k) 101,495
After Tax IRR (%) 74%

 

We are available to provide clarifications in case of any queries on this confirmation.

 

Yours faithfully
(-s- John Shimbala)
John Shimbala, Director
Ark Associates Limited
(SEAL)

 

Ark Associates Limited, Ground Floor 369 Kilwa House, Toure Drive – Oysterbay, P O Box 23197 Dar es salaam, Tanzania,
Tel +255 2222 96800, Email:
info@ark.co.tz Website: www.ark.co.tz TIN: 130-210- 392 VRN: 40-024085-J

 

Figure 32.14. Expert Opinion on Buckreef Gold Project After-Tax Cashflow, NPV & IRR

 
 (VIRIMAI PROJECTS LOGO)Page 230
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.1: Buckreef Project Full Schedule of Mined Tonnages

 

 TRX Mine Plan 2019                                  
 YEAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Total
 MINING Summary                                  
Oxide Ore (Tonnes) 274,483 256,217 79,578 109,536 38,713 30,525 159,318 64,833 320,880 117,506 16,298 1,232 40,585 - - - -
Oxide Ore (g/t) 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - - -
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Oxide Ore & Waste 2,987,867 1,699,167 2,166,326 707,445 229,881 1,581,042 2,245,162 2,205,193 2,299,065 3,440,074 934,664 82,939 1,086,332 - - - -
                                   
Trans Ore (Tonnes) 91,927 191,820 149,582 93,467 92,763 91,086 40,183 21,171 81,587 341,223 255,904 51,915 17,472 - - - -
Trans Ore (g/t) 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Trans Ore & Waste 1,388,387 1,289,207 2,283,879 1,503,798 825,459 1,615,673 1,969,973 1,297,984 1,710,757 3,041,416 3,134,227 1,419,675 385,177 - - - -
                                   
Hard Ore (Tonnes) 42,968 186,569 346,182 554,797 1,246,759 1,522,363 1,269,055 1,262,780 1,059,983 1,122,314 1,091,578 1,439,843 1,496,521 1,386,337 1,110,020 915,073 -
Hard Ore (g/t) 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70 -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Hard Ore & Waste 551,246 1,952,626 4,401,044 7,379,132 9,027,784 8,361,405 9,253,780 10,557,224 15,700,177 13,282,510 15,641,109 16,929,886 13,645,153 14,273,999 14,285,570 2,017,443 -
                                   
Total Ore (Tonnes) 409,378 634,606 575,342 757,800 1,378,235 1,643,974 1,468,556 1,348,784 1,462,450 1,581,043 1,363,781 1,492,990 1,554,578 1,386,337 1,110,020 915,073 -
Total Ore (g/t) 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70 -
Total Waste 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370 -
Total Ore & Waste 4,927,500 4,941,000 8,851,250 9,590,375 10,083,125 11,558,119 13,468,915 14,060,401 19,709,999 19,763,999 19,709,999 18,432,500 15,116,663 14,273,999 14,285,570 2,017,443 -
 MILL FEED Summary                                  
Oxide Ore (Tonnes) 348,730 187,710 57,425 208,941 73,014 29,574 159,318 66,452 308,940 117,506 21,063 - 40,585 2,241 7,930 - 1,629,430
Oxide Ore (g/t) 2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 - 1.79
Trans Ore (Tonnes) 91,927 150,814 136,218 133,167 106,462 77,843 40,183 27,971 81,587 308,576 269,834 51,538 17,472 5,842 20,668 - 1,520,100
Trans Ore (g/t) 2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 - 1.92
Hard Ore (Tonnes) 42,968 146,426 289,982 625,143 1,271,034 1,347,066 1,251,009 1,356,088 1,059,983 1,028,401 1,159,613 1,398,972 1,392,453 1,446,401 1,322,530 915,073 16,053,143
Hard Ore (g/t) 1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70 1.48
  483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484      
Total Ore (Tonnes) 483,625 484,950 483,625 967,250 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,450,510 1,450,510 1,450,510 1,454,484 1,351,128 915,073 19,202,673
Hard Ore (g/t) 1.98 2.02 1.64 1.48 1.58 1.37 1.23 1.88 1.63 1.90 1.33 1.22 1.35 1.64 1.40 1.70 1.54
Oz Fed to Plant 30,748 31,540 25,534 45,975 73,767 64,004 57,394 87,814 75,987 88,989 61,959 56,839 62,911 76,537 60,916 50,091 951,012
Oxide Waste 2,713,383 1,442,951 2,086,748 597,909 191,169 1,550,517 2,085,844 2,140,360 1,978,185 3,322,567 918,366 81,707 1,045,748 - - - -
Trans Waste 1,296,460 1,097,386 2,134,297 1,410,330 732,696 1,524,586 1,929,790 1,276,813 1,629,170 2,700,193 2,878,323 1,367,761 367,706 - - - -
Hard Waste 508,278 1,766,057 4,054,862 6,824,336 7,781,025 6,839,042 7,984,725 9,294,444 14,640,194 12,160,196 14,549,531 15,490,042 12,148,632 12,887,663 13,175,550 1,102,370 -
Total 4,518,121 4,306,394 8,275,908 8,832,575 8,704,890 9,914,145 12,000,359 12,711,617 18,247,549 18,182,956 18,346,219 16,939,510 13,562,085 12,887,663 13,175,550 1,102,370  
SR 9.34 8.88 17.11 9.13 6.00 6.82 8.27 8.76 12.58 12.50 12.65 11.68 9.35 8.86 9.75 1.20 9.56

