NOTE 15 SUBSEQUENT EVENT

 

On September 30, 2024, the U.S. Federal District Court (“Court”) issued a ruling in the lawsuit challenging the U.S. Army Corps of Engineers’ issuance of the 404 permit and the Department of Interior, Bureau of Land Management’s issuance of the ROW lease for the portions of the pipeline on Federal lands. The decision upheld the federal agencies’ analysis on two of the three issues raised in the litigation, however agreed with plaintiffs that the federal agencies took too narrow a view in analyzing the impacts of a theoretical release from the tailing storage facility. The Court requested supplemental briefing on the appropriate remedy for addressing this issue, which is due October 21, 2024. The Company has determined that the Court’s decision does not require an adjustment to the Company’s financial statements.