NOTE 12 – NOTES PAYABLE – EQUIPMENT

 

The following is a summary of the equipment notes payable:

 

   December 31,
2018
   December 31,
2017
 
Note payable to Komatsu Financial, collateralized by a Komatsu Telehandler lift, due in 48 monthly installments of $2,441 including interest at 4.99%.  $27,192   $47,154 
           
Note payable to CAT Financial, collateralized by crushing equipment, due in 7 monthly installments of $39,000, beginning in May 2018, including interest at 4.0%.   145,067    -0- 
           
Note payable to CAT Financial, collateralized by used mining equipment due in 36 monthly installments of varying amounts including interest at 4.68%.   117,002    266,675 
           
Note payable to Komatsu Financial, collateralized by a Komatsu D275 dozer, due in monthly installments of $11,674 including interest at 2.99%.   34,851    149,687 
           
Note payable to Star Capital, LLC, collateralized by a 2009 Multiquip generator, due in 24 monthly installments of $1,412, beginning in March 2016, including interest at 11.4%.   -0-    5,515 
           
   $324,111   $469,031 
Current portion   (324,111)   (452,214)
Long term portion  $-0-   $16,817 

 

In November 2016, five pieces of mining equipment financed by CAT Financial were repossessed by CAT. The note payable due to CAT at the time of disposition was $960,585. The loss on impairment of equipment in the amount of $147,214 was recognized in the 2016. On July 31, 2017, a new agreement was made with Wheeler Machinery and CAT Financial for the return of four pieces of this equipment to the Company. The equipment temporarily remained in the possession of Wheeler Machinery and a new payment schedule was established. In May 2018, a note for the remaining payments due for $273,067 was formalized. Of this amount, $141,631 represented the value of the equipment and the remaining amount of $131,436 was to settle accounts payable for past due rent. The equipment was refurbished and returned to the site in 2019.

 

All of the above notes were paid in full in March 2019 as part of funding from a Pre-paid Forward Gold Purchase Agreement. See Note 20.