AIA® Document A102TM - 2007
Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

AGREEMENT made as of the 2nd day of May in the year 2016
(In words, indicate day, month and year.)

BETWEEN the Owner:
(Name, legal status, address and other information)

DexCom, Inc.
6340 Sequence Drive
San Diego, CA 92121
Attn: James Gillard


and the Contractor:
(Name, legal status, address and other information)

Skanska USA Building Inc.
4742 N. 24th Street, Suite 165
Phoenix, AZ 85016
Attn: Ross Vroman


for the following Project:
(Name, location and detailed description)

Tenant Improvements at
232 South Dobson Road,
Mesa, AZ 85202 »

The Architect:
(Name, legal status, address and other information)

Mansour Architecture Corporation
6498 Weathers Place, Suite 100
San Diego, CA 92121
Attn: Anthony Mansour     ·


The Owner and Contractor agree as follows.

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.
This document is not intended for use in competitive bidding.
AIA Document A201™-2007, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
Electronic copying of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
1

(1346722099)




TABLE OF ARTICLES

1
THE CONTRACT DOCUMENTS

2
THE WORK OF THIS CONTRACT

3
RELATIONSHIP OF THE PARTIES

4
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

5
CONTRACT SUM

6
CHANGES IN THE WORK

7
COSTS TO BE REIMBURSED

8
COSTS NOT TO BE REIMBURSED

9
DISCOUNTS, REBATES AND REFUNDS

10
SUBCONTRACTS AND OTHER AGREEMENTS

11
ACCOUNTING RECORDS

12
PAYMENTS

13
DISPUTE RESOLUTION

14
TERMINATION OR SUSPENSION

15
MISCELLANEOUS PROVISIONS

16
ENUMERATION OF CONTRACT DOCUMENTS

17
INSURANCE AND BONDS

ARTICLE 1   THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, as modified herein by the parties, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, the Exhibits to this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. If anything in the other Contract Documents, other than a Modification, is inconsistent with this Agreement, then conflicts or discrepancies shall be resolved in the following descending order of priority: (i) approved revisions and addenda, including the GMP Amendment, of later date take precedence over those of earlier date or original documents; (ii) this Agreement (including the exhibits; (iii) modifications to the General Conditions; (iv) the General Conditions; and (v) Drawings and Specifications, where Drawings govern Specifications for quantity and location and Specifications govern Drawings for quality and performance. In the event of ambiguity in quantity or quality, the greater quantity and the better quality shall govern. Work not particularly detailed or specified shall be performed in the same manner as similar portions of the Work that are detailed or specified. Owner and Contractor entered into that certain Master Services Agreement dated as of January 12, 2016, which agreement concerns a

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
2

(1346722099)



different subject matter than this Agreement, remains in full force and effect and is not superseded by the Contract Documents.

ARTICLE 2   THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

§ 2.1 Contractor shall provide all general contractor services, and shall perform all the work required by the Contract Documents for the complete construction of the Project in accordance with the Contract Documents, which shall include, but not be limited to, relocation of existing utilities. Contractor shall provide and furnish all materials, supplies, equipment and tools, implements, and all other facilities, and all other labor, supervision, transportation, utilities, storage, services, sales taxes, appliances and all other services as and when required for or in connection with the complete construction of the Project, including any off site construction shown on the Contract Documents (hereinafter collectively referred to as the "Work"). The phrase "the complete construction of the Project" means to perform the totality of the obligations imposed upon Contractor by the Contract Documents or reasonably inferable therefrom as necessary to complete the Work and the Project and to provide a fully complete and operational construction solution, in Contractor’s exercise of its best professional judgment, to the standards generally conveyed in the Contract Documents and customarily found in the construction industry for projects similar in size and scope to the Project.

ARTICLE 3   RELATIONSHIP OF THE PARTIES
The Contractor accepts the relationship of reliance and confidence established by this Agreement and covenants with the Owner to cooperate with Owner, Owner's project manager, Gary Ghio with G2 Facilities Management Consulting (“Project Manager”) (provided, however, Owner may designate a different Project Manager by written notice to Contractor), and the Architect, and to exercise the Contractor’s best skill, efforts and judgment in furthering the interests of the Owner; to furnish efficient business administration and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner’s interests. The Owner agrees to furnish and approve, in a timely manner, information required by the Contractor and to make payments to the Contractor in accordance with the requirements of the Contract Documents. Contractor shall not be required to provide professional services that constitute the practice of architecture or engineering. Contractor shall not be responsible for the adequacy of the design criteria required by the Contract Documents.

ARTICLE 4   DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 4.1 The date for the commencement of the Work (the "Commencement Date") shall be set forth in a Notice to Proceed (NTP) issued by Owner concurrent with execution of this Agreement. However, the NTP shall not be effective, and Contractor shall have no obligation to commence its Work, until Owner has fulfilled the following conditions precedent and has delivered to Contractor copies of the building permit required to be obtained by the Owner for the commencement of the Work at the site, if any, and certificates of insurance for all insurance required to be provided by Owner, including the builder’s risk insurance;
(2)    evidence sufficient to reasonably satisfy Contractor of Owner’s financing for the Project; and
(3)    reasonable access to the site.

If Owner does not issue an effective NTP, Contractor shall have no obligation to commence the Work, or any part of the Work, until Owner satisfies the above conditions precedent to the effectiveness of the NTP.
.
(Insert the date of commencement, if it differs from the date of this Agreement or, if applicable, state that the date will be fixed in a notice to proceed.)
(paragraph deleted)



§ 4.2 The Contract Time shall be measured from the Commencement Date, subject to adjustments in Contract Time as expressly provided in the Contract Documents.

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
3

(1346722099)




§ 4.3 The Contractor shall diligently prosecute the Work and achieve Substantial Completion of the entire Work for the Project not later than the Substantial Completion date established in a written amendment to be signed by Owner and Contractor and delivered to each other setting forth the schedule for completion of each milestone of the Work, the deadline for Substantial Completion and the Guaranteed Maximum Price (the “GMP Amendment”), subject to adjustments of this Contract Time as provided in the Contract Documents (the "Substantial Completion Deadline"). Time is of the essence of this Agreement for meeting the milestones of Substantial and Final Completion.
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion of certain portions of the Work.)



Portion of Work
Substantial Completion date
 
 

, subject to adjustments of this Contract Time as provided in the Contract Documents.

(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time, or for bonus payments for early completion of the Work.)

Liquidated damages established as set forth in Section 4.5 below.

§ 4.4 The Contractor agrees to complete all of the Work in accordance with the Contractor’s Schedule included in the GMP Amendment.

§ 4.5 Liquidated Damages. The Owner and the Contractor acknowledge and agree that if the Contractor does not timely achieve Substantial Completion by the Substantial Completion Deadline set forth in the GMP Amendment, (a) the Owner will suffer substantial loss of income and revenue and other damages and losses, including, without limitation, loss of business and loss or damage to reputation, business relationships, goodwill, and loss of use of the property, and (b) the actual amount of damages which the Owner would suffer would be extremely difficult and impracticable to ascertain. Accordingly, the Owner and the Contractor agree that:

(a)    If the Contractor does not timely achieve Substantial Completion by the deadline set forth in the GMP Amendment, then the following sums shall constitute a reasonable estimate of the amount of damages for such delay, and the Contractor shall pay such sums to the Owner as liquidated damages for each day or portion of a day that Substantial Completion is delayed beyond the deadline within thirty (30) calendar days upon Owner’s invoice to the Contractor:

One Thousand Dollars ($1,000.00) for each day of unexcused delay.

(b)    In no event shall the liquidated damages, in the aggregate, exceed 10 percent (10%) of Contractors Fee. The liquidated damages set forth above are the sole and exclusive remedy for Contractor’s failure to achieve Substantial Completion by the deadline set forth in the GMP Amendment.

Final completion shall occur no later than thirty (30) days after Substantial Completion. Failure to achieve Final Completion before the expiration of such thirty (30)-day period will result in liquidated damages of Five Hundred Dollars ($500.00) per day for each day in excess of thirty (30) days after Substantial Completion until Final Completion is achieved, subject to the cap set forth above.

ARTICLE 5   CONTRACT SUM
§ 5.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract, in accordance with, and subject to the terms of the conditions of the Contract Documents. The Contract

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
4

(1346722099)



Sum shall be the lesser of (a) Cost of the Work as defined in Article 7 plus the Contractor’s Fee and (b) the Guaranteed Maximum Price. A Schedule of Billable Rates is attached hereto as Exhibit C and incorporated herein.

§ 5.1.1 The Contractor’s Fee:
(State a lump sum, percentage of Cost of the Work or other provision for determining the Contractor’s Fee.)

two and 65/100 percent (2.65%) of the Cost of Work.

§ 5.1.2 The method of adjustment of the Contractor’s Fee for changes in the Work:

In connection with any changes in the Work which increase the Contract Sum, the Contractor’s Fee shall be increased by an amount equal to two and 65/100 percent (2.65%) of that portion of the Cost of the Work incurred as a result of such changes in the Work, and in connection with any changes in the Work which decrease the Contract Sum, the Contractor’s Fee shall be reduced by an amount equal to two and 65/100 percent (2.65%) of that portion of the Cost of the Work reduced as a result of such changes in the Work.

§ 5.1.3 Limitations, if any, on a Subcontractor’s overhead and profit for increases in the cost of its portion of the Work:

Limitations, if any, will be agreed upon by Contractor and Owner on a trade-by-trade basis (and may be set forth in the amendment to this Agreement which documents, if applicable, the agreed-upon Guaranteed Maximum Price).

§ 5.1.4 Rental rates for Contractor-owned equipment shall not exceed the amounts set forth in Section 7.5.2 hereof.

§ 5.1.5 Unit prices, if any:
(Identify and state the unit price; state the quantity limitations, if any, to which the unit price will be applicable.)

Item
Units and Limitations
Price Per Unit ($0.00)
 
 
 

§ 5.2 GUARANTEED MAXIMUM PRICE
§ 5.2.1 The Contract Sum is guaranteed by the Contractor not to exceed a maximum amount (the "Guaranteed Maximum Price") established in the GMP Amendment, subject to additions and deductions by Change Order as provided in the Contract Documents. Costs which would cause the Guaranteed Maximum Price to be exceeded shall be paid by the Contractor without reimbursement by the Owner. Contractor acknowledges and agrees that the Guaranteed Maximum Price includes all inflationary costs and adjustments, and labor and material escalations, in connection with the performance of the Work so long as Owner satisfies its express obligations under the Schedule and timely issues the NTP . The Guaranteed Maximum Price shall not be adjusted due to any such inflationary costs and/or escalation events so long as Owner satisfies its express obligations under the Schedule and timely issues the NTP. There shall be no shared savings clause in this Agreement. All savings will accrue to the Owner.
(Insert specific provisions if the Contractor is to participate in any savings.)



§ 5.2.1.1 At a time to be mutually agreed upon by the Owner and the Contractor, the Contractor shall prepare a Guaranteed Maximum Price proposal for the Owner’s review and written acceptance. The Guaranteed Maximum Price in the proposal shall be the sum of the Contractor’s reasonable estimate of the Cost of the Work, including contingencies described in Section 5.2.1.4, and the Contractor’s Fee.

§ 5.2.1.2 To the extent that the Drawings and Specifications are anticipated to require further development, the Contractor shall provide in the Guaranteed Maximum Price for such further development consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include such things as

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
5

(1346722099)



changes in scope, systems, kinds and quality of materials, finishes or equipment, all of which, if required, shall be incorporated by Change Order.

§ 5.2.1.3 The Contractor shall include with the Guaranteed Maximum Price proposal a written statement of its basis, which shall include the following:
.1
A list of the Drawings and Specifications, including all Addenda thereto, and the Conditions of the Contract;
.2
A list of the clarifications and assumptions made by the Contractor in the preparation of the Guaranteed Maximum Price proposal, including assumptions to supplement the information provided by the Owner and contained in the Drawings and Specifications;
.3
A statement of the proposed Guaranteed Maximum Price, including a statement of the estimated Cost of the Work organized by trade categories or systems, allowances, contingency, and the Contractor’s Fee;
.4
The anticipated date of Substantial Completion upon which the proposed Guaranteed Maximum Price is based (i.e., the proposed “Substantial Completion Deadline”); and
.5
A date by which the Owner must accept or reject the Guaranteed Maximum Price, which shall not be less than 30 days from the date of the Guaranteed Maximum Price proposal (it being agreed if Owner does not accept or reject the Guaranteed Maximum Price proposal in writing, it shall be deemed rejected).

§ 5.2.1.4 In preparing the Contractor’s Guaranteed Maximum Price proposal, the Contractor shall include its contingency for the Contractor’s exclusive use (hereinafter the “Construction Contingency”) as necessary to cover those costs considered reimbursable as the Cost of the Work but not included in a Change Order, and to the extent not paid for by insurance, or Subcontractor defaults. Subject to the prior written consent of Owner, which consent shall not be unreasonably withheld, the Construction Contingency shall be available for the Contractor’s exclusive use at any time to cover costs intended to be covered by the Contract Documents, including at the time of Final Payment, for reimbursement of costs and expenses (1) reasonably incurred by Contractor in performing the Work, (2) of a type that are reimbursable under this Agreement as a Cost of the Work, and (3) that are not otherwise the basis for a Change Order (it being understood that the Construction Contingency shall not be used to fund any Work which would otherwise be subject to a Change Order); including, by way of example, but not limited to, (a) Work items inadvertently omitted during the estimating and bidding process, (b) schedule recovery costs associated with normal weather, (c) cost increases due to unanticipated local labor and material market conditions, (d) interfacing omissions between and from the various categories of work; and (e) additional costs incurred due to the withdrawal or disqualification of a subcontractor bid forming the basis for the GMP prior to signing of a written subcontract, provided, however, Contractor shall not be entitled to reimbursement for any costs attributable to its negligence or willful misconduct or the failure of Contractor to perform its obligations under this Agreement. Contractor shall furnish the Owner with a monthly Contingency Log showing all reimbursements from the Construction Contingency. Costs and expenses reimbursable from the Construction Contingency shall not exceed the amount of the Construction Contingency identified as an element of the Guaranteed Maximum Price set forth in the GMP Amendment. When the Construction Contingency is exhausted, all costs and expenses that would qualify for reimbursement from the Construction Contingency shall be borne by Contractor unless such costs and expenses are otherwise compensable under the terms of this Agreement and do not cause the Guaranteed Maximum Price to be exceeded. Any amount remaining in the Construction Contingency at Final Payment shall be counted as savings that shall accrue solely to Owner.

§ 5.2.1.5 The Contractor shall meet with the Owner to review the Guaranteed Maximum Price proposal. In the event that the Owner discovers any inconsistencies or inaccuracies in the information presented, it shall notify the Contractor, who shall promptly make appropriate adjustments to the Guaranteed Maximum Price proposal, its basis, or both, as the case may be.

§ 5.2.1.6 If the Owner notifies the Contractor in writing that the Owner has accepted the Guaranteed Maximum Price proposal before the date specified in the Guaranteed Maximum Price proposal, the Guaranteed Maximum Price proposal shall be deemed effective without further acceptance from the Contractor. Following acceptance of a Guaranteed Maximum Price, the Owner and Contractor shall execute the Guaranteed Maximum Price Amendment

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
6

(1346722099)



amending this Agreement, a copy of which the Owner shall provide to the Architect. The Guaranteed Maximum Price Amendment shall set forth the agreed upon Guaranteed Maximum Price with the information and assumptions upon which it is based.

§ 5.2.1.7 The Contractor shall not incur any cost to be reimbursed as part of the Cost of the Work prior to the commencement of the Construction Phase, unless the Owner, in its sole and absolute discretion, provides prior written authorization for such costs “Initial Release Work.”) Written authorization for Initial Release Work shall be provided by an Approval Letter in the form at Exhibit A. All Initial Release Work performed pursuant to the Approval Letters shall be performed in accordance with the Contract Documents unless otherwise specified in the Approval Letter.  All Initial Release Work, if any, shall be deemed to be included in the scope of the Work pursuant to the Contract Documents. The Approval Letters constitute the basis upon which Initial Release Work shall be performed and upon which the Contractor shall be paid for the Initial Release Work and, unless and until the GMP is agreed to by the Owner, the Contractor shall not proceed with any other Work. The GMP shall include the cost of any Initial Release Work authorized pursuant to the Approval Letter issued prior to the establishment of the GMP.

§ 5.2.1.8 The Owner shall provide the revisions to the Drawings and Specifications to incorporate the agreed-upon assumptions and clarifications contained in the Guaranteed Maximum Price Amendment. The Owner shall promptly furnish those revised Drawings and Specifications to the Contractor as they are revised and approved by Owner. The Contractor shall promptly notify the Owner of any inconsistencies between the Guaranteed Maximum Price Amendment and the revised Drawings and Specifications.

§ 5.2.2 The Guaranteed Maximum Price is based on the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If bidding or proposal documents permit the Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when the amount expires.)

