Zion Oil & Gas, Inc., a Delaware corporation (“we,” “our,” “Zion” or the “Company”) is an oil and gas exploration company with a history of 19 years of oil & gas exploration in Israel. As of June 30, 2019, the Company has no revenues from its oil and gas operations.

 

Zion maintains its corporate headquarters in Dallas, Texas. We also have branch offices in Caesarea, Israel and Geneva, Switzerland. The purpose of the Israel branch is to support the Company’s operations in Israel, and the purpose of the Switzerland branch is to operate a foreign treasury center for the Company.

 

Exploration Rights/Exploration Activities

 

The Company currently holds one active petroleum exploration license onshore Israel, the Megiddo-Jezreel License, comprising approximately 99,000 acres. The Megiddo Jezreel #1 (“MJ #1”) exploratory well was spud on June 5, 2017 and drilled to a total depth (“TD”) of 5,060 meters (approximately 16,600 feet). Thereafter, the Company successfully cased and cemented the well while awaiting the approval of the testing protocol. The Ministry of Energy approved the well testing protocol on April 29, 2018.

 

During the fourth quarter of 2018, the Company’s testing protocol was concluded at the MJ #1 well. The test results confirmed that the MJ #1 well did not contain hydrocarbons in commercial quantities in the zones tested. As a result, in the year ended December 31, 2018, the Company recorded a non-cash impairment charge to its unproved oil and gas properties of $30,906,000. During the three and six months ended June 30, 2019, the Company recorded a post-impairment charge of approximately $65,000 and $228,000, respectively.

 

The MJ#1 well provided Zion with information Zion believes is important for potential future exploration efforts within its license area. As with many frontier wildcat wells, the MJ#1 also left several questions unanswered.

 

While not meant to be an exhaustive list, a summary of what Zion believes to be key information learned in the MJ#1 well is as follows:

 

  1. The MJ#1 encountered much higher subsurface temperatures at a depth shallower than expected before drilling the well. In our opinion, this is significant because reaching a minimum temperature threshold is necessary for the generation of hydrocarbons from an organic-rich source rock.
     
  2. The known organic rich (potentially hydrocarbon bearing) Senonian age source rocks that are typically present in this part of Israel were not encountered as expected. Zion expected these source rocks to be encountered at approximately 1,000 meters in the MJ#1 well.
     
  3. MJ#1 had natural fractures, permeability (the ability of fluid to move through the rock) and porosity (pore space in rock) that allowed the sustained flow of formation fluid in the shallower Jurassic and lower Cretaceous age formations between approximately 1,200 and 1,800 meters. While no hydrocarbons were encountered, Zion believes this fact is nonetheless significant because it provides important information about possible reservoir pressures and the ability of fluids to move within the formation and to the surface.
     
  4. MJ#1 encountered oil in the Triassic Mohilla formation which Zion believes suggests an active deep petroleum system is in Zion’s license area. There was no natural permeability or porosity in the Triassic Mohilla formation to allow formation fluid to reach the surface naturally during testing, and thus the MJ#1 was not producible or commercial.
     
  5. The depths and thickness of the formations we encountered varied greatly from pre-drill estimates. This required the MJ#1 to be drilled to a much greater depth than previously expected. Zion has tied these revised formation depths to seismic data which will allow for more accurate interpretation and mapping in the future.

 

A summary of what Zion believes to be some key questions left to be answered are:

 

  1. Is the missing shallow Senonian age source rock a result of regional erosion, or is it missing because of a fault that cut the well-bore and could be reasonably expected to be encountered in the vicinity of the MJ#1 drill site? Zion believes this is an important question to answer because if the Senonian source rocks do exist in this area, the high temperatures encountered are sufficient to mature these source rocks and generate oil.
     
  2. Do the unusually high shallow subsurface temperatures extend regionally beyond the MJ#1 well, which could allow for the generation of hydrocarbons in the Senonian age source rock within our license area?
     
  3.

As a consequence of seismic remapping, where does the MJ#1 well lie relative to the potential traps at the Jurassic and Triassic levels, and was the well location too low on the structures and deeper than the potential hydrocarbons within those traps?

 

As a result of these unanswered questions and with the information gained drilling the MJ#1 well, as of June 15, 2019, Zion is in process of obtaining landowner permits, along with advance acquisition preparation. We are negotiating with Acoustic Geophysical Services Kft (“AGS”), based in Budapest, Hungary, for all surface and subsurface seismic mapping. A pricing matrix will be provided according to designated source parameters. Source parameters consist of multiple options and pricing according to time and length of source requirements. The final survey area consists of approximately 72 square kilometers surrounding the MJ#1 well.

