Rate & Regulatory Matters
12 Months Ended
Dec. 31, 2011
Rate and Regulatory Matters [Abstract]  
Rate and Regulatory Matters
20.  
Rate & Regulatory Matters

Vectren South Electric Base Rate Filing
On December 11, 2009, Vectren South filed a request with the IURC to adjust its base electric rates.  The requested increase in base rates addressed capital investments, a modified electric rate design that would facilitate a partnership between Vectren South and customers to pursue energy efficiency and conservation, and new energy efficiency programs to complement those currently offered for natural gas customers.  The IURC issued an order in the case on April 27, 2011.  The order provides for an approximate $28.6 million revenue increase to recover costs associated with approximately $325 million in system upgrades that were completed in the three years leading up to the December 2009 filing and modest increases in maintenance and operating expenses.  The approved revenue increase is based on rate base of $1,295.6 million, return on equity of 10.4 percent and an overall rate of return of 7.29 percent.  The new rates were effective May 3, 2011.  The IURC, in its order, denied the Company's request for implementation of the decoupled rate design, which is discussed further below.  Addressing issues raised in the case concerning coal supply contracts and related costs, the IURC found that current coal contracts remain effective and that a prospective review process of future procurement decisions would be initiated.

Coal Procurement Procedures
Vectren South submitted a request for proposal in April 2011 regarding coal purchases for a four year period beginning in 2012.  After negotiations with bidders, Vectren South has reached an agreement in principle for multi-year purchases with two suppliers, one of which is Vectren Fuels, Inc.  Consistent with the IURC direction in the electric rate case, a sub docket proceeding was established to review the Company's prospective coal procurement procedures, and the Company submitted evidence related to its recent request for proposal (RFP) and those coal procurement procedures to the IURC in September 2011.  In October 2011, the OUCC filed its testimony which, while suggesting enhancements to the process to be considered, does not challenge the results of the RFP and the resulting new contracts.  All hearings were completed in December 2011, and an order is expected in early 2012.

Vectren South Electric Fuel Cost Reduction
On December 5, 2011 within the quarterly Fuel Adjustment Clause (FAC) filing, Vectren South submitted a joint proposal with the OUCC to reduce its fuel costs by accelerating the impact of lower cost coal contracts to be effective after 2012.  In the spring of 2011, Vectren secured contracts for lower coal costs through a formal bidding process. This lower-priced coal is expected to start being delivered and used at Vectren's power plants by late 2012 to early 2013 and beyond. The agreement to accelerate savings into early 2012 means that the existing 2012 coal costs that are above the new, lower prices will be deferred to a regulatory asset and recovered over a six-year period without interest beginning in 2014.  This deferral also includes a reduction to the coal inventory balance at December 31, 2011 of approximately $17.7 million to reflect existing inventory at the new, lower price.  The IURC approved this proposal on January 25, 2012, with an impact to customer's rates effective February 1, 2012.

Vectren South Electric Demand Side Management Program Filing
On August 16, 2010, Vectren South filed a petition with the IURC, seeking approval of its proposed electric Demand Side Management (DSM) Programs, recovery of the costs associated with these programs, recovery of lost margins as a result of implementing these programs for large customers, and recovery of performance incentives linked with specific measurement criteria on all programs.  The DSM Programs proposed are consistent with a December 9, 2009 order issued by the IURC, which, among other actions, defined long-term conservation objectives and goals of DSM programs for all Indiana electric utilities under a consistent statewide approach.  In order to meet these objectives, the IURC order divided the DSM programs into Core and Core Plus programs.  Core programs are joint programs required to be offered by all Indiana electric utilities to all customers, and include some for large industrial customers.  Core Plus programs are those programs not required specifically by the IURC, but defined by each utility to meet the overall energy savings targets defined by the IURC.

On August 31, 2011 the IURC issued an order approving an initial three year DSM plan in the Vectren South service territory that complies with the IURC's energy saving targets.  Consistent with the Company's proposal, the order approved, among other items, the following: 1) recovery of costs associated with implementing the DSM Plan; 2) the recovery of a performance incentive mechanism based on measured savings related to certain DSM programs; 3) lost margin recovery associated with the implementation of DSM programs for large customers; and 4) deferral of lost margin up to $1 million in 2011 associated with small customer DSM programs for subsequent recovery under a tracking mechanism to be proposed by the Company.  This mechanism is an alternative to the electric decoupling proposal that was denied by the IURC in the order received April 27, 2011.  On January 26, 2012, the Company filed with the IURC a proposal for a small customer lost margin recovery mechanism within the existing Demand Side Management Adjustment (DSMA).  The proposal includes a request for recovery of the $1 million deferred in 2011, and a request for continued deferral of lost margins in 2012 until such point as these lost margins are included in DSMA rates.  The procedural schedule has not been set in this filing, but the Company expects an order in 2012.