To be set forth in GMP Amendment.

§ 5.2.3 Allowances included in the Guaranteed Maximum Price, if any:
(Identify allowance and state exclusions, if any, from the allowance price.)

Item
Price
 
 

To be set forth in GMP Amendment.

§ 5.2.4 Not used.

§ 5.2.5 To the extent that the Drawings and Specifications are anticipated to require further development by the Architect, the Contractor has provided in the Guaranteed Maximum Price for such further development consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include such things as changes in scope, systems, kinds and quality of materials, finishes or equipment, all of which, if required, shall be incorporated by Change Order.

ARTICLE 6   CHANGES IN THE WORK
§ 6.1 Adjustments to the Guaranteed Maximum Price on account of changes in the Work may be determined by any of the methods listed in Section 7.3.3 of AIA Document A201–2007, General Conditions of the Contract for Construction.

§ 6.2 In calculating adjustments to subcontracts (except those awarded with the Owner’s prior consent on the basis of cost plus a fee), the terms “cost” and “fee” as used in Section 7.3.3.3 of AIA Document A201–2007 and the term “costs” as used in Section 7.3.7 of AIA Document A201–2007 shall have the meanings assigned to them in AIA

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
7

(1346722099)



Document A201–2007 and shall not be modified by Articles 5, 7 and 8 of this Agreement. Adjustments to subcontracts awarded with the Owner’s prior consent on the basis of cost plus a fee shall be calculated in accordance with the terms of those subcontracts.

§ 6.3 In calculating adjustments to the Guaranteed Maximum Price, the terms “cost” and “costs” as used in the above-referenced provisions of AIA Document A201–2007 shall mean the Cost of the Work as defined in Article 7 of this Agreement and the term “fee” shall mean the Contractor’s Fee as defined in Section 5.1.1 of this Agreement.

§ 6.4 No change in the Work, whether by way of alteration or addition to the Work, shall be the basis of an addition to the Guaranteed Maximum Price or a change in the Contract Time unless and until such alteration or addition has been authorized by a written Change Order or Construction Change Directive executed and issued in accordance with and in strict compliance with the requirements of the Contract Documents. This requirement is of the essence of the Contract Documents. Accordingly, no course of conduct or dealings between the parties, nor express or implied acceptance of alterations or additions to the Work, and no claim that the Owner has been unjustly enriched by any alteration or addition to the Work, whether there is in fact any such unjust enrichment, shall be the basis for any claim to an increase in the Guaranteed Maximum Price or change in the Contract Time.

ARTICLE 7   COSTS TO BE REIMBURSED
§ 7.1 COST OF THE WORK
§ 7.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior written consent of the Owner. The Cost of the Work shall include only the items set forth in this Article 7.

§ 7.1.2 The "Lump Sum General Conditions” shall include the following categories of Work as further described in Exhibit C:

Wages or salaries of on-site personnel directly employed by the Contractor to supervise the Work at the site. Wages or salaries of supervisory and administrative personnel directly employed by the Contractor engaged in the performance of the Work and located at the Site or working off-Site but only for that portion of their time required for the Work
Travel, accommodations and meals for Contractor’s personnel necessarily and directly incurred in connection with the performance of the Work.
Travel to Owners office and other ADC’s sites as specifically described in Exhibit C.
Expenses incurred in accordance with the Contractor’s standard written personnel policy for relocation and temporary living allowance of the Contractor’s personnel required for the Work.
Reasonable costs of expenses incurred in operating, maintaining and demobilizing the Site office, including the cost of office furniture, telephones, internet, postage, express delivery charges, computing equipment, software, printing equipment, office supplies, photocopying and other miscellaneous expenses as detailed in Exhibit C.
Accounting and data processing costs related to the Work, including the cost of information technologies support services, check processing charges and document archiving.
On-site meeting expenses
Preparation and management of the Contractor’s loss prevention program including safety orientations for all site personnel and visitors, site safety signage, the cost for the Contractor’s sponsored safety incentive program for all project participants, and any required drug testing.
Personal protective equipment including, hardhats, safety glasses, safety vests, gloves for Contractor’s employees and visitors to the Site.
Preparation and management of the Contractor’s quality control program.
Preparation and periodic update of the construction master project schedule.
Drug testing for Skanska employees
Temporary jobsite signage
Blue print reproduction


AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
8

(1346722099)



The Lump Sum General Conditions shall be adjusted as part of any adjustment of the Contract Sum due to changes, excused delays or other circumstances extending the Contract Time. In such event, the lump sum amount for General Conditions shall be increased or decreased, as the case may be, by the additional or decreased General Conditions Costs incurred or saved by Contractor during the extended period, with the Schedule of Billable Rates attached hereto as Exhibit C being used to determine the supervisory and administrative personnel costs associated with the adjustment.

Notwithstanding anything to the contrary in this Agreement, the Owner shall not be charged under any other provision of this Agreement for items covered under the Lump Sum General Conditions. Where any open cost is subject to the Owner’s prior written approval, the Contractor shall obtain this approval prior to incurring the cost.

§ 7.2 LABOR COSTS
§ 7.2.1 Wages of construction workers directly employed by the Contractor to perform the construction of the Work at the site or, with the Owner’s prior written approval, at off-site workshops are included in the Lump Sum General Conditions.

§ 7.2.2 Wages or salaries of the Contractor’s supervisory and administrative personnel when stationed at the site are included in the Lump Sum General Conditions.
(If it is intended that the wages or salaries of certain personnel stationed at the Contractor’s principal or other offices shall be included in the Cost of the Work, identify in Article 15, the personnel to be included, whether for all or only part of their time, and the rates at which their time will be charged to the Work.)

§ 7.2.3 Wages and salaries of the Contractor’s supervisory or administrative personnel engaged at factories, workshops or on the road, in expediting the production or transportation of materials or equipment required for the Work are included in the Lump Sum General Conditions.

§ 7.2.4 Costs paid or incurred by the Contractor for taxes, insurance, contributions, assessments and benefits required by law or collective bargaining agreements and, for personnel not covered by such agreements, customary benefits such as sick leave, medical and health benefits, holidays, vacations and pensions, provided such costs are based on wages and salaries included in the Cost of the Work under Sections 7.2.1 through 7.2.3 are included in the Lump Sum General Conditions.

§ 7.2.5 Bonuses, profit sharing, incentive compensation and any other discretionary payments paid to anyone hired by the Contractor or paid to any Subcontractor or vendor, with the Owner’s prior written approval.

§ 7.3 SUBCONTRACT COSTS
Payments made by the Contractor to Subcontractors in accordance with the requirements of the subcontracts.

§ 7.4 COSTS OF MATERIALS AND EQUIPMENT INCORPORATED IN THE COMPLETED CONSTRUCTION
§ 7.4.1 Costs, including transportation and storage, of materials and equipment incorporated or to be incorporated in the completed construction.

§ 7.4.2 Costs of materials described in the preceding Section 7.4.1 in excess of those actually installed to allow for reasonable waste and spoilage. Unused excess materials, if any, shall become the Owner’s property at the completion of the Work or, at the Owner’s option, shall be sold by the Contractor. Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the Work.

§ 7.5 COSTS OF OTHER MATERIALS AND EQUIPMENT, TEMPORARY FACILITIES AND RELATED ITEMS
§ 7.5.1 Costs of transportation, storage, installation, maintenance, dismantling and removal of materials, supplies, temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Contractor at the site and fully consumed in the performance of the Work. Costs of materials, supplies, temporary facilities, machinery, equipment and tools that are not fully consumed shall be based on the cost or value of the item at the time it is first used on the Project site less the value of the item when it is no longer used at the Project site. Costs for items not fully consumed by the Contractor shall mean fair market value.

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
9

(1346722099)




§ 7.5.2 Rental charges for temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Contractor at the site and costs of transportation, installation, minor repairs, dismantling and removal. The total rental cost of any Contractor-owned item may not exceed the purchase price of any comparable item. Rates of Contractor-owned equipment and quantities of equipment shall be subject to the Owner’s prior written approval.

§ 7.5.3 Costs of removal of debris from the site of the Work and its proper and legal disposal.

§ 7.5.4 Costs of document reproductions, facsimile transmissions and long-distance telephone calls, postage and parcel delivery charges, telephone service at the site and reasonable petty cash expenses of the site office are included in the Lump Sum General Conditions.

§ 7.5.5 Costs of materials and equipment suitably stored off the site at a mutually acceptable location, subject to the Owner’s prior written approval.

§ 7.6 MISCELLANEOUS COSTS
§ 7.6.1 Contractor’s Controlled Insurance Program shall be charged at 1.89–% of the Cost of Work(excluding the insurance and SubGuard costs set forth in this Section). Contractor’s Builder’s Risk Insurance shall be charged at 0.8% of the Cost of Work (excluding the insurance and SubGuard costs set forth in this Section). SubGuard shall be charged at 0.9% of the Cost of Work (excluding the (i) Cost of Work for each contract of $250,000.00 or less with any Subcontractor or supplier, and (ii) insurance and SubGuard costs set forth in this Section).

§ 7.6.2 Sales, use or similar taxes imposed by a governmental authority that are related to the Work and for which the Contractor is liable.

§ 7.6.3 Fees and assessments for permits (other than the building permit which Owner will obtain), licenses and inspections for which the Contractor is required by the Contract Documents to pay.

§ 7.6.4 Fees of laboratories for tests required by the Contract Documents, except those related to defective or nonconforming Work for which reimbursement is excluded by Section 13.5.3 of AIA Document A201–2007 or by other provisions of the Contract Documents, and which do not fall within the scope of Section 7.7.3.

§ 7.6.5 Royalties and license fees paid for the use of a particular design, process or product required by the Contract Documents; the cost of defending suits or claims for infringement of patent rights arising from such requirement of the Contract Documents; and payments made in accordance with legal judgments against the Contractor resulting from such suits or claims and payments of settlements made with the Owner’s consent. However, such costs of legal defenses, judgments and settlements shall not be included in the calculation of the Contractor’s Fee or subject to the Guaranteed Maximum Price. If such royalties, fees and costs are excluded by the last sentence of Section 3.17 of AIA Document A201–2007 or other provisions of the Contract Documents, then they shall not be included in the Cost of the Work.

§ 7.6.6 Intentionally Deleted.

§ 7.6.7 Deposits lost for causes other than the Contractor’s negligence or failure to fulfill a specific responsibility in the Contract Documents.

§ 7.6.8 Legal mediation and arbitration costs, including attorneys’ fees, other than those arising from disputes between the Owner and Contractor, reasonably incurred by the Contractor after the execution of this Agreement in the performance of the Work with the Owner’s prior approval, which shall not be unreasonably withheld.

§ 7.6.9 Subject to the Owner’s prior written approval, reasonable, out-of-pocket expenses incurred in accordance with the Contractor’s standard written personnel policy for relocation and temporary living allowances of the Contractor’s personnel required for the Work.

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
10

(1346722099)




§ 7.6.10 That portion of the reasonable, out-of-pocket expenses of the Contractor’s supervisory or administrative personnel incurred while traveling in discharge of duties connected with, and necessary for, the Work. Such expenses shall be subject to Owner’s prior written approval.

§ 7.7 OTHER COSTS AND EMERGENCIES
§ 7.7.1 Other reasonable, out-of-pocket costs incurred in the performance of the Work if, and to the extent, approved in advance in writing by the Owner.

§ 7.7.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency affecting the safety of persons and property, as provided in Section 10.4 of AIA Document A201–2007 (not caused by the negligence or willful misconduct of Contractor and/or its Subcontractors of any tier).

§ 7.7.3 Costs of repairing or correcting damaged or nonconforming Work executed by the Contractor, Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused by negligence or failure to fulfill a specific responsibility of the Contractor or its Subcontractor and only to the extent that the cost of repair or correction is not recovered by the Contractor from insurance, sureties, Subcontractors, suppliers, or others.

§ 7.8 RELATED PARTY TRANSACTIONS
§ 7.8.1 For purposes of Section 7.8, the term “related party” shall mean a parent, subsidiary, affiliate or other entity having common ownership or management with the Contractor; any entity in which any stockholder in, or management employee of, the Contractor owns any interest in excess of ten percent in the aggregate; or any person or entity which has the right to control the business or affairs of the Contractor. The term “related party” includes any member of the immediate family of any person identified above.

§ 7.8.2 If any of the costs to be reimbursed arise from a transaction between the Contractor and a related party, the Contractor shall notify the Owner in writing of the specific nature of the contemplated transaction, including the identity of the related party and the anticipated cost to be incurred, before any such transaction is consummated or cost incurred. If the Owner, after such written notification, authorizes the proposed transaction, then the cost incurred shall be included as a cost to be reimbursed, and the Contractor shall procure the Work, equipment, goods or service from the related party, as a Subcontractor, according to the terms of Article 10. If the Owner fails to authorize the transaction, in writing, the Contractor shall procure the Work, equipment, goods or service from some person or entity other than a related party according to the terms of Article 10.

ARTICLE 8   COSTS NOT TO BE REIMBURSED
§ 8.1 The Cost of the Work shall not include the items listed below:
.1
Salaries and other compensation of the Contractor’s personnel stationed at the Contractor’s principal office or offices other than the site office, except as specifically provided in Section 7.2. or as may be expressly provided in Article 15;
.2
Expenses of the Contractor’s principal office and offices other than the site office;
.3
Overhead and general expenses, except as may be expressly included in Article 7;
.4
The Contractor’s capital expenses, including interest on the Contractor’s capital employed for the Work;
.5
Except as provided in Section 7.7.3 of this Agreement, costs due to the negligence or failure of the Contractor, Subcontractors and suppliers or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract;
.6
Any cost not specifically and expressly described in Article 7;
.7
Costs, other than costs included in Change Orders approved by the Owner, that would cause the Guaranteed Maximum Price to be exceeded;
.8
Any cost that is counted more than once (e.g., an item that is part of the General Condition Items may not also be counted as part of the other Cost of Work);
.9
Amounts required to be paid by Contractor for federal, state or local income or franchise taxes;

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
11

(1346722099)



.10
Unless otherwise agreed by Owner in writing, any acceleration costs, including any and all overtime wages, arising as a result of delay in carrying out the Work caused by Contractor or its Subcontractors of any tier;
.11
Any costs or expenses in connection with any indemnity provided by Contractor pursuant to the Contract Documents;
.12
Costs associated with Contractor’s failure to obtain any and all applicable permits for which Contractor is responsible in a timely manner, as more fully described in the General Conditions; and
.13
The costs incurred by Contractor resulting from the failure of Contractor or its Subcontractors to coordinate their work with the work of Owner and its contractors, if any, or otherwise to fail to comply with written directives of Owner not in conflict with the Schedule.

ARTICLE 9   DISCOUNTS, REBATES AND REFUNDS
§ 9.1 Cash discounts obtained on payments made by the Contractor shall accrue to the Owner if (1) before making the payment, the Contractor included them in an Application for Payment and received payment from the Owner, or (2) the Owner has deposited funds with the Contractor with which to make payments; otherwise, cash discounts shall accrue to the Contractor. Trade discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Contractor shall make provisions so that they can be obtained.

§ 9.2 Amounts that accrue to the Owner in accordance with the provisions of Section 9.1 shall be credited to the Owner as a deduction from the Cost of the Work.

ARTICLE 10   SUBCONTRACTS AND OTHER AGREEMENTS
§ 10.1 Those portions of the Work that the Contractor does not customarily perform with the Contractor’s own personnel shall be performed under subcontracts or by other appropriate agreements with the Contractor. The Owner may designate specific persons from whom, or entities from which, the Contractor shall obtain bids. For each trade, Contractor shall obtain at least three (3) bids from Subcontractors and from suppliers of materials or equipment fabricated especially for the Work and shall deliver such bids to the Architect. The Owner shall then determine, with the advice of the Contractor and the Architect, which bids will be accepted. The Contractor shall not be required to contract with anyone to whom the Contractor has reasonable objection.

§ 10.2 When a specific bidder (1) is recommended to the Owner by the Contractor; (2) is qualified to perform that portion of the Work; and (3) has submitted a bid that conforms to the requirements of the Contract Documents without reservations or exceptions, but the Owner requires that another bid be accepted, then the Contractor may require that a Change Order be issued to adjust the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Contractor and the amount of the subcontract or other agreement actually signed with the person or entity designated by the Owner.

§ 10.3 Subcontracts or other agreements shall conform to the applicable payment provisions of this Agreement, and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. If the Subcontract is awarded on a cost-plus a fee basis, the Contractor shall provide in the Subcontract for the Owner to receive the same audit rights with regard to the Subcontractor as the Owner receives with regard to the Contractor in Article 11, below.

