Joint Plant (Tables)
6 Months Ended
Jun. 30, 2025
Public Utilities, Property, Plant and Equipment [Abstract]  
Schedule of Jointly Owned Utility Plants

MGE has ownership interests in generation projects with other co-owners, some of which are under construction, as shown in the following table. Incurred costs are reflected in "Property, plant, and equipment, net" or "Construction work in progress" on the consolidated balance sheets.

 

Project

 

Ownership Interest

 

Source

 

Share of
Generation

 

Share of Estimated
Costs
(a)

 

Costs incurred as
of June 30, 2025
(a)

 

Date of
Commercial
Operation

Paris(b)

 

10%

 

Battery

 

11 MW

 

$25 million(g)

 

$23.4 million

 

June 2025 Battery

Darien(c)

 

10%

 

Solar/Battery

 

25 MW/7.5 MW

 

$63 million(g)

 

$46.3 million

 

March 2025 Solar
2026 Battery
(h)

Koshkonong(d)

 

10%

 

Solar/Battery

 

30 MW/16.5 MW

 

$104 million(g)

 

$24.8 million

 

2026 Solar(h)
2027 Battery
(h)

High Noon(e)

 

10%

 

Solar/Battery

 

30 MW/16.5 MW

 

$99 million

 

$17.8 million

 

2027(h)

Columbia Energy Dome(f)

 

19%

 

Storage

 

3 MW

 

$17 million

 

$0.7 million

 

2027(h)

 

(a)
Excluding AFUDC.
(b)
Paris Solar-Battery Park is located in the Town of Paris in Kenosha County, Wisconsin.
(c)
Darien Solar Energy Center is located in Walworth and Rock Counties in southern Wisconsin.
(d)
Koshkonong Solar Energy Center is located in the Towns of Christiana and Deerfield in Dane County, Wisconsin.
(e)
High Noon Solar Project is located in Columbia County, Wisconsin.
(f)
Columbia Energy Dome is located in Columbia County, Wisconsin.
(g)
Estimated costs are expected to exceed PSCW previously approved Certificate of Authority (CA) levels. Notifications are provided to the PSCW when costs increase above CA levels. MGE has and will continue to request recovery of the updates in its rate case proceedings.
(h)
Estimated date of commercial operation.