XML 40 R31.htm IDEA: XBRL DOCUMENT v3.23.2
Deposits on Mining Equipment (Tables)
3 Months Ended 12 Months Ended
Mar. 31, 2023
Dec. 31, 2022
Deposits On Mining Equipment    
Schedule of Mining Equipment

Deposits on mining equipment, consisted of the following:

 

   Cryptocurrency Miners   Mobile Data Centers   Total 
Balance December 31, 2021  $7,089,000   $524,230   $7,613,230 
Deposits on equipment during the period   1,602,300    530,430    2,132,730 
Equipment delivered during the period   (4,722,300)   (349,980)   (5,072,280)
Balance December 31, 2022  $3,969,000   $704,680   $4,673,680 
Deposits on equipment during the period   47,600        47,600 
Equipment delivered during the period            
Balance March 31, 2023  $4,016,600   $704,680   $4,721,280 

Deposits on mining equipment, consisted of the following:

 

  

Cryptocurrency

Miners

  

Mobile Data

Centers

  

 

Total

 
Balance December 31, 2020  $   $   $ 
Deposits on equipment during the period   7,089,000    524,230    7,613,230 
Equipment delivered during the period            
Balance December 31, 2021  $7,089,000   $524,230   $7,613,230 
Deposits on equipment during the period   1,602,300    530,430    2,132,730 
Equipment delivered during the period   (4,722,300)   (349,980)   (5,072,280)
Balance December 31, 2022  $3,969,000   $704,680   $4,673,680 
Schedule of Estimated Market Price of Miners  

Schedule of Estimated Market Price of Miners

  

Market Price

per Miner

   Total Amount 
July 2022 batch (100 miners)  $7,756   $775,600 
August 2022 batch (100 miners)   7,140    714,000 
September 2022 batch (100 miners)   7,140    714,000 
October 2022 batch (100 miners)   6,510    651,000 
November 2022 batch (100 miners)   5,810    581,000 
December 2022 batch (100 miners)   5,810    581,000 
Estimated total amount due        4,016,600 
Less: Payments made        3,969,000 
Remaining amount due       $47,600