Site Contingency [Line Items]  
Number of sites where regulated ash units will still be in operation at a specified date 3
Number of impoundments where closure plans will be expedited 1
Estimated cost of closure of an impoundment $ 4
Time period of existing ash pond closure completion in accordance with the CCR rule 5 years
Federal Clean Water Act Section 316 (b) | NSP Minnesota [Member]  
Site Contingency [Line Items]  
Minimum number of plants which could be required to make improvements to reduce entrainment | Plant 6
Federal Clean Water Act Section 316 (b) | Capital Addition Purchase Commitments  
Site Contingency [Line Items]  
Liability for estimated cost to comply with regulation $ 36