ARTICLE 11   ACCOUNTING RECORDS
The Contractor shall keep full and detailed records and accounts related to the cost of the Work and exercise such controls as may be necessary for proper financial management under this Contract and to substantiate all costs incurred. The accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner’s auditors shall, during regular business hours and upon reasonable notice, be afforded access to, and shall be permitted to audit and copy, the Contractor’s records and accounts, including complete documentation supporting accounting entries, books, correspondence, instructions, drawings, receipts, subcontracts, Subcontractor’s proposals, purchase orders, vouchers, memoranda and other data relating to this Contract. Owner agrees that the lump sum amounts, rates, multipliers and other fixed percentages and amounts to which it has agreed in writing that Contractor may charge as a Cost of the Work are subject to Owner’s audit rights only for Owner to confirm that such rates,

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
12

(1346722099)



quantities, hours, multipliers, percentages or amounts have been charged by Contractor in accordance with this Agreement, and that the composition of such rates, multipliers, percentages or amounts are not subject to audit by the Owner. The Contractor shall preserve these records for a period of three years after final payment, or for such longer period as may be required by law.

ARTICLE 12   PAYMENTS
§ 12.1 PROGRESS PAYMENTS
§ 12.1.1 Based upon monthly Applications for Payment submitted to the Architect, Project Manager and Owner by the Contractor, including any supporting documentation reasonably required by Owner and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 12.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:

On or before the twentieth (20th) day of the calendar month covered by an Application for Payment, the Owner (or its representative or Project Manager) and the Contractor shall meet to review a preliminary draft of the Application for Payment for such month (hereinafter referred to as a "Pencil Draw") prepared by the Contractor, which Pencil Draw shall be consistent with the requirements of the Contract Documents. The Contractor shall promptly revise the Pencil Draw in accordance with any objection or recommendation of the Owner that is consistent with the requirements of the Contract Documents. On or before the twenty-first (21st) day of such calendar month covered by an Application for Payment (or, if such day is not a business day, then the next succeeding business day), the Contractor and Owner shall walk the job to determine whether modification to the Pencil Draw should be made. A final Pencil Draw shall then be submitted by the Contractor to the Owner as the Application for Payment for such month, which is due by the first (1st) day of the month immediately following the month in which the Pencil Draw was first submitted.

§ 12.1.3 Provided that a complete Application for Payment is received by the Architect and the Owner, not later than the1st day of a month, the Owner shall make payment of the certified amount to the Contractor not later than the1st day of the following month. If an Application for Payment is received by the Architect after the application date fixed above, payment shall be made by the Owner not later than thirty (30) days after the Owner receives the Application for Payment, or such lesser time as is required by Arizona law.
(Federal, state or local laws may require payment within a certain period of time.)

§ 12.1.4 With each Application for Payment, the Contractor shall submit any evidence reasonably required by the Owner or Architect to demonstrate that cash disbursements already made by the Contractor on account of the Cost of the Work equal or exceed (1) progress payments already received by the Contractor; less (2) that portion of those payments attributable to the Contractor’s Fee; plus (3) payrolls for the period covered by the present Application for Payment. Further, with each Application for Payment, Contractor shall certify to Owner that except for claims previously submitted in writing, as of the date of each Application for Payment, Contractor has no claims for an increase in the Guaranteed Maximum Price.

§ 12.1.5 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor’s Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner and Architect may require. This schedule, unless objected to by the Owner or Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 12.1.6 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. The percentage of completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed; or (2) the percentage obtained by dividing (a) the expense that has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b)

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
13

(1346722099)



the share of the Guaranteed Maximum Price allocated to that portion of the Work. The Contractor shall ensure that each Application for Payment is accompanied by the following items: (a) certification by the Contractor that the Work for which payment is being sought has been completed in accordance with the Contract Documents and all applicable permits; (b) a conditional waiver and release of lien upon progress payment that complies with the Arizona statutory waiver form, ARS § 33-1008, for the Contractor, each Subcontractor and each Sub-Subcontractor for which payment is being sought in the total amount of the progress payment being requested; (c) an unconditional waiver and release of lien upon progress payment that complies with the Arizona statutory waiver form, ARS § 33-1008 for the Contractor with respect to all Work previously billed and paid through the preceding Application for Payment; (d) an unconditional waiver and release of lien upon progress payment that complies with the Arizona statutory waiver form, ARS § 33-1008, for each Subcontractor and Sub-Subcontractor with respect to all Work previously billed and paid through the preceding Application for Payment; and (e) a log of all Change Orders and other Modifications issued through the date of the Application for Payment.

§ 12.1.7 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
.1
Take that portion of the Guaranteed Maximum Price properly allocable to completed Work as determined by multiplying the percentage of completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values, less retainage of ten percent (10%). Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included as provided in Section 7.3.9 of the General Conditions;
.2
Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work, or if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing, less retainage of five percent (5%);
.3
Add the Contractor’s Fee, less retainage of zero percent ( 0 %).The Contractor’s Fee shall be computed upon the Cost of the Work at the rate stated in Section 5.1.1 or, if the Contractor’s Fee is stated as a fixed sum in that Section, shall be an amount that bears the same ratio to that fixed-sum fee as the Cost of the Work bears to a reasonable estimate of the probable Cost of the Work upon its completion;
    
.4
Subtract the aggregate of previous payments made by the Owner;
.5
Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Section 12.1.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner’s auditors in such documentation; and
.6
Subtract amounts, if any, for which the Architect (or Owner) has withheld or nullified a Certificate for Payment as provided in Section 9.5 of the General Conditions and as allowed by the Arizona Prompt Pay Act, § 32-1129.01 et seq., if applicable.

§ 12.1.8 The Owner and the Contractor shall agree upon a (1) mutually acceptable procedure for review and approval of payments to Subcontractors and (2) the percentage of retainage held on Subcontracts, and the Contractor shall execute subcontracts in accordance with those agreements. At Substantial Completion all retainage shall be released to Contractor less fifty percent (50%) of such retainage.

§ 12.1.9 In taking action on the Contractor’s Applications for Payment, the Architect shall be entitled to rely on the accuracy and completeness of the information furnished by the Contractor and shall not be deemed to represent that the Architect has made a detailed examination, audit or arithmetic verification of the documentation submitted in accordance with Section 12.1.4 or other supporting data; that the Architect has made exhaustive or continuous on-site inspections; or that the Architect has made examinations to ascertain how or for what purposes the Contractor has used amounts previously paid on account of the Contract. Such examinations, audits and verifications, if required by the Owner, will be performed by the Owner’s auditors acting in the sole interest of the Owner.


AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
14

(1346722099)



§ 12.2 FINAL PAYMENT
§ 12.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor within thirty (30) days or such lesser time as is required by Arizona law.
.1
the Contractor has fully performed the Contract (including all Punch List work) except for the Contractor’s responsibility to correct Work as provided in Section 12.2.2 of the General Conditions, and to satisfy other requirements, if any, which extend beyond final payment;
.2
the Contractor has submitted a final accounting for the Cost of the Work and a final Application for Payment;
.3
a final Certificate for Payment has been issued by the Architect;
.4
a Temporary Certificate of Occupancy has been issued by the appropriate governmental agencies or all governmental sign-offs for Work; and
.5
a Conditional Waiver and Release of Lien Upon Final Payment has been issued by Contractor and all of its Subcontractors, materialmen, vendors and suppliers of all tiers.

Owner shall have no obligation to make final payment of the Contract Sum until Contractor has property served and recorded a Notice of Completion of all of the Work pursuant to applicable Arizona law.

§ 12.2.2 As a condition to Owner's obligation to pay Contractor the Final Payment, (a) final building inspections shall have been completed and sign-offs on building permits by the appropriate governmental agency shall have been delivered by Contractor to Owner, Architect and Project Manager, (b) the Project shall have been completed in accordance with the Contract Documents; (c) Contractor must have delivered to Owner and Project Manager a final certificate certifying Substantial Completion of the Project in accordance with the Contract Documents; and (d) as-built plans for the entire Project shall have been delivered to Owner in PDF and hard copy formats.

§ 12.2.3 If the Owner’s auditors report the Cost of the Work as substantiated by the Contractor’s final accounting to be less than claimed by the Contractor, the Contractor shall be entitled to request mediation of the disputed amount without seeking an initial decision pursuant to Section 15.2 of A201–2007. A request for mediation shall be made by the Contractor within 30 days after the Contractor’s receipt of a copy of the Architect’s final Certificate for Payment. Failure to request mediation within this 30-day period shall result in the substantiated amount reported by the Owner’s auditors becoming binding on the Contractor. Pending a final resolution of the disputed amount, the Owner shall pay the Contractor the amount certified in the Architect’s final Certificate for Payment.

§ 12.2.4 The Owner’s final payment to the Contractor shall be made no later than thirty (30) days after the issuance of the Architect’s final Certificate for Payment and satisfaction of all other requirements under Sections 12.2.1 and 12.2.2.



§ 12.2.5 If, subsequent to final payment and at the Owner’s request, the Contractor incurs costs described in Article 7 and not excluded by Article 8 to correct defective or nonconforming Work, the Owner shall reimburse the Contractor such costs and the Contractor’s Fee applicable thereto on the same basis as if such costs had been incurred prior to final payment, but not in excess of the Guaranteed Maximum Price. If the Contractor has participated in savings as provided in Section 5.2, the amount of such savings shall be recalculated and appropriate credit given to the Owner in determining the net amount to be paid by the Owner to the Contractor.

ARTICLE 13   DISPUTE RESOLUTION
§ 13.1 INITIAL DECISION MAKER
The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A201–2007, unless the parties appoint below another individual, not a party to the Agreement, to serve as Initial Decision Maker.
(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.)




AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
15

(1346722099)





§ 13.2 BINDING DISPUTE RESOLUTION
For any Claim subject to, but not resolved by mediation pursuant to Section 15.3 of AIA Document A201–2007, the method of binding dispute resolution shall be as follows:
(Check the appropriate box. If the Owner and Contractor do not select a method of binding dispute resolution below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction.)

[
X
]
 
Arbitration pursuant to Section 15.4 of AIA Document A201–2007
 
 
 
 
 
[
 
]
 
Litigation in a court of competent jurisdiction
 
 
 
 
 
[
 
]
 
Other (Specify)
 
 
 
 
 


ARTICLE 14   TERMINATION OR SUSPENSION
§ 14.1 Subject to the provisions of Section 14.2 below, the Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2007.

§ 14.2 If the Owner terminates the Contract for cause as provided in Article 14 of AIA Document A201–2007, the amount, if any, to be paid to the Contractor under Section 14.2.4 of AIA Document A201–2007 shall not cause the Guaranteed Maximum Price to be exceeded, nor shall it exceed an amount calculated as follows:
.1
Take the Cost of the Work incurred by the Contractor to the date of termination;
.2
Add the Contractor’s Fee computed upon the Cost of the Work to the date of termination at the rate stated in Section 5.1.1 or, if the Contractor’s Fee is stated as a fixed sum in that Section, an amount that bears the same ratio to that fixed-sum Fee as the Cost of the Work at the time of termination bears to a reasonable estimate of the probable Cost of the Work upon its completion; and
.3
Subtract the aggregate of previous payments made by the Owner.

§ 14.3 The Owner shall also pay the Contractor fair compensation, either by purchase or rental at the election of the Owner, for any equipment owned by the Contractor that the Owner elects to retain and that is not otherwise included in the Cost of the Work under Section 14.2.1. To the extent that the Owner elects to take legal assignment of subcontracts and purchase orders (including rental agreements), the Contractor shall, as a condition of receiving the payments referred to in this Article 14, execute and deliver all such papers and take all such steps, including the legal assignment of such subcontracts and other contractual rights of the Contractor, as the Owner may require for the purpose of fully vesting in the Owner the rights and benefits of the Contractor under such subcontracts or purchase orders.

§ 14.4 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2007; in such case, the Guaranteed Maximum Price and Contract Time shall be increased as provided in Section 14.3.2 of AIA Document A201–2007, except that the term “profit” shall be understood to mean the Contractor’s Fee as described in Sections 5.1.1 and Section 6.4 of this Agreement.

ARTICLE 15   MISCELLANEOUS PROVISIONS
§ 15.1 Where reference is made in this Agreement to a provision of AIA Document A201–2007 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.


AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
16

(1346722099)



§ 15.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rate of interest agreed upon, if any.)

%

§ 15.3 The Owner’s representative:
(Name, address and other information)

Gary Ghio
G2 Facilities Management Consulting


Telephone:
Email:

Unless and until Owner notifies Contractor to the contrary or otherwise provides Contractor with different instructions, Gary Ghio is hereby designated by Owner as its authorized representative to make decisions for, and receive information on behalf of, Owner in connection with the Work, provided, however, all written notices required to Owner under the Contract Documents shall also be given to Owner at its address on Page 1 of this Agreement and to the following: Dexcom, 6340 Sequence Drive, San Diego, CA 92121, Attn: Timothy F. O’Brien, Director Legal Affairs. In addition, all submissions or notices made by Contractor to the Architect shall simultaneously be made to Owner’s representative.

§ 15.4 The Contractor’s representative:
(Name, address and other information)

Kevin E. Devlin, Project Executive
Skanska USA Building Inc.
4742 N. 24th Street, Suite 165
Phoenix, AZ 85016
Mobile: 1 787 466 8204 Kevin.Devlin@skanska.com


§ 15.5 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ written notice to the other party.

§ 15.6 Other provisions.

§ 15.6.1 Contractor covenants that all the Work shall be done in a good and workmanlike manner and that all materials furnished and used in connection therewith shall be new and meet the criteria provided in the Contract Documents. Contractor shall cause all materials and other parts of the Work to be readily available as and when required or needed for or in connection with the construction of the Project.

§ 15.6.2 In performing its obligations under this Agreement, the Contractor shall be deemed an independent contractor and not an agent or employee of the Owner.

§ 15.6.3 Contractor agrees to make such revisions to this Agreement as may be reasonably required by Owner’s construction lender, if any, and Contractor agrees to comply with customary requirements of construction and permanent lenders which may be reasonably imposed as a condition to payments due under this Agreement. Contractor further agrees to execute a mutually agreed upon consent of the Owner’s assignment of this Agreement to Owner’s lender within ten (10) days following a request therefor on such form as the lender may reasonably require.


AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
17

(1346722099)



§ 15.6.4 If any term, covenant or condition of the Contract Documents, or the application thereof to any persons or circumstance shall to any extent be invalid or unenforceable, then the remainder of the Contract Documents or the application of the term, covenant or condition to persons or circumstances other than those as to which it is held invalid or unenforceable shall not be affected thereby, and each term, covenant and condition of the Contract Documents shall be valid and enforceable to the fullest extent permitted by law.

§ 15.6.5 Owner may designate from time to time by written notice to Contractor one or more Owner’s representatives or other parties to deal with Contractor on matters pertaining to administration of the provisions of the Contract Documents. However, only those signatories designated in writing by Owner shall have the authority to approve Change Orders increasing or decreasing the Guaranteed Maximum Price or extending the Contract Time.

§ 15.6.6 The parties agree and declare that Contractor and Owner are separate and independent entities and that Contractor has full responsibility for performance of Work and direction of the work force, subject to and under the duty of Contractor to cooperate with Owner and other contractors. Contractor recognizes that in the performance of its Work it will be required to work side by side with other contractors and representatives of Owner on the job site. Owner, Contractor and /or other contractors may or may not be signatory to collective bargaining agreements of the various labor organizations. Contractor agrees that should there be picketing or a threat of picketing by any labor organization at or near the site, (i) Contractor shall immediately notify Owner in writing of such circumstances and (ii) Owner may establish or require Contractor to establish a reserve gate system and may require Contractor’s and Owner’s employees, suppliers and subcontractors to use one or more designated gates. In that event, it shall be the affirmative obligation of Contractor as a material consideration of this Agreement to ensure that its employees, suppliers and Subcontractors use only the gate(s) or other entry way(s) so designated. Notwithstanding the establishment or non-establishment of a reserve gate system, it shall be the continuing obligation of Contractor (and its Subcontractors) to properly staff the job with qualified and skilled workmen and employees without interruption or delay and without any increase to the Guaranteed Maximum Price. Contractor agrees to cooperate fully and promptly with Owner and its representatives and attorneys with respect to any labor dispute that should arise on the site, including but not limited to the giving of testimony and evidence to the agent or judge of the National Labor Relations Board or in connection with proceedings in State or Federal court. Contractor agrees to undertake or cause to be undertaken in a prompt and expeditious manner, all action involved to resolve and/or minimize the consequences of any labor dispute that should arise on the site. Contractor hereby warrants that it is not now nor will Contractor be delinquent in the payment or reporting to any labor management benefit trust fund and further warrants that Contractor is not now nor will Contractor appear on any delinquency list published by any labor management benefit trust fund. Contractor indemnifies, defends and holds Owner entirely harmless from and against all costs, claims, liabilities, damages, delays, losses and expenses (including attorneys’ fees and costs) arising directly or indirectly from Contractor’s failure to comply with the provisions of this Section 15.6.6.

§ 15.6.7 The Contractor and Owner entered into that certain Nondisclosure Agreement dated as of November 19, 2015 (“NDA”) in order to protect certain confidential information of Owner, as further set forth in the NDA. Contractor and Owner hereby incorporate the terms, provisions and obligations of the NDA in this Agreement.

