Commitments and Contingencies Commitments and Contingencies
We believes that we will generate excess cash from property operations in the next twelve months; such excess, however, might not be sufficient to discharge all of our obligations as they become due. We intend to sell income-producing assets, refinance real estate and obtain additional borrowings primarily secured by real estate to meet our liquidity requirements.
We were the primary guarantor, on a $24,300 mezzanine loan between UHF and a lender. The guarantee was removed on January 29, 2021, concurrent with the repayment of the loan by UHF.
We were a defendant in litigation with David Clapper and related entities (collectively, "Clapper”) regarding a multifamily property transaction that occurred in 1988. In March 2016, the court ruled in favor of Clapper and awarded them approximately $59,000. We appealed the ruling, and the appellate court remanded the case to trial, which occurred in May 2021. As a result, the Court vacated the prior award and determined that Clapper would take nothing.
In February 2019, a lawsuit was brought by Paul Berger (“Berger”) against us and others that alleges that TCI completed improper sales and/or transfers of property with IOR. Berger requests that TCI pay off various related party loans to IOR and that IOR then distribute the funds to its shareholders. We intend to vigorously defend against the allegations. The trial for this matter is set for November 2022.
On July 13, 2021, we received the arbitration verdict in connection with our dispute on the measurement of the Earn Out Obligation (See Note 9 – Investment in Unconsolidated Joint Ventures), which determined that our position and claims were declined, and the position of Macquarie was fully accepted. As a result, we are required to pay approximately $39,600 to Macquarie to satisfy the Earn Out Obligation.