NOTE 20    GOODWILL AND REGULATORY

Tuscarora – On January 21, 2016, FERC issued an Order initiating an investigation pursuant to Section 5 of the Natural Gas Act of 1938 (NGA) to determine whether Tuscarora's existing rates for jurisdictional services are just and reasonable. On July 22, 2016, Tuscarora filed a petition with FERC requesting approval of the Stipulation and Agreement of Settlement (Tuscarora Settlement) Tuscarora made with its customers. On September 22, 2016, FERC approved the Tuscarora Settlement that resolved the Section 5 rate review initiated by FERC in January 2016. Under the terms of the Tuscarora Settlement, Tuscarora's system-wide unit rate initially decreased by 17 percent, effective August 1, 2016. Unless superseded by a subsequent rate case or settlement, this rate will remain in effect until July 31, 2019, after which time the unit rate will decrease an additional seven percent from August 1, 2019 through July 31, 2022. The settlement does not contain a rate moratorium and requires Tuscarora to file to establish new rates no later than August 1, 2022.

The reduction in Tuscarora's future cash flows as a result of the Tuscarora Settlement constituted a triggering event in the second quarter of 2016 that led us to evaluate, for possible impairment, the $82 million of goodwill related to our acquisition of Tuscarora.

Our second quarter analysis, which was also reviewed for any material updates as part of our annual impairment test on goodwill, resulted in the estimated fair value of Tuscarora exceeding its carrying value but the excess was less than 10 percent. The fair value was measured using a discounted cash flow analysis and included revenues expected from Tuscarora's current and expected future contracting level. There is a risk that reductions in future cash flow forecasts as a result of Tuscarora not being able to maintain its current contracting level and/or not being able to realize other opportunities on the system, together with adverse changes in other key assumptions such as expected outcome of future rate proceedings, projected operating costs and estimated rate of return on invested capital, could result in a future impairment of the goodwill balance relating to Tuscarora.

North Baja – On January 6, 2017, North Baja notified FERC that current market conditions do not support the replacement of the compression that was temporarily abandoned in 2013 and requested authorization to permanently abandon two compressor units and a nominal volume of unsubscribed firm capacity. The requested abandonments will not have any impact on existing firm transportation service.

GTN – GTN operates under rates established pursuant to a settlement approved by FERC in June 2015. Beginning in January 2016, GTN's rates decreased by 10 percent and will continue in effect through December 31, 2019. Unless superseded by a subsequent rate case or settlement, GTN's rates will decrease an additional eight percent for the period January 1, 2020 through December 31, 2021 when GTN will be required to establish new rates.