A summary of the property, plant and equipment for Greystone is as follows, as of May 31:

 

    2016     2015  
Production machinery and equipment   $ 18,616,603     $ 13,120,285  
Plant buildings and land     4,663,339       4,663,339  
Leasehold improvements     198,568       198,568  
Furniture and fixtures     168 005       90,280  
      23,646,515       18,072,472  
                 
Less: Accumulated depreciation     (11,081,196 )     (9,563,157 )
                 
Net Property, Plant and Equipment   $ 12,565,319     $ 8,509,315