COMMITMENTS AND CONTINGENCIES
3 Months Ended
Mar. 31, 2023
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
We have significant commitments and contingencies arising from our operations, including those related to unconditional purchase obligations, environmental matters, and enforcement and litigation matters.

Unconditional Purchase Obligations

We have obligations to distribute and sell electricity and natural gas to our customers and expect to recover costs related to these obligations in future customer rates. In order to meet these obligations, we routinely enter into long-term purchase and sale commitments for various quantities and lengths of time. Our minimum future commitments related to these purchase obligations as of March 31, 2023, were approximately $1.0 billion.
Environmental Matters

Consistent with other companies in the energy industry, we face significant ongoing environmental compliance and remediation obligations related to current and past operations. Specific environmental issues affecting us include, but are not limited to, current and future regulation of air emissions such as sulfur dioxide, NOx, fine particulates, mercury, and GHGs; water intake and discharges; management of coal combustion products such as fly ash; and remediation of impacted properties, including former manufactured gas plant sites.

Air Quality

Cross State Air Pollution Rule – Good Neighbor Plan

In March 2023, the EPA issued its final Good Neighbor Plan, which requires significant reductions in ozone-forming emissions of NOx from power plants and industrial facilities. The rule took effect for the 2023 ozone season. After review of the final rule, we believe that we are well positioned to meet the requirements.

Our planned RICE units in Wisconsin are not currently subject to the final rule as each unit is less than 25 MWs. To the extent we use RICE engines for natural gas distribution operations, those engines may be subject to the emission limits and operational requirements of the rule beginning in 2026. The EPA has exempted LDCs from the final rule but included new language defining an LDC that we are still evaluating.

Mercury and Air Toxics Standards

In 2012, the EPA issued the MATS to limit emissions of mercury, acid gases, and other hazardous air pollutants. In April 2023, the EPA issued the pre-publication version of a proposed rule to strengthen and update MATS to reflect recent developments in control technologies and performance of coal and oil-fired units. The EPA proposed three revisions including a proposal to lower the PM limit from 0.03 lb/MMBtu to 0.01 lb/MMBtu, which could have an adverse effect on our utilities. The EPA is also seeking comments on an even lower limit of 0.006 lb/MMBtu. We are still evaluating the proposed rule revisions to understand the impacts, if any, to our operations.

National Ambient Air Quality Standards

Ozone

After completing its review of the 2008 ozone standard, the EPA released a final rule in October 2015, creating a more stringent standard than the 2008 NAAQS. The 2015 ozone standard lowered the 8-hour limit for ground-level ozone. In November 2022, the EPA's 2022 CASAC Ozone Review Panel issued a draft report supporting a previously issued EPA staff-written Integrated Science Assessment for ozone which supported the reconsideration of the 2015 standard. The EPA staff issued a draft Policy Assessment in March 2023 in support of revisiting the 2020 decision to retain the 2015 ozone standards with no changes and indicated that they intend to publish their reconsideration in early 2024, with an anticipated final rule by early 2025.

In February 2022, revisions to the Wisconsin Administrative Code to adopt the 2015 standard were finalized. The amended regulations incorporated by reference the federal air pollution monitoring requirements related to the standard. The WDNR submitted the rule updates as a SIP revision to the EPA, which the EPA approved in February 2023.

We believe that we are well positioned to meet the requirements associated with the 2015 ozone standard and do not expect to incur significant costs to comply with the associated state and federal rules.

Particulate Matter

In December 2020, the EPA completed its 5-year review of the 2012 annual and 24-hour standards for fine PM and determined that no revisions were necessary to the current annual standard of 12 µg/m3 or the 24-hour standard of 35 µg/m3. Under the Biden Administration's policy review, the EPA concluded that the scientific evidence and information from the December 2020 determination supports revising the level of the annual standard for the PM NAAQS to below the current level of 12 µg/m3, while retaining the 24-hour standard. In January 2023, the EPA announced its proposed decision to revise the primary (health-based)
annual PM2.5 standard from its current level of 12 µg/m3 to within the range of 9 to 10 µg/m3. The EPA also proposed not to change the current secondary (welfare-based) annual PM2.5 standard, primary and secondary 24-hour PM2.5 standards, and primary and secondary PM10 standards. The EPA is also taking comments on the full range (between 8 and 11 µg/m3) included in the CASAC's latest report. The EPA has announced it plans to issue a final decision on the reconsideration in summer 2023. All counties within our service territory are in attainment with the current 2012 standards. If the EPA lowers the annual standard to 10 or 11 µg/m3, our generating facilities within our service territory should remain in attainment. If the EPA lowers it to below 10 µg/m3, there could be some nonattainment areas that may affect permitting of some smaller ancillary equipment located at our facilities. After finalization of the rule, the WDNR will need to draft and submit a SIP for the EPA's approval.

