Regulatory and Rate Matters - SJGS Abandonment Application (Details)
$ in Millions
Apr. 01, 2020
USD ($)
Jul. 01, 2019
USD ($)
scenario
MW
May 31, 2019
MW
Mar. 31, 2020
USD ($)
MW
Mar. 27, 2020
MMBTU
MW
Feb. 21, 2020
USD ($)
Jun. 14, 2019
PNM Solar Direct              
Public Utilities, General Disclosures [Line Items]              
Solar generation capacity (in megawatts) | MW     50        
Power purchase agreement term     15 years        
Required Percentage by 2020 | Energy Transition Act | Electric-Generation Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Renewable energy, percentage             0.20
Required Percentage by 2025 | Energy Transition Act | Electric-Generation Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Renewable energy, percentage             0.40
Required Percentage by 2030 | Energy Transition Act | Electric-Generation Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Renewable energy, percentage             0.50
Required Percentage by 2040 | Energy Transition Act | Electric-Generation Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Renewable energy, percentage             0.80
Required Percentage by 2045 | Energy Transition Act | Electric-Generation Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Renewable energy, percentage             1
PNM              
Public Utilities, General Disclosures [Line Items]              
Number of megawatts in battery storage facilities (in megawatts) | MW         40    
Solar generation capacity (in megawatts) | MW         300    
Solar generation capacity, power purchase agreements (in Megawatts) | MMBTU         20    
PNM | Renewable Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Solar generation capacity (in megawatts) | MW       133.0      
PNM | PNM Solar Direct              
Public Utilities, General Disclosures [Line Items]              
Solar generation capacity (in megawatts) | MW         50    
PNM | Required Percentage by 2011 | Renewable Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Required percentage of renewable energy in portfolio to electric sales       10.00%      
PNM | Required Percentage by 2015 | Renewable Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Required percentage of renewable energy in portfolio to electric sales       15.00%      
PNM | Required Percentage by 2020 | Renewable Portfolio Standard              
Public Utilities, General Disclosures [Line Items]              
Required percentage of renewable energy in portfolio to electric sales       20.00%      
San Juan Generating Station | Other deferred credits              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       $ 38.1      
San Juan Generating Station | Employee Severance              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       9.4      
San Juan Generating Station | PNM              
Public Utilities, General Disclosures [Line Items]              
Number of megawatts in natural gas-fired peaking plant (in megawatts) | MW   280          
Number of megawatts in battery storage facilities (in megawatts) | MW   70          
Solar generation capacity (in megawatts) | MW   350          
Number of megawatts in battery storage facilities, replacement resource scenario (in megawatts) | MW   60          
Number of replacement resource scenarios | scenario   3          
Request issuance of energy transition bonds   $ 361.0          
Forecasted undepreciated investment   283.0       $ 361.0  
Plant decommissioning and coal mine reclamation costs   28.6          
Upfront financing costs   9.6          
Severance costs   20.0          
Proceeds from securitization bonds   $ 19.8          
San Juan Generating Station | PNM | Other deferred credits              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       36.8      
San Juan Generating Station | PNM | Employee Severance              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       8.1      
San Juan Generating Station | PNM | Other Restructuring              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       8.9      
San Juan Generating Station | PNM | Economic Development and Workforce Training Costs              
Public Utilities, General Disclosures [Line Items]              
Restructuring reserve       $ 19.8      
Subsequent event | San Juan Generating Station | PNM              
Public Utilities, General Disclosures [Line Items]              
Request issuance of energy transition bonds $ 361.0