 

Zion received a multi-year license extension through December 2, 2020.

 

Zion’s ability to fully undertake all of these aforementioned activities is subject to its raising the needed capital from its continuing offerings, of which no assurance can be provided.

 

Megiddo-Jezreel Petroleum License, No. 401 (“MJL”)

 

The MJL was awarded on December 3, 2013 for a three-year primary term through December 2, 2016, with the possibility of additional one-year extensions up to a maximum of seven years. The MJL lies onshore, south and west of the Sea of Galilee, and the Company continues its exploration focus here as it appears to possess the key geologic ingredients of an active petroleum system with significant exploration potential. In late November 2016, The State of Israel’s Petroleum Commissioner officially approved Zion’s drilling date and license extension request.

 

On October 30, 2017, the Company sought a multi-year extension to its existing license. After receiving feedback from Israel’s Petroleum Commissioner, the Company submitted a revised extension request on November 9, 2017. On November 20, 2017, Israel’s Petroleum Commissioner officially approved the Company’s multi-year extension request on its Megiddo-Jezreel License No. 401, extending its validity to December 2, 2019 which was subsequently extended to December 2, 2020. Until recently, the Company remained subject to the following updated key license terms:

 

No.   Activity Description   Execution by:
1   Submit final report on the results of drilling   31 May 2018
2   Submit program for continuation of work under license   30 June 2018

 

On June 1, 2018, Zion submitted its Megiddo-Jezreel #1 End of Well Report (EOWR) for the Megiddo-Jezreel License No. 401, thus fulfilling its No. 1 Final Report license work plan obligation, shown above. 

 

On June 14, 2018 Zion submitted its Application for Extension of Continued Work Program Due Date on the Megiddo-Jezreel License No. 401. The additional time was necessary because we had still not completed testing and evaluating all planned testing zones. On July 1, 2018, Israel’s Petroleum Commissioner granted Zion’s work program report extension to November 1, 2018, as shown below.

 

No.   Activity Description   Execution by:
1   Submit program for continuation of work under license   1 November 2018

 

On October 16, 2018 Zion submitted its Application for Extension of Continued Work Program Due Date on the Megiddo-Jezreel License No. 401. The additional time was necessary because we had still not completed testing and evaluating all planned testing zones. On October 28, 2018, Israel’s Petroleum Commissioner granted Zion’s work program report extension to January 31, 2019, as shown below. 

 

No.   Activity Description   Execution by:
1   Submit program for continuation of work under license   31 January 2019

 

On January 31, 2019, Zion submitted its Application for Extension of Continued Work Program Due Date on the Megiddo-Jezreel License No. 401. The additional time was necessary to finalize the work program. On February 3, 2019 Israel’s Petroleum Commissioner granted Zion’s work program report extension to February 28, 2019, as shown below:

 

 Number   Activity Description   Execution by:
3   Submit program for continuation of work under license   28 February 2019

 

The continuation of work program was timely submitted to Israel’s Petroleum Commissioner and subsequently approved.

  

On February 24, 2019 and thereafter on February 26, 2019 Zion submitted its proposed 2019 WORK PROGRAM ON the Megiddo-Jezreel License No. 401. 

 

On February 28, 2019 Israel’s Petroleum Commissioner officially approved the revised and updated Work Program on the Megiddo-Jezreel License No. 401 as shown below:

 

Number   Activity description   Execution by:
1   Submission of seismic survey plan to the Commissioner and execution of an agreement with a contractor to perform   30 April 2019
2   Commence 3D seismic survey in an area of approximately 50 square kilometers   1 August 2019
3   Transfer of field material configuration and processed material to the Ministry pursuant to Ministry guidelines   15 December 2019
4   Submit interpretation report   20 February 2020

 

On February 24, 2019 Zion submitted a request to the Commissioner to extend the Megiddo-Jezreel License No. 401 up to December 2, 2020.

 

On February 28, 2019 the Commissioner approved the extension of the Megiddo-Jezreel License No. 401 up to December 2, 2020.