ARTICLE 16   ENUMERATION OF CONTRACT DOCUMENTS
§ 16.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in the sections below.

§ 16.1.1 The Agreement is this executed AIA Document A102–2007, Standard Form of Agreement Between Owner and Contractor.

§ 16.1.2 The General Conditions (as modified) are attached hereto as Exhibit C.

§ 16.1.3 The Supplementary and other Conditions of the Contract:

Document
Title
Date
Pages
 
 
 
 

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
18

(1346722099)




§ 16.1.4 The Specifications:
(Either list the Specifications here or refer to an exhibit attached to this Agreement.)
See list of Exhibits at 16.1.7.2.

Section
Title
Date
Pages
 
 
 
 

§ 16.1.5 The Drawings:
(Either list the Drawings here or refer to an exhibit attached to this Agreement.)
See list of Exhibits at 16.1.7.2.

Number
Title
Date
 
 
 

§ 16.1.6 The Addenda, if any:

Number
Date
Pages
 
 
 

Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding requirements are also enumerated in this Article 16.

§ 16.1.7 Additional documents, if any, forming part of the Contract Documents:
.1
AIA Document E201™–2007, Digital Data Protocol Exhibit, if completed by the parties, or the following:



.2
Other documents, if any, listed below:

Exhibit A – Approval Letter
Exhibit B Clarifications and Assumptions to GMP
Exhibit C – Lump Sum General Conditions & Schedule of Billable Rates
Exhibit D – Drawings
Exhibit E – Specifications
Exhibit F – CCIP Insurance Exhibit


ARTICLE 17   INSURANCE AND BONDS
 
§ 17.1.1 Contractor Controlled Insurance Program. Contractor will satisfy the requirements of Section 11.1.1 of the General Conditions through a project specific Contractor Controlled Insurance Program (“CCIP”) as described in Exhibit F, which will afford similar coverage for the Subcontractors, in the minimum coverage amounts set forth below in this Article 17, with insurance written on an occurrence basis purchased from and maintained in a company or companies which have a Best’s Rating of “A/VIII” or above and which are lawfully authorized to do business in the State of Arizona. The program will be administered through the Contractor and will be billed at the value set forth in the A102 Agreement, and will be included on all change orders though Final Completion. The Contractor is responsible for all deductibles. The CCIP will include coverage for completed operations through the statute of repose for the State of Arizona. The Owner, Contractor and all tiers of Subcontractors that enter the Project site are

AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
19

(1346722099)



expected to be covered, except structural demolition and abatement Subcontractors, if there are any. Any instances where work is contracted by the Owner directly (other than with Contractor) or with separate contractors are not covered by the CCIP. The Owner is required to obtain insurance from those parties, if any.

No cost saving have been guaranteed to Owner by Contractor and Contractor is not responsible for deducts in regard to any accounting for the CCIP.

§ 17.1.1.1 Workers’ Compensation
Coverage A. Statutory Benefits
Coverage B. Employers Liability

Bodily injury by accident:             $2,000,000 each accident
Bodily injury by disease:                 $2,000,000 policy limit
Bodily injury by disease:                $2,000,000 each employee

§ 17.1.1.2 Commercial General Liability
Commercial General Liability coverage (equivalent in coverage to ISO Form CG 00 01 with an edition date of at least 11/88) of not less than:

Each Occurrence Limit:                        $2,000,000
Personal Advertising Injury Limit:                    $2,000,000
Products/Completed Operations Aggregate Limit:            $4,000,000
General Aggregate Limit (other than Products/Completed Operations    $4,000,000

§ 17.1.1.3 Excess Liability Umbrella
Excess Liability or Umbrella coverage of not less than and including all above liability policies in the underlying.

Each Occurrence                            $25,000,000
General Aggregate                        $25,000,000

ALL OF 17.1 SUBJECT TO SKANSKA RISK MANAGEMENT REVIEW
§ 17.2 INSURANCE REQUIRED OF THE OWNER
The Owner shall purchase and maintain liability insurance, including waivers of subrogation, as set forth in Sections 11.2 of the General Conditions.
This Agreement entered into as of the day and year first written above.


 
 
 
THE OWNER 
DexCom, Inc. 
a Delaware corporation

s/ Jess Roper

By: Jess Roper
Its: CFO
Date: 4/29/16

 
THE CONTRACTOR 
Skanska USA Building Inc.


s/ Ross A Vroman

By: Ross A. Vroman
Its: Area General Manager, EVP
Date: 5/2/16



 
 
 


AIA Document A102™ - 2007 (formerly A111™ - 1997). Copyright © 1920, 1925, 1951, 1958, 1961, 1963, 1967, 1974, 1978, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:15:24 on 01/04/2016 under Order No.3294902806_1 which expires on 12/13/2016, and is not for resale.
User Notes:                                                                                                                                                                                                                                                                       
20

(1346722099)

 

EXHIBIT A

APPROVAL LETTER

 

LOGO

AWARD APPROVAL LETTER NO. 014

May 16, 2016

DexCom

6340 Sequence Drive

San Diego, CA 92121    m

 

Attention:

Project:

  

Gary Ghio

DexCom Phoenix – Phase One

Phoenix, AZ

Subject:    Subcontractor /Vendor Award Recommendation
   Bid Package No.:    4415014-012
   Trade:    Fire Sprinkler System
   Subcontractor:    Fire Protection Systems
   Award Amount:    $832,500

In accordance with the Agreement, we submit as follows our Bid Package Report and Award recommendation for the above Subcontract. We have included the final bid leveling sheet detailing the costs proposals provided. The award to Fire PS was based on the price, availability and schedule to complete the Fire Sprinkler scope items.

Note, as directed by DexCom, this Approval Letter includes the design and installation of the sprinkler system. If the supply of materials and install is wanted at a later date, an official AL will need to be signed.

Attached is the bid leveling sheet and proposals issued previously on January 08th, 2016 from the fire sprinkler bidders for your reference. Fire alarm, wiring of equipment, permits have been excluded. Also excluded are sprinklers under the equipment platform. Proposals are based off of the 10/22/15 drawings and specifications.

 

1.0 Bid Submission Results and Analysis:

 

Vendor:

   Firetrol Protection Systems  

Fire PS

   $ 832,500   

Olympic

   $ 880,028   

Aero

   $ 954,650   

American

   $ 968,200   

 

2.0 Pricing Details:

 

  a) Included/Excluded in the amount of this award is ALLOWANCE/Alternates:

 

  1. EXCLUDED ALLOWANCE – Fire/Jockey Pumps/Control Panel $205,000

 

  2. EXCLUDED ALLOWANCE – Sprinkler System under Equipment Platform per Fire Marshall $140,000

 

  3. EXCLUDED Alternate – Nitrogen Gen System $49,385 plus Skanska’s Markups

 

  4. EXCLUDED Alternate – Credit to not remove the underground ductile pipe noted on FP-101A and cap riser with blind flange at riser stub up. ($17,000)

 

Exhibit A - Approval Letter - Fire Sprinkler System 1

 

  Exhibit A   Page 1


LOGO

 

b) Recommended amount of this award. (Please refer to attached Bid Leveling Documentation for additional breakdown.)

As directed by DexCom, the price below only includes the design costs associated to the fire sprinkler system.

 

Fire PS (Design Only)

     $ 45,000   

CCIP

     1.88   $ 846.00   

Subguard

     0.90   $ 405.00   

Builders Risk

     1.25   $ 563.00   

Skanska - Fee

     3.25   $ 1,521.00   

TAX

       EXCLUDED   
     Total:      $ 48,335.00   

As issued previously, the complete system for the fire sprinkler system for design, supply and install is as follows:

 

Fire PS

     $ 832,500   

CCIP

     1.88   $ 15,651.00   

Subguard

     0.90   $ 7,493.00   

Builders Risk

     1.25   $ 10,406.00   

Skanska - Fee

     3.25   $ 28,147.00   

TAX

       EXCLUDED   
     Total:      $ 894,197.00   

 

** Note: Taxes have been excluded from this AL. A specific AL for taxes will be issued if taxes are ever to be included.

 

3.0 Alternates. The Award Recommendation amount includes the following alternates (as noted above):

 

  x The Award Recommendation amount does not incorporate any alternates

OR

 

  ¨ The Award Recommendation amount includes the following alternates/allowances:

 

  5. EXCLUDED ALLOWANCE – Fire/Jockey Pumps/Control Panel $205,000

Please refer to attached Bid Leveling Documentation for additional breakdown:

We have evaluated the Sub-contractors proposal, and have determined that the Sub-contractor has included the full scope of work. Any deviations from the original drawings, specifications, bid package documents or subcontract documents are clearly delineated in the revised scope of work which shall become part of the subcontract documents. The following documents shall be incorporated into the subcontract documents:

 

A

  

CM’s standard form of subcontract agreement with no changes

  

B

  

CM’s project schedule dated

  

N/A

C

  

Site Logistics Plan dated

  

N/A

D

  

Issue for Construction specifications dated

  

10/22/2015

E

  

Pre-Bid Meeting Minutes dated

  

Dec. 2015

F

  

Meeting minutes from Scope review meeting dated

  

N/A

G

  

Bid Addendum (a) No(s). 2

  

Dated

H

  

Other items as appropriate

  

 

Exhibit A - Approval Letter - Fire Sprinkler System 2

 

  Exhibit A   Page 2


LOGO

 

4.0 Schedule. We have reviewed the subcontractor’s proposal, and proposed execution of the scope, and confirm that the subcontractor will work to the Project Schedule as defined in the Contract Documents. Please note key schedule dates/durations:

 

5.0 M/WBE Participation.

The recommended Contractor is not a M/WBE and has submitted a M/WBE utilization plan, which lists 0% Dollars ($0) of M/WBE participation.

We hereby recommend that the award of this sub-contract is made to Fire PS for the purchase order price of:

 

Forty Eight Thousand Three Hundred Thirty Five

   $ 48,335.00         Dollars   

 

In making this recommendation, we have carried out certain checks and procedures to satisfy ourselves as to the present capability of (Firetrol) to perform the sub-contract work; details of these are given on the attached Bid Recording Sheet.

If you are in agreement with the above recommendation, please sign where indicated below and return one signed copy of this letter authorizing us to award the subcontract. Upon receipt of this signed approval letter we will incorporate the committed sub-contract price and pending items into our next Anticipated Cost Report.

 

Sincerely,   DexCom
   

Todd Kadjan

Project Manager

  Approved By:   

 

   
  Date:   

 

Cc:   Kevin Devlin, Skanska USA Building

 Ian Miles, Aligned Energy

        

 

Exhibit A - Approval Letter - Fire Sprinkler System 3

 

  Exhibit A   Page 3


EXHIBIT B

CLARIFICATIONS AND ASSUMPTIONS TO GMP

 

LOGO

Exhibit B

GMP Assumptions & Clarifications

 

  - N/A – to be issued when GMP is established

 

  Exhibit B   Page 1


EXHIBIT C

LUMP SUM GENERAL CONDITIONS & SCHEDULE OF BILLABLE RATES

 

LOGO

EXHIBIT “C”

SCHEDULE OF BILLABLE RATES

 

Project Executive

   $ 135/hr   

Project Manager

   $ 100/hr   

Superintendent

   $ 110/hr   

Preconstruction Director

   $ 100/hr   

MEP Coordinator

   $ 135/hr   

Mechanical Estimator

   $ 100/hr   

C/S/A Estimator

   $ 100/hr   

Electrical Estimator

   $ 100/hr   

Accounting

   $ 70/hr   

Director of Accounting

   $ 80/hr   

 

   Page 1 of 1   

Alternates, Unit Prices, and Labor Rates

(05/2009 ed. Rev. 1)

     

 

  Exhibit C   Page 1


EXHIBIT C

 

LOGO

DEXCOM Preconstruction & Construction General Conditions, General Requirements & Closeout, Start-up & Commission Support

 

Description                     2016  
                      Jan     Feb     Mar     Apr     May     Jun     Jul     Aug     Sep     Oct     Nov     Dec     Jan     Feb     Mar     Apr  

Preconstruction GC’s

    Rate        Unit                                     

Mechanical Estimator

  $ 100.00        hour          70        40        40                             

C/S/A Estimator

  $ 100.00        hour          30        30        20                             

Electrical Estimator

  $ 100.00        hour          30        30        20                             

Admin

  $ 55.00                                       

Accountant

  $ 70.00        hour          8        8        8                             

Director of accounting

  $ 80.00        hour          4                                 

IT

  $ 45.00        hour                                     

VDC Budget

                                     

VDC Director

  $ 110.00        Hour          19        5        5                             

VDC Manager

  $ 75.00        Hour          20        20        20                             

VDC travel

  $ 1,100.00        Per Trip          1                                 

General travel to SAN (single day)

  $ 600.00        Per Trip          10        5        5                             

General travel to SAN (with overnight)

  $ 1,100.00        Per Trip          7        5        5                             

Meeting Expenses

  $ 750.00        ea          2        2        2                             

Blueprints

  $ 250.00        per month          2        2        2                             

FEDEX

  $ 175.00        per month          1        1        1                             

Project Management Software

  $ 150.00        ea          2        2        2                             

Construction GC’s

                                     

Project Executive

  $ 135.00        hour                  70        70        70        70        70        70        70        70        70        70        70        70   

Project Manager

  $ 100.00        hour                  175        175        175        175        175        175        175        175        175        175        175        175   

Project Engineer

  $ 85.00        hour                  175        175        175        175        175        175        175        175        175        175        175        175   

Superintendent

  $ 110.00        hour                  175        175        175        175        175        175        175        175        175        175        175        175   

Precon Dir/Coordination Specialist

  $ 100.00        hour                  40        40        40        40        40        40        40        40        40        40        40        40   

Safety

  $ 75.00        hour                  20        20        20        20        20        20        20        20        20        20        20        20   

QA/QC - TOP Manager

  $ 75.00        hour                  40        88        175        175        175        175        175        175        175        175        175        40   

Admin

  $ 55.00        hour                  175        175        175        175        175        175        175        175        175        175        155        20   

Accountant

  $ 70.00        hour                  15        15        15        15        15        15        15        15        15        15        15        15   

Director of accounting

  $ 80.00        hour                  5        5        5        5        5        5        5        5        5        5        5        5   

IT

  $ 45.00        hour                  8        8        8        8        8        8        8        8        8        8        8        8   

VDC Budget

                                     

VDC Director

  $ 110.00        Hour                  8        8        8        8        8        8        8        8        8        8        8        8   

VDC Manager

  $ 75.00        Hour                  20        64        64        20        20        20        20        20        20        20        20        20   

VDC travel

  $ 2,500.00        Per Trip                  2                         

Check Processing

  $ 175.00        per million        29                                   

Archiving

  $ 135.00        per million        29                                   

Meeting Expenses

  $ 750.00        ea                  1        1        1        1        1        1        1        1        1        1        1        1   

Legal Costs for Contract Nego

  $ 5,000.00        LS                                     

Job Meetings

  $ 150.00        per month                  3        3        3        3        3        3        3        3        3        3        3        3   

Blueprints

  $ 250.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

FEDEX

  $ 175.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

Water

  $ 200.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

VDC software license

  $ 950.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

Project Management Software

  $ 150.00        ea                  3        3        3        3        3        3        3        3        3        3        3        3   

Office Supplies

  $ 200.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

WIFI

  $ 250.00        per month                  1        1        1        1        1        1        1        1        1        1        1        1   

Computers/Printers

  $ 5,000.00        LS        2                                   

Owner Connectivity

  $ 5,000.00        Is        1                                   

Prolog for 5 users

  $ 350.00          5                                   

Safety Orientation

  $ 50.00        ea                  1        1        1        1        1        1        1        1        1        1        1        1   

Hardhats

  $ 50.00        ea                  1        1        1        1        1        1        1        1        1        1        1        1   

Safety Glasses

  $ 50.00        ea                  1        1        1        1        1        1        1        1        1        1        1        1   

OSHA PPE

  $ 250.00        ea                  1                         

Safety Equipment

  $ 150.00        ea                    1        1        1        1        1        1        1        1        1        1        1   

Fuel/Oil/Truck

  $ 900.00        ea                    2        2        2        2        2        2        2        2        2        2        2   

GR’s - FROM GC’s

                                     

Jobsite signage

  $ 3,000.00        LS        1                                   

Office Furniture (In Existing Facility)

  $ 15,000.00        LS        1                                   

Field Toilets

  $ 350.00        ea                  2        4        4        4        4        4        4        4        4        4        4        4   

Temporary Fencing (access control)

      LS                                     

Office Cleaning

  $ 150.00        ea                  2        4        4        4        4        4        4        4        4        4        4        4   

Permits

    By Owner                                       

Subguard

    0.90                                    

Dumpsters - Below

                                     

Laborer - Below

                                     

GR’s - FROM Logistics

                                     