Climate Change

The Affordable Clean Energy rule, which replaced the Clean Power Plan, was vacated by the D.C. Circuit Court of Appeals in January 2021. In October 2021, the Supreme Court agreed to review the D.C. Circuit Court's ruling and in June 2022, the Supreme Court issued its decision. The Supreme Court found that the EPA may regulate GHGs under section 111 of the CAA but cannot rely on generation shifting to lower carbon emitting sources to do so. A new GHG replacement rule for existing sources is under review by the OMB.

In January 2021, the EPA finalized a rule to revise the New Source Performance Standards for GHG emissions from new, modified, and reconstructed fossil-fueled power plants; however, it was vacated by the D.C. Circuit Court of Appeals in April 2021. A new GHG replacement rule for new, modified, and reconstructed sources is under review by the OMB. WEC Energy Group continues to move forward on the ESG Progress Plan, which is heavily focused on reducing GHG emissions.

The EPA released proposed regulations for the Mandatory Greenhouse Gas Reporting Rule, 40 Code of Federal Regulations Part 98, in June 2022. The proposed revisions could impact the reporting required of our local natural gas distribution operations and underground natural gas storage facilities. The EPA intends to issue a new supplemental notice of proposed rulemaking in the second quarter of 2023 with an anticipated final rule to be issued in the fourth quarter of 2023 for all subparts of this rule.

The ESG Progress Plan includes the retirement of older, fossil-fueled generation, to be replaced with zero-carbon-emitting renewables and clean natural gas-fueled generation. We have already retired approximately 400 MWs of coal-fired generation since the beginning of 2018. Through its ESG Progress Plan, WEC Energy Group expects to retire approximately 1,500 MWs of additional fossil-fueled generation by the end of 2026, which includes the planned retirement by June 2026 of jointly-owned Columbia Units 1-2. See Note 6, Property, Plant, and Equipment, for more information on the timing of the retirement. In May 2021, WEC Energy Group announced goals to achieve reductions in carbon emissions from its electric generation fleet by 60% by the end of 2025 and by 80% by the end of 2030, both from a 2005 baseline. WEC Energy Group expects to achieve these goals by making operating refinements, retiring less efficient generating units, and executing its capital plan. Over the longer term, the target for WEC Energy Group's generation fleet is net-zero CO2 emissions by 2050.

WEC Energy Group also continues to reduce methane emissions by improving its natural gas distribution systems, and has set a target across its natural gas distribution operations to achieve net-zero methane emissions by the end of 2030. WEC Energy Group plans to achieve its net-zero goal through an effort that includes both continuous operational improvements and equipment upgrades, as well as the use of RNG throughout its utility systems.

Water Quality

Clean Water Act Cooling Water Intake Structure Rule

The EPA issued a final regulation under Section 316(b) of the CWA that became effective in October 2014 and requires the location, design, construction, and capacity of cooling water intake structures at existing power plants reflect the BTA for minimizing adverse environmental impacts. The rule applies to all of our existing generating facilities with cooling water intake structures.

Pursuant to a WDNR rule, which became effective in June 2020, the requirements of federal Section 316(b) of the CWA were incorporated into the Wisconsin Administrative Code. The WDNR applies this rule when establishing BTA requirements for cooling water intake structures at existing facilities. These BTA requirements are incorporated into WPDES permits for our facilities.

We have received interim BTA determinations for Weston Units 3 and 4. We believe that existing technology installed at the Weston facility will result in a final BTA determination during the WPDES permit reissuance in 2023.
As a result of past capital investments completed to address Section 316(b) compliance, we believe our fleet overall is well positioned to continue to meet this regulation.

Steam Electric Effluent Limitation Guidelines

The EPA's ELG rule, effective January 2016 and modified in 2020, revised the treatment technology requirements related to BATW at existing facilities and created new requirements for several types of power plant wastewaters. We are impacted by the new requirement related to discharge limits for BATW. Although our power plant facilities already have advanced wastewater treatment technologies installed that meet many of the discharge limits established by this rule, certain facility modifications are necessary to meet the ELG rule requirements. Through 2023, we expect that compliance costs associated with the ELG rule will require $10 million in capital investment. The BATW modification does not require PSCW approval prior to construction. This ELG required project is on track for completion by the WPDES permit deadline in December 2023.

In March 2023, the EPA issued the proposed "supplemental ELG rule." The rule would replace the existing 2020 ELG rule and, as proposed, would establish stricter limitations on: 1) BATW; 2) FGD wastewater; 3) CCR leachate; and 4) legacy wastewaters. Once the Weston 3 BATW project is complete, currently expected by the end of 2023, we anticipate that Weston 3 will have a compliant dry bottom ash transport system. At this time, we do not anticipate significant costs related to complying with the proposed rule as it relates to FGD wastewater, CCR leachate, and legacy wastewater.

