XML 34 R23.htm IDEA: XBRL DOCUMENT v3.25.2
COMMITMENTS AND CONTINGENCIES
6 Months Ended
Jun. 30, 2025
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
We have significant commitments and contingencies arising from our operations, including those related to unconditional purchase obligations, environmental matters, and enforcement and litigation matters.

Unconditional Purchase Obligations

We have obligations to distribute and sell electricity and natural gas to our customers and expect to recover costs related to these obligations in future customer rates. In order to meet these obligations, we routinely enter into long-term purchase and sale commitments for various quantities and lengths of time. Our minimum future commitments related to these purchase obligations as of June 30, 2025, were approximately $1.0 billion.

Environmental Matters

Consistent with other companies in the energy industry, we face significant ongoing environmental compliance and remediation obligations related to current and past operations. Specific environmental issues affecting us include, but are not limited to, current and future regulation of air emissions such as sulfur dioxide, NOx, fine particulates, ozone, mercury, and GHGs; water intake and discharges; management of coal combustion products such as fly ash; and remediation of impacted properties, including former manufactured gas plant sites.

Federal Deregulatory Actions

In March 2025, the EPA announced a large-scale deregulatory effort. The EPA announced that, in total, it expects to take 31 deregulatory actions that will likely take multiple years to complete. Of these 31 deregulatory actions, the actions that would apply to us include those impacting the Good Neighbor Rule, MATS, the PM Standard, the GHG Power Plant Rule, the Mandatory Greenhouse Gas Reporting Rule, the ELG, and the CCR Rule. Any EPA actions will require formal rulemaking proceedings and any such actions are likely to be subject to legal challenges. We continue to monitor and evaluate potential risks and benefits to us, depending on the actions ultimately taken.

In July 2025, the EPA proposed to rescind a 2009 declaration that determined that CO2 and other GHGs endanger public health and welfare. The "endangerment finding" is the legal underpinning of a host of climate regulations under the CAA. The proposal is subject to a review process and public comment and will likely be litigated. We are monitoring the status of the proposal and assessing the potential impact on our business and operations.
Air Quality

Cross State Air Pollution Rule – Good Neighbor Rule

In March 2023, the EPA issued its final Good Neighbor Rule, which became effective in August 2023 and requires significant reductions in ozone-forming emissions of NOx from power plants and industrial facilities. After review of the final rule, we believe we are well positioned to meet the requirements.

Our RICE units are not currently subject to the final rule as each unit is less than 25 MWs. To the extent we use RICE engines for natural gas distribution operations, those engines not part of an LDC are subject to the emission limits and operational requirements of the rule beginning in 2026. The EPA has exempted LDCs from the final rule.

In February 2024, the Supreme Court heard oral arguments regarding stay applications related to the EPA's Good Neighbor Rule. In June 2024, the Supreme Court granted a stay of the Good Neighbor Rule pending disposition of the applicants' petitions for review at the D.C. Circuit Court of Appeals. After a series of procedural motions and orders, in March 2025, the D.C. Circuit Court of Appeals issued an order removing the case from its active docket and holding the case in abeyance, pending quarterly updates from the parties beginning in July 2025. We will continue to monitor this case as arguments at the D.C. Circuit Court of Appeals move forward.

In November 2024, the EPA issued a Good Neighbor Interim Final Rule that administratively stayed the effectiveness of the Good Neighbor Rule in all states to which it originally applies and ensured implementation of good neighbor obligations previously established to address the 2008 ozone NAAQS while the process works through the courts. We believe we are well positioned to comply with the rule's requirements. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

Mercury and Air Toxics Standards

In 2012, the EPA issued the MATS to limit emissions of mercury, acid gases, and other hazardous air pollutants. In April 2023, the EPA issued the pre-publication version of a proposed rule to strengthen and update MATS to reflect recent developments in control technologies and performance of coal and oil-fired units. In May 2024, the EPA published a final rule in the Federal Register (the "2024 Final Action") lowering the PM limit from 0.03 lb/MMBtu to 0.01 lb/MMBtu. We believe we are well positioned to comply with the rule's requirements.

In June 2025, the EPA announced a proposed rule to repeal the 2024 Final Action on the basis that it imposed large compliance costs and raised technical feasibility concerns. Currently, the EPA is taking comments on the proposed rule.