 
 (VIRIMAI PROJECTS LOGO)Page 231
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.2 Buckreef Project Summary of Schedule of Milled Tonnages

 

 Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
 MINING Summary                                
Oxide Ore (Tonnes) 274 256 80 110 39 31 159 65 321 118 16 1 41 - - -
Oxide Ore (g/t) 2.04 1.53 1.13 0.89 0.70 1.22 1.02 2.08 1.98 3.92 0.74 0.79 2.11 - - -
Oxide Waste 2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - -
Oxide Ore & Waste 2,988 1,699 2,166 707 230 1,581 2,245 2,205 2,299 3,440 935 83 1,086 - - -
                                 
Trans Ore (Tonnes) 92 192 150 93 93 91 40 21 82 341 256 52 17 - - -
Trans Ore (g/t) 2.18 2.86 1.63 0.87 1.01 1.01 1.57 1.04 1.05 3.10 1.29 0.91 2.72 - - -
Trans Waste 1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - -
Trans Ore & Waste 1,388 1,289 2,284 1,504 825 1,616 1,970 1,298 1,711 3,041 3,134 1,420 385 - - -
                                 
Hard Ore (Tonnes) 43 187 346 555 1,247 1,522 1,269 1,263 1,060 1,122 1,092 1,440 1,497 1,386 1,110 915
Hard Ore (g/t) 1.37 2.14 1.73 1.49 1.63 1.48 1.29 1.86 1.57 1.26 1.31 1.22 1.29 1.65 1.41 1.70
Hard Waste 508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102
Hard Ore & Waste 551 1,953 4,401 7,379 9,028 8,361 9,254 10,557 15,700 13,283 15,641 16,930 13,645 14,274 14,286 2,017
                                 
Total Ore (Tonnes) 409 635 575 758 1,378 1,644 1,469 1,349 1,462 1,581 1,364 1,493 1,555 1,386 1,110 915
Total Ore (g/t) 2.00 2.11 1.62 1.33 1.56 1.45 1.27 1.85 1.63 1.85 1.30 1.21 1.32 1.65 1.41 1.70
Total Waste 4,518 4,306 8,276 8,833 8,705 9,914 12,000 12,712 18,248 18,183 18,346 16,940 13,562 12,888 13,176 1,102
Total Ore & Waste 4,927 4,941 8,851 9,590 10,083 11,558 13,469 14,060 19,710 19,764 19,710 18,432 15,117 14,274 14,286 2,017
                                 
 MILL FEED
Summary
                               
Oxide Ore (Tonnes) 349 188 57 209 73 30 159 66 309 118 21 - 41 2 8 -
Oxide Ore (g/t) 2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 -
Trans Ore (Tonnes) 92 151 136 133 106 78 40 28 82 309 270 52 17 6 21 -
Trans Ore (g/t) 2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 -
Hard Ore (Tonnes) 43 146 290 625 1,271 1,347 1,251 1,356 1,060 1,028 1,160 1,399 1,392 1,446 1,323 915
Hard Ore (g/t) 1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70
  484 485 484 967 1,451 1,454 1,451 1,451 1,451 1,454 1,451 1,451 1,451 1,454 1,351 915
Total Ore (Tonnes) 484 485 484 967 1,451 1,454 1,451 1,451 1,451 1,454 1,451 1,451 1,451 1,454 1,351 915
Hard Ore (g/t) 1.98 2.02 1.64 1.48 1.58 1.37 1.23 1.88 1.63 1.90 1.33 1.22 1.35 1.64 1.40 1.70
Oz Fed to Plant 31 32 26 46 74 64 57 88 76 89 62 57 63 77 61 50
Oxide Waste 2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - -
Trans Waste 1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - -
Hard Waste 508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102

