The Company has minimum royalty obligations with certain of its mineral properties and leases. Minimum royalty payments payable are $57,400 per year in 2015, increasing by approximately $5,000 per year through 2017 and $2,000 thereafter. For most of the mineral properties and leases, the Company is subject to a range of royalty obligations once production commences. These royalties range from 0.5% to 6% of net smelter revenues (NSR) from minerals produced on the properties. Some of the factors that will influence the amount of the royalties include ounces extracted and the price of gold.

The Company has an operating agreement with Northern Comstock LLC, a related party and an entity controlled by a member of the Board of Directors. As part of the operating agreement, the Company obtained the exclusive rights of production and exploration on certain parcels in Storey County, Nevada. The terms of this agreement provide that the Company will make annual contributions in the amount of $862,500, in the form of Series A-1 convertible preferred stock or cash. The operating agreement requires these payments, at least annually, through October 2049. At March 31, 2015, $30.2 million remained due and may be prepaid without penalty. The above disclosure assumes cash payments are made, although the actual fair value of the payment amount may differ if preferred stock is issued in lieu of cash.

    
On October 20, 2010, the Company exchanged all of its senior secured convertible and senior indebtedness owed to members of the Winfield Group, shareholders of the Company, for newly created Series A-1 preferred stock. As part of the exchange, the Company agreed to indemnify the Winfield Group for any amounts as part of the exchange that were determined to be taxable as ordinary income to each member of the Winfield Group. As a result of this transaction, the Company recorded an accrual loss contingency provision in 2010. In September 2014, a portion of the indemnity lapsed. In March 2015, the remaining portion of the indemnity has lapsed, and accordingly, the Company recognized a reduction in the loss contingency accrual of approximately $3.2 million, which is included in other income in the condensed consolidated statements of operations.

The Company’s mining and exploration activities are subject to various laws and regulations governing the protection of the environment. These laws and regulations are continually changing and are generally becoming more restrictive. The Company conducts its operations so as to protect the public health and environment and believes its operations are in compliance with applicable laws and regulations in all material respects. The Company has made, and expects to make in the future, expenditures to comply with such laws and regulations, but cannot predict the full amount of such future expenditures. 

In early February, the Nevada Department of Transportation, (NDOT), closed an approximate two-mile section of SR-342, south of Gold Hill, as a safety precaution following roadway cracking and area specific sinking during a weekend of heavy rains. The area of sinking is above a historic mine-shaft dating back to the early 1900's, and that portion of the road sits on old mine dumps and looser fill that has a history of instability and, in some cases, failure. The Company owns the land, with NDOT granted prescriptive rights to operate the state roadbed over that private land.  Storey County, NDOT, the Company, and other applicable regulatory agencies evaluated several remedies for the realignment of SR-342. The route will be realigned to the east of the historic shaft, enabling safe travel and continued mining, while positioning the area for future mining and development.

The realignment will occur over two phases, with Phase 1 completion taking approximately 10-12 weeks and Phase 2 requiring an additional six months. Phase 1 begins with the Company removing the unconsolidated fill that now exists above the base bedrock level and beneath the existing road, followed by construction of a bypass road upon the base bedrock. In connection with this project, the historic Silver Hill Shaft will be capped permanently.

During the construction of Phase 1, SR-342 remains closed. Through traffic continues to detour through nearby State Route 341, commonly known as the truck route.  The truck route provides direct access between Virginia City and U.S. 50 in the Dayton area, with about 1.5 miles of additional travel.

Once Phase 1 is complete in June, the road will be reopened during construction of the second phase. Phase 2 includes removal of additional material on the east side of the canyon and will conclude with a tie in of the south end of the newly constructed alignment. A short closure will be necessary toward the end of Phase 2 for the tie in and completion of the realignment. The project is estimated to last through December of 2015.  The estimated cost for the project is $3 million. The project will be managed and funded by Comstock Mining, with NDOT and Storey County oversight, resulting ultimately in completing all phases of the realignment, plus achieving and advancing additional reclamation and mining objectives.

Upon completion of the bypass, NDOT’s prescriptive rights to operate the road would be transferred from the existing closed section of State Route 342 to the new roadway alignment.

From time to time, we are involved in lawsuits, claims, investigations and proceedings that arise in the ordinary course of business. There are no matters pending that we expect to have a material adverse impact on our business, results of operations, financial condition or cash flows.