Rate Matters
3 Months Ended
Mar. 31, 2016
Public Utilities, General Disclosures [Abstract]  
Rate Matters
Rate Matters

Except to the extent noted below, the circumstances set forth in Note 10 to the consolidated financial statements included in NSP-Minnesota’s Annual Report on Form 10-K for the year ended Dec. 31, 2015, appropriately represent, in all material respects, the current status of other rate matters, and are incorporated herein by reference.

Pending and Recently Concluded Regulatory Proceedings — Minnesota Public Utilities Commission (MPUC)

NSP-Minnesota – Minnesota 2016 Multi-Year Electric Rate Case — In November 2015, NSP-Minnesota filed a three-year electric rate case with the MPUC. The rate case is based on a requested return on equity (ROE) of 10.0 percent and a 52.50 percent equity ratio. The request is detailed in the table below:
Request (Millions of Dollars)
 
2016
 
2017
 
2018
Rate request
 
$
194.6

 
$
52.1

 
$
50.4

Increase percentage
 
6.4
%
 
1.7
%
 
1.7
%
Interim request
 
$
163.7

 
$
44.9

 
N/A

Rate base
 
$
7,800

 
$
7,700

 
$
7,700



NSP-Minnesota also proposed a five-year alternative plan that would extend the rate plan two additional years. In addition, NSP-Minnesota has requested the MPUC encourage parties to engage in a formal mediation type procedure as outlined by Minnesota’s rate case statute which may streamline the settlement process.

In December 2015, the MPUC approved interim rates for 2016. The MPUC deferred making a decision on incremental interim rates for 2017 and indicated that NSP-Minnesota could bring back its request in the fourth quarter of 2016.

The major components of the requested rate increase are summarized below:
(Millions of Dollars)
 
2016
 
2017
 
2018
 
Total
2014 multi-year rate case items:
 
 
 
 
 
 
 
 
Excess depreciation reserve
 
$
26.0

 
$
51.0

 
$
—

 
$
77.0

Department of Energy (DOE) settlement
 
25.7

 
—

 
—

 
25.7

Monticello life cycle management (LCM)/extended power uprate (EPU)
 
11.2

 
(1.6
)
 
(1.5
)
 
8.1

 
 
62.9

 
49.4

 
(1.5
)
 
110.8

Additional items:
 
 
 
 
 
 
 
 
Capital investments
 
128.7

 
12.8

 
44.6

 
186.1

Property taxes
 
30.2

 
7.6

 
5.2

 
43.0

NOL carryforwards
 
(6.3
)
 
(24.5
)
 
(6.5
)
 
(37.3
)
Other costs
 
(20.9
)
 
6.8

 
8.6

 
(5.5
)
 
 
131.7

 
2.7

 
51.9

 
186.3

 
 
 
 
 
 
 
 
 
Total rate request
 
$
194.6

 
$
52.1

 
$
50.4

 
$
297.1



The next steps in the procedural schedule are expected to be as follows:

•
Intervenors’ direct testimony — June 14, 2016;
•
Rebuttal testimony — Aug. 9, 2016;
•
Surrebuttal testimony — Sept. 16, 2016;
•
Settlement conference — Sept. 26, 2016;
•
Evidentiary hearing — Oct. 4-7, 2016;
•
Administrative law judge (ALJ) report — Feb. 21, 2017; and
•
MPUC order — June 1, 2017.

2016 Transmission Cost Recovery (TCR) Filing — In October 2015, NSP-Minnesota submitted its 2016 TCR filing with the MPUC, requesting recovery of $19.2 million of 2016 transmission investment costs not included in electric base rates. This filing included an option to keep approximately $59.1 million of revenue requirements associated with two
CapX2020 projects completed in 2015 within the TCR rider or to include these revenue requirements in electric base rates during the interim rate implementation of the next electric rate case. In November 2015, NSP-Minnesota submitted an update to its TCR filing in which it confirmed that it was requesting the MPUC approve keeping the two CapX2020 projects in the TCR rider, increasing the revenue requirements to $78.3 million, until the conclusion of the 2016 Minnesota electric rate case.