 
 (VIRIMAI PROJECTS LOGO)Page 232
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.3: Full Schedule of Staffing Requirements of the Buckreef Project

 

      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
MANAGEMENT   (US$)                                  
Chief Operating Officer M 120,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
General Manager   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Executive Secretary S 42,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL   162,000 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
MINE OPERATION                                      
Mine /Production Manager M 72,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Pit Superintendent   0   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Shift Supervisor S 12,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Driller-Contractor/Supervisor C 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Blasters-Contractor/Supervisor C 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Loader Operator S 9,600   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Excavator Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Truck Driver /Dumper S 8,400 1 10 10 10 5 10 10 10 10 10 10 10 10 10 10 10 10
Wheel Dozer Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Track Dozer Operator S 9,600 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Water Truck Operator S 8,400 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Grader Operator S 9,600   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Lube Fuel Truck Operator S 9,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Ore Spotter S 9,000 2 2 2 2 6 2 2 2 2 2 2 2 2 2 2 2 2
Pit Pump Operator S 9,000 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Laborer L 9,000 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
TOTAL   202,800 12 36 36 36 35 36 36 36 36 36 36 36 36 36 36 36 36
MINING ENGINEERING                                      
Engineering Manager   60,000 0 0 0 0 1 0 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Shift Supervisor S 30,000 2 3 4 5 4 7 4 3 3 3 3 3 3 3 3 3 3
Mine Engineers S 24,000 1 2 2 2 2 2 1                    
Fitters and Mechanics S 12,000 10 20 20 20 20 10 10                    
Fuel Bay Attendants Fitter Asst L 6,000 4 4 4 4 14 4 4 2 2 2 2 2 2 2 2 2 2
Data Clerks L 6,000 1 1 1 1 1 1 1 11 7 7 7 7 7 7 7 7 7
TOTAL     18 30 31 32 42 24 20 16 12 12 12 12 12 12 12 12 12
                                       
TECHNICAL SERVICES                                      
Geology Manager   0 0 0 0 0 0 0 0 0.0                  
Mine Surveyor S 30,000 2 2 2 2 3 3 3                    
      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

 
 (VIRIMAI PROJECTS LOGO)Page 233
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Geotechnical Engineer L 21,600 1 1 1 1 1 1 1                    
Survey Technician L 10,800 1 3 3 3 4 4 4                    
Geotechnical Technicisn L 10,800 1 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1
Mine/Exploration Geologist S 36,000 2 2 2 2 2 2 1                    
Resource Geologist   0 0 0 0 0 0 0 0                    
Geology Technician L 10,800 4 2 4 4 4 4 4                    
Data Clerk L 6,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     12 13 15 15 17 17 16 2 2 2 2 2 2 2 2 2 2
                                       
PROCESS PLANT                                      
Plant Manager/Supritendent M 72,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Process/Maintanance Engineer S 30,000   1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1
Shift Supervisor S 30,000   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Gold Room Supervisor S 30,000   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Operators L 10,800   20 20 20 0 20 20 20 20 20 20 20 20 20 20 20 20
Fitters and Mechanics S 10,800   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
Metallurgist S 24,000 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1
Effluent Treatment Operator L 8,400   2 2 2 0 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 31 31 31 1 31 31 31 31 31 31 31 31 31 31 31 31
                                       
SAFETY, HEALTH & ENVIRONMENT                                      
SHE Manager M 60,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Medical Doctor S 36,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety/Environment Officer S 30,000 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Nurse S 11,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Lab Technician S 11,400 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     2 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
METALLURGICAL LABORATORY                                      
Chief Chemist S 36,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Assayers S 8,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Sample Preparation L 8,400   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Instrumentation Techn. S 10,800   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     0 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
HUMAN RESOURCES                                      
Human Resource Manager   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
HR Officer S 30,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Community Relations Officer S 18,000 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
      2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

 
 (VIRIMAI PROJECTS LOGO)Page 234
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Administration Officer S 18,000   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
PURCHASING                                      
Chief Buyer S 48,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Procurement Officer S 12,000   1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Receiving Supervisor   0   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Data Clerks L 7,200   2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
ACCOUNTING                                      
Chief Accountant M 72,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Accountant/Payroll Officer S 36,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Accountant/Accounts payable officer S 36,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Cost accountant/PPE S 48,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
IT Technician S 18,000 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL     2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
CAMP                                      
Camp Manager S 42,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Chief Cook S 30,000 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Assistant Cook L 10,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Kitchen Assistant L 10,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Office Cleaners L 7,200 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TOTAL     8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8