National Ambient Air Quality Standards

Ozone

After completing its review of the 2008 ozone standard, the EPA released a final rule in October 2015, creating a more stringent standard than the 2008 NAAQS. The 2015 ozone standard lowered the 8-hour limit for ground-level ozone. In November 2022, the EPA's 2022 CASAC Ozone Review Panel issued a draft report supporting reconsideration of the 2015 standard. The EPA staff initially issued a draft Policy Assessment in March 2023 that also supported the reconsideration; however, in August 2023, the EPA announced that it was instead restarting its ozone standard evaluation. The EPA released the first two volumes of its Integrated Review Plan in December 2024. This new review is anticipated to take 3 to 5 years to complete.

In February 2022, revisions to the Wisconsin Administrative Code to adopt the 2015 standard were finalized. The amended regulations incorporated by reference the federal air pollution monitoring requirements related to the standard. The WDNR submitted the rule updates as a SIP revision to the EPA, which the EPA approved in February 2023.

Particulate Matter

All counties within our service territory are in attainment with current 2012 standards for fine PM2.5. Under the former presidential administration's policy review, the EPA concluded that the scientific evidence and information from a December 2020 review of the 2012 standards supported revising the level of the annual standard for the PM2.5 NAAQS to below the current level of 12 µg/m3, while retaining the 24-hour standard of 35 µg/m3. In February 2024, the EPA finalized a rule which lowered the primary (health-
based) annual PM2.5 NAAQS to 9 µg/m3. The secondary (welfare-based) PM2.5 standard and 24-hour standards (both primary and secondary) remain unchanged. The EPA has until February 2026 to designate areas as attainment and nonattainment with the new standard. The WDNR will need to draft and submit a SIP for the EPA's approval. A designation of nonattainment status could impact future permitting activities for facilities in applicable locations, including the potential need for improved or new air pollution control equipment. With our planned transition from coal-fired plants to natural gas-fired plants and renewable generating facilities, we do not expect this new standard to have a material impact on our units. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

Climate Change

Pursuant to the final GHG Power Plant Rule, there are no applicable standards for coal plants until the end of 2031 and after 2031, the applicable standard is dependent upon the unit's retirement date. Coal-fired units that are planned to refuel to natural gas-fired units must convert to natural gas and no longer retain the capability to burn coal by the end of 2029. For new combined cycle natural gas plants above a 40% capacity factor, the rule is dependent upon the implementation of carbon capture by the end of 2031. For new simple cycle natural gas-fired combustion turbines, there are no applicable limits as long as the capacity factor is less than 20%. Our Weston RICE units are not affected under the rule because the rule excludes RICE units that are less than 25 MWs. Numerous parties have challenged the GHG Power Plant Rule through litigation pending in the D.C. Circuit Court of Appeals.

In March 2024, the EPA announced it had removed regulations on existing natural gas combustion turbines from the rule. At that time, the EPA indicated it would work on new rulemaking phases, focusing on CO2 emissions, as well as NOx and hazardous air pollutants (formaldehyde) emissions. In November 2024, the EPA released the first proposed rule of the three rule "packages" to address NOx emissions from existing combustion turbines. The proposed rule for turbines that operate at a greater than 20% capacity factor will require more stringent NOx limits and control requirements for new, modified, or reconstructed turbines. For turbines that operate at a capacity of 20% or lower, less restrictive standards and the use of combustion controls would apply. We currently believe our existing combined-cycle natural gas facilities would be positioned to comply with the proposed rule if finalized in its current form. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

In June 2025, the EPA announced a proposed rule that contains co-proposals for addressing the GHG Power Plant Rule. The lead proposal would exclude the power sector from the GHG regulation on the grounds that it does not "significantly" contribute to dangerous air pollution. A secondary proposal would eliminate the carbon capture and sequestration/storage and other requirements from the GHG Power Plant Rule. By issuing co-proposals, the EPA is providing public notice of two very different potential regulatory paths. Based on the comments received, the EPA may choose to finalize either approach.