General Conditions — Laborers

    32.50        HR                                     

Cleanroom Protocol — Consumables

    15,000.00        MO                                     

Final Clean — Cleanroom — 2ea

    3.00        SF                                     

Final Clean — Site

    25,000.00        LS                                     

HEPA Filter — Replacement

    150.00        EA                                     

SuperClean — Certification

                                     

General Requirements — Misc Equipment Dumpsters

    650.00        EA                  2        4        4        4        6        6        6        6        6        6        6        4   

Start-up & Commission - FROM Logistics

                                     

Closeout, Start-up, Functional Testing & Commissioning Support

  $ 1.00        LS                                     

TOTALS

                                     

 

  Exhibit C   Page 2


Description                     Total MH     Cost                                                  
                      =sum(D:P)     =T x B     Precon
Allowance
    GC-Original     Re-Allocation
1-28-16
    4-19-16     Logistics -
Original
    Logistics -
Revised
    General
Req. 1-28-16
    General
Req. 4-19-16
 

Preconstruction GC’s

    Rate        Unit                         

Mechanical Estimator

  $ 100.00        hour          150      $ 15,000.00      $ 15,000.00                 

C/S/A Estimator

  $ 100.00        hour          80      $ 8,000.00      $ 8,000.00                 

Electrical Estimator

  $ 100.00        hour          80      $ 8,000.00      $ 8,000.00                 

Admin

  $ 55.00            0      $ —        $ —                   

Accountant

  $ 70.00        hour          24      $ 1,680.00      $ 1,680.00                 

Director of accounting

  $ 80.00        hour          4      $ 320.00      $ 320.00                 

IT

  $ 45.00        hour          0      $ —        $ —                   

VDC Budget

                         

VDC Director

  $ 110.00        Hour          29      $ 3,190.00      $ 3,190.00                 

VDC Manager

  $ 75.00        Hour          60      $ 4,500.00      $ 4,500.00                 

VDC travel

  $ 1,100.00        Per Trip          1      $ 1,100.00      $ 1,100.00                 

General travel to SAN (single day)

  $ 600.00        Per Trip          20      $ 12,000.00      $ 12,000.00                 

General travel to SAN (with overnight)

  $ 1,100.00        Per Trip          17      $ 18,700.00      $ 18,700.00                 

Meeting Expenses

  $ 750.00        ea          6      $ 4,500.00      $ 4,500.00                 

Blueprints

  $ 250.00        per month          6      $ 1,500.00      $ 1,500.00                 

FEDEX

  $ 175.00        per month          3      $ 525.00      $ 525.00                 

Project Management Software

  $ 150.00        ea          6      $ 900.00      $ 900.00                 

Construction GC’s

                         

Project Executive

  $ 135.00        hour          840      $ 113,400.00        $ 68,040.00      $ 68,040.00      $ 113,400.00      $ —        $ —         

Project Manager

  $ 100.00        hour          2,100      $ 210,000.00        $ 122,300.00      $ 122,300.00      $ 210,000.00      $ —        $ —         

Project Engineer

  $ 85.00        hour          2,100      $ 178,500.00        $ 103,955.00      $ 103,955.00      $ 178,500.00      $ —        $ —         

Superintendent

  $ 110.00        hour          2,100      $ 231,000.00        $ 134,530.00      $ 134,530.00      $ 231,000.00      $ —        $ —         

Precon Dir/Coordination Specialist

  $ 100.00        hour          480      $ 48,000.00        $ 28,000.00      $ 28,000.00      $ 48,000.00      $ —        $ —         

Safety

  $ 75.00        hour          240      $ 18,000.00        $ 11,100.00      $ 11,100.00      $ 18,000.00      $ —        $ —         

QA/QC - TOP Manager

  $ 75.00        hour          1,743      $ 130,725.00        $ 65,100.00      $ 65,100.00      $ 130,725.00      $ —        $ —         

Admin

  $ 55.00        hour          1,945      $ 106,975.00        $ 59,950.00      $ 59,950.00      $ 106,975.00      $ —        $ —         

Accountant

  $ 70.00        hour          180      $ 12,600.00        $ 8,400.00      $ 8,400.00      $ 12,600.00      $ —        $ —         

Director of accounting

  $ 80.00        hour          60      $ 4,800.00        $ 3,200.00      $ 3,200.00      $ 4,800.00      $ —        $ —         

IT

  $ 45.00        hour          96      $ 4,320.00        $ 4,320.00      $ 4,320.00      $ 4,320.00      $ —        $ —         

VDC Budget

                         

VDC Director

  $ 110.00        Hour          96      $ 10,560.00        $ 7,040.00      $ 7,040.00      $ 10,560.00      $ —        $ —         

VDC Manager

  $ 75.00        Hour          328      $ 24,600.00        $ 18,600.00      $ 18,600.00      $ 24,600.00      $ —        $ —         

VDC travel

  $ 2,500.00        Per Trip          2      $ 5,000.00        $ 5,000.00      $ 5,000.00      $ 5,000.00      $ —        $ —         

Check Processing

  $ 175.00        per million        29        29      $ 5,075.00        $ 3,150.00      $ 3,150.00      $ 5,075.00           

Archiving

  $ 135.00        per million        29        29      $ 3,915.00        $ 2,430.00      $ 2,430.00      $ 3,915.00           

Meeting Expenses

  $ 750.00        ea          12      $ 9,000.00        $ 6,000.00      $ 6,000.00      $ 9,000.00           

Legal Costs for Contract Nego

  $ 5,000.00        LS          0      $ —          $ —        $ —        $ —             

Job Meetings

  $ 150.00        per month          36      $ 5,400.00        $ 3,150.00      $ 3,150.00      $ 5,400.00           

Blueprints

  $ 250.00        per month          12      $ 3,000.00        $ 2,000.00      $ 2,000.00      $ 3,000.00           

FEDEX

  $ 175.00        per month          12      $ 2,100.00        $ 1,400.00      $ 1,400.00      $ 2,100.00           

Water

  $ 200.00        per month          12      $ 2,400.00        $ 1,600.00      $ 1,600.00      $ 2,400.00           

VDC software license

  $ 950.00        per month          12      $ 11,400.00        $ 7,600.00      $ 7,600.00      $ 11,400.00           

Project Management Software

  $ 150.00        ea          36      $ 5,400.00        $ 3,600.00      $ 3,600.00      $ 5,400.00           

Office Supplies

  $ 200.00        per month          12      $ 2,400.00        $ 1,600.00      $ 1,600.00      $ 2,400.00           

WIFI

  $ 250.00        per month        2        12      $ 3,000.00        $ 2,000.00      $ 2,000.00      $ 3,000.00           

Computers/Printers

  $ 5,000.00        LS        1        2      $ 10,000.00        $ 5,000.00      $ 5,000.00      $ 10,000.00           

Owner Connectivity

  $ 5,000.00        Is        5        1      $ 5,000.00        $ 5,000.00      $ 5,000.00      $ 5,000.00           

Prolog for 5 users

  $ 350.00            5      $ 1,750.00        $ 1,750.00      $ 1,750.00      $ 1,750.00           

Safety Orientation

  $ 50.00        ea          12      $ 600.00        $ 400.00      $ 400.00      $ 600.00           

Hardhats

  $ 50.00        ea          12      $ 600.00        $ 400.00      $ 400.00      $ 600.00           

Safety Glasses

  $ 50.00        ea          12      $ 600.00        $ 400.00      $ 400.00      $ 600.00           

OSHA PPE

  $ 250.00        ea          1      $ 250.00        $ 250.00      $ 250.00      $ 250.00           

Safety Equipment

  $ 150.00        ea          11      $ 1,650.00        $ 1,050.00      $ 1,050.00      $ 1,650.00           

Fuel/Oil/Truck

  $ 900.00        ea          22      $ 19,800.00        $ 12,600.00      $ 12,600.00      $ 19,800.00           

GR’s - FROM GC’s

                         

Jobsite signage

  $ 3,000.00        LS        1        1      $ 3,000.00        $ 3,000.00          $ —        $ —        $ 3,000.00      $ 3,000.00   

Office Furniture (In Existing Facility)

  $ 15,000.00        LS        1        1      $ 15,000.00        $ 15,000.00          $ —        $ —        $ 15,000.00      $ 15,000.00   

Field Toilets

  $ 350.00        ea          46      $ 16,100.00        $ 9,800.00          $ —        $ —        $ 9,800.00      $ 16,100.00   

Temporary Fencing (access control)

      LS          0      $ —          $ —            $ —        $ —        $ —        $ —     

Office Cleaning

  $ 150.00        ea          46      $ 6,900.00        $ 4,200.00          $ —        $ —        $ 4,200.00      $ 6,900.00   

Permits

    By Owner            0                     

Subguard

    0.90         0                     

Dumpsters - Below

          0                     

Laborer - Below

          0                     

GR’s - FROM Logistics

                         

General Conditions — Laborers

    32.50        HR          4,160      $ 135,200.00              $ 270,400.00        $ 135,200.00      $ 135,200.00   

Cleanroom Protocol — Consumables

    15,000.00        MO          6      $ 90,000.00              $ 90,000.00        $ 90,000.00      $ 90,000.00   

Final Clean — Cleanroom — 2ea

    3.00        SF          28,000      $ 84,000.00              $ 84,000.00        $ 84,000.00      $ 84,000.00   

Final Clean — Site

    25,000.00        LS          1      $ 25,000.00              $ 25,000.00        $ 25,000.00      $ 25,000.00   

HEPA Filter — Replacement

    150.00        EA          351      $ 52,650.00              $ 52,650.00        $ 52,650.00      $ 52,650.00   

SuperClean — Certification

          0                  By Owner        By Owner        By Owner      $ —     

General Requirements — Misc Equipment Dumpsters

    650.00        EA          60      $ 39,000.00              $ 50,000.00        $ 20,800.00      $ 39,000.00   

Start-up & Commission - FROM Logistics

                         

Closeout, Start-up, Functional Testing & Commissioning Support

  $ 1.00        LS                      $ 160,900.00       
         

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

TOTALS

            1,738,585        79,915        732,915        700,915        1,191,820        572,050        160,900        439,650        466,850   
         

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

 

  Exhibit C   Page 3


EXHIBIT D

DRAWINGS

 

LOGO

Exhibit D – Drawings

N/A – Drawing List to be issued when GMP is established.

 

   Exhibit D    Page 1


EXHIBIT E

SPECIFICATIONS

 

LOGO

Exhibit E – Specifications

N/A – no final specifications have been issued on the project to date.

 

   Exhibit E    Page 1


EXHIBIT F

CCIP INSURANCE EXHIBIT

FORMS

 

 

Forward the completed Enrollment Application to the Aon administrator identified at the bottom of page 2 of this form. The administrator prior to the start of your work on-site must receive this form.

 

EXHIBIT 1 – Sample Enrolled Off-Site Certificate of Insurance

 

ACORD©                                 CERTIFICATE OF INSURANCE           ISSUE DATE: CURRENT DATE      

PRODUCER

Insurance Agent’s Name And Address

      THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW

 

TELEPHONE #

    COMPANIES AFFORDING COVERAGE
INSURED       COMPANY A LETTER           INSURANCE CARRIER    
Subcontractor’s Name and Address     COMPANY B LETTER            
Sample Certificate for Enrolled Parties   COMPANY C LETTER            
Required Insurance     COMPANY D LETTER        
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

CO  

LTR  

 

TYPE OF

INSURANCE

  POLICY NO.   

POLICY EFF. 

DATE 

MM/DD/YY 

 

POLICY EXP. 

DATE 

MM/DD/YY 

  ALL LIMITS
A     GENERAL LIABILITY   Policy Number            GENERAL AGGREGATE   $2,000,000      
   

x  COMMERCIAL GEN. LIABILITY

            PRODUCTS-COMP/OPS AGGREGATE   $2,000,000
   

¨   CLAIMS MADE    x OCCUR.

            PERSONAL & ADVERTISING INJURY   $1,000,000
   

¨   OWNER’S &  CONTRACTOR’S PROT. 

            EACH OCCURRENCE   $1,000,000
   

x  PER PROJECT AGGREGATE

       ENDORSEMENT

           

FIRE DAMAGE (Any one fire)

MEDICAL EXPENSE (Any one person)

 
                   
A     AUTOMOBILE LIABILITY   Policy Number            COMBINED SINGLE LIMIT   $1,000,000
   

x  ANY AUTO

            BODILY INJURY (Per person)    
   

¨  ALL OWNED AUTOS

            BODILY INJURY (Per accident)    
   

¨  SCHEDULED AUTOS

            PROPERTY DAMAGE    
   

x  HIRED AUTOS

                 
   

x  NON-OWNED AUTOS

                 
A     EXCESS LIABILITY   Policy Number            EACH OCCURRENCE   $5,000,000
   

x  UMBRELLA

            AGGREGATE   $5,000,000
   

¨  OTHER THAN UMBRELLA FORM

                 

 

A  

 

 

WORKERS’ COMPENSATION

AND

EMPLOYER’S LIABILITY

  Policy Number            STATUTORY LIMITS x Florida    
              (Each accident)   $500,000
                (Disease-policy limit)   $500,000
                    (Disease-each employee)   $500,000
A     OTHER: EQUIPMENT FLOATER   Policy Number            Limit equal to Full Coverage of Subcontractor’s owned or rented machinery, equipment, tools, & temporary structures not designed to become a permanent part of the Work
DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/SPECIAL ITEMS: RE: Work performed at the Skanska USA Building ABC Project. Certificate Holders are Additional Insureds on a Primary and Non-contributing basis on the General Liability (ISO endorsement CG 20 10-11/85 or its equivalent), Automobile and Excess/Umbrella Liability Policies. Waiver of Subrogation in favor of Certificate Holders applies to all policies. GL and WC coverage apply off-site.

CERTIFICATE HOLDER

 

Skanska USA Building Inc., Skanska USA, Inc. Indemnified Parties, any other parties as required by the Owner contract, Skanska Inc., and their respective directors, officers, employees and affiliates and ALL ENROLLED PARTIES

c/o Aon Risk Services, Inc.

4 Overlook Point

Lincolnshire, IL 60069

 

CANCELLATION

 

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES.

Attention:       AUTHORIZED REPRESENTATIVE
          By: (original signature)
ACORD 25-S (3/93)               © ACORD CORPORATION 1993

 

 

Skanska USA Building Inc. CCIP Insurance Manual – Exhibit G1

 

   Exhibit F    Page 1


FORMS

EXHIBIT 2 – Sample Excluded On/Off-Site Certificate of Insurance

 

ACORD©                                 CERTIFICATE OF INSURANCE       ISSUE DATE: CURRENT DATE      

PRODUCER

Insurance Agent’s Name and Address

      THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW
TELEPHONE #     COMPANIES AFFORDING COVERAGE
INSURED       COMPANY A LETTER           INSURANCE CARRIER    
Name and Address     COMPANY B LETTER            
Sample Certificate for Excluded Parties   COMPANY C LETTER            
Required Insurance     COMPANY D LETTER        
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

CO  

LTR  

 

TYPE OF

INSURANCE

  POLICY NO.   

POLICY EFF. 

DATE 

MM/DD/YY 

 

POLICY EXP. 

DATE 

MM/DD/YY 

  ALL LIMITS
A     GENERAL LIABILITY   Policy Number            GENERAL AGGREGATE   $2,000,000      
   

x  COMMERCIAL GEN. LIABILITY

            PRODUCTS-COMP/OPS AGGREGATE   $2,000,000
   

¨   CLAIMS MADE    x OCCUR.

            PERSONAL & ADVERTISING INJURY   $1,000,000
   

¨   OWNER’S &  CONTRACTOR’S PROT. 

            EACH OCCURRENCE   $1,000,000
   

x  PER PROJECT AGGREGATE

       ENDORSEMENT

           

FIRE DAMAGE (Any one fire)

MEDICAL EXPENSE (Any one person)

   
                   
A     AUTOMOBILE LIABILITY   Policy Number            COMBINED SINGLE LIMIT   $1,000,000
   

x  ANY AUTO

            BODILY INJURY (Per person)    
   

¨   ALL OWNED AUTOS

            BODILY INJURY (Per accident)    
   

¨   SCHEDULED AUTOS

            PROPERTY DAMAGE    
   

x  HIRED AUTOS

                 
   

x  NON-OWNED AUTOS

                 
A     EXCESS LIABILITY   Policy Number            EACH OCCURRENCE   $5,000,000
   

x  UMBRELLA

            AGGREGATE   $5,000,000
   

¨   OTHER THAN UMBRELLA FORM

                 
A    

WORKERS’ COMPENSATION

AND

EMPLOYER’S LIABILITY

  Policy Number            STATUTORY LIMITS x Florida    
                (Each accident)   $500,000
                (Disease-policy limit)   $500,000
                  (Disease-each employee)   $500,000
A     OTHER: EQUIPMENT FLOATER   Policy Number            Limit equal to Full Coverage of Subcontractor’s owned or rented machinery, equipment, tools, & temporary structures not designed to become a permanent part of the Work
DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/SPECIAL ITEMS: RE: Work performed at the Skanska USA Building ABC Project. Certificate Holders are Additional Insureds on a Primary and Non-contributing basis on the General Liability (ISO endorsement CG 20 10-11/85 or its equivalent – attached a copy with this Certificate of Insurance), Automobile and Excess/Umbrella Liability Policies. Waiver of Subrogation in favor of Certificate Holders applies to all policies. ALL COVERAGES LISTED APPLY ON AND OFF-SITE FOR ALL OPERATIONS OF THE INSURED.