 
 (VIRIMAI PROJECTS LOGO)Page 235
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.4: Summary of Capital Costs Estimates

 

    60tph Prod   120tph Prod

180tph Prod 

   
Item Capital Description No Unit Cost Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
  Capital Plan   USD USD              
1 Mining                    
1.1 Mining Equipment ( Fleet) 1 17,531,424 17,531,424 8,737,653 4,581,271   4,212,500    
1.2 Loader 3 265,500 796,500 796,500            
1.3 Water Truck 0 100,000 100,000 100,000            
1.4 Service Truck 1 100,000 100,000 100,000            
1.5 Light Trucks & Cars 8 41,500 332,000 166,000 166,000          
1.6 Dewatering Pump 4 40,000 160,000 160,000            
1.7 Survey Tools 1 45,000 45,000 45,000            
1.8 Pit Optimisation 1 75,000 75,000 75,000            
1.9 Mining Offices/Shop 1 300,000 300,000 300,000            
1.1 Haul Roads 1 100,000 100,000 100,000            
1.11 HME - Workshop Construction 1 700,000 700,000 700,000            
1.12 Explosive magazine 1 150,000 150,000   150,000          
1.13 Fuel Tanks with a Capacity to hold 400klt 1 240,000 240,000 240,000            
  Subtotal Mining     20,629,924 11,520,153 4,897,271 0 4,212,500      
2 Processing Plant                    
2.1 TSF Construction & Design 1 1,750,000 1,750,000 1,250,000   250,000 250,000      
2.2 Portable Water Plant 1 600,000 600,000 300,000   300,000        
2.3 Laboratory 1 500,000 500,000 500,000            
2.4 Process Plant Development 1 35,284,625 35,284,625 11,500,000 150,000 11,500,000 12,134,625      
2.5 Generators 4No x 2.5MVa 1 1,243,000 1,243,000 414,333 - 414,333 414,333      
2.6 Substation and Power Reticulation 1 500,000 500,000 500,000            
2.7 Engineering Workshop for Plant +tools 1 400,000 400,000 400,000            
  Subtotal Processing Plant   40,277,625 40,277,625 14,864,333 150,000 12,464,333 12,798,958      
3 Human Resources & Community                    
3.1 Camping Facilities 1 250,000 250,000 250,000            
3.2 Camp Houses (2Bx20+4Bx30) 50 15,000 750,000 750,000            
3.3 Relocation of Mnekezi road 1 250,000 250,000 250,000            
3.4 Airport/Aerodrome 1 35,000 35,000 35,000            
3.5 Helicopter Pad 1 10,000 10,000 10,000            
3.6 Compensation - Relocation from SML 1 2,500,000 2,500,000 2,500,000            
3.7 Sewer Ponds & Facilities 1 350,000 350,000 350,000            
3.8 Security fencing 1 520,000 520,000 520,000            
  Subtotal Human Resources & Community   3,930,000 4,665,000 4,665,000 0 0 0      
4 HSE                    
4.1 Clinic 1 100,000 100,000 100,000            

 
 (VIRIMAI PROJECTS LOGO)Page 236
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

    60tph Prod   120tph Prod

180tph Prod

   
Item Capital Description No Unit Cost Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
4.2 Waste Handling Facilties 1 75,000 75,000 75,000            
  Subtotal HSE   175,000 175,000 175,000 0 0 0      
5 Finance + IT                    
5.1 Computer & Server 1 40,000 40,000 40,000            
5.2 Desktop 1 45,000 45,000 45,000            
5.3 Laptop 1 30,000 30,000 30,000            
5.4 Networking & Communication 1 40,000 40,000 40,000            
5.5 Process Plant Insurance - 6% Plant Cost 1 600,000 600,000 600,000            
5.6 Mining Equipment Insurance - 2.5% Equip Cost 1 19,913 19,913 19,913            
  Subtotal Finance +IT   774,913 774,913 774,913 0 0 0      
6 Contingency 15% 15%   9,978,369 4,799,910 757,091 1,869,650 2,551,719      
7 Total Capex     76,500,831 36,799,309 5,804,362 14,333,983 19,563,177      
                       
  For Depreciation     Total Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
1 Plant and Equipment US$   64,707,681 26,873,384 5,876,725 14,657,200 20,113,750      
2 Building and Infrastructure US$   11,059,500 10,887,000 3,952,500 3,780,000 3,780,000      
3 Office & Computers Equipment US$   891,150 891,150 0 0 0      
4 Total US$   76,658,331 38,651,534 9,829,225 18,437,200 23,893,750      

 
 (VIRIMAI PROJECTS LOGO)Page 237
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

Table 32.50: Equipment Operating Costs\

 