In April 2024, the EPA issued its final Mandatory Greenhouse Gas Reporting Rule, 40 Code of Federal Regulations Part 98, which includes updates to the global warming potentials to determine CO2 equivalency for threshold reporting and the addition of a new section regarding energy consumption. The revisions will impact the reporting required for our electric generation facilities, LDCs, and underground natural gas storage facilities. In May 2024, the EPA also issued its final rule to amend reporting requirements for petroleum and natural gas systems. Under the final rule, new leak emission factors and reporting requirements for large release events will impact the reporting required for our LDCs and underground natural gas storage facilities. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

WEC Energy Group's capital plan includes the retirement of older, fossil-fueled generation, to be replaced with zero-carbon-emitting renewables and reliable, efficient natural gas-fired generation. We have already retired approximately 400 MWs of fossil-fueled generation since the beginning of 2018, which includes the 2018 retirements of the Pulliam power plant and the jointly-owned Edgewater Unit 4 generating unit. WEC Energy Group expects to retire approximately 1,200 MWs of additional coal-fired generation by the end of 2031, which includes the planned retirement of the jointly-owned Columbia Units 1 and 2 while investigating conversion of at least one unit to natural gas, and Weston Unit 3. See Note 5, Property, Plant, and Equipment, for more information related to planned power plant retirements. In the third quarter of 2025, WEC Energy Group made a decision to reconsider its near-term CO2 emission reduction goals due to a combination of factors, including tightened energy supply requirements in the Midwest power market and the need to serve customers with safe, reliable, and affordable energy. However, WEC Energy Group's long-term goal to achieve net carbon neutral electric generation by 2050 remains intact. It expects to achieve this goal by continuing to make operating refinements, retiring less efficient generating units, and executing its capital plan. As part of our path toward this goal, we plan to begin testing co-firing with natural gas at Weston Unit 4 in 2025. WEC Energy Group expects to use coal only as a backup fuel by the end of 2030 and to be in a position to eliminate coal as an energy source by the end of 2032.
WEC Energy Group also continues to focus on methane emission reductions by improving and upgrading its natural gas distribution system, and using RNG throughout its natural gas utility systems. In light of WEC Energy Group's progress, significant uncertainty surrounding the market for renewable thermal credits, and WEC Energy Group's desire to focus on long-term GHG emissions-reduction across the enterprise, in the third quarter of 2025, WEC Energy Group made a decision to reassess its previous, standalone goal related to methane emissions from natural gas distribution.

Water Quality

Clean Water Act Cooling Water Intake Structure Rule

Revisions to an EPA rule authorized under Section 316(b) of the CWA became effective in October 2014 and requires the location, design, construction, and capacity of cooling water intake structures at existing power plants reflect the BTA for minimizing adverse environmental impacts. The rule applies to all of our existing generating facilities with cooling water intake structures.

Effective in June 2020, the requirements of Section 316(b) were incorporated into the Wisconsin Administrative Code. The WDNR applies this rule when establishing BTA requirements for cooling water intake structures at existing facilities. These BTA requirements are incorporated into WPDES permits for our facilities.

We have received a final BTA determination for Weston Units 3 and 4. In accordance with the requirements in the CWA, the WDNR reissued the Weston WPDES permit in June 2024 (effective July 1, 2024) that includes a determination that existing technology (wet cooling towers) installed at the units represents BTA for minimizing adverse environmental impacts.

Steam Electric Effluent Limitation Guidelines

The EPA's 2015 final ELG rule, which took effect in January 2016 (2015 ELG rule), was modified in 2020 (2020 ELG rule), and again in May 2024 with the publication of the Supplemental ELG Rule. These rules establish federal technology-based requirements for several types of power plant wastewaters. The two requirements that affect our facilities relate to wastewater discharge limits for BATW and CRL (landfill leachate). Although our coal-fueled facilities were constructed with advanced wastewater treatment technologies that meet many of the discharge limits established by the 2015 rule, facility modifications were still necessary at Weston to meet all of the 2015 ELG requirements and the additional ones established by the 2020 ELG rule. Compliance costs associated with the 2015 and 2020 ELG rules required $8 million in capital investment.

The 2024 Supplemental ELG rule established zero discharge requirements for BATW and CRL wastewaters at coal-fueled units with no planned retirement date. The Supplemental ELG Rule also kept one existing and created one new “permanent cessation of coal” subcategory. Those electing to cease coal combustion by either retiring or repowering a unit by December 31, 2028 or December 31, 2034 can limit ELG-related capital investments to what was required by either the 2015 or the 2020 ELG Rule, respectively. For units where cessation of coal is planned to occur no later than December 31, 2034, facility owners must complete all 2020 ELG rule required capital investments by December 31, 2025. All of our coal-fueled units fully meet the 2020 ELG rule requirements. Based on current electrical generation resource planning, we plan to file a Notice of Planned Participation by December 31, 2025 to opt into the "cessation of coal by December 31, 2034" subcategory for the Weston coal-fired facilities.