 

On April 30, 2019 Zion submitted its Application for Extension of Continued Work Program Due Date on the Megiddo-Jezreel License No. 401. The additional time is necessary for Zion to conduct a 3D survey in an area of approximately 72 square kilometers. This requires, among other things, extensive permitting activities with relevant local landowners, the Israel Land Authority (“ILA”), certain authorities and others throughout the seismic survey area and may not conclude prior to the beginning of the Jewish holidays in October and rainy season. This in turn would result in additional delays, as rain and mud are not conducive to the performance of a seismic survey which includes extensive use of vibrators.

 

Zion’s proposed new timelines and activity descriptions are shown below:

 

Number   Activity description   Execution by:
1   Submission of seismic survey plan to the Commissioner and execution of an agreement with a contractor to perform   30 November 2019
2   Commence 3D seismic survey in an area of approximately 72 square kilometers   1 April 2020
3   Transfer of field material configuration and processed material to the Ministry pursuant to Ministry guidelines   15 August 2020
4   Submit interpretation report   15 November, 2020

 

On May 1, 2019, Israel’s Petroleum Commissioner granted Zion’s work program report extension.

 

As previously disclosed, the Company required authorization from the ILA, the formal lessor of the land to Kibbutz Sde Eliyahu, on whose property the drilling pad is currently situated, to access and utilize the drill site (“surface use agreement”). The Company received this authorization on July 4, 2016. This was preceded by the Company’s May 15, 2016 signed agreement with the kibbutz. On January 11, 2017, an agreement was signed by the Company and the ILA by which the surface usage agreement was extended through December 3, 2017. On December 31, 2017, an agreement was signed by the Company and the ILA by which the surface usage agreement was extended through December 3, 2019. On July 1, 2019, an agreement was signed by the Company and the ILA by which the surface usage agreement was extended through December 3, 2020.

 

Zion’s Former Jordan Valley, Joseph, and Asher-Menashe Licenses

 

On March 29, 2015, the Energy Ministry approved the Company’s application to merge the southernmost portion of the Jordan Valley License into the Megiddo-Jezreel License. The Company has plugged all of its exploratory wells (in the former Joseph and Asher-Menashe Licenses) but acknowledges its obligation to complete the abandonment of these well sites in accordance with guidance from the Environmental Ministry and local officials.

 

B. Basis of Presentation

 

The accompanying unaudited interim condensed financial statements of Zion Oil & Gas, Inc. have been prepared in accordance with accounting principles generally accepted in the United States of America (“GAAP”) for interim financial information and with Article 8-03 of Regulation S-X. Accordingly, they do not include all of the information and notes required by GAAP for complete financial statements. In the opinion of management, all adjustments, consisting only of normal recurring accruals necessary for a fair statement of financial position, results of operations and cash flows, have been included. The information included in this Quarterly Report on Form 10-Q should be read in conjunction with the financial statements and the accompanying notes included in the Company’s Annual Report on Form 10-K for the year ended December 31, 2018. The year-end balance sheet data presented for comparative purposes was derived from audited financial statements, but does not include all disclosures required by GAAP. The results of operations for the three and six months ended June 30, 2019 are not necessarily indicative of the operating results for the year ending December 31, 2019 or for any other subsequent interim period.

 

C. Going Concern 

 

The Company incurs cash outflows from operations, and all exploration activities and overhead expenses to date have been financed by way of equity or debt financing. The recoverability of the costs incurred to date is uncertain and dependent upon achieving significant commercial production. 

 

The Company’s ability to continue as a going concern is dependent upon obtaining the necessary financing to undertake further exploration and development activities and ultimately generating profitable operations from its oil and natural gas interests in the future. The Company’s current operations are dependent upon the adequacy of its current assets to meet its current expenditure requirements and the accuracy of management’s estimates of those requirements. Should those estimates be materially incorrect, the Company’s ability to continue as a going concern may be impaired. The financial statements have been prepared on a going concern basis, which contemplates realization of assets and liquidation of liabilities in the ordinary course of business. During the six months ended June 30, 2019, the Company incurred a net loss of approximately $3.5 million and had an accumulated deficit of approximately $203 million. These factors raise substantial doubt about the Company’s ability to continue as a going concern.

 

To carry out planned operations, the Company must raise additional funds through additional equity and/or debt issuances or through profitable operations. There can be no assurance that this capital or positive operational income will be available to the Company, and if it is not, the Company may be forced to curtail or cease exploration and development activities. The financial statements do not include any adjustments that might result from the outcome of this uncertainty.