Jointly Owned Utility Plant Interests [Line Items]  
Projected Solar Farm Project Costs $ 65.0
Public Utilities Property Plant And Equipment Construction Work In Progress 44.2
Allowance for Funds Used During Construction  
AFUDC - equity funds $ 0.8
Two Creeks Units [Member] | MGE [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Jointly owned utility plant, ownership interest 33.00%
Jointly owned utility plant, plant capacity (in MW) | MW 150
Two Creeks Units [Member] | MGE [Member] | Public Service Commission of Wisconsin [Member]  
Allowance for Funds Used During Construction  
Authorized AFUDC rate - Signficiant projects (100%) 100.00%
Badger Hollow Units [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Projected Solar Farm Project Costs $ 65.0
Public Utilities Property Plant And Equipment Construction Work In Progress 22.3
Allowance for Funds Used During Construction  
AFUDC - equity funds $ 0.4
Badger Hollow Units [Member] | MGE [Member]  
Jointly Owned Utility Plant Interests [Line Items]  
Jointly owned utility plant, ownership interest 33.00%
Jointly owned utility plant, plant capacity (in MW) | MW 150
Badger Hollow Units [Member] | MGE [Member] | Public Service Commission of Wisconsin [Member]  
Allowance for Funds Used During Construction  
Authorized AFUDC rate - Signficiant projects (100%) 100.00%