In April 2016, NSP-Minnesota received comments from the Minnesota Department of Commerce (DOC) requesting additional support for the costs incurred for the CapX2020 La Crosse-Madison project and the CapX2020 Big Stone-Brookings project, as well as the updated financial impact for the actual non-prorated accumulated deferred income tax (ADIT) as opposed to the forecasted prorated ADIT used in the cost recovery calculations. An MPUC decision is expected later in 2016.

Nuclear Project Prudence Investigation — In 2013, NSP-Minnesota completed the Monticello LCM/EPU project. The multi-year project extended the life of the facility and increased the capacity from 600 to 671 megawatts (MW) in 2015. The Monticello LCM/EPU project expenditures were approximately $665 million. Total capitalized costs were approximately $748 million, which includes allowance for funds used during construction (AFUDC). In 2008, project expenditures were initially estimated at approximately $320 million, excluding AFUDC.

In 2013, the MPUC initiated an investigation to determine whether the final costs for the Monticello LCM/EPU project were prudent. In March 2015, the MPUC voted to allow for full recovery, including a return, on approximately $415 million of the total plant costs (inclusive of AFUDC), but only allow recovery of the remaining $333 million of costs with no return on this portion of the investment over the remaining life of the plant. Further, the MPUC determined that only 50 percent of the investment was considered used-and-useful for 2014.  As a result of these determinations, Xcel Energy recorded an estimated pre-tax loss of $129 million in the first quarter of 2015, after which the remaining book value of the Monticello project represented the present value of the estimated future cash flows.

Pending Regulatory Proceedings — Federal Energy Regulatory Commission (FERC)

Midcontinent Independent System Operator, Inc. (MISO) ROE Complaints/ROE Adder — In November 2013, a group of customers filed a complaint at the FERC against MISO transmission owners (TOs), including NSP-Minnesota and NSP-Wisconsin. The complaint argued for a reduction in the ROE in transmission formula rates in the MISO region from 12.38 percent to 9.15 percent, a prohibition on capital structures in excess of 50 percent equity, and the removal of ROE adders (including those for regional transmission organization (RTO) membership and being an independent transmission company), effective Nov. 12, 2013.

In June 2014 the FERC adopted a new ROE methodology, which requires electric utilities to use a two-step discounted cash flow analysis that incorporates both short-term and long-term growth projections to estimate the cost of equity.

In December 2015, an ALJ initial decision recommended the FERC approve a ROE of 10.32 percent. A FERC order is expected to be issued no earlier than late 2016 or 2017.

Certain MISO TOs separately requested FERC approval of a 50 basis point ROE adder for RTO membership, which was approved effective Jan. 6, 2015, subject to the outcome of the ROE complaint. Certain intervenors sought rehearing of this order, which the FERC denied in 2015.

In February 2015, a second complaint was filed seeking to reduce the MISO region ROE from 12.38 percent to 8.67 percent, prior to any adder.  The FERC set the second complaint for hearings, and established a refund effective date of Feb. 12, 2015. The MPUC, the North Dakota Public Service Commission (NDPSC), the South Dakota Public Utilities Commission and the Minnesota Department of Commerce (DOC) joined a joint complainant/intervenor initial brief recommending an ROE of either 8.82 percent or 8.81 percent. FERC staff recommended a ROE of 8.78 percent. The MISO TOs recommended a ROE of 10.92 percent. An ALJ initial decision is expected in June 2016 with a FERC decision expected no earlier than late 2016 or 2017.

NSP-Minnesota has recorded a current liability representing the current best estimate of a refund obligation associated with the new ROE, including the RTO membership adder, as of March 31, 2016. The new FERC ROE methodology is estimated to reduce transmission revenue, net of expense, between $8 million and $10 million, annually, for the NSP System.