XML 12 R20.htm IDEA: XBRL DOCUMENT v3.19.3
Leases (Tables)
9 Months Ended
Sep. 30, 2019
Leases [Abstract]  
Schedule of Components of Lease Expense
The components of lease expense were as follows:
Three months ended September 30,Nine months ended September 30,
2019201820192018
Lease Cost
Operating lease cost
Operating lease$82  $81  $246  $244  
Variable lease costs  10   
Total lease cost$85  $82  $256  $245  
Schedule of Supplemental Cash Flow Information
Nine months ended September 30,
20192018
Other Information
Cash paid for amounts included in the measurement of lease liabilities Operating cash flows from operating leases
$261  $245  

Nine months ended September 30,
20192018
Lease Term and Discount Rate
Weighted-average remaining lease term Operating leases3.0 years4.0 years
Weighted-average discount rate Operating leases11.8 %11.8 %
Schedule of Future Minimum Lease Payments
Future minimum lease payments under non-cancellable leases as of September 30, 2019 were as follows:
Maturity of Lease Liabilities
2019$89  
2020360  
2021370  
2022219  
Total lease payments$1,038  
Less: Interest(152) 
Present value of lease liabilities$886  
Components of Lease Assets and Liabilities
September 30,
2019
Assets
Property and equipment, net Operating lease-right of use asset$777  
Liabilities
Current liabilities Operating lease- current liability$271  
Other long-term liabilities Operating lease- noncurrent liability615  
Total lease liabilities$886