The final Supplemental ELG Rule allows owners of coal-fired units who opted into a cessation of coal subcategory to operate beyond the end of 2028 or 2034, as allowed by either the 2015 or the 2020 ELG Rule, respectively, if needed for reliability concerns (i.e., energy emergencies and reliability must run agreements) as determined by the United States Department of Energy, a public utility commission, or independent system operator.

In November 2024, Edison Electric Institute, on behalf of its members, submitted a petition for reconsideration to the EPA regarding the CRL provisions in the Supplemental ELG Rule in an effort to codify the rule interpretations articulated by the EPA staff during informational conference calls on this issue. We are still awaiting either a rule revision or clear written guidance from the EPA about the Supplemental ELG Rule CRL provisions to determine the applicability and potential compliance costs for inactive/closed landfills.

Numerous parties have challenged the 2024 Supplemental ELG Rule through litigation in SWEPCO v. U.S. EPA pending in the U.S. Court of Appeals for the Eighth Circuit. The outcome of this case may affect our compliance plans. This case has been held in abeyance since February 2025. The Supplemental ELG Rule remains in effect during the pendency of the legal challenge.
In June 2025, the EPA announced its intent to update the 2024 Supplemental ELG Rule. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

Land Quality

Manufactured Gas Plant Remediation

We have identified sites at which we or a predecessor company owned or operated a manufactured gas plant or stored manufactured gas. We have also identified other sites that may have been impacted by historical manufactured gas plant activities. We are responsible for the environmental remediation of these sites, some of which are in the EPA Superfund Alternative Approach Program. We are also working with the state of Wisconsin in our investigation and remediation planning. These sites are at various stages of investigation, monitoring, remediation, and closure.

In addition, we are coordinating the investigation and cleanup of some of these sites subject to the jurisdiction of the EPA under what is called a "multisite" program. This program involves prioritizing the work to be done at the sites, preparation and approval of documents common to all of the sites, and use of a consistent approach in selecting remedies. At this time, we cannot estimate future remediation costs associated with these sites beyond those described below.

The future costs for detailed site investigation, future remediation, and monitoring are dependent upon several variables including, among other things, the extent of remediation, changes in technology, and changes in regulation. Historically, our regulators have allowed us to recover incurred costs, net of insurance recoveries and recoveries from potentially responsible parties, associated with the remediation of manufactured gas plant sites. Accordingly, we have established regulatory assets for costs associated with these sites.

We have established the following regulatory assets and reserves for manufactured gas plant sites:
(in millions)June 30, 2025December 31, 2024
Regulatory assets$109.5 $114.0 
Reserves for future environmental remediation76.8 77.3 

Coal Combustion Residuals Rule

The EPA finalized a rule for CCR in April 2024 that would apply to landfills, historic fill sites, and projects where CCR was placed at a power plant site. The rule will regulate previously exempt closed landfills.

The final rule, which became effective in November 2024, will have an impact on some of our coal ash landfills, requiring additional remediation that is not currently required under the state programs. The rule is being challenged through litigation pending in the D.C. Circuit Court of Appeals. In June 2025, the D.C. Circuit Court of Appeals granted the EPA's request to extend its ongoing abeyance for an additional 60 days. We expect the cost of the additional remediation would be recovered through future rates. See the Federal Deregulatory Actions discussion above for more information regarding potential deregulatory actions regarding this rule.

Enforcement and Litigation Matters

We are involved in legal and administrative proceedings before various courts and agencies with respect to matters arising in the ordinary course of business. Although we are unable to predict the outcome of these matters, management believes that appropriate reserves have been established and that final settlement of these actions will not have a material impact on our financial condition or results of operations.

Consent Decrees

Joint Ownership Power Plants – Columbia Energy Center and Edgewater Generating Station

In December 2009, the EPA issued an NOV to WPL, the operator of the Columbia and Edgewater plants, and the other joint owners of these plants, including MG&E, WE (former co-owner of an Edgewater unit), and us. The NOV alleged violations of the CAA's New Source Review requirements related to certain projects completed at those plants. We, along with WPL, MG&E, and WE, entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the
Western District of Wisconsin in June 2013. As a result of the continued implementation of the Consent Decree related to the jointly owned Columbia and Edgewater plants, the Edgewater Unit 4 generating unit was retired in September 2018. WPL started the process to close out this Consent Decree.