 

 

Skanska USA Building Inc., Skanska USA, Inc. Indemnified Parties, any other parties as required by the Owner contract, Skanska Inc., and their respective directors, officers, employees and affiliates and ALL ENROLLED PARTIES

c/o Aon Risk Services, Inc.

4 Overlook Point

Lincolnshire, IL 60069

 

 

CANCELLATION

 

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES.

Attention:       AUTHORIZED REPRESENTATIVE
          By: (original signature)
ACORD 25-S (3/93)               © ACORD CORPORATION 1993

 

 

Skanska USA Building Inc. CCIP Insurance Manual – Exhibit G1

 

   Exhibit F    Page 2
 


AIA® Document A201TM - 2007
General Conditions of the Contract for Construction

for the following PROJECT:
(Name and location or address)
Tenant Improvements at
232 South Dobson Road,
Mesa, AZ 85202

THE OWNER:
(Name, legal status and address)
DexCom, Inc.
6340 Sequence Drive
San Diego, CA 92121
Attn: James Gillard

THE CONTRACTOR:
(Name, legal status, address and other information)

Skanska USA Building Inc.
4742 N. 24th Street, Suite 165
Phoenix, AZ 85016
Attn: Ross Vroman

THE ARCHITECT:
(Name, legal status and address)


ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

1
(1500995949)



TABLE OF ARTICLES

1
GENERAL PROVISIONS

2
OWNER

3
CONTRACTOR

4
ARCHITECT

5
SUBCONTRACTORS

6
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

7
CHANGES IN THE WORK

8
TIME

9
PAYMENTS AND COMPLETION

10
PROTECTION OF PERSONS AND PROPERTY

11
INSURANCE AND BONDS

12
UNCOVERING AND CORRECTION OF WORK

13
MISCELLANEOUS PROVISIONS

14
TERMINATION OR SUSPENSION OF THE CONTRACT

15
CLAIMS AND DISPUTES

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

2
(1500995949)



INDEX
(Topics and numbers in bold are section headings.)


Acceptance of Nonconforming Work
9.6.6, 9.9.3, 12.3
Acceptance of Work
9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3
Access to Work
3.16, 6.2.1, 12.1
Accident Prevention
10
Acts and Omissions
3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.4.2, 13.7, 14.1, 15.2
Addenda
1.1.1, 3.11
Additional Costs, Claims for
3.7.4, 3.7.5, 6.1.1, 7.3.7.5, 10.3, 15.1.4
Additional Inspections and Testing
9.4.2, 9.8.3, 12.2.1, 13.5
Additional Insured
11.1.4
Additional Time, Claims for
3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.5
Administration of the Contract
3.1.3, 4.2, 9.4, 9.5
Advertisement or Invitation to Bid
1.1.1
Aesthetic Effect
4.2.13
Allowances
3.8, 7.3.8
All-risk Insurance
11.3.1, 11.3.1.1
Applications for Payment
4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.6.3, 9.7, 9.10, 11.1.3
Approvals
2.1.1, 2.2.2, 2.4, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10, 4.2.7, 9.3.2, 13.5.1
Arbitration
8.3.1, 11.3.10, 13.1, 15.3.2, 15.4
ARCHITECT
4
Architect, Definition of
4.1.1
Architect, Extent of Authority
2.4, 3.12.7, 4.1, 4.2, 5.2, 6.3, 7.1.2, 7.3.7, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.5.1, 13.5.2, 14.2.2, 14.2.4, 15.1.3, 15.2.1
Architect, Limitations of Authority and Responsibility
2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.3, 9.6.4, 15.1.3, 15.2
Architect’s Additional Services and Expenses
2.4, 11.3.1.1, 12.2.1, 13.5.2, 13.5.3, 14.2.4
Architect’s Administration of the Contract
3.1.3, 4.2, 3.7.4, 15.2, 9.4.1, 9.5
Architect’s Approvals
2.4, 3.1.3, 3.5, 3.10.2, 4.2.7
Architect’s Authority to Reject Work
3.5, 4.2.6, 12.1.2, 12.2.1

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

3
(1500995949)



Architect’s Copyright
1.1.7, 1.5
Architect’s Decisions
3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.5.2, 15.2, 15.3
Architect’s Inspections
3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.5
Architect’s Instructions
3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.5.2
Architect’s Interpretations
4.2.11, 4.2.12
Architect’s Project Representative
4.2.10
Architect’s Relationship with Contractor
1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.4.2, 13.5, 15.2
Architect’s Relationship with Subcontractors
1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3.7
Architect’s Representations
9.4.2, 9.5.1, 9.10.1
Architect’s Site Visits
3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.5
Asbestos
10.3.1
Attorneys’ Fees
3.18.1, 9.10.2, 10.3.3
Award of Separate Contracts
6.1.1, 6.1.2
Award of Subcontracts and Other Contracts for Portions of the Work
5.2
Basic Definitions
1.1
Bidding Requirements
1.1.1, 5.2.1, 11.4.1
Binding Dispute Resolution
9.7, 11.3.9, 11.3.10, 13.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.4.1
Boiler and Machinery Insurance
11.3.2
Bonds, Lien
7.3.7.4, 9.10.2, 9.10.3
Bonds, Performance, and Payment
7.3.7.4, 9.6.7, 9.10.3, 11.3.9, 11.4
Building Permit
3.7.1
Capitalization
1.3
Certificate of Substantial Completion
9.8.3, 9.8.4, 9.8.5
Certificates for Payment
4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.3
Certificates of Inspection, Testing or Approval
13.5.4
Certificates of Insurance
9.10.2, 11.1.3
Change Orders
1.1.1, 2.4, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.6, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.3.1.2, 11.3.4, 11.3.9, 12.1.2, 15.1.3
Change Orders, Definition of
7.2.1

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

4
(1500995949)



CHANGES IN THE WORK
2.2.1, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.3.9
Claims, Definition of
15.1.1
CLAIMS AND DISPUTES
3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4
Claims and Timely Assertion of Claims
15.4.1
Claims for Additional Cost
3.2.4, 3.7.4, 6.1.1, 7.3.9, 10.3.2, 15.1.4
Claims for Additional Time
3.2.4, 3.7.4, 6.1.1, 8.3.2, 10.3.2, 15.1.5
Concealed or Unknown Conditions, Claims for
3.7.4
Claims for Damages
3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3.5, 11.3.7, 14.1.3, 14.2.4, 15.1.6
Claims Subject to Arbitration
15.3.1, 15.4.1
Cleaning Up
3.15, 6.3
Commencement of the Work, Conditions Relating to
2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.3.1, 11.3.6, 11.4.1, 15.1.4
Commencement of the Work, Definition of
8.1.2
Communications Facilitating Contract Administration
3.9.1, 4.2.4
Completion, Conditions Relating to
3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 13.7, 14.1.2
COMPLETION, PAYMENTS AND
9
Completion, Substantial
4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 13.7
Compliance with Laws
1.6, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 10.2.2, 11.1, 11.3, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3
Concealed or Unknown Conditions
3.7.4, 4.2.8, 8.3.1, 10.3
Conditions of the Contract
1.1.1, 6.1.1, 6.1.4
Consent, Written
3.4.2, 3.7.4, 3.12.8, 3.14.2, 4.1.2, 9.3.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 11.3.1, 13.2, 13.4.2, 15.4.4.2
Consolidation or Joinder
15.4.4
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
1.1.4, 6
Construction Change Directive, Definition of
7.3.1
Construction Change Directives
1.1.1, 3.4.2, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1
Construction Schedules, Contractor’s
3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2
Contingent Assignment of Subcontracts
5.4, 14.2.2.2
Continuing Contract Performance
15.1.3
Contract, Definition of
1.1.2
CONTRACT, TERMINATION OR SUSPENSION OF THE
5.4.1.1, 11.3.9, 14

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

5
(1500995949)



Contract Administration
3.1.3, 4, 9.4, 9.5
Contract Award and Execution, Conditions Relating to
3.7.1, 3.10, 5.2, 6.1, 11.1.3, 11.3.6, 11.4.1
Contract Documents, Copies Furnished and Use of
1.5.2, 2.2.5, 5.3
Contract Documents, Definition of
1.1.1
Contract Sum
3.7.4, 3.8, 5.2.3, 7.2, 7.3, 7.4, 9.1, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.3.1, 14.2.4, 14.3.2, 15.1.4, 15.2.5
Contract Sum, Definition of
9.1
Contract Time
3.7.4, 3.7.5, 3.10.2, 5.2.3, 7.2.1.3, 7.3.1, 7.3.5, 7.4, 8.1.1, 8.2.1, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 14.3.2, 15.1.5.1, 15.2.5
Contract Time, Definition of
8.1.1
CONTRACTOR
3
Contractor, Definition of
3.1, 6.1.2
Contractor’s Construction Schedules
3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2
Contractor’s Employees
3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.1.1, 11.3.7, 14.1, 14.2.1.1
Contractor’s Liability Insurance
11.1
Contractor’s Relationship with Separate Contractors and Owner’s Forces
3.12.5, 3.14.2, 4.2.4, 6, 11.3.7, 12.1.2, 12.2.4
Contractor’s Relationship with Subcontractors
1.2.2, 3.3.2, 3.18.1, 3.18.2, 5, 9.6.2, 9.6.7, 9.10.2, 11.3.1.2, 11.3.7, 11.3.8
Contractor’s Relationship with the Architect
1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.5, 15.1.2, 15.2.1
Contractor’s Representations
3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2
Contractor’s Responsibility for Those Performing the Work
3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8
Contractor’s Review of Contract Documents
3.2
Contractor’s Right to Stop the Work
9.7
Contractor’s Right to Terminate the Contract
14.1, 15.1.6
Contractor’s Submittals
3.10, 3.11, 3.12.4, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3, 11.1.3, 11.4.2
Contractor’s Superintendent
3.9, 10.2.6
Contractor’s Supervision and Construction Procedures
1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.5, 7.3.7, 8.2, 10, 12, 14, 15.1.3
Contractual Liability Insurance
11.1.1.8, 11.2
Coordination and Correlation
1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1
Copies Furnished of Drawings and Specifications
1.5, 2.2.5, 3.11
Copyrights
1.5, 3.17
Correction of Work
2.3, 2.4, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

6
(1500995949)



Correlation and Intent of the Contract Documents
1.2
Cost, Definition of
7.3.7
Costs
2.4, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.7, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.3, 12.1.2, 12.2.1, 12.2.4, 13.5, 14
Cutting and Patching
3.14, 6.2.5
Damage to Construction of Owner or Separate Contractors
3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 11.1.1, 11.3, 12.2.4
Damage to the Work
3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 11.3.1, 12.2.4
Damages, Claims for
3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3.5, 11.3.7, 14.1.3, 14.2.4, 15.1.6
Damages for Delay
6.1.1, 8.3.3, 9.5.1.6, 9.7, 10.3.2
Date of Commencement of the Work, Definition of
8.1.2
Date of Substantial Completion, Definition of
8.1.3
Day, Definition of
8.1.4
Decisions of the Architect
3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 15.2, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.5.2, 14.2.2, 14.2.4, 15.1, 15.2
Decisions to Withhold Certification
9.4.1, 9.5, 9.7, 14.1.1.3
Defective or Nonconforming Work, Acceptance, Rejection and Correction of
2.3, 2.4, 3.5, 4.2.6, 6.2.5, 9.5.1, 9.5.2, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1
Definitions
1.1, 2.1.1, 3.1.1, 3.5, 3.12.1, 3.12.2, 3.12.3, 4.1.1, 15.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1
Delays and Extensions of Time
3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.5, 15.2.5
Disputes
6.3, 7.3.9, 15.1, 15.2
Documents and Samples at the Site
3.11
Drawings, Definition of
1.1.5
Drawings and Specifications, Use and Ownership of
3.11
Effective Date of Insurance
8.2.2, 11.1.2
Emergencies
10.4, 14.1.1.2, 15.1.4
Employees, Contractor’s
3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3.3, 11.1.1, 11.3.7, 14.1, 14.2.1.1
Equipment, Labor, Materials or
1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2
Execution and Progress of the Work
1.1.3, 1.2.1, 1.2.2, 2.2.3, 2.2.5, 3.1, 3.3.1, 3.4.1, 3.5, 3.7.1, 3.10.1, 3.12, 3.14, 4.2, 6.2.2, 7.1.3, 7.3.5, 8.2, 9.5.1, 9.9.1, 10.2, 10.3, 12.2, 14.2, 14.3.1, 15.1.3
Extensions of Time
3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3, 7.4, 9.5.1, 9.7, 10.3.2, 10.4, 14.3, 15.1.5, 15.2.5
Failure of Payment
9.5.1.3, 9.7, 9.10.2, 13.6, 14.1.1.3, 14.2.1.2

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

7
(1500995949)



Faulty Work
(See Defective or Nonconforming Work)
Final Completion and Final Payment
4.2.1, 4.2.9, 9.8.2, 9.10, 11.1.2, 11.1.3, 11.3.1, 11.3.5, 12.3, 14.2.4, 14.4.3
Financial Arrangements, Owner’s
2.2.1, 13.2.2, 14.1.1.4
Fire and Extended Coverage Insurance
11.3.1.1
GENERAL PROVISIONS
1
Governing Law
13.1
Guarantees (See Warranty)
Hazardous Materials
10.2.4, 10.3
Identification of Subcontractors and Suppliers
5.2.1
Indemnification
3.17, 3.18, 9.10.2, 10.3.3, 10.3.5, 10.3.6, 11.3.1.2, 11.3.7
Information and Services Required of the Owner
2.1.2, 2.2, 3.2.2, 3.12.4, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.6.1, 9.6.4, 9.9.2, 9.10.3, 10.3.3, 11.2, 11.4, 13.5.1, 13.5.2, 14.1.1.4, 14.1.4, 15.1.3
Initial Decision
15.2
Initial Decision Maker, Definition of
1.1.8
Initial Decision Maker, Decisions
14.2.2, 14.2.4, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5
Initial Decision Maker, Extent of Authority
14.2.2, 14.2.4, 15.1.3, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5
Injury or Damage to Person or Property
10.2.8, 10.4
Inspections
3.1.3, 3.3.3, 3.7.1, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 12.2.1, 13.5
Instructions to Bidders
1.1.1
Instructions to the Contractor
3.2.4, 3.3.1, 3.8.1, 5.2.1, 7, 8.2.2, 12, 13.5.2
Instruments of Service, Definition of
1.1.7
Insurance
3.18.1, 6.1.1, 7.3.7, 9.3.2, 9.8.4, 9.9.1, 9.10.2, 11
Insurance, Boiler and Machinery
11.3.2
Insurance, Contractor’s Liability
11.1
Insurance, Effective Date of
8.2.2, 11.1.2
Insurance, Loss of Use
11.3.3
Insurance, Owner’s Liability
11.2
Insurance, Property
10.2.5, 11.3
Insurance, Stored Materials
9.3.2
INSURANCE AND BONDS
11

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

8
(1500995949)



Insurance Companies, Consent to Partial Occupancy
9.9.1
Intent of the Contract Documents
1.2.1, 4.2.7, 4.2.12, 4.2.13, 7.4
Interest
13.6
Interpretation
1.2.3, 1.4, 4.1.1, 5.1, 6.1.2, 15.1.1
Interpretations, Written
4.2.11, 4.2.12, 15.1.4
Judgment on Final Award
15.4.2
Labor and Materials, Equipment
1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2
Labor Disputes
8.3.1
Laws and Regulations
1.5, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 9.9.1, 10.2.2, 11.1.1, 11.3, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14, 15.2.8, 15.4
Liens
2.1.2, 9.3.3, 9.10.2, 9.10.4, 15.2.8
Limitations, Statutes of
12.2.5, 13.7, 15.4.1.1
Limitations of Liability
2.3, 3.2.2, 3.5, 3.12.10, 3.17, 3.18.1, 4.2.6, 4.2.7, 4.2.12, 6.2.2, 9.4.2, 9.6.4, 9.6.7, 10.2.5, 10.3.3, 11.1.2, 11.2, 11.3.7, 12.2.5, 13.4.2
Limitations of Time
2.1.2, 2.2, 2.4, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2.7, 5.2, 5.3, 5.4.1, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 11.1.3, 11.3.1.5, 11.3.6, 11.3.10, 12.2, 13.5, 13.7, 14, 15
Loss of Use Insurance
11.3.3
Material Suppliers
1.5, 3.12.1, 4.2.4, 4.2.6, 5.2.1, 9.3, 9.4.2, 9.6, 9.10.5
Materials, Hazardous
10.2.4, 10.3
Materials, Labor, Equipment and
1.1.3, 1.1.6, 1.5.1, 3.4.1, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1.2, 10.2.4, 14.2.1.1, 14.2.1.2
Means, Methods, Techniques, Sequences and Procedures of Construction
3.3.1, 3.12.10, 4.2.2, 4.2.7, 9.4.2
Mechanic’s Lien
2.1.2, 15.2.8
Mediation
8.3.1, 10.3.5, 10.3.6, 15.2.1, 15.2.5, 15.2.6, 15.3, 15.4.1
Minor Changes in the Work
1.1.1, 3.12.8, 4.2.8, 7.1, 7.4
MISCELLANEOUS PROVISIONS
13
Modifications, Definition of
1.1.1
Modifications to the Contract
1.1.1, 1.1.2, 3.11, 4.1.2, 4.2.1, 5.2.3, 7, 8.3.1, 9.7, 10.3.2, 11.3.1
Mutual Responsibility
6.2
Nonconforming Work, Acceptance of
9.6.6, 9.9.3, 12.3
Nonconforming Work, Rejection and Correction of
2.3, 2.4, 3.5, 4.2.6, 6.2.4, 9.5.1, 9.8.2, 9.9.3, 9.10.4, 12.2.1

