XML 80 R61.htm IDEA: XBRL DOCUMENT v3.25.0.1
Variable Interest Entities (Details) - USD ($)
$ in Thousands
Dec. 31, 2024
Dec. 31, 2023
Variable Interest Entity [Line Items]    
In-service utility plant, net $ 2,149,138 $ 2,018,121
Construction work in progress 138,208 110,091
Accrued interest and accrued (prepaid) taxes 11,558 9,372
Deferred income taxes 316,397 279,029
Unamortized discount and debt issuance costs 4,419 4,579
MGE Power Elm Road [Member]    
Variable Interest Entity [Line Items]    
In-service utility plant, net 159,576 162,210
Construction work in progress 514 834
Other Receivables $ 0 $ 0
Other Receivable, after Allowance for Credit Loss, Related Party [Extensible Enumeration] Affiliated Entity [Member] Affiliated Entity [Member]
Accrued interest and accrued (prepaid) taxes $ (184) $ 376
Deferred income taxes 30,902 30,502
Long-term debt [1] 41,082 43,714
Noncontrolling interest 104,304 103,751
Unamortized discount and debt issuance costs 200 300
MGE Power West Campus [Member]    
Variable Interest Entity [Line Items]    
In-service utility plant, net 76,378 75,392
Construction work in progress 3,052 1,533
Other Receivables $ 911 $ 2,550
Other Receivable, after Allowance for Credit Loss, Related Party [Extensible Enumeration] Affiliated Entity [Member] Affiliated Entity [Member]
Accrued interest and accrued (prepaid) taxes $ (78) $ (22)
Deferred income taxes 15,435 15,249
Long-term debt [1] 28,550 31,019
Noncontrolling interest 46,082 45,780
Unamortized discount and debt issuance costs $ 100 $ 100
[1] MGE Power Elm Road's long-term debt includes debt issuance costs of $0.2 million and $0.3 million, respectively, as of December 31, 2024 and 2023. The debt is secured by a collateral assignment of lease payments that MGE makes to MGE Power Elm Road for use of the Elm Road Units pursuant to the related long-term leases. MGE Power West Campus's long-term debt includes debt issuance costs of $0.1 million as of December 31, 2024 and 2023. The debt is secured by a collateral assignment of lease payments that MGE makes to MGE Power West Campus for use of the cogeneration facility pursuant to the long-term lease. See Footnote 14 for further information on the long-term debt securities.