Zion Oil and Gas, Inc.
|
|||
Date: July 12, 2011
|
By:
|
/s/ Richard J. Rinberg
|
|
Richard J. Rinberg
|
|||
Chief Executive Officer
|
|||
Mr Bill Ottaviani
Zion Oil & Gas Inc
22 Bareket,
North Industrial Zone
Caesarea 38900
|
Fax:04/6231427 |
a.
|
No later than 1 November 2011update the geophysical maps, continue the geological analysis of the license and submit a summary report.
|
b.
|
No later than 1 December 2011 prepare an engineering analysis of Elijah-3 drilling and examine the possibility of deepening or moving from Elijah -3 and submit a summary report.
|
c.
|
No later than 1 December 2011 present a contract for a supplementary 2D seismic survey within the license area totaling approximately 10 kilometers.
|
d.
|
Prepare the seismic survey, process the data and submit the process report and ancillary material no later than 1 February 2012 to the National archives at the Geophysics Institute as defined in the guidelines for transferring seismic data.
|
e.
|
No later than 1 March 2012 prepare an interpretation of the new seismic survey, integrate with old lines, update the geophysical maps and submit a geophysical summary.
|
f.
|
No later than 1 April 2012 prepare a drilling prospectus that includes a description of the geological background, the purposes of the drilling the petroleum system/s that are related therein and a geological forecast and engineering plan for the proposed drilling.
|
g.
|
No later than April 1 2012 execute a contract with a drilling contractor to drill a new well or drill the existing well.
|
h.
|
Begin drilling no later than 1 June 2012.
|
i.
|
In the event that you do not continue drilling Elijah-3 you must seal the well in a final manner no later than 1 June 2012.
|
j.
|
You must deposit with the Commissioner an autonomous irrevocable bank guarantee for the amount of $35,000 U.S. dollars valid to 1 December 2012 as a guarantee for damages that may occur from activities as a result of the Menashe license and sealing the wells.
|