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

9
(1500995949)



Notice
2.2.1, 2.3, 2.4, 3.2.4, 3.3.1, 3.7.2, 3.12.9, 5.2.1, 9.7, 9.10, 10.2.2, 11.1.3, 12.2.2.1, 13.3, 13.5.1, 13.5.2, 14.1, 14.2, 15.2.8, 15.4.1
Notice, Written
2.3, 2.4, 3.3.1, 3.9.2, 3.12.9, 3.12.10, 5.2.1, 9.7, 9.10, 10.2.2, 10.3, 11.1.3, 11.3.6, 12.2.2.1, 13.3, 14, 15.2.8, 15.4.1
Notice of Claims
3.7.4, 10.2.8, 15.1.2, 15.4
Notice of Testing and Inspections
13.5.1, 13.5.2
Observations, Contractor’s
3.2, 3.7.4
Occupancy
2.2.2, 9.6.6, 9.8, 11.3.1.5
Orders, Written
1.1.1, 2.3, 3.9.2, 7, 8.2.2, 11.3.9, 12.1, 12.2.2.1, 13.5.2, 14.3.1
OWNER
2
Owner, Definition of
2.1.1
Owner, Information and Services Required of the
2.1.2, 2.2, 3.2.2, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.3.2, 9.6.1, 9.6.4, 9.9.2, 9.10.3, 10.3.3, 11.2, 11.3, 13.5.1, 13.5.2, 14.1.1.4, 14.1.4, 15.1.3
Owner’s Authority
1.5, 2.1.1, 2.3, 2.4, 3.4.2, 3.8.1, 3.12.10, 3.14.2, 4.1.2, 4.1.3, 4.2.4, 4.2.9, 5.2.1, 5.2.4, 5.4.1, 6.1, 6.3, 7.2.1, 7.3.1, 8.2.2, 8.3.1, 9.3.1, 9.3.2, 9.5.1, 9.6.4, 9.9.1, 9.10.2, 10.3.2, 11.1.3, 11.3.3, 11.3.10, 12.2.2, 12.3, 13.2.2, 14.3, 14.4, 15.2.7
Owner’s Financial Capability
2.2.1, 13.2.2, 14.1.1.4
Owner’s Liability Insurance
11.2
Owner’s Relationship with Subcontractors
1.1.2, 5.2, 5.3, 5.4, 9.6.4, 9.10.2, 14.2.2
Owner’s Right to Carry Out the Work
2.4, 14.2.2
Owner’s Right to Clean Up
6.3
Owner’s Right to Perform Construction and to Award Separate Contracts
6.1
Owner’s Right to Stop the Work
2.3
Owner’s Right to Suspend the Work
14.3
Owner’s Right to Terminate the Contract
14.2
Ownership and Use of Drawings, Specifications and Other Instruments of Service
1.1.1, 1.1.6, 1.1.7, 1.5, 2.2.5, 3.2.2, 3.11, 3.17, 4.2.12, 5.3
Partial Occupancy or Use
9.6.6, 9.9, 11.3.1.5
Patching, Cutting and
3.14, 6.2.5
Patents
3.17
Payment, Applications for
4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5, 9.6.3, 9.7, 9.8.5, 9.10.1, 14.2.3, 14.2.4, 14.4.3
Payment, Certificates for
4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 13.7, 14.1.1.3, 14.2.4
Payment, Failure of
9.5.1.3, 9.7, 9.10.2, 13.6, 14.1.1.3, 14.2.1.2
Payment, Final
4.2.1, 4.2.9, 9.8.2, 9.10, 11.1.2, 11.1.3, 11.4.1, 12.3, 13.7, 14.2.4, 14.4.3

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

10
(1500995949)



Payment Bond, Performance Bond and
7.3.7.4, 9.6.7, 9.10.3, 11.4
Payments, Progress
9.3, 9.6, 9.8.5, 9.10.3, 13.6, 14.2.3, 15.1.3
PAYMENTS AND COMPLETION
9
Payments to Subcontractors
5.4.2, 9.5.1.3, 9.6.2, 9.6.3, 9.6.4, 9.6.7, 14.2.1.2
PCB
10.3.1
Performance Bond and Payment Bond
7.3.7.4, 9.6.7, 9.10.3, 11.4
Permits, Fees, Notices and Compliance with Laws
2.2.2, 3.7, 3.13, 7.3.7.4, 10.2.2
PERSONS AND PROPERTY, PROTECTION OF
10
Polychlorinated Biphenyl
10.3.1
Product Data, Definition of
3.12.2
Product Data and Samples, Shop Drawings
3.11, 3.12, 4.2.7
Progress and Completion
4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.3
Progress Payments
9.3, 9.6, 9.8.5, 9.10.3, 13.6, 14.2.3, 15.1.3
Project, Definition of
1.1.4
Project Representatives
4.2.10
Property Insurance
10.2.5, 11.3
PROTECTION OF PERSONS AND PROPERTY
10
Regulations and Laws
1.5, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 9.9.1, 10.2.2, 11.1, 11.4, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14, 15.2.8, 15.4
Rejection of Work
3.5, 4.2.6, 12.2.1
Releases and Waivers of Liens
9.10.2
Representations
3.2.1, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.4.2, 9.5.1, 9.8.2, 9.10.1
Representatives
2.1.1, 3.1.1, 3.9, 4.1.1, 4.2.1, 4.2.2, 4.2.10, 5.1.1, 5.1.2, 13.2.1
Responsibility for Those Performing the Work
3.3.2, 3.18, 4.2.3, 5.3, 6.1.3, 6.2, 6.3, 9.5.1, 10
Retainage
9.3.1, 9.6.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3
Review of Contract Documents and Field Conditions by Contractor
3.2, 3.12.7, 6.1.3
Review of Contractor’s Submittals by Owner and Architect
3.10.1, 3.10.2, 3.11, 3.12, 4.2, 5.2, 6.1.3, 9.2, 9.8.2
Review of Shop Drawings, Product Data and Samples by Contractor
3.12
Rights and Remedies
1.1.2, 2.3, 2.4, 3.5, 3.7.4, 3.15.2, 4.2.6, 5.3, 5.4, 6.1, 6.3, 7.3.1, 8.3, 9.5.1, 9.7, 10.2.5, 10.3, 12.2.2, 12.2.4, 13.4, 14, 15.4
Royalties, Patents and Copyrights
3.17

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

11
(1500995949)



Rules and Notices for Arbitration
15.4.1
Safety of Persons and Property
10.2, 10.4
Safety Precautions and Programs
3.3.1, 4.2.2, 4.2.7, 5.3, 10.1, 10.2, 10.4
Samples, Definition of
3.12.3
Samples, Shop Drawings, Product Data and
3.11, 3.12, 4.2.7
Samples at the Site, Documents and
3.11
Schedule of Values
9.2, 9.3.1
Schedules, Construction
3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2
Separate Contracts and Contractors
1.1.4, 3.12.5, 3.14.2, 4.2.4, 4.2.7, 6, 8.3.1, 12.1.2
Shop Drawings, Definition of
3.12.1
Shop Drawings, Product Data and Samples
3.11, 3.12, 4.2.7
Site, Use of
3.13, 6.1.1, 6.2.1
Site Inspections
3.2.2, 3.3.3, 3.7.1, 3.7.4, 4.2, 9.4.2, 9.10.1, 13.5
Site Visits, Architect’s
3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.5
Special Inspections and Testing
4.2.6, 12.2.1, 13.5
Specifications, Definition of
1.1.6
Specifications
1.1.1, 1.1.6, 1.2.2, 1.5, 3.11, 3.12.10, 3.17, 4.2.14
Statute of Limitations
13.7, 15.4.1.1
Stopping the Work
2.3, 9.7, 10.3, 14.1
Stored Materials
6.2.1, 9.3.2, 10.2.1.2, 10.2.4
Subcontractor, Definition of
5.1.1
SUBCONTRACTORS
5
Subcontractors, Work by
1.2.2, 3.3.2, 3.12.1, 4.2.3, 5.2.3, 5.3, 5.4, 9.3.1.2, 9.6.7
Subcontractual Relations
5.3, 5.4, 9.3.1.2, 9.6, 9.10, 10.2.1, 14.1, 14.2.1
Submittals
3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 7.3.7, 9.2, 9.3, 9.8, 9.9.1, 9.10.2, 9.10.3, 11.1.3
Submittal Schedule
3.10.2, 3.12.5, 4.2.7
Subrogation, Waivers of
6.1.1, 11.3.7
Substantial Completion
4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 13.7
Substantial Completion, Definition of
9.8.1

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

12
(1500995949)



Substitution of Subcontractors
5.2.3, 5.2.4
Substitution of Architect
4.1.3
Substitutions of Materials
3.4.2, 3.5, 7.3.8
Sub-subcontractor, Definition of
5.1.2
Subsurface Conditions
3.7.4
Successors and Assigns
13.2
Superintendent
3.9, 10.2.6
Supervision and Construction Procedures
1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.7, 8.2, 8.3.1, 9.4.2, 10, 12, 14, 15.1.3
Surety
5.4.1.2, 9.8.5, 9.10.2, 9.10.3, 14.2.2, 15.2.7
Surety, Consent of
9.10.2, 9.10.3
Surveys
2.2.3
Suspension by the Owner for Convenience
14.3
Suspension of the Work
5.4.2, 14.3
Suspension or Termination of the Contract
5.4.1.1, 14
Taxes
3.6, 3.8.2.1, 7.3.7.4
Termination by the Contractor
14.1, 15.1.6
Termination by the Owner for Cause
5.4.1.1, 14.2, 15.1.6
Termination by the Owner for Convenience
14.4
Termination of the Architect
4.1.3
Termination of the Contractor
14.2.2
TERMINATION OR SUSPENSION OF THE CONTRACT
14
Tests and Inspections
3.1.3, 3.3.3, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 10.3.2, 11.4.1, 12.2.1, 13.5
TIME
8
Time, Delays and Extensions of
3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.5, 15.2.5
Time Limits
2.1.2, 2.2, 2.4, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2, 5.2, 5.3, 5.4, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 11.1.3, 12.2, 13.5, 13.7, 14, 15.1.2, 15.4
Time Limits on Claims
3.7.4, 10.2.8, 13.7, 15.1.2
Title to Work
9.3.2, 9.3.3
Transmission of Data in Digital Form
1.6
UNCOVERING AND CORRECTION OF WORK
12

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

13
(1500995949)



Uncovering of Work
12.1
Unforeseen Conditions, Concealed or Unknown
3.7.4, 8.3.1, 10.3
Unit Prices
7.3.3.2, 7.3.4
Use of Documents
1.1.1, 1.5, 2.2.5, 3.12.6, 5.3
Use of Site
3.13, 6.1.1, 6.2.1
Values, Schedule of
9.2, 9.3.1
Waiver of Claims by the Architect
13.4.2
Waiver of Claims by the Contractor
9.10.5, 13.4.2, 15.1.6
Waiver of Claims by the Owner
9.9.3, 9.10.3, 9.10.4, 12.2.2.1, 13.4.2, 14.2.4, 15.1.6
Waiver of Consequential Damages
14.2.4, 15.1.6
Waiver of Liens
9.10.2, 9.10.4
Waivers of Subrogation
6.1.1, 11.3.7
Warranty
3.5, 4.2.9, 9.3.3, 9.8.4, 9.9.1, 9.10.4, 12.2.2, 13.7
Weather Delays
15.1.5.2
Work, Definition of
1.1.3
Written Consent
1.5.2, 3.4.2, 3.7.4, 3.12.8, 3.14.2, 4.1.2, 9.3.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 11.4.1, 13.2, 13.4.2, 15.4.4.2
Written Interpretations
4.2.11, 4.2.12
Written Notice
2.3, 2.4, 3.3.1, 3.9, 3.12.9, 3.12.10, 5.2.1, 8.2.2, 9.7, 9.10, 10.2.2, 10.3, 11.1.3, 12.2.2, 12.2.4, 13.3, 14, 15.4.1
Written Orders
1.1.1, 2.3, 3.9, 7, 8.2.2, 12.1, 12.2, 13.5.2, 14.3.1, 15.1.2

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

14
(1500995949)



ARTICLE 1   GENERAL PROVISIONS
§ 1.1 BASIC DEFINITIONS
§ 1.1.1 THE CONTRACT DOCUMENTS
The Contract Documents are enumerated in the Agreement between the Owner and Contractor (hereinafter the Agreement) and consist of the Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of the Contract, other documents listed in the Agreement and Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work issued by the Owner or Architect. Unless specifically enumerated in the Agreement, the Contract Documents do not include the advertisement or invitation to bid, Instructions to Bidders, sample forms, other information furnished by the Owner in anticipation of receiving bids or proposals, the Contractor’s bid or proposal, or portions of Addenda relating to bidding requirements.

§ 1.1.2 THE CONTRACT
The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. Except as set forth in Section 5.3 and 5.4, below, the Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Contractor and the Architect or the Architect’s consultants, (2) between the Owner and a Subcontractor or a Sub-subcontractor, (3) between the Owner and the Architect or the Architect’s consultants or (4) between any persons or entities other than the Owner and the Contractor. The Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Architect’s duties.

§ 1.1.3 THE WORK
The term “Work” means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations. The Work may constitute the whole or a part of the Project.

§ 1.1.4 THE PROJECT
The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner and by separate contractors.

§ 1.1.5 THE DRAWINGS
The Drawings are the graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams.

§ 1.1.6 THE SPECIFICATIONS
The Specifications are that portion of the Contract Documents consisting of the written requirements for materials, equipment, systems, standards and workmanship for the Work, and performance of related services.

§ 1.1.7 INSTRUMENTS OF SERVICE
Instruments of Service are representations, in any medium of expression now known or later developed, of the tangible and intangible creative work performed by the Architect and the Architect’s consultants under their respective professional services agreements. Instruments of Service may include, without limitation, studies, surveys, models, sketches, drawings, specifications, and other similar materials.

§ 1.1.8 INITIAL DECISION MAKER
The Initial Decision Maker is the person identified in the Agreement to render initial decisions on Claims in accordance with Section 15.2 and certify termination of the Agreement under Section 14.2.2.

§ 1.1.9 THE GUARANTEED MAXIMUM PRICE
The Guaranteed Maximum Price or “GMP” as used herein shall refer to the Contractor’s Guaranteed Maximum Price as defined in Section 5.2 of the Agreement. Except for its use in Sections 9.1, 9.4.2 and 14.2.4, the term “Contract Sum” as used in this A201™–2007, as modified, refers to the Guaranteed Maximum Price as defined in Section 5.2 of the Agreement.

§ 1.2 CORRELATION AND INTENT OF THE CONTRACT DOCUMENTS
§ 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results.

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

15
(1500995949)




§ 1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. Contractor represents that the Subcontractors, manufacturers and suppliers engaged or to be engaged by Contractor are and will be familiar with the requirements of the Contract Documents for performance by them of their obligations.

§ 1.2.3 Unless otherwise stated in the Contract Documents, words that have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings.

§ 1.3 CAPITALIZATION
Terms capitalized in these General Conditions include those that are (1) specifically defined, (2) the titles of numbered articles or (3) the titles of other documents published by the American Institute of Architects.

§ 1.4 INTERPRETATION
In the interest of brevity the Contract Documents frequently omit modifying words such as “all” and “any” and articles such as “the” and “an,” but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.