Waters of the United States

In January 2023, the EPA and the United States Army Corps of Engineers together released a final rule revising the definition of WOTUS. This rule became effective on March 20, 2023. The final rule states that it is based on the pre-2015 definition of "waters of the United States." The pre-2015 approach involves applying factors established through case law and agency precedents to determine whether a wetland or surface drainage feature is subject to federal jurisdiction.

The recent rulemaking could be affected by a significant pending Supreme Court case involving WOTUS determination. In October 2022, the Supreme Court heard oral arguments in a case, Sackett v. Environmental Protection Agency, to evaluate the proper test for determining whether wetlands are WOTUS. A decision by the Supreme Court is expected during the second quarter of 2023.

At this point, our projects requiring federal permits are moving ahead, but we are monitoring these recent developments to better understand potential future impacts. The Sackett case, once decided, should provide some clarity regarding the definition of WOTUS. We will continue to monitor this litigation and any subsequent agency action.

Land Quality

Manufactured Gas Plant Remediation

We have identified sites at which we or a predecessor company owned or operated a manufactured gas plant or stored manufactured gas. We have also identified other sites that may have been impacted by historical manufactured gas plant activities. We are responsible for the environmental remediation of these sites, some of which are in the EPA Superfund Alternative Approach Program. We are also working with the state of Wisconsin in our investigation and remediation planning. These sites are at various stages of investigation, monitoring, remediation, and closure.

In addition, we are coordinating the investigation and cleanup of some of these sites subject to the jurisdiction of the EPA under what is called a "multisite" program. This program involves prioritizing the work to be done at the sites, preparation and approval of documents common to all of the sites, and use of a consistent approach in selecting remedies. At this time, we cannot estimate future remediation costs associated with these sites beyond those described below.

The future costs for detailed site investigation, future remediation, and monitoring are dependent upon several variables including, among other things, the extent of remediation, changes in technology, and changes in regulation. Historically, our regulators have allowed us to recover incurred costs, net of insurance recoveries and recoveries from potentially responsible parties, associated with the remediation of manufactured gas plant sites. Accordingly, we have established regulatory assets for costs associated with these sites.
We have established the following regulatory assets and reserves for manufactured gas plant sites:
(in millions)March 31, 2023December 31, 2022
Regulatory assets$117.3 $118.5 
Reserves for future environmental remediation84.5 88.6 

Coal Combustion Residuals Rule

In January 2023, the EPA released a notice regarding their intent to revise the CCR rule. The EPA is drafting regulations for CCR storage at inactive generating units or "legacy units." The EPA is also considering proposing corrective action requirements for all CCR contamination at any regulated facility, regardless of how or when the CCR was placed at such site. Our legacy units are currently regulated by the states in which they are located. The proposed rule is expected in summer 2023.

In February 2023, the EPA published notice in the Federal Register of a proposed consent decree to resolve a citizen suit related to conducting a review of Resource Conservation and Recovery Act regulations pertaining to the CCR rule. We are still evaluating the proposed language to understand the impact, if any, to our operations.

Enforcement and Litigation Matters

We are involved in legal and administrative proceedings before various courts and agencies with respect to matters arising in the ordinary course of business. Although we are unable to predict the outcome of these matters, management believes that appropriate reserves have been established and that final settlement of these actions will not have a material impact on our financial condition or results of operations.

Consent Decrees

Weston and Pulliam Power Plants

In November 2009, the EPA issued an NOV to us, which alleged violations of the CAA's New Source Review requirements relating to certain projects completed at the Weston and Pulliam power plants from 1994 to 2009. We entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Eastern District of Wisconsin in March 2013. With the retirement of Pulliam Units 7 and 8 in October 2018, we completed the mitigation projects required by the Consent Decree and received a completeness letter from the EPA in October 2018. We are working with the EPA on a closeout process for the Consent Decree and expect that process to begin later in 2023.

Joint Ownership Power Plants – Columbia and Edgewater

In December 2009, the EPA issued an NOV to Wisconsin Power and Light Company, the operator of the Columbia and Edgewater plants, and the other joint owners of these plants, including Madison Gas and Electric Company, WE (former co-owner of an Edgewater unit), and us. The NOV alleged violations of the CAA's New Source Review requirements related to certain projects completed at those plants. We, along with Wisconsin Power and Light Company, Madison Gas and Electric Company, and WE, entered into a Consent Decree with the EPA resolving this NOV. This Consent Decree was entered by the United States District Court for the Western District of Wisconsin in June 2013. As a result of the continued implementation of the Consent Decree related to the jointly owned Columbia and Edgewater plants, the Edgewater 4 generating unit was retired in September 2018. Wisconsin Power and Light Company started the process to close out this Consent Decree in early 2023.