Property and Equipment
3 Months Ended
Mar. 31, 2022
Property, Plant and Equipment [Abstract]  
Property and Equipment Property and Equipment
Property and equipment consisted of the following (in thousands):

March 31,December 31,
20222021
Software$5,993 $4,051 
Computers and equipment461 456 
ROU assets - finance lease375 375 
Leasehold improvements17 17 
Software development in progress10 1,514 
   Subtotal6,856 6,413 
Less: Accumulated depreciation and amortization(3,310)(2,628)
    Property and equipment, net$3,546 $3,785 

Total depreciation and amortization expense relating to property and equipment presented above was $0.7 million and $0.2 million for the three months ended March 31, 2022 and 2021, respectively.

Capitalized Internal Use Software Costs
During the three months ended March 31, 2022 and 2021, we capitalized $0.4 million and $1.0 million, respectively, of costs relating to development of internal use software, and recorded $0.6 million and $0.1 million, respectively, of amortization expense relating to capitalized internal use software, which was included in total depreciation and amortization expense as described above.