FUEL PRICE USD 1.20 Type TRACKED
BULL
DOZER
TRACKED
BULL
DOZER
MOTOR GRADER HYDRAULIC
EXCAVATOR
HYDRAULIC
EXCAVATOR
ARTICULATED
DUMP TRUCK
FUEL
BOWSER
WATER
BOWSER
TRACKED
DRILL
RIG
ENGINE OIL USD 4.60 Make BELL CAT CAT CAT LIEBHEER BELL BELL BELL Sandvik
TRANS OIL USD 7.17 Model PR754 D8R 140H 374 R966 B40D B25E B30E  
HYD OIL USD 4.60 kW   123 112            
F / DRIVE OIL USD 5.10 kg 32,000 17,083 13,529           32,000
Delivery Price DP   USD 683,771.00 USD 850,000.00 USD 385,000.00 USD 855,000.00 USD 855,000.00 USD 540,000.00 USD 343,000.00 USD 385,000.00 USD 675,750.00
Residual Value At Replacement RVR   USD 0.00 USD 85,000.00 USD 38,500.00 USD 85,500.00 USD 85,500.00 USD 54,000.00 USD 34,300.00 USD 38,500.00 USD 0.00
Value To Be Recovered
Through Work
VRTW   USD 683,771.00 USD 765,000.00 USD 346,500.00 USD 769,500.00 USD 769,500.00 USD 486,000.00 USD 308,700.00 USD 346,500.00 USD 675,750.00
Estimated Ownership N years 5 5 5 5 5 6 10 5 5
Estimated Usage H hours/year 7,200 7,200 7,200 7,200 7,200 7,200 4,500 7,200 7,200
Ownership Usage T hours 36,000 36,000 36,000 36,000 36,000 43,200 45,000 36,000 36,000
Cost Per Hour CPH USD/hr USD 18.99 USD 21.25 USD 9.63 USD 21.38 USD 21.38 USD 11.25 USD 6.86 USD 9.63 USD 18.77
Simple Interest Rate SI % 12% 12% 12% 12% 12% 12% 12% 12% 12%
Interest Costs SIC USD/hr USD 6.84 USD 8.50 USD 3.85 USD 8.55 USD 8.55 USD 5.25 USD 5.03 USD 3.85 USD 6.76
Insurance Rate IN % 2% 2% 2% 2% 2% 2% 4% 4% 2%
Insurance Costs INSC USD/hr USD 1.14 USD 1.42 USD 0.64 USD 1.43 USD 1.43 USD 0.88 USD 1.68 USD 1.28 USD 1.13
                       
TOTAL OWNING COSTS TOC USD/hr USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
                       
Fuel Consumption Rate F litres/hour 35 35 20 60 60 28 20 27 28
Fuel Price FP USD/litre USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20 USD 1.20
Dry (D) Or Wet (W) Rate D/W w w w w w w w w w w
Fuel Consumption FC USD/hour USD 42.00 USD 42.00 USD 24.00 USD 72.00 USD 72.00 USD 33.60 USD 24.00 USD 32.40 USD 33.60
                       
Engine Oil Price EOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60
Engine Oil Consumption Rate EOCR litres/hour 0.160 0.140 0.140 0.300 0.200 0.150 USD 0.15 0.150 0.160
Transmission Oil Price TOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60
Transmission Oil Consumption Rate TOCR litres/hour 0.150 0.144 0.047 0.000 0.000 0.040 USD 0.04 0.040 0.150
Final Drives Fluid Price FDFP USD USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 5.10 USD 0.00
Final Drives Fluid Consumption
Rate
FDFCR litres/hour 0.015 0.013 0.065 0.150 0.040 0.050 USD 0.05 0.050 0.015
Hydraulic Oil Price HOP USD USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 4.60 USD 0.00
Hydraulic Oil Consumption
Rate
HOCR litres/hour 0.075 0.050 0.019 1.000 1.000 0.250 USD 0.25 0.250 0.075
Grease Price GP USD USD 6.20 USD 6.20 USD 6.20 USD 6.20 USD 6.20 6.200 USD 6.20 USD 6.20 USD 6.20
Grease Consumption Rate GCR kg/hour 0.140 0.139 0.139 0.200 0.200 0.140 0.140 0.140 0.140
Engine Oil Cost EOC USD/hour USD 0.74 USD 0.64 USD 0.64 USD 1.38 USD 0.92 USD 0.69 USD 0.69 USD 0.69 USD 0.74
Transmission Oil Cost TOC USD/hour USD 0.69 USD 0.66 USD 0.22 USD 0.00 USD 0.00 USD 0.18 USD 0.18 USD 0.18 USD 0.69
Final Drives Fluid Cost FDFC USD/hour USD 0.08 USD 0.07 USD 0.33 USD 0.77 USD 0.20 USD 0.26 USD 0.26 USD 0.26 USD 0.00
Hydraulic Oil Cost HOC USD/hour USD 0.35 USD 0.23 USD 0.09 USD 4.60 USD 4.60 USD 1.15 USD 1.15 USD 1.15 USD 0.00
Grease Cost GC USD/hour USD 0.87 USD 0.86 USD 0.86 USD 1.24 USD 1.24 USD 0.87 USD 0.87 USD 0.87 USD 0.87
Filter Cost [From Tables] FILC USD/hour USD 2.00 USD 1.50 USD 1.50 USD 2.50 USD 2.50 USD 2.00 USD 2.00 USD 2.00 USD 2.00
Total Lubricants, Oils And
Filter Cost
LC USD/hour USD 6.51 USD 6.51 USD 3.72 USD 11.16 USD 11.16 USD 5.04 USD 3.72 USD 5.02 USD 5.21
                       