§ 1.5 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER INSTRUMENTS OF SERVICE
§ 1.5.1 All Drawings, Specifications, and other documents prepared by the Architect are and shall remain the property of Owner, and Owner shall retain all common law, statutory and other reserved rights with respect thereto. They shall not be used by Contractor on any other project without the prior written consent of Owner, and Contractor shall take such action as may be necessary to prevent their use on any other project or for additions to the Project outside the scope of the Work by any Subcontractor, Sub-subcontractor, or material or equipment supplier. Contractor, Subcontractors, Subsubcontractors, and material and equipment suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications, and other documents prepared by Architect appropriate to and for use in the execution of their Work under the Contract Documents. All copies made under this license shall bear the statutory copyright notice, if any, shown on the originals. Submittals or distributions necessary to meet official regulatory requirements or for other purposes relating to completion of the Project are not to be construed as a publication in derogation of the Owner's copyright or other reserved rights.

§ 1.5.2 Contractor acknowledges that it has taken measures reasonably necessary to verify and ascertain the nature and location of the Work, and that it has investigated and satisfied itself as to all general and local conditions that may affect the Work or its cost, including but not limited to: (a) conditions relating to transportation, handling, storage and disposal of materials and equipment; (b) availability of labor, power, water and other utilities, and roads; (c) uncertainties of weather, river stages, and similar physical characteristics of the site and its surroundings; and (d) character of equipment and other facilities required relative to the Work, both prior to commencement of the Work at the site and during the performance of the Work. Contractor further acknowledges that it has fully satisfied itself as to the nature, character, quality and quantity of surface conditions, materials or obstacles to be encountered to the extent that such information is reasonably available from the local municipality and other public bodies, and from the Contract Documents.

§ 1.5.3 Owner assumes no responsibility for any conclusions or interpretations made by Contractor based on the information made available by Owner, unless such information is included in the Contract Documents.

§ 1.6 TRANSMISSION OF DATA IN DIGITAL FORM
If the parties intend to transmit Instruments of Service or any other information or documentation in digital form, they shall endeavor to establish necessary protocols governing such transmissions, unless otherwise already provided in the Agreement or the Contract Documents, and such protocols, when agreed, shall be incorporated into the Contract Documents by amendment.

ARTICLE 2   OWNER
§ 2.1 GENERAL
§ 2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Owner shall designate in writing a representative who shall have express authority to bind the Owner with respect to all matters requiring the Owner’s approval or authorization. Except as otherwise provided in Section 4.2.1, the Architect does not have such authority. The term “Owner” means the Owner or the Owner’s authorized representative.

§ 2.1.2 The Owner shall furnish to the Contractor within fifteen days after receipt of a written request, information necessary and relevant for the Contractor to evaluate, give notice of or enforce mechanic’s lien rights. Such information shall include a

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

16
(1500995949)



correct statement of the record legal title to the property on which the Project is located, usually referred to as the site, and the Owner’s interest therein.

§ 2.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER
§ 2.2.1 Prior to and after commencement of the Work, but not more than once every three (3) months, the Contractor may request in writing that the Owner provide reasonable evidence that the Owner has made financial arrangements or has the financial ability to fulfill the Owner’s obligations under the Contract. The Owner shall furnish such evidence within fifteen (15) days after written request thereof from Contractor as a condition precedent to commencement of the Work. Thereafter, the furnishing of such evidence shall be a condition precedent to continuation of the Work if the request is made because (1) the Owner fails to make payments to the Contractor as the Contract Documents require; (2) a change in the Work materially increases the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due. The Owner shall furnish such evidence or as a condition precedent to commencement or continuation of the Work or the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements, if applicable, without prior notice to the Contractor.

§ 2.2.2 Except for permits and fees that are the responsibility of the Contractor under the Contract Documents, including those required under Section 3.7.1, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.

§ 2.2.3 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. The Contractor shall be entitled to rely on the accuracy of information furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work. Owner does not assume any responsibility whatsoever with respect to the sufficiency or accuracy of surveys or reports of borings made, or of the logs of test borings, or other investigations, or of the interpretations made thereof, and there is no warranty or guaranty, expressed or implied, that the conditions indicated by such investigations, borings, logs or information are representative of those existing throughout the Project site, or any part thereof, or the concealed conditions may be different from those described or may not have been identified.

§ 2.2.4 The Owner shall furnish information or services required of the Owner by the Contract Documents with reasonable promptness. The Owner shall also furnish any other information or services under the Owner’s control and relevant to the Contractor’s performance of the Work with reasonable promptness after receiving the Contractor’s written request for such information or services.

§ 2.2.5 Unless otherwise provided in the Contract Documents, the Owner shall furnish to the Contractor one copy of the Contract Documents for purposes of making reproductions pursuant to Section 1.5.2.

§ 2.3 OWNER’S RIGHT TO STOP THE WORK
If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may, after giving Contractor written notice and a reasonable opportunity to cure, but such notice shall only be required for the first such failure as to any particular issue or obligation, issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Section 6.1.3. Owner's exercise of the right described in this Section 2.3 shall not give rise to any extension of the Contract Time nor shall the Contract Sum include any sums, costs, or charges directly attributable to Owner's exercise of this right.

§ 2.4 OWNER’S RIGHT TO CARRY OUT THE WORK
If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a ten-day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of correcting such deficiencies, including Owner’s expenses and compensation for the Architect’s additional services made necessary by such default, neglect or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner, upon receipt of a written demand accompanied by documentation substantiating the amounts claimed.

§ 2.5 At all times prior to the completion of the Work, Owner, Architect, Project Manager, Owner's lender(s) (“Lender(s)”), if any, and all of their employees and agents, subject to Contractor’s reasonable requirements, shall have the right to have full

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

17
(1500995949)



access and use of the Work site. Owner's right hereunder shall include, without limitation, making inspections of the Work, including inspections carried out by Owner's agents (such as without limitation, Project Manager, Architect, engineers or other professional inspectors), stationing a Project director, a job supervisor and other personnel employed by Owner at the Work site, showing the Work to prospective concessionaires, tenants, lenders and other interested persons, and carrying out the work of fixturing the improvements comprising the Work for Owner's purposes in using the completed Work. Such use shall not constitute acceptance of the Work or any part thereof, or waive any of Owner's rights under the Contract Documents.

§ 2.6 Owner will not be responsible for and will not have control or charge over construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, and Owner will not be responsible for Contractor's failure to carry out the Work in accordance with the Contract Documents and applicable laws, rules and regulations. Owner will not be responsible for or have control or charge over the acts or omissions of Contractor, Subcontractors, or any of their agents or employees, or any other person performing any of the Work.

§ 2.7 Owner has the authority to reject the Work which does not conform to the Contract Documents. Whenever, in its opinion, Owner considers it necessary or advisable for implementation of the intent of the Contract Documents, Owner will have the authority to require special inspection or testing of the Work in accordance with Section 13.5.2 whether or not such Work is then fabricated, installed or completed. However, neither Owner's authority to act under this Section 2.7, nor any decision made by Owner in good faith, either to exercise or not to exercise such authority, shall give rise to any duty or responsibility of Owner to Contractor, any Subcontractor, any of their agents or employees, or any other person performing any of the Work.

§ 2.8 In the event Owner reasonably determines that the progress of Work affecting the critical path of construction is behind the progress anticipated in the schedule for the Work set forth in the GMP Amendment (the “Schedule”) , and Contractor is not entitled to receive an extension of the Contract Time in accordance with Contract Documents, Contractor shall submit to Owner for its approval a “Recovery Plan” which will indicate the manner in which Contractor intends to get the Work back on schedule in accordance with the Schedule. The cost of preparing the Recovery Plan shall be borne solely by Contractor, and shall not be the subject of a Change Order or the use of any contingency funds. In addition, Owner may require Contractor to take such actions as Owner reasonably deems necessary to expedite progress of the Work in conformance with the progress anticipated by the Schedule, which actions may include, without limitation, increasing the number of workmen performing the Work, utilizing overtime work and requiring additional work shifts. Such action by Owner to place Contractor back on schedule shall not entitle Contractor to receive any additional compensation for these activities unless Contractor would be entitled to receive an extension of Contract Time and Contractor has made such a request, all in accordance with Section 8.3.1, below.

ARTICLE 3   CONTRACTOR
§ 3.1 GENERAL
§ 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Contractor shall be lawfully licensed, if required in the jurisdiction where the Project is located. The Contractor shall designate in writing a representative who shall have express authority to bind the Contractor with respect to all matters under this Contract. The term “Contractor” means the Contractor or the Contractor’s authorized representative.

§ 3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.

§ 3.1.3 The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents either by activities or duties of the Architect in the Architect’s administration of the Contract, or by tests, inspections or approvals required or performed by persons or entities other than the Contractor, unless the Contract Documents require the Contractor to rely upon such administration, tests, inspections or approvals.

§ 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
§ 3.2.1 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become generally familiar with local conditions under which the Work is to be performed and correlated personal observations with requirements of the Contract Documents. Contractor and each Subcontractor shall evaluate and satisfy themselves as to the conditions and limitations under which the Work is to be performed, including without limitation, (1) the location, condition, layout, nature of the Project site and surrounding areas, (2) generally prevailing climactic conditions, (3) anticipated labor supply and cost, (4) availability and costs of materials, tools and equipment and (5) other similar issues. Owner assumes no responsibility or liability for the safety of the Project site or any improvements located at the Project site. The Owner shall not be required to make any adjustment in either the Contract Sum or the Contract Time in connection with any failure by the Contractor or any Subcontractor to comply with the requirements of this Section 3.2.1. The Contract Sum includes provisions for all Work that may be performed by Contractor to overcome patent site and soil conditions and, except as expressly provided in Section 3.7.4,

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

18
(1500995949)



below, claims for additional compensation or extension of time because of the Contractor’s failure to familiarize himself with such conditions will not be allowed.

§ 3.2.2 Because the Contract Documents are complementary, the Contractor shall, before starting each portion of the Work, carefully study and compare the various Contract Documents relative to that portion of the Work, as well as the information furnished by the Owner pursuant to Section 2.2.3, shall take field measurements of any existing conditions related to that portion of the Work, and shall observe any conditions at the site affecting it. Contractor shall at once report to Architect, Project Manager and Owner errors, inconsistencies or omissions discovered. If Contractor fails to so report such discovered errors, inconsistencies or omissions, or those that it discovered in the exercise of reasonable care, it shall be responsible for the cost of correction or, at Owner’s option, the reduction in value of any defective portion of the Work thereafter performed. Contractor further acknowledges that it has visited the site, examined all conditions affecting the Work, is fully familiar with all of the conditions thereon and affecting the same, and having carefully examined all Drawings, Specifications, and documents. These obligations are for the purpose of facilitating coordination and construction by the Contractor and are not for the purpose of discovering errors, omissions, or inconsistencies in the Contract Documents; however, the Contractor shall promptly report to the Architect any errors, inconsistencies or omissions discovered by or made known to the Contractor as a request for information in such form as the Architect may require. It is recognized that the Contractor’s review is made in the Contractor’s capacity as a contractor and not as a licensed design professional, unless otherwise specifically provided in the Contract Documents.

§ 3.2.3 Except as otherwise provided in the Contract Documents, the Contractor is not required to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Contractor shall promptly report to the Owner, Project Manager and Architect any nonconformity discovered by or made known to the Contractor as a request for information in such form as the Architect may require.

§ 3.2.4 If the Contractor believes that additional cost or time is involved because of clarifications or instructions the Architect issues in response to the Contractor’s notices or requests for information pursuant to Sections 3.2.2 or 3.2.3, the Contractor shall make Claims as provided in Article 15. If the Contractor fails to perform the obligations of Sections 3.2.2 or 3.2.3, it shall pay such costs and damages to the Owner as would have been avoided if the Contractor had performed such obligations. If the Contractor performs those obligations, the Contractor shall not be liable to the Owner or Architect for damages resulting from errors, inconsistencies or omissions in the Contract Documents, for differences between field measurements or conditions and the Contract Documents, or for nonconformities of the Contract Documents to applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities.

§ 3.2.5 Any ambiguities, missing information, illegible words or numbers or discrepancies discovered by Contractor shall be promptly submitted to Owner, Project Manager and Architect for a recommendation before products are ordered or construction initiated for that portion of the Work. Contractor shall perform the Work reflecting the correction of such errors, inconsistencies, and omissions subject to Owner's execution of appropriate Change Orders.
§ 3.2.5.1 Work ordered, fabricated or constructed by Contractor, when the Contract Documents do not clearly specify in detail the Work to be done or where the Work conflicts with the Contract Documents without such Change Orders, shall be corrected by Contractor at its own expense.
§ 3.2.5.2 Recommendations of Architect with regard to such ambiguities or discrepancies shall not make Architect an arbitrator to establish responsibilities of Subcontractors to Contractor with regard to such portions of the Work.

§ 3.2.6 Contractor shall notify Architect, Project Manager and Owner in writing, of materials, systems, procedures or methods of construction either shown on the Drawings or specified in the Specifications which Contractor believes are incorrect or inappropriate for the purposes intended, or for which Contractor objects to furnishing the warranties required by the Contract Documents. Architect and Owner will make a determination of such matters in writing, Contractor shall be responsible for any additional costs resulting from its failure to so notify Architect, Project Manager and Owner that such materials, systems, procedures and methods, are incorrect or inappropriate.

§ 3.2.7 Dimensions indicated on the Drawings are required dimensions, regardless of measurement per given scale. Contractor shall verify at site necessary levels, measurements, etc., for complete fabrication, assembly and installation, fitting of equipment, fixtures and the Work. Where dimensions are not indicated and exact location is not apparent, Contractor shall promptly notify Architect, Project Manager and Owner's Representative, and Architect shall compute the required measurements.


AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No.5763238807_1 which expires on 09/23/2016, and is not for resale.
User Notes: 

19
(1500995949)



§ 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
§ 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters. If the Contract Documents give specific instructions concerning construction means, methods, techniques, sequences or procedures, the Contractor shall evaluate the jobsite safety thereof and, except as stated below, shall be fully and solely responsible for the jobsite safety of such means, methods, techniques, sequences or procedures (excluding any separate work performed by a third party under a separate contract directly with Owner). If the Contractor determines that such means, methods, techniques, sequences or procedures may not be safe, the Contractor shall give timely written notice to the Owner and Architect and shall not proceed with that portion of the Work without further written instructions from the Architect, and the GMP or Contract Time or both shall be equitably adjusted. If the Contractor is then instructed to proceed with the required means, methods, techniques, sequences or procedures without acceptance of changes proposed by the Contractor, the Owner shall be solely responsible for any loss or damage arising solely from those Owner-required means, methods, techniques, sequences or procedures.

The Contractor shall engage workers who are skilled in performing the Work, and all Work shall be performed with care and skill and in a good workmanlike manner under the full-time supervision of an approved superintendent. The Contractor shall be liable for all property damage, including repairs and replacements of the Work, which proximately result from the breach of this duty. The Contractor shall advise the Owner:

a)    if a specified product deviates from good construction practices.

b)    If following the Specifications will affect any warranties; or

c)    any objections which the Contractor may have to the Specifications.

§ 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor’s employees, Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for, or on behalf of, the Contractor or any of its Subcontractors.

§ 3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work.

§ 3.3.4 In addition to Section 10.2, below, Contractor shall institute and supervise reasonable precautions to prevent damage, injury or loss to (i) all employees involved with the Work and other persons who may be affected thereby, including, without limitation, invitees, licensees, trespassers and persons on adjacent properties, (ii) all the Work and all materials and equipment to be incorporated therein, including those in storage on or off site under the care, custody or control of Contractor or any Subcontractor, (iii) Owner's personal and real property and other property at the Work site or adjacent thereto, including without limitation, fixtures, carpets, and other related items, and (iv) all of Owner's employees, agents and representatives. Contractor shall at all times take such precautions as may be necessary to shore, brace, secure and protect the Work and shall protect such parts of the Work and shall provide and maintain such security, including, without limitation, rules, guards, fences, lights and signs, as may be necessary or required to comply with this Section 3.3.4. Contractor shall further post necessary danger signs and other warnings against hazards, promulgate and enforce safety codes, rules and regulations and notify owners, lessees and users of adjacent property. Contractor shall particularly ensure and be responsible for compliance with all applicable state and federal safety laws, ordinances, rules, regulations and lawful orders of all governmental authorities and other persons or entities having jurisdiction. In any emergency threatening the Work or adjoining property, Contractor may act pursuant to Section 10.4. Contractor shall not be responsible for the costs of such emergency work, unless the emergency was due to Contractor's own fault or neglect. The Contractor shall inspect all materials delivered to the Project and shall reject any materials that will not conform with the Contract Documents when properly installed.

§ 3.3.5 Contractor shall not cause or permit any disruption to the streets and utilities serving any occupied portion of the Project, the remainder of the Project, or other properties without Owner's prior consent, which may be conditioned upon restrictions in the time, place and manner of such disruption.

§ 3.4 LABOR AND MATERIALS
§ 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, and temporary water, heat, utilities (including connections), transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.

AIA Document A201™ - 2007 Copyright © 1911, 1915, 1918, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA®  Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®  Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:06:04 on 04/28/2016 under Order No