Vectren South Electric Dense Pack Filing
On September 14, 2011, Vectren South filed a petition with the IURC seeking recovery of and return on the capital investment in dense pack technology to improve the efficiency of its A.B. Brown Generating Station.  This investment is expected to be approximately $32 million over the next two years, of which approximately $19 million has been invested to date.  This technology is expected to allow the A.B. Brown units to run at least 5 percent more efficient, thereby burning less fuel, and reducing fuel costs and emissions of pollutants.  Indiana statute provides for timely recovery of investments, with a return, in instances where the investment increases the efficiency of existing generating plants that are fueled by coal.  Several parties have intervened in the case and are requesting that the IURC deny recovery of these project costs outside of a base rate proceeding.  The IURC will conduct a hearing in February 2012.

Vectren North Reporting Location Consolidation Proceeding
Vectren North implemented a reporting location consolidation plan in 2011 and closed certain locations throughout the North territory.  On May 26, 2011, the International Brotherhood of Electrical Workers Local 1393, United Steel Workers Locals 12213 and 7441 and others filed a formal complaint with the IURC claiming that the consolidation and simultaneous closing by Vectren North of select reporting locations endangers public safety and impairs Vectren North's ability to provide adequate, safe and reliable service.  These parties have asked the IURC to require Vectren North to reopen previously consolidated reporting locations and maintain and staff those locations.  A hearing in this case was held in February 2012, and the Company expects the IURC to act some time in 2012.

Vectren North & Vectren South Gas Decoupling Extension Filing
On April 14, 2011, the Company's Indiana based gas companies (Vectren North and Vectren South) filed with the IURC a joint settlement agreement with the OUCC on an extension of the offering of conservation programs and the supporting gas decoupling mechanism originally approved in December 2006.  On August 18, 2011, the IURC issued an order approving the settlement as filed, granting the extension of the current decoupling mechanism in place at both gas companies and recovery of new conservation program costs through December 2015.
 
VEDO Gas Rate Design
The rate design approved by the PUCO on January 7, 2009, and initially implemented on February 22, 2009, allowed for the phased movement toward a straight fixed variable rate design, which places substantially all of the fixed cost recovery in the monthly customer service charge.  This rate design mitigates most weather risk as well as the effects of declining usage, similar to the company's lost margin recovery mechanism in place in the Indiana natural gas service territories and the mechanism in place in Ohio prior to this rate order.  Since the straight fixed variable rate design was fully implemented in February 2010, nearly 90 percent of the combined residential and commercial base rate gas margins were recovered through the customer service charge.  As a result, some margin previously recovered during the peak delivery winter months, such as January and the first half of February 2010, is more ratably recognized throughout the year.

In addition in 2010, the Company began recognizing a return on and of investments made to replace distribution risers and bare steel and cast iron infrastructure per a PUCO order.

VEDO Continues the Process to Exit the Merchant Function
On August 20, 2008, the PUCO approved the results of an auction selecting qualified wholesale suppliers to provide the gas commodity to the Company for resale to its customers at auction-determined standard pricing.  This standard pricing was comprised of the monthly NYMEX settlement price plus a fixed adder.  This standard pricing, which was effective from October 1, 2008 through March 31, 2010, was the initial step in exiting the merchant function in the Company's Ohio service territory.  The approach eliminated the need for monthly gas cost recovery (GCR) filings and prospective PUCO GCR audits. 

The second phase of the exit process began on April 1, 2010.  During this phase, the Company no longer sells natural gas directly to customers.  Rather, state-certified Competitive Retail Natural Gas Suppliers, that were successful bidders in a similar regulatory-approved auction, sell the gas commodity to specific customers for a 12-month period at auction-determined standard pricing.  The first auction was conducted on January 12, 2010, and the auction results were approved by the PUCO on January 13, 2010.  The plan approved by the PUCO required that the Company conduct at least two annual auctions during this phase.  As such, the Company conducted another auction on January 18, 2011 in advance of the second 12-month term which commenced on April 1, 2011.  The results of that auction were approved by the PUCO on January 19, 2011. Vectren Source, the Company's former wholly owned nonutility retail gas marketer, was a successful bidder in both auctions winning one tranche of customers in the first auction and two tranches of customers in the second auction.  Each tranche of customers equates to approximately 28,000 customers.  As per the terms of the plan approved by the PUCO, because no application for a full exit of the merchant function was neither sought nor approved by April 1, 2011, VEDO conducted a third retail auction on January 31, 2012 to address the 12-month term beginning April 1, 2012.  The results of that auction were approved by the PUCO on February 1, 2012.  Consistent with current practice, customers continue to receive a single bill for the commodity as well as the delivery component of natural gas service from VEDO.

The PUCO provided for an Exit Transition Cost rider, which allows the Company to recover costs associated with the transition process.  Exiting the merchant function has not had a material impact on earnings or financial condition.  It, however, has and will continue to reduce Gas utility revenues and have an equal and offsetting impact to Cost of gas sold and revenue related taxes recorded in Taxes other than income taxes as VEDO no longer purchases gas for resale to these customers.