Number Of Wheels NW     0 6 0 0 6 6 6 0
Tyre Size TS     0 17.5x25 0 0 26.5R25 26.5R25 26.5R25 0
Tyre Price CT     USD 0.00 USD 2,500.00 USD 0.00 USD 0.00 USD 6,500.00 USD 6,500.00 USD 6,500.00 0
Life Of Tyre LT hours   0 2,000 0 0 4,500 6,000 3,000 0
Tyre Replacement Cost TRC     USD 0.00 USD 7.50 USD 0.00 USD 0.00 USD 8.67 USD 6.50 USD 13.00 USD 0.00
                       
FUEL PRICE USD 1.20 Type TRACKED TRACKED MOTOR HYDRAULIC HYDRAULIC ARTICULATED FUEL WATER TRACKED

 
 (VIRIMAI PROJECTS LOGO)Page 238
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Project 

      BULL
DOZER
BULL
DOZER
GRADER EXCAVATOR EXCAVATOR DUMP
TRUCK
BOWSER BOWSER DRILL
RIG
ENGINE OIL USD 4.60 Make BELL CAT CAT CAT LIEBHEER BELL BELL BELL Sandvik
TRANS OIL USD 7.17 Model PR754 D8R 140H 374 R966 B40D B25E B30E  
Impact Factor IF   0.4 0.4 0.0 0.5 0.4 0.0 0.0 0.0 0.4
                       
Abrasiveness A   0.6 0.6 0.0 0.6 0.6 0.0 0.0 0.0 0.6
“Z” Factor Z   0.5 0.5 0.0 1.0 1.0 0.0 0.0 0.0 0.5
Undercarriage Basic Factor Ba   10.0 10.0 0.0 10.0 10.0 0.0 0.0 0.0 6.0
Extended Use Multiplier EM   1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Basic Repair Factor BF   10 10 5.0 10.0 10.0 10.0 6.0 6.0 4
Undercarriage Repair Costs URC USD/hour USD 15.00 USD 15.00 USD 0.00 USD 21.00 USD 20.00 USD 0.00 USD 0.00 USD 0.00 USD 9.00
Repair Reserve RR   USD 10.00 USD 10.00 USD 5.00 USD 10.00 USD 10.00 USD 10.00 USD 6.00 USD 6.00 USD 11.00
                       
Price Of Cutting Edges/Bucket PCE USD USD 400.00 USD 460.00 USD 248.39 USD 20,000.00 USD 20,000.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Ripper Tips/Picks PRT USD USD 200.00 USD 230.00 USD 16.16 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Bucket Tips/Pick Holders PBT USD USD 0.00 USD 0.00 USD 0.00 USD 400.00 USD 400.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Price Of Bin Liners/Corner
Piece/End Ring
PEB USD USD 350.00 USD 402.50 USD 281.54 USD 0.00 USD 0.00 USD 3,000.00 USD 2,000.00 USD 2,000.00 USD 0.00
No. Of Cutting Edges NCE   2 2 2 1 1 0 0 0 0
No. Of Ripper Tips/Picks NRT   1 3 3 0 0 0 0 0 0
No. Of Bucket Tips/Pick Holders NRT   0 0 0 4 4 0 0 0 0
No. Of Bin Liners/Corner Piece/Endrings NEB   2 2 2 1 0 1 1 1 0
Life Of Cutting Edges/Bucket LCE hours 200 200 200 2,000 2,000 0 0 0 0
Life Of Ripper Tips/Picks LRT hours 200 200 200 0 0 0 0 0 0
Life Of Bucket Tips/Pick
Holders
LBT hours 0 0 0 150 150 0 0 0 0
Life Of Bin Liners/Corner
Piece/End Ring
LEB hours 200 250 0 0 0 2,500 4,000 4,000 0
Cost Of Cutting Edges CCE USD/hour USD 4.00 USD 4.60 USD 2.48 USD 10.00 USD 10.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Ripper Tips CRT USD/hour USD 1.00 USD 3.45 USD 0.24 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Bucket Tips CBT USD/hour USD 0.00 USD 0.00 USD 0.00 USD 10.67 USD 10.67 USD 0.00 USD 0.00 USD 0.00 USD 0.00
Cost Of Bin Liners CEB USD/hour USD 3.50 USD 3.22 USD 0.00 USD 0.00 USD 0.00 USD 1.20 USD 0.50 USD 0.50 USD 0.00
Special Wear Items SWI USD/hour USD 8.50 USD 11.27 USD 2.73 USD 20.67 USD 20.67 USD 1.20 USD 0.50 USD 0.50 USD 0.00
                       
Operator Costs OPC USD/hour USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00 USD 0.00
                       
TOTAL OPERATING CXOSTS TOC USD/hour USD 82.01 USD 84.78 USD 42.95 USD 134.83 USD 133.83 USD 58.51 USD 40.72 USD 56.92 USD 58.81
                       
    USD/hour USD 82.01 USD 84.78 USD 42.95 USD 134.83 USD 133.83 USD 58.51 USD 40.72 USD 56.92 USD 58.81
                       

 
 (VIRIMAI PROJECTS LOGO)Page 239
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Mine Project 

Table 32.7: Buckreef Cash Flow Analysis

 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Ore Mining                                      
Oxide Ore (Tonnes) kt   349 188 57 209 73 30 159 66 309 118 21 - 41 2 8 - 1,629
Oxide Ore (g/t) g/t   2.00 1.40 1.24 1.28 1.17 1.20 1.02 2.07 1.98 3.92 0.97 - 2.11 1.65 1.65 -  
Trans Ore (Tonnes) kt   92 151 136 133 106 78 40 28 82 309 270 52 17 6 21 - 1,520
Trans Ore (g/t) g/t   2.18 2.68 1.72 1.46 1.25 1.01 1.57 1.06 1.05 3.27 1.30 0.92 2.72 1.41 1.41 -  
Hard Ore (Tonnes) kt   43 146 290 625 1,271 1,347 1,251 1,356 1,060 1,028 1,160 1,399 1,392 1,446 1,323 915 16,053
Hard Ore (g/t) g/t   1.37 2.15 1.69 1.55 1.63 1.39 1.25 1.89 1.57 1.26 1.34 1.23 1.31 1.64 1.40 1.70  
Oxide Waste kt   2,713 1,443 2,087 598 191 1,551 2,086 2,140 1,978 3,323 918 82 1,046 - - - 20,155
Trans Waste kt   1,296 1,097 2,134 1,410 733 1,525 1,930 1,277 1,629 2,700 2,878 1,368 368 - - - 20,346
Hard Waste kt   508 1,766 4,055 6,824 7,781 6,839 7,985 9,294 14,640 12,160 14,550 15,490 12,149 12,888 13,176 1,102 141,207
Oxide & Trans Ore Recovery % 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%  
Sulphide Ore Recovery   85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%  
Mining Dilution % 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%  
Gold produced                                      
Fine (kg) kg   876 869 677 1,208 1,878 1,621 1,468 2,225 1,989 2,405 1,599 1,433 1,595 1,924 1,535 1,258 24,559
Fine (oz) (1oz =31.1034768grams) koz   28,162 27,944 21,752 38,837 60,375 52,111 47,181 71,532 63,956 77,320 51,412 46,069 51,295 61,851 49,347 40,448 789,593
Gold price (US$000) $/oz 1300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300  
                                       
Gross revenue US ($000) 0 36,610 36,327 28,277 50,488 78,487 67,744 61,336 92,992 83,143 100,516 66,835 59,890 66,684 80,406 64,151 52,583 1,026,471
Less Royalties & Selling Costs                                     -
: Royalties 7.3% on Revenue   7.3% (2,673) (2,652) (2,064) (3,686) (5,730) (4,945) (4,478) (6,788) (6,069) (7,338) (4,879) (4,372) (4,868) (5,870) (4,683) (3,839) (74,932)
: Selling Costs per oz of gold   4.40 (124) (123) (96) (171) (266) (229) (208) (315) (281) (340) (226) (203) (226) (272) (217) (178) (3,470)
Net revenue     33,814 33,553 26,117 46,631 72,492 62,570 56,651 85,889 76,792 92,838 61,730 55,315 61,590 74,264 59,251 48,566 948,064

 
 (VIRIMAI PROJECTS LOGO)Page 240
  

 (TANZANIAN GOLD CORPORATION LOGO)NI43-101 ITR - Updated Mineral Resource Estimate for Buckreef Gold Mine Project 

  YEARS
Description Rates Fact Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Total
Capital Costs US ($k)                                    
Start up Capital     36,799 5,804 14,334 19,563                         76,501
Closure Costs U$                                 4,507 4,507
Sustaining Costs U$ 7.5% - - -   5,738 - - 5,738 - - 5,738 - - 5,738   - 22,950
Total Capital Costs U$ - 36,799 5,804 14,334 19,563 5,738 - - 5,738 - - 5,738 - - 5,738 - 4,507 103,958
Operating expenditure U$                                    
Mining Rates US ($k)                                    
Drill & Blast Waste $/tw 0.74 1,337 2,122 3,796 6,103 6,310 6,198 7,348 7,834 12,057 11,013 12,916 12,493 9,276 9,551 9,764 817 118,936
Drill & Blast Ore $/to 0.90 122 269 385 685 1,244 1,287 1,166 1,250 1,031 1,208 1,291 1,310 1,274 1,312 1,213 827 15,876
Load and Haul Ore $/to 1.13 544 546 544 1,088 1,632 1,637 1,632 1,632 1,632 1,637 1,632 1,632 1,632 1,637 1,520 1,030 21,609
Load and Haul waste $/tw 1.03 4,663 4,444 8,541 9,115 8,983 10,231 12,384 13,118 18,831 18,764 18,933 17,481 13,996 13,300 13,597 1,138 187,519
Overhaul rate $/t/km 0.08                                  
Mine Rehabilitation $/tw 0.03 136 129 248 265 261 297 360 381 547 545 550 508 407 387 395 33 5,451
Processing Rates                                      
Processing reagents $/to 10.24 4,952 4,966 4,952 9,905 14,853 14,894 14,853 14,853 14,853 14,894 14,853 14,853 14,853 14,894 13,836 9,370 196,646
Labour Costs $/to 1.98 958 960 958 1,915 2,872 2,880 2,872 2,872 2,872 2,880 2,872 2,872 2,872 2,880 2,675 1,812 38,023
Total operating costs US ($k)   12,712 13,436 19,424 29,076 36,156 37,425 40,616 41,942 51,825 50,941 53,048 51,151 44,310 43,960 43,001 15,026 584,048
Opex +Capex US ($k) - 49,511 19,240 33,758 48,639 41,894 37,425 40,616 47,679 51,825 50,941 58,786 51,151 44,310 49,698 43,001 19,533 688,006
Pre Tax Net Cash Flows US ($k) - (15,697) 14,313 (7,641) (2,008) 30,598 25,145 16,035 38,210 24,967 41,897 2,944 4,165 17,280 24,567 16,250 29,033 260,058
Taxable Income US ($k)   12,644 27,206 16,607 31,338 50,119 33,483 23,247 48,350 25,515 42,444 9,229 4,712 17,828 30,852 16,797 34,088 424,457
Tax Payable US ($k)   3,793 8,162 4,982 9,401 15,036 10,045 6,974 14,505 7,654 12,733 2,769 1,414 5,348 9,255 5,039 10,226 127,337
Net Cashflows after Tax US ($k)   (19,490) 6,151 (12,623) (11,409) 15,563 15,100 9,061 23,705 17,313 29,164 176 2,751 11,932 15,311 11,211 18,807 132,721
Add back Depreciation US ($k)   5,955 7,090 9,913 13,783 13,783 8,338 7,212 4,403 547 547 547 547 547 547 547 547 74,854
Net Cashflow after tax adjusted for tax dep US ($k)   (13,536) 13,240 (2,709) 2,373 29,346 23,438 16,273 28,107 17,860 29,711 723 3,298 12,479 15,859 11,758 19,354 207,575
After Tax NPV @ ( 3%) US ($k) 3%   156,552                              
After Tax @ NPV (5%) US ($k) 5%   130,964                              
After Tax @ NPV (8%) US ($k) 8%   101,495                              
After Tax IRR %     74%                              
Cash cost per oz $/oz   451 481 893 749 599 718 861 586 810 659 1,032 1,110 864 711 871 371 735
All in cash costs $/oz   1,758 689 1,552 1,252 694 718 861 667 810 659 1,143 1,110 864 804 871 483 933

 
 (VIRIMAI PROJECTS LOGO)Page 241